Method Statement For Water Heaters Installation
Method Statement For Water Heaters Installation
1. SCOPE............................................................................................................................... 3
2. ABBREVIATION................................................................................................................. 3
3. REFERENCES.................................................................................................................... 2
4. RESPONSIBILITIES........................................................................................................... 4
5. SITE PLANNING AND PREPARATION..............................................................................4
6.0 WORK METHODOLOGY & SEQUENCE OF WORK.......................................................5
6.1 INSTALLATION OF WATER HEATERS...........................................................................5
7. RESOURCES..................................................................................................................... 8
7.1 TOOLS & EQUIPMENT 8
7.2 MATERIALS 8
7.3 MANPOWER 8
8.0 QUALITY CONTROL........................................................................................................9
9.0 HEALTH, SAFETY & ENVIRONMENT (HSE)...................................................................9
10.0 SAFETY INSTRUCTIONS...............................................................................................9
11.PERSONEL PROTECTIVE EQUIPMENT........................................................................10
12.ENVIRONMENTAL ISSUES.............................................................................................10
12.1 INTRODUCTION........................................................................................................... 10
12.2 MITIGATION MEASURES.............................................................................................11
13. APPENDIX...................................................................................................................... 11
13.1. RISK ASSESSMENT FOR INSTALLATION OF WATER HEATERS. 11
1.0 SCOPE
The purpose of this method statement is to describe the procedure and methodology to be adopted
as a part of water heaters installation for the Construction of Bird Breeding Building and Majlis at
Ruwayyah Conservation. This document should be read in conjunction with the Project Quality Plan
and Contract Specifications.
2.0 ABBREVIATION
1. MS - Method Statement
2. RA - Risk Assessment
3. E/E - Employer /Engineer
4. PPE -Personal Protective Equipment
5. HSE - Health Safety and Environment
6. PTW – Permit to Work
7. EPCM- Engineering, Procurement, and Construction management.
3.0 REFERENCES
Project Manager: Shall be responsible for the proper execution of this procedure and to
ensure that works are undertaken in a safe manner as described herein, to the requisite
quality in accordance with relevant quality procedures and to the agreed timescale.
Safety Manager: Shall be responsible for the implementation of safety procedures on site
and to ensure that the Risk Assessment within this method statement is followed. He shall
assign a competent Safety Officer to enforce these procedures and to provide guidance to
the operations where applicable.
MEP Engineer: Shall be responsible for the overall execution of works, and also responsible
for following all HSE and quality procedure.
Safety Officers: Shall be responsible for the implementation of all safety requirements and
to ensure that the works are undertaken in a safe and proper manner, all in accordance with
the approved Construction Phase HSE Plan, the approved method statement and the
approved Job Safety Analysis.
Quality Control Inspector: Shall be responsible for inspection and verification that the
procedures are properly implemented and that inspections are undertaken in accordance
with the approved Inspection Test Plan in a timely manner.
Ensure all the employees attend site-specific induction covering safety, environment, and
quality.
Acquire approvals and inspection for plant & machinery to enter inside the site locations if
any.
Any PTW for General works will be applied and obtained prior to works on site.
All environmental control will be established in accordance with the Site Environmental
Plan.
Ensure that all the necessary clearances from the Construction team are obtained prior to
start the work.
Check that the shop drawings and material submittals are approved and verify that the
materials are as per the approved by the Engineer.
Check that pipes are delivered pre-packed in standard quantities
Inspect the pipes stored on a reasonably flat surface free from large stones or sharp
projections.
Loading and unloading of pipes should be carried out by hand and use of skids should be
avoided
Pipes should not be dragged along a rough surface.
Extra care should be exercised in handling pipes to avoid damages.
Check work area is clean and safe to proceed for the installation & testing works.
Upon confirmation of the correct model and size of the water heater, mark the
final location with exact bolts holes dimension on the wall/block with reference to
the manufacturer's product catalog.
If there is a requirement for additional steel structure support, such as steel
channel or angle bar supports, mark and drill the correct bolts holes on the steel
support strictly according to the exact dimension of water heater base support
Use appropriate drilling machine to drill for anchor bolts insertion on the wall with
a correct drill bit and fix the approved anchor bolts accordingly making sure that
all bolts and nuts are properly tightened, support are aligned and secured.
Raise and install the electric hot water heater to the structure support with the
isolation pads to the inserted anchor or stud bolts. Recheck that water heater is
properly and securely installed, all bolts and nuts are fastened and brackets
and/or support are rigid.
Install necessary piping by removing plastic caps from the water heater inlet and
outlet connection nipples as per approved water supply drawing. Recheck to
ensure that all pipe, valves fittings and accessories are properly connected and
the direction of water flow is correct.
Provide proper pipe support and/or pipe hanger to the associated piping, ensure pipe
support and hangers are secured. The potential steam water from the pressure safety
relief valve is recommended to correct to the nearest drain pipe or to any nearby floor
drain.
Make sure to complete electrical work i.e. power supply, grounding, wiring and other
connection as required
7. RESOURCES
7.2 MATERIALS
7.3 MANPOWER
The required manpower shall be reassessed for each activity. In general, the following Supervision
& resources will be in deployed:
MEP Engineer
Safety Officers
Foreman and charge hands
Technician
General Labors
All delivered water heaters shall be subject to inspection and approval of the Engineer/
Consultant in line with the approved material submittal.
All water heaters shall be inspected in accordance with the approved drawings.
The Health Safety and Environment Project Management Plan institutes the overall mechanism for the
risk management processes with regard to the Project. Processes are implemented at the earliest
stages within the project cycle, identifying risk and facilitating an opportunity for the application of
appropriate mitigation strategies. As an integral part of the planning process, prior to the commencement
of any operational activity a suitable and sufficient specific assessment (RA) of the risks associated with
the works should be undertaken.
Starting instructions will be given by the supervisors at the start of each activity to explain
the methodology of works and to communicate safe working procedures to the operatives.
These talks are structured in a way to highlight to major risks involved in the activity and
the various control measures required in order to minimize the risk. It is delivered in a
manner such as the key points that will be remembered by the operatives receiving it.
Toolbox talk meetings will be held for each crew, on group or employees, regarding more
general topics of the Project HSE Policy; for example, lessons learned, near-miss reports,
implementation of the requirements and message from the LBS management or
Employers HSE personnel.
11.0 PERSONAL PROTECTIVE EQUIPMENTS
All workers will be issued and trained in the use of the required PPE equipment to comply with
contract procedures and local regulations and will be supplemented with PPE as required by MSDS
& COSHH assessments. This will include but will not be limited to;
Hard Hats
Safety Boots with ankle support and steel toe caps
Safety Goggles
High Visibility Vests / Overalls with integrated reflective strips
Hand gloves
Face Masks
A variety of mechanisms, such as method statement briefings and toolbox talks will be
implemented to ensure all relevant personnel is appropriately informed.
In addition to their safety induction received at their arrival on-site, all the workers will have a
toolbox meeting in order to be briefed about the risks of their specific work task, prior to the
start of works.
13. APPENDIX