Mining Methods Underground Mining
Mining Methods Underground Mining
in Underground Mining
www.atlascopco.com
Contents
Foreword
2 Foreword by Hans Fernberg M
Sc Mining Engineering, Senior
Adviser, Atlas Copco Rock Drills AB
Talking Technically
3 Trends in underground mining
7 Geology for underground mining
13 Mineral prospecting and exploration
17 Finding the right balance in exploration drilling
21 Underground mining infrastructure
25 Principles of raise boring
29 Mechanized bolting and screening
33 Mining in steep orebodies
39 Mining in flat orebodies
43 Backfilling for safety and profit 105 High speed haulage at Stawell
46 Atlas Copco rock bolts for mining 109 Sublevel stoping at Olympic Dam
115 Improved results at Meishan iron ore mine
Case Studies
119 Mechanized mining in low headroom at Waterval
47 Innovative mining at Garpenberg 121 Large scale copper mining adapted to lower seams
53 Changing systems at Zinkgruvan 125 Underground mining of limestone and gypsum
59 Increasing outputs at LKAB iron ore mines 129 Sub level caving for chromite
63 From surface to underground at Kemi 133 Getting the best for Peñoles
69 Mining magnesite at Jelšava 137 Keeping a low profile at Panasqueira
73 All change for Asikoy copper mine
77 Mining challenge at El Soldado
Front cover: Headframe at Australia´s Golden Grove mine.
83 Pioneering mass caving at El Teniente
91 Boxhole boring at El Teniente All product names such as Boomer, Boltec, Simba, COP,
Scooptram and Swellex are registered Atlas Copco trademarks.
97 Modernization at Sierra Miranda
For machine specifications contact your local Atlas Copco
99 Mount Isa mines continues to expand Customer Center or refer to www.atlascopco.com/rock
Produced by tunnelbuilder ltd for Atlas Copco Rock Drills AB, SE-701 91 Örebro, Sweden, tel +46 19 670 -7000, fax - 7393. Publisher
Ulf Linder [email protected] Editor Mike Smith [email protected] Senior Adviser Hans Fernberg
[email protected] Picture Editor Patrik Johansson [email protected]
Contributors Marcus Eklind, Patrik Ericsson, Jan Jönsson, Mathias Lewén, Gunnar Nord, Björn Samuelsson,
all [email protected], Adriana Potts [email protected], Kyran Casteel [email protected], Magnus
Ericsson [email protected]. The editor gratefully acknowledges extracts from Underground Mining Methods
– engineering fundamentals and international case studies by William A Hustrulid and Richard L Bullock, published by SME, details
from www.smenet.org
Designed and typeset by ahrt, Örebro, Sweden Digital copies of all Atlas Copco reference editions can be ordered from the
Printed by Welins Tryckeri AB, Örebro, Sweden publisher, address above, or online at www.atlascopco.com/rock. Reproduction of
Copyright 2007 Atlas Copco Rock Drills AB. individual articles only by agreement with the publisher.
Hans Fernberg
M Sc Mining Engineering
Senior Adviser
Atlas Copco Rock Drills AB
terly wrong.
Dynamic growth in China.
Stable growth
Investments into new mines have in- Figure 1: Mining projects under construction. (Raw Materials Data 2007)
creased dramatically and all indicators
point to a continued high level of proj- M USD
ect activities during the next couple of
years, see figure 1. 30 000
25 000
Whatever the investment activities or
metal prices, the amount of metal 20 000 Trends
produced every year in global mining is
fairly stable and increasing slowly but
15 000
steadily. Total volumes of rock and ore
handled in the global mining industry Trends
10 000
amount to approximately 30,000 Mt/y.
This figure includes ore and barren rock 5 000
Metal shares of total value gold copper iron ore nickel lead zinc PGMs diamonds other
Assumptions: 10% waste in underground metal and industrial mineral operations. Strip ratio (overburden/ore) in open
pit metal operations is 2.5. The strip ratio in industrial minerals is 1.8. For coal, underground barren rock is set at 20%, and the strip
ratio in open-pit mines is 2.5. Industrial minerals includes limestone, kaolin, etc. but excludes crushed rock and other construction
materials. Salt, dimensional stones, precious stones are not included. Diamonds are included in metals.
noise and vibration, affect the miners manufacturer promotes new technolo-gies, densely populated countries has
and equipment operators. Safety de- as does competition from other suppliers. further meant that underground mining
mands have already completely In the early years of the 21st century, new is the only viable alternative. Such
changed some unit operations, such as efficient underground me-thods and developments have halted the growth
rock bolt-ing and scaling. Similar equipment have made it possible to turn of open pit mi-ning and it is projected
developments will continue. open pit mines that had become that the pre-sent ratio 1:6 underground
Customers demand higher productiv- uneconomical because of their depth into to open pit mining will continue in the
ity, and there is an increasing focus on profitable underground ope-rations. The medium term.
machine availability and simpler service orebody in these mines is usually steep
procedures in order to reduce down- dipping, and can be mined with the most Magnus Ericsson
time. Reduction of internal development efficient block caving meth-ods. The Raw Materials Group
and production costs by the equipment competition for land in some
2500 2
1.8
(%)
Copper/oreproduction metal(mt)
2000 1.6
1.4
1500 1.2
Ore grade
1
1000 0.8
0.6
500 0.4
0.2
0 0
1930 1945 1960 1975 1988 1991 1994 1997 2000
Copper production Ore production Copper ore grade
Bingham Canyon copper mine near Salt Lake City, Utah, USA.
to mine or tunnel through them, or both. mineral, but not following a crystal- Samples of common rock types
Some of these important characteris- lographically defined plane. Fracture
tics, which are also important for cor- is usually uneven in one direction or
rect mineral identification in the field another.
before chemical analysis, are hardness, Cleavage denotes the properties of
density, colour, streak, lustre, fracture, a crystal whereby it allows itself to be
cleavage and crystalline form. split along flat surfaces parallel with
The particle size, and the extent to certain formed, or otherwise crystal-
which the mineral is hydrated or other- lographically defined, surfaces. Both
wise mixed with water, can be very im- fracture and cleavage can be important
portant to the behaviour of the rock to the structure of rocks containing sub-
structure when excavated. Mineral hard- stantial amounts of the minerals con-
ness is commonly graded according to cerned. Amphibolite.
the Moh 10-point scale Properties
The density of light- coloured miner-
als is usually below 3. Exceptions are
barite or heavy spar (barium sulphate Rocks, normally comprising a mixture
– BaSO4 – density 4.5), scheelite (cal- of minerals, not only combine the prop-
cium tungstate – CaWO4 – density 6.0) erties of these minerals, but also exhibit
and cerussite (lead carbonate – PbCO4 properties resulting from the way in
– density 6.5). Dark coloured miner- which the rocks have been formed, or
als with some iron and silicate have perhaps subsequently altered by heat,
densities between 3 and 4. Metallic ore pressure and other forces in the earth’s
(0.5-1.0 mm) or dense (grain size 0.05 become fine-grained, sometimes even
mm). A granite may be coarse-grained forming glass.
(size >5 mm), medium-grained (1-5 Depending on where the magma soli-
mm) or fine-grained (0.5-1.0 mm). difies, the rock is given different names,
A rock can also be classified in even if its chemical composition is the
terms of its structure. If the mineral same, as shown in the table of main
grains are mixed in a homogeneous igneous rock types. A further subdivi-
mass, the rock is termed massive, as sion of rock types depends on the silica
with most granite. In mixed rocks, the content, with rocks of high silica con-
grains tend to be segregated in layers, tent being termed acidic, and those with
whether due to sedimentary formation lower amounts of silica termed basic.
or metamorphic action from heat The proportion of silica content can
and/or pressure. Thus, the origin of a determine the behaviour of the magma
Sandstone.
rock is also important, although rocks and lava, and hence the structures it can
of different origin may have similar produce.
structural properties such as layering.
The three classes of rock origin are: Sedimentary rocks
Igneous or magmatic: formed
from solidified lava at or near the Sedimentary rocks are formed by the
surface, or magma underground. deposition of material, by mechanical or
Sedimentary: formed by the deposi- chemical action, and its consolidation
tion of reduced material from other under the pressure of overburden. This
rocks and organic remains, or by chemi- generally increases the hardness of the
cal precipitation from salts, or similar. rock with age, depending on its mineral
Metamorphic: formed by the composition. Most commonly, sedimen-
trans-formation of igneous or tary rocks are formed by mechanical
Gneiss. action such as weathering or abrasion on
sedimentary rocks, in most cases by an
increase in pressure and heat. a rock mass, its transportation by a
Many salts, for example, are particu- medium such as flowing water or air,
larly elastic, and can absorb the shocks
of blasting without a second free face
Igneous rocks and subsequent deposition, usually in
still water. Thus, the original rock will
being cut, thereby directly influencing Igneous rocks are formed when mag-ma partially determine the characteristics of
mining method. solidifies, whether plutonic rock, deep in the sedimentary rock. Weathering or
The drillability of a rock depends the earth’s crust as it rises to the surface erosion may proceed at different rates,
on, among other things, the hardness in dykes cutting across other rock or sills as will the transportation, affected by the
of its constituent minerals, and on the following bedding planes, or volcanic, climate at the time and the nature of the
grain size and crystal form, if any. as lava or ash on the sur-face. The most original rock. These will also affect the
Quartz is one of the commonest mi- important mineral con-stituents are nature of the rock eventually formed, as
nerals in rocks. Since quartz is a very quartz and silicates of vari-ous types, but will the conditions of deposi-tion.
hard material, high quartz content in
mainly feldspars. Plutonic rocks solidify Special cases of sedimentary rock
rock can make it very hard to drill, and
slowly, and are therefore coarse-grained, include those formed by chemical depo-
will certainly cause heavy wear, par-
whilst volcanic rocks solidify sition, such as salts and limestones, and
ticularly on drill bits. This is known as
abrasion. Conversely, a rock with a high comparatively quickly and organic material such as coral and shell
content of calcite can be comparatively
easy to drill, and cause little wear on Table of main igneous rock types
Silica (SiO ) Plutonic rocks Dykes and Sills Volcanic (mainly
drill bits. As regards crystal form, 2
min-erals with high symmetry, such as content lava)
cubic galena, are easier to drill than Basic – <52% Gabbro Diabase Basalt
minerals with low symmetry, such as SiO2
amphiboles and pyroxenes. Intermediate Diorite Porphyrite Andesite
A coarse -grained structure is easier – 52-65%
to drill, and causes less wear of the drill SiO2 Syenite Syenite Trachyte porphyry
string than a fine-grained structure. Con- Acidic – >65% Quartz diorite Quartz porphyrite Dacite
sequently, rocks with essentially the SiO2 Granodiorite Granodiorite Rhyodacite
same mineral content may be very dif-
porphyry
ferent in terms of drillability. For Granite Quartz porphyry Rhyolite
example, quartzite can be fine-grained
drives within the mineral deposit, per- the existence and location of
haps of shorter life, but requiring more worthwhile minerals, but also to check
support measures. Setting aside sup-port on rock qua-lities in and around the
requirements, in general terms it would deposit. In un-derground mining,
seem beneficial to carry out as much of information from surface borehole and
the development work as pos-sible geophysical me-thods of investigation
within the mineral deposit, ma-king can be supple-mented by probe or core
development drives in non- pro-ductive drilling under-ground. The resulting
gangue rocks as short as pos-sible. vast amount of data may be too much
However, it may be decided that a major to be assessed manually, but computer
development asset, such as a shaft or software pro-grams are available to
transport level, should be in as stable a deduce the best strategies for mineral
ground area that can be found, with deposit exploi-tation. In addition, the
further drives or levels made from it. mining exper-tise of Atlas Copco is
In extreme cases, it may be found that available to help mining engineers
the mineral deposit cannot support decide, not only on the best equipment
development workings without consid- to use for investi-gation, development
erable expense. In these circumstances, and production, but also how these can
it might be better to make development be used to maximum effect.
