KCM Nchanga Monthly Geological Report To GSD - July 2018
KCM Nchanga Monthly Geological Report To GSD - July 2018
During the month of April 2018, there was no reportable injury or damage to property incidents
within the Geological Services Department at Nchanga Open Pits or Underground.
2. Drilling
Infill Drilling
During the month of April 2018, no infill drilling was done at Nchanga Open Pits.
During the month of April 2018, no brownfield surface exploration drilling was done at Nchanga.
3. Dewatering
SP12
No water was pumped from sp12.
3.2 Underground
During the month of July 2018, an average volume of 74,562 m 3/day of water was pumped from the
underground. The flow measurements carried out on the total number of boreholes from the 2720L
and 3020L, both east & west was 98,818 m3/day.
4. Ore Mining
During the month under review, 39,695 tonnes of copper ore was mined from Nchanga open Pit at
an average grade of 0.90% TCU and 0.42% ASCU translating into a total of 357 tonnes of contained
copper.
COPF&D open pit ore mined amounted to 21,128 tonnes at average grades of 0.94%TCU and
0.13%ASCU; consequently, contained copper metal was 199 tonnes.
4.2 Underground
During the month of July 2018, a total of 194,291 tonnes of ore was mined at an average grade of 1.08
%TCu, 0.41 %ASCU producing 2,097 and 800 tonnes of contained and acid soluble copper respectively.