drives near and below the mineral de- Diabase. The value of the mineral to be
posit, and exploit it with little direct en- mined will obviously be a determinant
try, such as by longhole drilling and on how much investigation work is
blasting, with the ore being drawn off desirable, but there will be a minimum
from below. level for each type of mine, in order to
Depending on the amount of distur- give some assurance of success.
bance that the mineral-bearing strata For example, lowvalue stratified
has been subjected to, the mineral de- de-posits, which are known to be
posit can vary in shape from stratified fairly uniform in thickness and have
rock at various inclinations, to highly regular dips, may not necessitate many
contorted and irregular vein bore-holes, although there could still
formations requiring a very irregular be surprises from sedimentary
development pattern. washouts or faults. On the other hand,
The latter may require small drives gold de-posits in contorted rock
to exploit valuable minerals, although formations will require frequent
the productivity of modern mining
boreholes from under-ground, as well
equipment makes larger section drives
as from the surface, to give assurance
more economic, despite the excavation
of the location of the deposit and to
of more waste rock.
sample the minerals it contains.
The tendency of a rock to fracture,
sometimes unpredictably, is also im- Rock classification
portant to determine drivage factors,
such as support requirements, and the
Granite. for drilling
charging of peripheral holes to prevent chances of mining success. There are Having determined the value and
overbreak. Although overbreak may not plenty of potential risks in underground shape of a mineral deposit, the nature
be so important in mining as in civil mining, and it is best to minimize these. and structure of the rocks that
tunnelling, it can still be a safety con- Using modern mining equipment, surround it, and the likely strategy for
sideration to prevent the excavation of there is the potential to turn the mine the mine deve-lopment, it should be
too much gangue material, and to pre- into a mineral factory. However, if un- possible to deter-mine the suitability
serve the structure of a drive. certainties manifest themselves in un- of various excava-tion methods for the
foreseen ground conditions, disap- rocks likely to be encountered.
Investigation pearing orebodies, and factors such as It will also be necessary to deter-
excessive water infiltration, then the mine which ancillary equipment may
and exploration advantage of productive mining equip- be required, and how best to fit this
It is clear that rock structures, and the ment will be lost, as it is forced to into the excavation cycle.
minerals they contain, can result in a stand idle. With drill - and-blast development
wide variety of possible mining strate- The only way to avoid these situa- drivages, for example, the rock types
gies. Obviously, the more information tions is to carry out as much exploration and structure may determine that sub-
that is gained, the better should be the work as possible, not only to investigate stantial support is required. This, in
Mineral prospecting
and exploration
Finding orebodies
For a geologist in the mining busi-
ness, exploiting an orebody is the
easy part of the job. The hardest
part is to find the orebody and de-
fine it. But how do you find these
accumulations of metallic miner-als
in the earth's crust? The mining
company has to ensure that an ore-
body is economically viable, and
needs a guarantee of ore produc-
tion over a very long period of time,
before it will engage in the heavy
investment required to set up a
mining operation. Even after pro-
duction starts, it is necessary to
locate and delineate any exten-
sions to the mineralization, and to
look for new prospects that may
replace the reserves being mined.
Investigating extensions, and
searching for new orebodies, are
vital activities for the mining
company.
Prospecting
Prospecting involves searching a district
for minerals with a view to further ope-
ration. Exploration, while it sounds si-
milar to prospecting, is the term used for
systematic examination of a deposit. It is
not easy to define the point where
prospecting turns into exploration.
A geologist prospecting a district is
looking for surface exposure of miner-
als, by observing irregularities in co-
lour, shape or rock composition. He uses
a hammer, a magnifying glass and some
Gold panning in the wind.
other simple instruments to examine trenches can be dug across the miner- the surrounding ground. Exploration is
whatever seems to be of interest. His alized area to expose the bedrock. A a term embracing geophysics, geo-
experience tells him where to look, to prospector will identify the discovery, chemistry, and also drilling into the
have the greatest chances of success. measure both width and length, and ground for obtaining samples from
Sometimes he will stumble across an- calculate the mineralized area. Rock any depth.
cient, shallow mine workings, which samples from trenches are sent to the
may be what led him to prospect that laboratory for analysis. Even when mi- Geophysical exploration
particular area in the first place. nerals show on surface, determining any
Soil-covered ground is inaccessible to extension in depth is a matter of quali- From surface, different geophysical me-
the prospector, whose first check would fied guesswork. If the prospector's thods are used to explore subsurface for-
be to look for an outcrop of the findings, and his theorizing about the mations, based on the physical proper-
mineralization. Where the ground cover probable existence of an orebody are ties of rock and metal bearing minerals
comprises a shallow layer of alluviums, solid, the next step would be to explore such as magnetism, gravity, electrical
specialities, the main one being to de- in the hole. Beyond that, the drillhole This was the accidental birth of
tect the presence of metals in the top- itself can provide a complementary core drilling, a technique now very
soil cover. By taking a large number of amount of information, particularly by widely used within the mining
samples over an extended area and logging using devices to detect industry. Core drilling is carried out
analyzing the minute contents of each physical anomalies, similar to the with special drill rigs, using a hollow
metal, regions of interest are identi- geophysical surveys mentioned above. drill string with an impregnated
fied. The area is then selected for more Core drilling is also used to define diamond cutting bit to re-sist wear
detailed studies. the size and the exact borders of minera- while drilling hard rock. The crown-
lization during the lifetime of the mine. shaped diamond bit cuts a cylindrical
Exploratory drilling This is important for determining ore core of the rock, which is caught and
grades being handled, and vital for cal- retained in a double tube core-barrel.
For a driller, all other exploration me- culating the mineral reserves that will A core-catcher is embedded in, or just
thods are like beating about the bush. keep the mine running in the future. A above, the diamond bit, to make sure
Drilling penetrates deep into the ground, that the core does not fall out of the
strategically-placed underground core
and brings up samples of whatever it tube. In order to retrieve the core, the
drill may also probe for new ore bodies
finds on its way. If there is any miner- core-barrel is taken to surface, either by
in the neighbourhood.
alization at given points far beneath the pulling up the complete drill string or, if
surface, drilling can give a straight- the appropriate equipment is being used,
forward answer, and can quantify its
Core drilling by pulling up only the inner tube of the
presence at that particular point. In 1863, the Swiss engineer M Lescot core-barrel with a special fishing device
There are two main methods of ex- designed a tube with a diamond set face, run inside the drill string at the end of a
ploratory drilling. The most common, for drilling in the Mount Cenis tunnel, thin steel wire.
core drilling, yields a solid cylinder where the rock was too hard for conven- The core is an intact sample of the
shaped sample of the ground at an tional tools. The intention was to explore un-derground geology, which can be
exact depth. Percussion drilling yields rock quality ahead of the tunnel face, exam-ined thoroughly by the geologist
a crushed sample, comprising cuttings and warn miners of possible rock falls. to determine the exact nature of the rock
from a fairly well-determined depth and any mineralization. Samples of
% rC drilling
100
80
Core drilling
60
40
20
Ratios between core and RC drilling. The figures reflect total exploration expenditures from national statistics for surface and underground.
exploration drilling will not be carried of 500 m. By sealing off the bit from the favour core drilling rigs, which are
out by the same people, so reliability rest of the hole it can be kept dry. A much lighter and more adaptable in
of information is critical. There are correct selection of shroud vs bit tol- order to be flown into remote and
many reasons why geologists should erance maintains a pressurized zone sensitive environments.
choose their drilling method carefully. around the bit. Boosted air pressure is In areas with extremely cold climates
If there is no need for continuous in- needed to meet the higher water pres- and where permafrost is present, RC
formation about the geological forma- sure on its way down the hole. In addi- drilling may have its limitations. Anti-
tion on the way down, there is no need tion, a dry bit drills faster. freeze rock drill oil can help to keep the
for samples. It is just a matter of mini- It must be remembered that infor- hammer and bottom of the hole free
mizing the drilling time. The geometry mation from a core is crucial in esti- from ice. Other purely practical issues
of the orebody is already known, and mating the period of mineralized struc- determine the choice of one or the other
just a reconfirmation of the boundaries tures. The core helps the geologist to drilling method.
is necessary. In this case, RC drilling is calculate the cost of extracting the An intelligent, balanced choice be-
an efficient method to use. mineral from the ore. Large volumes of tween the two methods is the key to
A first scanning of virgin territory is rock have to be excavated to obtain just optimal results. The geologist plays an
being done where the goal is just to a few grammes of a valuable mineral. extremely important role in finding this
obtain a preliminary indication of pos- Cores also yield geotechnical data. balance, as do the manufacturers such as
sible content. In this case, the geologist Data about slope stability can be of the Atlas Copco Geotechnical Drilling and
is not relying on any mineralized struc- highest importance. Ground Exploration, who continue to pro-vide
ture or geometry. With an evaluation conditions are naturally also of great the right tools for the job.
giving positive results, a programme of importance and may produce
core drilling is the logical way to con- questionable sam-ples if some of the Jan Jönsson
tinue in order to bring the project to a information from fissured zones is left
resource/reserve status.If the minera- behind in the hole and not collected.
lized structure is identified but the In such circum-stances, core drilling
geometry and rate of content varies, RC could be the only alternative.
drilling is used as an indicator for
ensuring continued grade control. Increased usage
The geologist wants dry and repre-
sentative samples in order to make opti-
of RC drilling
mal evaluations. RC drilling below the RC drilling is on the increase, and may
groundwater table was previously be- well account for 55% of all metres
lieved to undermine sample quality. drilled in 2008. The diagram above
Core drilling therefore remained the shows some estimated ratios between
only viable method for these depths core and RC drilling in different parts of
Today, the availability of high pressure the world in 2002. In terms of metres
compressors and hammer tools makes it drilled, RC accounts for 50% and core
possible for RC drilling to reduce costs drilling for 50%. Tradition and environ-
even for these depths. mental impact play large roles. RC rigs
These days, professional contractors are heavy, and are mounted on trucks or
Explorac 220RC.
deliver dry sampling down to depths track carriers. This fact tends to
www.atlascopco.com
Mine Infrastructure
Transport infrastructure
Production Each mining method requires a differ-
Headframe plant ent underground infrastructure, such
Settling
pond
as access drifts to sublevels, drifts for
longhole drilling, loading drawpoints,
Tailings and orepasses. Together, they form an
intricate network of openings, drifts,
ramps, shafts and raises, each with its
designated function.
The shaft is a long-lived installation,
Skip
Open pit Ventilation and may be more than 50 years old. The
shaft hoist and cage provide access to the shaft
(mined out) station, which connects with a main level
Decline
along which trains or conveyors may run.
The skip is the most efficient way to hoist
ore from underground to surface.
Materials handling may be by utility
Mined out Abandoned vehicles or locomotive-hauled trains.
level The co-ordination of train haulage with
and
backfilled shaft hoisting, from level to level, makes
Sublevel Ore the logistics of rail transport complex.
Workers in a rail-track mine are requi-
pass
Cage red to wait for cage riding until shift
Producing Main level changes, or scheduled hours, with ma-
stopes Haulage level Crusher Skip terial transport only permitted at certain
Water basin periods. Ore hoisting takes priority over
Development Internal Workshop, Ore Pump station manriding and material transport.
of stopes fuelling, bin
ramp storage Conveyor belt The Load Haul Dump (LHD) loader
Ore Skip filling introduced mines to diesel power and
rubber-tyred equipment in the 1970s.
station
Exploration Measuring Sump
This was the birth of trackless mining, a
new era in which labour was replaced by
pocket
Drilling mobile equipment throughout the mine.
Future reserves? © Atlas Copco Rock Drills AB, 2000 Maintenance workshops are now located
underground at convenient points,
usually on main levels between ramp
positions.
Basic infrastructure required for a typical underground mine. The shaft remains the mine’s main
artery, and downward development is by
places and to power drill rigs, pumps system, to remove smoke from blasting ramps to allow access for the machines.
and other machines. A compressor plant and exhaust gases from diesel-powered On newer mines, as mentioned above, a
supplies air to pneumatic rock drills and machines, and to provide fresh air for decline ramp from surface may facili-
other tools, through a network of pipes. the workers. This is normally provided tate machine movements and transport
Water reticulation is necessary in the via downcast fresh -air shafts. High- of men and materials, and may also be
mine, wherever drilling, blasting and pressure fans on surface extract exhaust used for ore transportation by truck or
mucking takes place, for dust suppres- air through the upcast shafts. Ventilation conveyor, eliminating the need for
sion and hole flushing. Both ground doors control the underground airflow, hoisting shafts.
water and flushing water are collected in passing fresh air through active work
drains, which gravitate to settling dams
and a pump station equipped with high-
areas. Polluted air is collected in a sy- Ramps and shafts
stem of exhaust airways for channelling
lift pumps to surface. Mine development involves rock excava-
back to the upcast shafts. As most of the
Air quality in mine workings must infrastructure is located on the footwall tion of vertical shafts, horizontal drifts,
be maintained at an acceptable health side of the orebody, the fresh air is inclined ramps, steep raises, crusher sta-
standard. The mine needs a ventilation normally channelled via the footwall tions, explosives magazines, fuel stores,
be used to excavate raises where there is from the machine by the use of a Gunnar Nord
limited, or no, access to the upper le-vel. muck collector and a muck chute.
In this boxhole boring method, the An alternative method to excavate Holes at breakthrough after 32 m.
machine is set up on the lower level, and box holes is to use longhole drilling with
a full diameter raise is bored upward. extremely accurate holes to enable bla-
This method is used for slot hole drill- sting in one shot. The Simba MC 6 -ITH
ing in sub level caving and block caving shown below is modified for slot dril-
methods. The cuttings are carried by ling so that the holes will closely fol-low
gravity down the raise, and are deflected each other, providing sufficient open
set up at the lower level, and a full dia- pilot hole. Stabilizers in the drill string
meter raise is bored upward. Stabilizers prevent bending.
are periodically added to the drill string The BorPak is a relatively new ma-
to reduce oscillation and bending stress- chine for blind hole boring which climbs
es. Cuttings gravitate down the hole and up the raise as it bores. It comprises a
are deflected away from the RBM at the guided boring machine, power unit,
lower level. launch tube and transporter assembly,
Blind shaft boring is used where conveyor and operator console. Cuttings
access to the lower level is limited, or pass through the centre of the machine,
impos-sible. A down reaming system down the raise and launch tube, and onto
is used, in which weights are attached the conveyor. The BorPak has the poten-
to the reamer mandrel. Stabilizers are tial to bore holes from 1.2 m to 2.0 m-
located above and below the weight diameter at angles as low as 30 degrees
stack to ensure verticality of the hole. from horizontal. It eliminates the need
Cuttings are removed using a vacuum for a drill string and provides the steer-
or reverse circulation system. ing flexibility of a raise climber.
Rotary drilling is used for holes up
Boxhole boring. to 250 mm-diameter, and is similar in Raise boring machine
concept to pilot hole drilling in that a
production. Standard RBMs are bit is attached to the drill string to The raise boring machine (RBM) pro-
capable of boring at angles between excavate the required hole size. vides the thrust and rotational forces ne-
45 degrees and 90 degrees from Down reaming involves drilling a cessary for boring, as well as the equip-
horizontal, and with minor adjustment conventional pilot hole and enlarging it ment and instruments needed to control
can actually bore at angles between 45 to the final raise diameter by reaming and monitor the process. It is composed
degrees and hori-zontal. from the upper level. Larger diameter of five major assemblies: the derrick; the
A whole host of methods of mechani- raises are achieved by reaming the pilot hydraulic, lubrication, and electrical
cal raise and shaft excavation have been hole conventionally, and then enlarging systems; and the control console.
developed around the use of the RBM. it by down reaming. The down reamer is The derrick assembly supplies the ro-
These include boxhole boring, blind fitted with a non-rotating gripper and tational and thrust forces necessary to
thrust system, and a torque-multiply-ing turn the pilot bit and reamer, as well as
shaft boring, rotary drilling, down rea-
gearbox driven by the drill string. Upper to raise and lower the drill string. Base-
ming, pilot up/ream down, pilot down/
and lower stabilizers are installed to plates, mainframe, columns and head-
ream down, hole opening, and BorPak.
ensure correct kerf cutting and to re- frame provide the mounting structure for
Alternative duce oscillation. the boring assembly. Hydraulic cy-
Pilot up/ream down was a predeces- linders provide the thrust required for
boring methods sor of modern raise boring techniques lowering and lifting the drillstring, and
Boxhole boring is used to excavate raises using standard drilling rigs. Pilot down/ for drilling and reaming. The drive train
where there is limited access, or no access ream down, or hole opening, employs a assembly, comprising crosshead, main
at all, to the upper level. The machine is small diameter reamer to follow the drive motor, and gearbox, supplies the
rotational power to the drill string and employing a planetary reduction for its
Acknowledgements
compactness. The hydraulic power This article has been prepared using
cutting components.
unit is skid- mounted, and comprises The Raise Boring Handbook, Second
Four types of main drive motor the ne-cessary reservoir, motors, Edition, researched and compiled by
systems are available: pumps, valves, filters and manifolds. Scott Antonich, as its main reference.
AC, DC, hydraulic and VF. The gearbox The lubrication system ensures
mounts directly to the main drive motors, proper delivery of lubricating oil to the
Ever since the first Robbins raise drill was built in 1962, it
has been a constant success. By meeting customer needs
through innovation, reliability and an unrivalled product
range, we have gained the lion’s share of the global market
– and we intend to keep it that way!
www.raiseboring.com
Mechanized Bolting
Significant improvements
Mechanized cablebolting with Cabletec LC.
Long-hole
Sublevel open stoping drilling and
blasting
Sublevel open stoping (SLOS) is used
for mining mineral deposits with: steep
dip where the footwall inclination exce-
eds the angle of repose; stable rock in
both hanging wall and footwall; compe-
tent ore and host rock; and regular ore
Stope
boundaries. SLOS recovers the ore in
large open stopes, which are normally
backfilled to enable recovery of pillars.
The orebody is divided into separate
stopes, between which ore sections are
set aside for pillars to support the roof
and the hanging wall. Pillars are nor-
Blasted ore
mally shaped as vertical beams, across
Undercut
the orebody. Horizontal sections of ore
are also left as crown pillars.
Miners want the largest possible
sto-pes, to obtain the highest mining
effi-ciency, subject to the stability of Transport drift
Loading
the rock mass. This limits their design Draw point crosscut
dimen-sions.
Shrinkage stoping
In shrinkage stoping, traditionally a
common mining method, ore is excavated
in horizontal slices, starting from the stope
bottom and advancing upwards. Part of the
Drill
overcut blasted ore is left in the stope, to serve as a
working platform, and to give support to
the stope walls.
Crater Blasting swells the ore by about 50%,
blasting Primary stope no2
charges undercut and drilling
which means that a substantial amount
done has to be left in the stope until mining
Primary sto pe no1 has reached the top section, following
in production
100
Typical ore/waste ly using an upwards raise to provide ini-
= 100%
80
ratio during tial expansion, and mining then retreats
a mucking cycle. toward the footwall. Adjacent crosscuts
Ore volume in slice
60
are mined at a similar pace, with upper
ore
www.atlascopco.com
flat Mining
Complete package
Hanging wall Atlas Copco offers three key mining
(The Venstop formation) Strike
tools to provide the total solution for
Dip low seam mining applications: drill
Limestone
(The Steinvika formation) rigs, loaders and bolting rigs. These
are all compact and technically ad-
vanced low profile versions, specially
designed for efficient production in
crosscut
crosscut
rigorous underground locations: the
drift
bench
Rocket Boomer S1 L face drilling rig is
bench
Horisontal benching benching
adapted to this specific type of mining,
approx. 40 m
with a coverage area between 6 and 29
pill sq m in a tramming height as low as 1.3
ar 8
m; the Boltec SL bolt-ing rig carrier,
Foot wall m drift
(The Fossum formation) Dip boom and bolting unit have been
designed for efficient ope-ration in roof
13 -20 o
heights between 1.8 and 2.5 m; and the
Scooptram ST600LP can operate safely
in 1.8 m headroom as one of a range of
loaders of vari-
Room and pillar with benching at Dalen mine, Norway. ous capacities.
in terms of mechanization. In the coal as thin as 1.0 m, which constitutes a
mine, shearers shuttle back and forth along great challenge for equipment manufac-
the face, cutting coal and depositing it on turers to mechanize. Pillars of timber or
chain conveyors. The gold reef con- concrete are installed to support the roof
glomerate is much harder, and difficult to in the very deep mines.
tackle. South Africa gold mines have
developed their own techniques, using Hans Fernberg
handheld pneumatic rock drills in reefs
Slashing holes
Blasting barricade
Rocket Boomer S1 L, the rear view.
Transport
drift
Pillars of timber/concrete to
support roof
Scraper
©
Atlas Copco
Rock
Drills
AB, 200
Scooptram ST600LP.
www.atlascopco.com
Backfilling
CAF fill
CAF fill
Tertiary
Secondary
Primary
Primary
Secondary
Unmined
Unmined
Unmined
Unmined
Unmined
Designed stopes
Unmined
Unmined
Primary stope extracted
ROCK fill CAF filled due to unmined adjacent stopes
CAF fill 2nd Primary stope extracted
CAF filled due to adjacent unmined stopes
ROCK fill
Unmined
Unmined
on the design, as do the fill mix and The first hydraulic fills were com-
strength attainable using available ma-
Hydraulic fill posed of concentrator tailings that
terials. Fill quantities will determine Originally, backfill comprised waste would otherwise have been deposited
the size of the preparation and rock, either from development or hand on the surface. The mill tailings were
placement systems, and the location picked from broken ore. Some larger cycloned to remove slimes so that the
and eleva-tion of stope openings mines in the US quarried rock and gra- contained water would decant.
relative to sur-face facilities such as vitated it down fill raises to the mine This fill was transported under-
tailing dams and concentrator are workings. ground as slurry, composed of around
major considerations. Mine planners Nowadays, rock fill is used for fil- 55% solids, which is the typical under-
focus on tailormade fill to save cement ling secondary and tertiary stopes, and flow for thickeners and is the pulp
costs by strengthening the fill only is usually a convenient and econo-mic den-sity normally used for surface
where it is required, close to the stopes means of disposal for waste from tailings lines.
to be mined, such as at Olympic Dam. When the grind from the mill was too
development.
fine for decanting in the stopes, alluvial
Underhand cut and fill mining sequence. sand was employed instead of tailings.
Particles of alluvial sand are naturally
rounded, enabling a higher content to
Hydraulic fill
be pumped than for hydraulic fill
Low cement
made from cycloned tailings. This
content type of fill is commonly referred to as
Slice 1 sand fill. Many mines still employ
non-cemented hydraulic fill,
particularly for filling ter-tiary stopes.
High cement
Cyclone
Thickener
Vacuum filter
Mixer
Paste pump
Swellex
The Swellex concept entails that the rock is secured by immediate and
full support action from the Swellex bolts. The moment the Swellex
bolt is expanded in the hole, it interacts with the rock to maintain its
integrity. The quality of the bolt installation is auto-matically confirmed
when the pump stops, and is independent of rock mass conditions or
operator experience. Controllability means safety! The Swellex
rockbolts are designed to optimize the effective-ness of each bolt, so
the bolting operation matches the required safety levels as planned by
the engineers. See pictures to the left.
Roofex
Roofex features a high quality steel bar inside a smooth plastic shea-
thing which is fixed inside the borehole with cement or resin grout.
The bolt also has an energy absorber which functions as a sliding
element over the steel bar. This allows the bolt to extend outwards
during sudden displacements such as rock burst or seismic events while
still providing constant load capacity. This capability makes the Roofex
rock bolt especially suitable for developing new, deep underground
excavations in poor quality rock or in areas where rock burst or sei-
smic events are frequent. The bolt can be produced in standard lengths
typically used in mining and tunnelling, and the displacement capa-
city can be pre-selected during manufacture. See picture below.
Mathias Lewén
Pre-calculated Pre-calculated
maximum maximum
deformation deformation
Roofex at
1.
installation
Energy
2.
absorbing
phase
Roofex at
3. max load
and max
deformation
Energy absorber
(a sliding element)
46 underground mining methods
Garpenberg, Sweden
500-785 Z 500-
Finnhyttan
Tyskgården 800 Z Gransjön
700-
800 Z Kaspersbo 800 Z
1000 Z 870 Z
910 Z
Kanal Ore Strand Ore ? 925-1100 Z
Potential
1200 Z Dammsjön Kvarnberget 1100- 1000 -1300 Z 1200 Z
1400 Z
1600 Y 2000 Y 2400 Y 2800 Y 3200 Y 3600 Y 4000 Y 4400 Y 4800 Y 5200 Y
Production levels
Sublevel stoping
at Lappberget
The geological and geotechnical char-
acteristics of significant portions of the Sublevel stoping layout and mining sequence for Lappberget orebody.
newly-discovered orebodies allow mi-
ning using more productive longhole concentrator capacity to 1.2 Mt/y; of development muck have to be accom-
methods instead of cut-and-fill. Lapp- designing and building a paste fill pro- modated underground as hoisting facili-
berget ore, for instance, can be 60 m-wide duction/distribution system; and start- ties are used for ore only.
through considerable vertical distances, ing longhole drilling. This latter The method can be described as a
and has proved to be suitable for sub-level modified sublevel stoping with succes-
project involved rill mining in the
stoping using a system of primary and sive back fill as mining is progressing.
Tyskgården orebody, followed by
secondary stopes progressing up-wards. The 10 m-wide cut- off slots are drilled
sublevel stoping in Lappberget.
Primary stopes are 15 m -wide and 40 m- across the orebody using up -holes and
high and filled with paste made from blasted in one single firing, starting from
concentrator tailings mixed with about 5%
Rill mining the centre. Seven 127 mm holes are left
cement. The 20 m-wide secondary stopes A special mining method known as rill uncharged to provide sufficient expan-
are filled with devel-opment muck without mining has been developed for excavating sion for the remaining 64 mm holes.
cement. High pre-cision drilling is After the slot has been opened, 70 de-
the Tyskgården orebody. The orebody is
necessary to get opti-mum ore recovery
relatively small, and large quantities grees up -holes fans consisting of eight,
and fragmentation.
This mining method can possibly be
Development and primary stoping layout 1080 level.
used in parts of the Kaspersbo orebody,
if rock quality is high enough. This will
help with cost control, which is crucial
for mining in Sweden. With Lappberget
alone containing 5.46 Mt of the current
reserves, grading over 7% zinc and 2.6%
lead, plus silver and gold, it is no sur-
prise that present development activities
focus on using longhole-based produc-
tion from these orebodies to raise total
metal-in-concentrate output. Presently
eight orebodies are being exploited.
Garpenberg has generated a strategic
plan for 2006–2019 allocating SEK 1
billion for developing Lappberget. The
overall programme includes: increasing
Refill of waste
One fan
Max
2m
App
c
5m1.x
ea
8
holes
Blasted ore
m .15Approx
3 blast
fans in
off slot in
Cut Waste one
h
fan Ø
1
m 70
.
8 mm
70°
45°
approximately 17 m-long, holes are available, with a limited amount of might double the amount of
blasted into the void. Three rows having truck ore haulage to surface possible.
investment initially planned.
a total of 24 holes are blasted simulta- And, although flotation capacity has
been improved, concentrator through-
neously. After mucking out each blast, New drilling technology
new waste is discharged into the stope put is now limited to the same sort of
forming a 45 degrees rill down into the tonnage by grinding mill capacity. Atlas Copco has supplied drilling equip-
drawpoint. As the waste material will Assuming demand for Garpenberg ment to Boliden’s underground mines
stay quite stable at 45 degrees rill angle, con-centrates increases in the near for many years. Recently, the company
term, it will be necessary for New has worked particularly closely with
the risk of ore dilution is negligible.
Boliden to decide whether to increase Garpenberg on the development of
hoisting capacity.
Output limitations Developing the now-available reserves
computer-based technology for more
precise drilling and blasting to enhance
The total mine output is restricted to for higher long-term production using ad- productivity and reduce ore dilution and
the 1.2-1.3 Mt/y hoisting capacity ditional hoisting and processing capacity operating costs.
Headframe at Garpenberg.
Rib
pillar Rib
Ore outline pillar
Rib
pillar
A 7 9
Plan view of typical bottom drawpoint level 8
11 4
Drill level 3
(for below)
6
10
Cable bolts Development level 5 2
(for above)
1
45 m
Drawpoint level
(shown in plan view)
Paste fill
Hydraulic fill was introduced to Zink-
gruvan in the early 1970s when the new
mill was built, and was used success-
fully for many years. However, during
the transition to sub-level open stoping,
difficulties arose in sealing the open
stopes when using hydraulic fill. The
bulkheads could not be sealed against
the cracked rock in the draw points, and
there was also seepage through cracked Rocket Boomer M2 C developing the sublevels.
pillars. Because of the difficulties of
managing the fill, certain stopes have
not been filled, as the risk of fill col- Paste fill specifications
lapsing is greater than the chances of a Nygruvan Burkland
hanging wall collapsing in the open Primary stope 4 % cement 6 % cement
stopes. Secondary stope 1.5 % cement 2 % cement
Alternatives that were studied includ-
Slump 150-180 mm 200-250 mm
ed hydraulic fill, with cement for about
50% solidity; paste fill, with cement for
70-76% solidity; and high-density fill, for paste fill in the two orebodies shown Paste fill is transported to the 350 m-
with cement for greater than 76% solid- in the table above. level of the mine through two boreholes,
ity. Paste fill with cement was selected
for longhole open stoping with primary Plan of stope extraction level.
and secondary stopes. Investments P Ore outline
required in the paste plant, and for pipe
installations underground, reached about
45 million SEK. Golder Paste S P
Technology, together with Zinkgruvan S P = Primary
personnel, handled the design, construc- Ore drive
tion and building. P S = Secondary
S P
Stope design criteria
Ore shaft S
The design of stope sizes was based
Waste shaft
on the developed levels in the P
Burkland ore. The paste fill is Ventilation
horizontally trans-ported 1.4 km in
order to reach these stopes, so has to Transport drift
be pumpable. The fill also has to have Ramp Footwall drive
a minimum strength of 0.35 Mpa, to
handle a free- standing height of 40 m.
The uni-axial pressure test and pump-
ability test resulted in the specifications
Rock reinforcement
The mine installs up to 20,000 resin
an-chored rockbolts each year, and,
having upgraded its production
process, found that bolting became the
new bottleneck. After prolonged
testing of the latest Atlas Copco
Boltec LC, they ordered two units.
Using these machines, the working
environment for the bolting operatives
has improved immeasurably, since the
continuous manual handling of resin
cartridges has been eliminated. The
Boltec LC is a fully mechanized rock-
bolting rig, with computer-based control
system for high productivity and preci-
sion. The Zinkgruvan models feature a
new type of magazine holding 80 resin
cartridges, sufficient for installation of
16 rockbolts. It is equipped with a
stinger, which applies constant pressure
to keep it stable at the hole during the
Boltec LC installing rockbolts in a development drift. entire installation process. The operator
can select the number of resin cartridges
a 165 mm hole for gravitating into Ny- ratio in the paste fill, with a view to to be shot into the hole, for which the
gruvan, and a 300 mm hole for pumping blow capacity is excellent.
reducing the amount of cement used.
under high pressure into Burkland. The Rig Control System (RCS) fea-
The fill is transported through 6 in tures an interactive operator control
steel pipes along the distribution
Lower development
panel, with full -colour display of the
levels, connected by plastic pipes into In order to mine below the 800 m level, computer-based drilling system. Auto-
the stopes. the mine uses three Kiruna Electric matic functions in the drilling process,
Advantages of longhole open stoping trucks for ore and waste haulage to the such as auto-collaring and anti-jamming
with paste fill are: improved working main crusher. A Simba M4C longhole protection, as well as improved regula-
environment for all underground activi- drill rig is used on production, drilling tion of the rock drill, provide high per-
ties with regards to exposure of open up to 40 m-long x 76 mm or 89 mm- formance and outstanding drill steel
stopes and backfill; reduced pillar diameter blastholes. The machine pro- economy. There is integrated diagnos-tic
reservation, leading to increased ore duces some 50,000 drillmetres/year, and fault location, and a distributed
reserves; increased flexibility, with more while an older Simba 1357 drills a simi- hydraulic system, with fewer and shorter
stopes in simultaneous production and lar number of metres in the 51- 64 mm hoses for increased availability. Data
lower grade fluctuation; all tailings can range. The mine is so impressed with the transfer is by PC- card, which also
be used; no bulkheads required; reduced stability of the Simba M4C rotation unit allows service engineers to store opti-
drainage water; and possibility of filling that it has had an old Simba 1354 rebuilt mal drill settings.
abandoned stopes. to incorporate the same unit. A new The MBU bolting unit on the Boltec
Disadvantages are: higher costs Simba M7C handles the cable bolt LC features a single feed system, uti-
than conventional hydraulic fill; and drilling. The drilling consumables are lizing a cradle indexer at the rear end,
plugged fill pipes and drill holes supplied by Atlas Copco Secoroc under and a robust drill steel support plus
require more effort. contract. The ramp will be driven from indexer for grouting at the top end. It is
The long-term focus is directed to- the current 980 m to the 1,100 m level. equipped with a low-mounted magazine
wards optimization of the water/cement An Atlas Copco Rocket Boomer L2 C for 10 bolts, designed for maximum
www.atlascopco.com
Kiruna, Sweden
Increasing outputs at
LKAB iron ore mines
1910 1900 Nivå m
Mining of the
0
Kirunavaara orebody 1920 Ore beneficiation plant
1930 142
1940
1950
1960 Railway to Narvik port 230
1965 275
320
1970
1980 420
1990 540
Skip hoisting
1060 m Crusher
1365 m New haulage level 1175
1365
Crusher
Increasing outputs
From their control rooms, the LKAB
ope-rators run several drill rigs out in the
pro-duction areas via remote control.
The fans are drilled forwards, 10 degrees
off vertical, generally with a burden of 3
m, although a 3.5 m burden is used in
some parts of the Malmberget mine.
Pumped emulsion and Nonel detonators
are the standard explosives.
Kiruna mine is aiming to achieve one
Simba W6 C drilling upholes at Kiruna mine. million metres of production drilling in
2007. Malmberget, on the other hand, is
LKAB performance, increasing output from its 2007 base of 16 million t to going for 0.6 million metres. But both
by 40%. In 2007, Kiruna will extract will need to increase their capacity in
17 million t in 2012.
around 27 million t of crude ore, with a order to maintain and increase the buffer
between production drilling and loading.
plan to increase to 30 million t in 2009. Optimizing ore recovery
Malmberget’s plan is less ambitious, but It was in 2005 that LKAB took the
The Kiruna orebody is a single large decision to install three Simba W6 C
significant, in moving production up
slice of magnetite about 4 km-long and units which are modified versions of
Setting up a Simba W6 C for production drilling.
80 m-wide, extending to a depth of 2 km the Simba L6 C. Two of these are
with a dip of around 60 degrees. Sub- designed for optimized production
level caving is used, drilling upward drilling at Kiruna Mine with the
fans of 115 mm- diameter holes. The Wassara water hammer.
method lends itself to a high degree of The third, a Simba W6 C Slot, was
automa-tion, resulting in high redesigned for optimized up -hole slot
productivity. LKAB is constantly drilling in the Malmberget mine. This
striving to mini-mize ore losses and rig has the ability to drill production
waste dilution, seeking the best holes around the slot, with the added
combination to achieve optimum results. benefit of drilling parallel rings from the
Under investigation are: analysis of same set-up with a burden of 500 mm.
the positive effects of accurate drilling The criteria from LKAB were high
on ore recovery rates, waste dilution and productivity, efficiency and accuracy.
fragmentation; the impact of alternative The rigs in the Kiruna mine will have
drill fan configurations and hole burdens to drill 60 m-long holes in order to
on mucking and operating costs; and the meet future targets.
optimum distance between levels. Such long holes have to be very
All agree on one thing: straight, ac- straight, and with the new rigs LKAB
curate holes which reach their preplan- has high expectations for both produc-
ned target points are vital, because hole tion rates and precision, with the flex-
deviation has a negative impact on all ibility of being able to run the rigs
aspects of the production operation.
manually as well as automatically. The
Thanks to the improving ability to
Wassara hammer has the advantage that
drill straight holes, LKAB has been it does not leak oil into the environment.
43
Groups of ore passes 38
1048 m
34
29
25
20
16
11
For each of the Simba W6 C rigs rate drops with hole depth, and the to an existing network system via
LKAB has set targets of 80,000 drill- risk of deviation increases. LAN or WLAN. RRA is used for
metres/year. Since October 2006, the All of the rigs have drill tube maga- remote su-pervision when drilling
two drill rigs at Kiruna have achieved zines which are sufficient for drilling unmanned in full fan automation, as
65,000 and just over 70,000 drillme- the required hole lengths, thereby well as for transfer-ring drill plans and
tres/year respectively, with an average eliminat-ing the need for manual log files and hand-ling messages from
monthly performance of 10,000 drill- addition of tu-bes. They are also the rigs' control systems.
metres. equipped with a PC-based Rig Control If manual operation is preferred, the
System (RCS) specially designed for rig cabin offers a good working
Alternative configurations ITH applications. The new water environ-ment with vibration damping
pump system reduces water spillage and noise insulation.
The rigs drill alternative configurations and lowers the overall cost. The pump The LKAB rigs are working with
with holes 15-58 m long. The fans are pressure control has been modified to ABC Total, the highest level of auto-
spaced at three metre intervals, and any optimize hammer efficiency. mation, facilitating drilling a full fan in
deviation of more than 2% might cause With increased automation and re- automatic mode with only some initial
the fans to overlap. The average pene- duced manning there is a growing need steps needed from the operator. Within
tration rate is 0.65 m/min over the entire for remote surveillance. Atlas Copco's the ABC Total package, there is also the
hole, which can be compared to top- Rig Remote Access (RRA) interface possibility to drill manually or with one
hammer drilling where the penetration allows the user to connect the drill rig -hole automatics if preferred. The
The Wassara W 100 hammer on the Simba W6 gives good penetration and, as it is water-powered, does not release any oil into the air.
automatic systems also enable the rigs to better fit in with LKAB schedules. problems. As a result Atlas Copco is
to run unmanned during shift changes, Another was to move the service
seen by LKAB as safe and reliable.
centre for the team of 18 service and
lunch breaks and night shifts.
mainte-nance staff from underground Acknowledgements
to sur-face.
Service agreements LKAB confirms that the improve-ments Atlas Copco is grateful to the manage-
Both LKAB mines have full service have had the desired effect, with more ments of Kiruna and Malmberget
agreements with Atlas Copco, who pro- consistent maintenance. Regular meetings, mines for their assistance in the
vide continuous preventive maintenance
for their fleet of 20 rigs. Under the terms
spontaneous as well as planned, ensure a production of this article.
of the agreement, Atlas Copco runs a more structured approach to
thorough check on each rig at the rate of
All on the same team: From the left, Robert Wetterborn, Construction Supervisor, Mining Dept. at LKAB, Patrik
one per week. The agreement, which
Kansa, Atlas Copco Service Manager and Roger Lärkmo, Production Manager, Production Drilling at LKAB.
is based on the number of metres
drilled, also includes the supply of all
spare parts. Only genuine Atlas Copco
parts are used on contract
maintenance, guar-anteeing longer
service life and greater availability.
The availability target is 92%, and
penalties are payable on underper-
formance, with bonuses awarded if the
targets are exceeded. LKAB is pleased
with the agreements and the way they
have been designed, feeling they can let
go of the maintenance responsibility and
concentrate on drilling.
Many changes have been introduced
to ensure communication between mine
and manufacturer on a regular basis,
resulting in a mutual approach to prob-
lem solving with a focus on proactive
and preventive maintenance.
One of the most important changes
was to reorganize the service intervals
Underground production
Trial stopes in three areas accessed
from the 275 m and 300 m levels were
mined to determine the parameters of Rocket Boomer L2 C is used for sublevel development.
the bench cut-and-fill technique to be
used. These had a width of 15 m, and expand the smelting operation. Rig Control System RCS, mounts the
were 30 -40 m-long, with 25,000 Budgeted cost for mine development latest Swellex HC1 pump, for bolt infla-
-30,000 t of ore apiece. Both uphole and tion at 300 bar pressure, and reports
down-hole drilling methods were tested, is EUR70 million.
progress on the operator’s screen.
and 51 mm-diameter downholes selected The HC1 hydraulic pump is robust,
as being the safest. Rock reinforcement simple, and with low maintenance cost.
For production purposes, 25 m-high 2.4 m-long Swellex Mn12 bolts are used Coupled to an intelligent system, it rea-
transverse stopes are laid out, with cable
for support in ore contact formations. ches the 300 bar pressure level quickly,
bolt and mesh support to minimize dilu-
These are being installed at a rate of 80- and maintains it for the minimum time
tion. Primary stopes are 15 m-wide, and
secondary stopes 20 m-wide. Cemented 120 bolts/shift using an Atlas Copco for perfect installation. Combined with
fill, using furnace slag from an iron ore Boltec LC rig, which is returning drilling the rig’s RCS system, the pump can
smelter and fly ash from local power penetration rates of 3.2 to 4 m/min. The confirm the number of bolts successfully
stations, is placed in the primary stopes, Boltec LC rig, featuring Atlas Copco installed and warn of any problems
while the secondary stopes will be back-
Stoping sequence at Kemi mine.
filled with mine waste rock. The pri-
mary stopes are being extracted one or
two levels above the secondary stopes.
Mining sublevels with 5 m x 5 m cross
sections are being established at 25 m
vertical intervals, using an Atlas Copco
Rocket Boomer L2 C drill rig equipped
with COP 1838ME rock drills and 5 m-
long Secoroc steel and bits. Rounds of 60-
80 holes take about 2 hours to drill, charge
and prime. An emulsion charging truck
with elevating platform and Atlas Copco
GA15 compressor provides fast and
efficient explosives delivery. The footwall
granite is very competent, but lots of rock
reinforcement is required in the weaker
host rock, where all drives are
systematically rock bolted and secu-red
with steel fibre reinforced shotcrete.
The planned nominal capacity is
2.7 million t/y of ore, which allows for
increased ferrochrome production at
Tornio when Outokumpu decides to
400 m a.s.
1 2 5 6
323 m
3
Idealised section of the mining operations and process plant at SMZ (Industrial Minerals).
diabase, comprises graphitic slate, 1,000 m-wide and 400 m-thick, but is source of ferric magnesium, this being
bench-like dolomite, and the dolomite irregular in shape and contains cavities one reason why it is imported by con-
which hosts the magnesite. Graphitic often filled with ochre. However, it is sumers so far away. SMZ estimates a
slate also overlies the dolomite. structurally sound, to the extent that it reserve sufficient for 150 years’
Magnesite formation has been dated could be mined with pillar support and mining at the present production rate
at 320 million years and the mechanism no rock reinforcement. The raw mag- of 1.2 mil-lion t/y.
is thought to have been hydrothermal nesite analyses 36-44% MgO, 48 -50%
alteration of a fine-grained Carboni- CO2, 0.1-12% CaO, 0-2.3% SiO 2 and Room and pillar
ferous limestone bioherm. The orebody 3.2- 6% Fe2O3 . The specific mineral-
Around 35% of the ore is mined by the
is estimated to be 4,000 m-long, ogy makes Jelšava magnesite a unique room and pillar method in blocks which
are up to 100 m-long, 50 m-high and 30
Sequence of room and pillar mining.
m-wide, with 10 m-wide pillars along
the short and long walls of the chamber,
and a crown pillar at the top. Within
2
these blocks, it is impossible to avoid
mining some lower grade material, and
this is stored in surface dumps.
4
Parallel uphole and inclined hole
drilling up to 30 m was initially used
3
for blasting the chambers, but the
mine later switched to fan drilling in
order to achieve better mining
efficiency and safety.
6 This method again allows the mining
of long, high blocks of magnesite up to
5
200 m x 300 m x 60 m, mined in up to
1 five ascending slices.
The technique provides much greater
1. Fresh air ventilation raises 2. Exhaust airways 3. Ore passes stability in the rock mass because, not
4. Re-fill raises 5. Pillars 6. Re-fill
only are the rooms lower at 4.8 m to
Pillar
Front New level development
pillar
between In 2000-2001 SMZ started to develop a
stopes
boundary
new mining level at 220 m asl. Whereas
pillar extraction had thus far all been above
pe
Open sto
the local erosion base level, providing
cut natural drainage at 287 m asl, this new
cross
s level is below the water table. The am-
loading drift
wit
h port ount of water to be pumped out is equal
trans
Pillar to the amount of ore to be extracted.
and
For initially driving the access ramp,
and later development, plus some pro-
duction drilling, Atlas Copco offered
SMZ a new Rocket Boomer M2 C twin-
boom rig, and helped train six Simba
Overhand stoping room and pillar system at SMZ.
operators to use it.
5.0 m-high, but also the voids are filled, rock drill. This rig achieved the expect- Work on the ramp and some lateral
providing a bench for drilling the next ed performance improvement, and was development started in 2001 and was
slice as mining proceeds up each block. bought by SMZ, together with a Rocket scheduled to take 3-4 years. The Rocket
Pillars are 5 m x 5 m at 12 m spacing. Boomer 281 and a Simba H357, for pre- Boomer M2 C normally works either
The smaller rooms allow more selective cise and rapid pillar recovery. The latter one or two of the mine’s three eight-hour
mining, producing a higher proportion unit was equipped with a COP 1838 shifts on the ramp, but also works on
of processable magnesite, while the 4.4 rock drill. Switching from pneumatic to production. The new level will be
million t of waste material dumped on hy-draulic drilling using the two Rocket
worked in 10 m-high slices, improving
surface during chamber mining can now Boomers increased overhand stoping
geotechnical conditions and saving on
be used as fill. The fill rate is up to magnesite output by a factor of four.
primary development costs. However,
300,000 t/y. In the overhand stoped sections muck
although many blocks of high quality
In 1971, a new rail haulage was in- is loaded by a fleet of three LHDs and magnesite are directly accessible using
stalled, equipped with locomotives two wheel loaders. The LHDs typically overhand stoping from the new level,
and 20 t -capacity bottom -dump
wagons. The rail system still handles Rocket Boomer 281 drilling a crosscut entry.
ore from the core area of the mine, but
it is more cost effective to use truck
haulage from more peripheral parts.
Overhand stoping
Chamber and pillar mining has created
a huge void within the mine, now
total-ling 13 million cu m, and
undercut sec-tions of the hanging wall
have collapsed in places.
Studies resulted in an overhand stop-
ing method being introduced in some of
the mining blocks above the 323 m level
from 1990 onwards, and this now
accounts for 65% of production.
By 1998, SMZ was looking to increase
production and productivity in the over-
hand stoping blocks. In consultation with
Atlas Copco, the mine trialled a Rocket
Boomer 282 equipped with a COP 1432
Graphitic slate
Magnesite
Dolomite
Bench-like dolomite
Diabase
Ochre
some ore is located between access approximately 700,000 t. Back in 2001, Including the units at SMZ, ISOP
levels, some is distant from the core chamber and pillar mining supplied presently supports nine Atlas Copco
facili-ties, and some occurs as layers too 430,000 t, overhand stoping 705,000 t underground drill rigs in mines. Other
thin for overhand stoping. Extraction and development 28,000 t. By 2002, customers include Siderit, which has
tech-nology for all these various sources 70% of drill/blast production came from two Boomer H104 drill rigs and several
will require new drilling, loading and overhand stoping with the Rocket Atlas Copco hydraulic breakers work-
hauling equipment. Boomers, 20% from pneumatic drilling ing at its iron-manganese ore mine at
Although the new mining level is be- in chamber and pillar sections, and 10% Nižná Slaná, not far from Jelšava.
low the rail haulage, and ore will prob- from pillar recovery with the Simba ISOP modified these Boomer H104 rigs
ably be delivered directly to the primary H357. The improvement in average at the workshop in Zvolen so they could
grade achieved by the more selective work as longhole drilling rigs. Siderit
crusher, SMZ expects the rail system to
delivers ore to the US Steel plant in
remain in use for another 10 years. over-hand stoping with hydraulic drills
Košice, and to the Novy Huta works at
has increased the output of clinker,
Ostrava in the Czech Republic.
Grade improvement despite lower gross output.
There are also six Atlas Copco sur-
Secoroc equipment supplied through Atlas Copco face drilling rigs in the country, five of
ISOP is used for the Atlas Copco rigs which are DTH machines and the sixth a
at Jelšava. Despite the very abrasive
representation
Coprod-fitted hydraulic rig. This latter
nature of the magnesite, bit life ranges Atlas Copco has a Customer Center in machine yields 500,000 t/y limestone for
from 600 m to 1,500 m. The three Prague, serving the Czech Republic and
supply to US Steel Košice.
Rocket Boomers use 51 mm bits, and adjacent countries. In 1992 ISOP, based
the Simba H357 drills with 64 -65 mm at Zvolen in the centre of the country, Acknowledgements
bits. The mine does 80% of its blasting was appointed as its sole distributor in
with ANFO, and uses plastic explosive Slovakia. The Rocket Boomer 282 Atlas Copco is grateful to the manage-
for wet holes. provided for trials in 1998 was the first ment of SMZ for its assistance with
Of the annual mine production of two boom hydraulic rig supplied to a the production of this article.
1.2 million t, around 1.16 million t is Slovakian mine, and the Rocket Boomer
magnesite, and concentrate output is M2 C was also a first.
Access
The vehicle access adit is horizontal,
and connects with the spiral ramp
developed in the footwall of the
orebody down to the sump level. The
orebody, which dips at between 45 and
60 degrees, is accessed from the ramp,
along levels spaced at 12 m vertical
intervals.
The 20 sq m oval-plan spiral ramp
was driven at 5-7 degrees from 932 m
level to 792 m level by hand between
1998 and 2000 using Atlas Copco BBC
16W pneumatic rock drills with jack-
legs. This work was carried out under
Development
An Atlas Copco Rocket Boomer 282
equipped with COP 1838ME rock
drills is used to develop the ore and
waste drifts.
The Rocket Boomer has one extend-ing
boom to facilitate drilling off the first
rounds in strike drifts at right angles.
Drill hole diameter is 45 mm, and
hole length 3.5 m. The mine has
conducted trials of bits from differ-ent
manufacturers, and has settled on
Secoroc as the most cost-effec-tive.
Around 250 m/month of drivage is
required to keep pace with the stopes,
all of which are mined on the retreat.
Filling
HW HW
sublevels, and the extraction drives are located in Samsun, along the Black There are 140 men on the mine. In total,
4.5 m-high. The latest stope, which thirteen engineers have been employed
Sea coast, and to export markets.
lies between 894 m and 912 m levels, for production and engineering. Atlas
has a height of 12 m, and this larger Training Copco has a maintenance contract for its
dimen-sion will be increasingly used. equipment at the mine, and provides a
This is the first mining operation where
workshop container manned by a fitter.
SFTA has been involved and, being the
Rock handling
only Turkish-operated mechanized mine,
The 2.5 m-diameter main orepasses are the company takes education and
also longhole drilled using the Rocket
Acknowledgements
training very seriously. Atlas Copco
Boomer 282, or hand drilled. An ore- undertook the training of the mine Atlas Copco is grateful to the man-
pass system to the 804 level feeds the instructors, and SFTA has car-ried on, agement of Asikoy copper mine for the
underground crusher. Crushed ore sized giving every man on the mine specific opportunity to visit the project.
at –10 cm travels along a conveyor belt education, each with a course every Particular thanks are due to Kenan
to a feeder, and into a Flexowell verti- three months. The average age of Ozpulat, project manager, and Serkan
cal conveyor belt system at 792 level. A operators is around 30, and most have Yuksel, chief mine engineer, for their
trunk conveyor at average grade of 8 been with the group for many years. assistance at site and in reading draft.
degrees transfers the ore to the surface
primary crusher. Minetruck MT2000 discharges cemented backfill into a primary stope.
There are four vertical shafts for
backfilling at Asikoy, with three sub-
vertical shafts.
Two types of fill are used for
backfill-ing. These are cemented rock
fill (CRF) and uncemented waste fill
(WF). CRF, with a cement content of
5% by weight, is used for backfilling of
primary stopes. Secondary stopes are
waste filled. Minetruck MT2000 trucks
are used for both types of backfilling.
SFTA has a ten-year contract to
produce 30,000 t/month of ore grading
2% copper at a fixed price per tonne,
although 414,000 t was produced over
the last year. The ore is concen-trated
to 17% at site, and is trucked to the
port of Inebolu, some 25 km away,
from where it is shipped to a smelter
A
leadership in environmental practices VALPARAISO I 33°
LOS BRONCES T
and its high standards in environmental N
E
management. G
CHILE
SANTIAGO R
Disputada produces around 250,000
A
SAN ANTONIO
t/ year of copper. When, in 2002, Anglo
American plc agreed to purchase Dis-
putada from Exxon Mobil, it substan- EL TENIENTE 34°
tially enhanced the quality of its base RANCAGUA
Development
Boomer drilling
DTH Drilling 5½" Simba
DTH drilling
Raise
Simba
drilling
2½"Simba
radial drilling
Ore-pass
Extraction level
Transport level
Scooptram
loading
total concentrator feed, but rather numerous isolated orebodies, with a strong
more of the contained copper.
Problematical geology structural control, located through-out an
The sulphide plant's current capac- The El Soldado deposit is located in the area 1,800 m-long by 800 m-wide. The
ity is 6.5 million t/year, of which the Lower Cretaceous Lo Prado formation, lateral limits of the orebodies are
underground mine supplied 2 million t and is thought to be of epigenetic origin. characterized by abrupt variations in the
in 2006. This is expected to decrease The main host rocks are trachytes, fol- copper grade. The transition from high-
to 1.6 million t in 2007 as open pit lowed in importance by andesites and grade mineralization of 1.2% to 2% Cu to
output increases. tuffs. Copper mineralization occurs as low grade areas of 0.5%
m
shaft 22
Max15.0
m 2.5 x 2.5 m m m
m
50.m0
Max15.0m
underground, needs to satisfy safety and
22
Max15.0m
Max 15.0 m
+
22
++
10.0 m to to
++
40-50o 17 17
Shaft
40-50o efficiency criteria. In particular, the
40-50o
17 40-50 o
design and extraction sequence of
Max.transportdis tanc e
Max.transportdis tanc e
to
underground stopes have to be managed
0150.m
0150.m
22
Max 15.0 m 18.0 to 20.0 m
18.0 to 20.0 m in such a way that they do not affect the
Ventilation 18.0 to 20.0 m open pit operations, and minimize
shaft
OP disturbance to unmined areas, enabling
18.0 to 20.0 m OP
maximum resource recovery. This has to
be balanced with the need to main-tain
high-grade feed, and the selectivity that
Extraction level layout. comes with underground mining. There
has been a large amount of de-
to 1.2% Cu takes place within a few The nature of the major structures, velopment in the underground mine,
metres. Orebodies typically exhibit an and the inherent condition of the rock creating a large number of stopes, and
outer pyrite-rich halo, followed mass, play a critical role in determin-ing a complex layout.
inwards by an abundant chalcopyrite the extent of any likely instability Because of all the aspects that need
and bor-nite core, with minor surrounding excavations at El Soldado to be taken into account before mining
chalcocite and hematite. The main mine. Seven main fault systems, and a can start, extensive geotechnical moni-
gangue minerals are calcite, quartz, system of bed contacts, have been de- toring is applied to rock conditions, to
chlorite, epidote and albite. fined within the ore deposit limits as detect and identify failures and insta-
The orebodies are of tabular shape, being significant in geotechnical terms. bilities, to collect data for mine plan-
with dimensions that vary from 100 to The induced state of stress after excava- ning and stope design, and for ongoing
200 m in length, 30 to 150 m in width, tion is a significant mine design crite-ria, assessment of mine stability. Over the
and 80 to 350 m in height. The ground and a monitoring objective. In an longer term, the collected data
conditions are classified as competent, attempt to obtain information on the in- provides control points to update the
with an intact rock strength greater than situ stress in critical areas of the mine, geotechni-cal database, and to verify
200 Mpa, in a moderate stress regime measurements have been carried out. the assump-tions made in the design.
ranging from 15 to 30 Mpa. These geo-
technical conditions facilitate the devel- Mine stability Underground layout
opment of large open cavities, normally
Mine stability is a matter of prime im- The access points to the orebodies are
as large as the orebodies, with dimen-
sions from 40 to 90 m width, 50 to 290 portance in the planning process, particu- located on the slope of the Chilean coa-
m length, and up to 300 m height. larly as the El Morro open pit is situated stal range hosting the mine, several
Production stopes
Production block access is provided by
developing sublevels, with a pattern of
5.0 m x 3.7 m LHD drawpoints at the
base of the stope. Block undercutting is
accomplished with a fan pattern of 60 to
75 mm-diameter holes up to 25 m-long
loaded with ANFO and HE boosters.
Uphole production drilling pattern. Slots are made by enlarging a 2.5 x 2.5
m blast hole slot raise, at one end, or in
hundred metres above the valley floor. increase in production rates. Nominal the middle, of the stope. Blast holes of
Today, the main entry is located at -100 stope dimensions are 30 to 60 m-wide, 165 mm-diameter and up to 80 m-long
level (730 m asl) and the haulage level is 50 to 100 m-long, and up to 100 m- are drilled with an underhand pattern.
at 300 m below datum (530 m asl). The high, though large orebodies are Blast size and blasting sequence is
mine has been developed by a network divided into several units, leaving rib defined for each stope, according to
of sublevels, providing access to the tops and crown pillars as temporary sup- major structural features and the prox-
and bottoms of the mining areas. port structures. Rib pillars are 30 to 50 imity of existing cavities. Dilution con-
Sublevels are linked by ramps, with a m-wide, and crown pillars 25 to 40 m- trol is improved, and blast hole losses
maximum slope of 15%. Ore is loaded thick. The stopes are mined avoided, by carefully considering the
directly into ore passes with an overall progressively down-wards by a particular geometries created by the in-
capacity of 10,000 to 30,000 t, which traditional SBOS method, and are left tersection of major discontinuities and
connect sub levels with the haulage unfilled. Pillars are subse-quently the free faces of the planned excavation.
level. This ore is transported to a crush- recovered by a mass blast tech-nique, Often, faults present geometries which
er located on surface, near the concen- and are sometimes designed to break generate wedges that can slide into the
trator, using 50 t-capacity, highway-type more than 1 million t of ore each. cavity, affecting fragmentation and gen-
trucks. Some ore is mined below the The rock is very competent, and the erating oversize rock at drawpoints. The
main haulage level, and this material is stope cavities can be left open, sometimes presence of cavities, or simultaneous
trans-ported directly to the surface standing for 5 or 10 years, depending on mining in nearby locations, also impose
crusher using trucks and ramps. the sector and the rock structure. Smaller restrictions in the mining sequence and
Historically, the massive, but irregular, stope cavities normally have stable size of blast.
orebodies and the competent ground geometries, with less than 5% dilution Production ore from stopes is loaded
conditions made sublevel open stoping the out with 10 cu yd LHDs. One -way dis-
from back extension or wall failure.
preferred mining method. However, in tances of 100 to 150 m are maintained to
However, three large open sto-pes, the
1983, fully mechanized sublevel and large- orepass tips, which are not equipped
Santa Clara, California and Valdivia Sur
with grizzlies as oversize rock is drilled
diameter blast hole open stope (SBOS) stopes, have experienced controlled
and blasted in place at the drawpoints.
was introduced as a variation of the structural caving, filling the existing void Orepasses terminate in hydraulically-
standard method, enabling an and breaking through to controlled chutes at the –300 haulage
level, where the 50 t trucks are loaded
Downhole production drilling pattern. with run-of- mine ore or development
waste.
A square pattern of 1.90 m x 1.7 m
Parallel hole drilling Radial hole drilling
split set bolts, 2.05 m-long, in combina-
C tion with wire mesh, is used to maintain
adp 450 working areas free of rock fall, and to
50 to 75 m protect personnel and equipment. This
50 to 75 m A Nonel approach to ground control is not in-
tended for heavy rock loads or massive
B
A´
stress- induced instabilities, though is
adequate for local support. Where
45° C´ needed, cable bolting is used to sup-port
45° unfavourable geometries, such as large
wedges or low dip bedding layers,
www.atlascopco.com
El Teniente, Chile
Pioneering mass
caving at El Teniente
Mining in
primary rock
One of the five mining divisions of the
Corporación Nacional del Cobre de
Chile, Codelco, El Teniente is an
integrated copper operation com-
prising mine, concentrator and
smelter installations. Faced with the
depletion of its reserves of high-
grade secondary mineraliza-tion, the
division has completed the change to
mining in primary rock. The early
years were trauma-tic, with major
geotechnical prob-lems including a
series of fatal rockbursts and the
collapse of significant areas of the
production levels. However, El
Teniente rose to the challenge and,
following an extended period of study
and trial mining, is successfully using
a variation of the Panel Caving me-
thod in the new Esmeralda Sector.
This method is now being applied to
future development plans for the New
Mine Level project, which starts
production in 2014. Isometric representation of El Teniente mining sectors.
in the 1800s. Exploitation first began in formed around a central, barren, brec-cia underground, each sector being, in
1819, when the highest-grade minerals, pipe of 1.0 to 1.2 km diameter, sur- effect, a large mine in its own right.
from what became the Fortuna sector, rounded by a mineralized rock mass. The This case story focuses on the
were mined manually and transported on bulk of the mineralization within the Esmeralda Sector, which is set to
animals to the coast. In 1904, William orebody is typical of massive, homo- become the most impor-tant section of
Braden, an American engineer, founded geneous copper porphyries. In fact, El the mine, producing 45,000 t of the
the first El Teniente company, Braden Teniente is one of the largest porphyry 130,000 t/day planned for El Teniente.
Copper Company, and built a road for deposits of copper in the world. The main Since El Teniente began operations
carts and a concentration plant. rock types of the deposit are: andesite in the early 1900s, several exploitation
In 1916, Braden Copper became a sub- 73%, diorite 12%, dacite 9% and breccia methods have been used, though the
sidiary of the Kennecott Corporation, 6%. At some time during its history, the se-condary mineralization was ideally
which was able to supply the funds nec- deposit was affected by supergene sui-ted to conventional block caving.
essary to expand the mine. Kennecott alteration through percolation of mete- However, the last mining sector lo-
operated El Teniente until 1971. In April, orological water close to surface, which cated in secondary ore, Quebrada
1967 the Chilean Government acquired a gave rise to secondary mineralization. This Teniente, was exhausted in 2003, and
51% interest in the property, and foun-ded secondary ore is high in copper grade, but all current mining is in primary ore for
the Sociedad Minera El Teniente. weak, and of good fragmen-tation and processing at the expanded Colón
Following this agreement, major mine caveability. In contrast, the deeper primary concentrator.
expansion was undertaken, and a new mineralization is rela-tively low in copper El Teniente started large-scale mi-
concentration plant was built in Colón, grade, harder, and of moderate ning of the primary ore in 1982, using
which increased total production capac-ity fragmentation and cavea-bility. As can be LHDs and the fully mechanized panel
to 63,000 t/day. Full nationalization appreciated, secondary ore and primary ore caving method. The essential difference
followed in 1971, and El Teniente mine require very differ-ent approaches in terms between panel caving and conventional
became a fully state- owned company. In of mining. block caving is that the former is a dy-
1976 Codelco was formed, and El Teniente namic method in which the undercut is
became part of it. Mining method being continuously developed, and
drawpoints incorporated at the extrac-
El Teniente produces some 334,000 t fine
Reserves tion front, rather than being fully de-
copper and 4,720 t molybdenum each year. veloped before caving is started. This
In total, the El Teniente orebody meas- Mass caving methods are employed to method has been broadly successful at
ures 2.8 km-long, 1.9 km-wide, and 1.8 deliver approximately 98,000 t/day of ore El Teniente, and close to 250 million t of
km-deep. Schematically, the deposit is to the mill from several sectors ore have been extracted using panel
Exploitation sequence
The panel caving exploitation sequence
initially used involved development and
construction of production levels,
undercutting at the undercut level, and
ore extraction. However, the dynamic
caving fronts, under high stress condi-
tions of 40-60 Mpa, resulted in sub-
stantial damage to the infrastructure.
Indeed, extraction in El Teniente Sub 6
Sector had to be stopped in March, 1992
after several rockbursts caused fatal
accidents, reflecting the low level of
knowledge at the time about mining in
primary rock.
Between June, 1994 and August, 1997,
El Teniente carried out experimental
mining in a pilot area of 12,000 sq m. This
process was closely monitored, and the
data served as the basis for a full
geomechanical study. From September,
1997 to June, 1998, during the pre-
operational phase, it was realized that it
was necessary to research the rela-tionship
between seismic potential, undercutting
speed and the mining of new areas.
Because of this, and for the
Panel caving with pre-undercut at Esmeralda.
first time since the 1992 production on the west by the Braden breccia pipe,
freeze, El Teniente carried out prepara-
Esmeralda pre-undercut and in the north by El Teniente Sub 6
tory work in a 6,000 sq m area using Following on from the studies and con- Sector, and is below the Teniente 4 Sur
simultaneous production techniques. trolled tests, El Teniente introduced a Sector. Lithologically, it occurs mainly
The test succeeded, with no significant variation of its conventional panel ca- in andesite, and contains a total mineral
rockbursts, thus proving the relation- ving undercut sequence. Known as pre- reserve of 365 million t, with an average
ship between seismicity and caving undercut, it essentially consists of grade of 1.01% of copper and 0.024% of
speed. Indeed, it is now recognized that developing the production level behind molybdenum. The total investment for
the uncontrolled seismicity induced by the undercut, rather than the more Esmeralda was US$205.6 million, with
the mining extraction rate of advance of typical method where the production conceptual engineering and design
the caving face and extraction speed has development is carried in parallel with initiated in 1992, and caving starting in
been the main cause of damage to the the undercut ahead of the caving face. August, 1996. Ore production started in
tunnels and infrastructure on the lower The pre-undercut achieves a better re- September, 1997, and has built up from
levels. distribution of the stresses ahead of the an average of 4,000 t/day in 1998 to
Nowadays, there are variables incor- production development, resulting in 19,500 t/day in 2001, and full produc-
porated into the mining design and plan- less damage and improved safety. tion of 45,000 t/day from 2005.
ning concept to control the excess of Although the pre-undercut variant Caving at Esmeralda was achieved
seismic activity, not only improving the had been tested in some small sectors of with 16,800 sq m of available produc-
working conditions on the production the mine, it was first used on an indus- tion undercut, once a problem of 'sup-
level, but also increasing productivity. trial scale in the new Esmeralda sector. port points' was solved. These formed
During the pre- operational phase, over Occupying a total area of 714,000 sq m, above the apex of the crown pillar, and
2 million t were removed from Teniente Esmeralda is located at 2,210 m asl reduced the interaction between draw-
Sub 6, with only two small rockbursts. within the El Teniente deposit, bounded points, making the flow of ore from
Basic concepts
In the conventional panel caving and the
pre-undercut variant, the same basic con-
cepts apply. The main difference is the
sequence of each of the operational ele-
ments. In the conventional panel caving
method, the sequence of activities is:
Standard drill plan with 4 hole-fans
development of tunnels on each level for
production and undercut; drawbell
opening; undercut blasting; and extrac-
tion. In the pre-undercut variant, the un-
dercut is excavated first, and the pro-
duction level is developed subsequently
within the stress-relieved zone: devel-
opment of the undercut level; undercut
blasting; development of the production
level; drawbell opening; and extraction.
The main challenge associated with
this variant involved the undercutting.
Several alternatives were tried, with
the current preference being a flat, low
height 3.6 m undercut. The undercut is
Plan of pre-undercut holes. blasted some 80 m ahead of the actual
the undercut level difficult. The effec- through the ore pass and into the loa- production zone, with the production
tive extraction rate defined for the Es- ding bin. On the haulage level, the level and drawbell development
meralda sector was 0.14 to 0.44 t/day/ mineral is loaded into trains featuring follow-ing around 22.5 m behind the
sq m at the initial caving stage, and Automatic Train Protection (ATP) and undercut, and 57.5 m ahead of the
reached 0.28 to 0.65 t/day/sq m at the consisting of a locomotive with eight 50 production zone.
steady-state caving stage. The height t cars. These trains, which were retrofit- The undercut comprises drives, 3.6 m-
of primary ore column to be exploited ted with an Automatic Train Operation wide by 3.6 m-high, developed paral-lel to
is around 150 m, relatively low if each other on 15 m centres. The
(ATO) system, tip into storage bins
com-pared with Teniente 4 Sur, where excavation of the undercut is achieved by
which feed a 5.0 m -diameter orepass to
the height is over 240 m. blasting three- or four-hole fans, some 7 m
the main transport level Teniente 8.
At Esmeralda, 7 cu yd LHDs work- to 10 m length, drilled into the side-wall.
Trains with 90 t electric locomotives and The drill holes are fanned slightly, to
ing on the production level load and tip 18 cars each of 80 t capacity carry the ensure an undercut height equal to the
into 3.5 m-diameter ore passes. Here, mineral out to the Colón concentra-tor. height of the drives. Swell material from
teleremote controlled hydraulic break- The main haulage level at Teniente 8 each undercut blast is removed by LHD to
ers positioned above 1 m x 1 m grizzlies was recently upgraded, incorporating provide a free face for the next blast. The
break any oversize rock before it goes new technology similar to Esmeralda. production haulage level is developed 18
m below the undercut,
Drilling patterns in andesite and breccia.
giving a crown pillar thickness of 14.4
m through which the drawbells are then
developed straight into the pre -blasted
undercut. The production level requires
substantial support, with fully grouted 2.
HW FW HW FW 3 m rebar installed in a 0.9 m x 1.0 m
pattern immediately behind the face,
Drill plan with 3 x 3 hole-fans Drill plan with 4 x 4 hole-fans
followed by chain mesh and shotcrete.
Permanent support is added around 15 m
behind the face, and consists of fully
grouted long cable bolts, with additional
reinforcement at drawpoints. One of the
challenges of this method is that two
HW FW HW FW mining fronts have to be managed, one
on the undercut level, and the other lo-
cated on the production level, and these
Raise boring
In an interesting application during the
2 1 development of Esmeralda, two Atlas
4 1.Development
Copco Robbins raise boring machines,
5 3 2.Drilling & blasting to start caving a 34RH and a 53RH were used. These
3.Development are multipurpose machines, and can be
4.Open trenches (boxholes + drilling)
5.Extraction
employed for upwards boxhole boring
or down reaming, as well as conven-
tional raiseboring.
Principle of pre-undercut at Esmeralda. At Esmeralda, the Robbins 34RH unit
was used in the production level to drill
in turn are related to the scheduling of for sublevel caving. Hence, El Teniente draw bell slot vertical holes approxi-
the development of the drawbells, and is developing its new productive sectors mately 15 m to 20 m-long and 0.7 m-
construction of the drawpoints. using the panel caving method with pre- diameter. The machine worked three
The pre -undercut variant has been a undercut, though other variants could be shifts/day, giving a penetration rate of
substantial success in the Esmeralda sec- used, depending on the local condi-tions, 2.1 m/h. It had a capacity of 93
tor, with only minimal damage occur- lithology, stresses and economics of m/month and a utilization rate of 39%.
ring on the production level, and its The Robbins 53RH was employed
each sector.
associated orepasses and drawpoints. to bore 1.5 m-diameter boxholes up to
There was a significant reduction of 75 m-long for use as ventilation shafts,
Production at Esmeralda
damage to the drifts located under the and inclined pilot raises for orepasses,
undercut level, as well as a significant Cave undercutting at Esmeralda is pres- with an average length of 24 m. The
reduction of rockburst occurrence by ently carried out with the 'parallel long machine worked three shifts/day,
better draw management. The stability hole' technique, which basically consists giving a pen-etration rate of 1.8 m/hr.
and rock condition with the pre-under- of excavating an 855 cu m pillar of solid It had a capa-city of 111 m/month and
cut variant dramatically improves, so it rock 11.4 m-wide, 25 m-long and 3 m- a utilization rate of 57.3%.
was possible to reduce the cost of sup- high. A triangular pattern of 14 parallel Atlas Copco trained the operators
port, and increase the availability of the long holes of 3 in-diameter, with 9 rows from El Teniente, and was in charge of
area by nearly 90%. of 2 holes and 1 hole each is used. This
the equipment maintenance during the
Some optimization of the pre-under- pattern has better efficiency, absorbs
cut is still continuing, in particular some blast hole deviation, and avoids forma- first few months.
fine-tuning of undercut level pillars and tion of residual pillars.
improvement of the co -ordination and Drilling is carried out with an Atlas
Rocket Boomer drill rigs
scheduling of the development activi- Copco Simba H157 drill rig, whose out- Shortly after acquiring the raise boring
ties. It is vital that the spacing of the ac- put is 60 m/shift of 3 in- diameter holes machines, El Teniente acquired two
tivities is maintained, so as to keep the and 85 m/shift of 2.5 in-diameter holes. Atlas Copco Rocket Boomer 282 drill
production development ahead of the Standard ANFO is the column charge, rigs for drift development at Esmeralda.
active cave, but still within the destres- with 300 gm cylindrical pentolite as the In order to increase the drilling pre-
sed area. booster, detonated using Nonel. cision, the mine installed the Atlas
Current productivity obtained at Atlas Copco equipment at Esmeralda Copco Feed Angle Measurement
Esmeralda is over 115 t/day/worker. In includes one Rocket Boomer, two Boltec (FAM) instrument on the Rocket
comparison with other methods such rigs, two Simba rigs and one 3.5 cu yd Boomer units. The machines also
as sublevel caving, panel caving gives Scooptram loader. featured the direct controlled drilling
El Teniente more advantages. The In the production level, a fleet of system, which in-corporates the anti-
direct cost of the sublevel caving nine LHDs is used, including Atlas jamming function Rotation Pressure
method is at least double that of panel Copco Scooptram ST6C and ST1000 Controlled Feed Force (RPCF).
caving, and the current direct cost for loaders of capacities 6 cu yd and 7.3 The Rocket Boomer rigs were fitted
mine at El Teniente is US$2.5/t of ore, cu yd respectively. with COP 1838 rock drills with 20
and indirect costs close to US$1/t The support methods used in Es-
KW impact power and dual-damping
The average cost of panel caving is meralda include 22 mm-diameter and 2.3 system, giving high speed drilling and
US$3.5/t, compared to more than US$5/t m-long bolts, 6 mm-diameter by 10 cm good steel economy.
age and ventilation levels. F Varas, Automation of Mineral Ex- E Rojas, R Molina, A Bonani and H
traction and Handling at El Teniente. Constanzo: The Pre -Undercut
References Massmin 2004. Caving Method at the El Teniente
Mine, Codelco, Chile. Massmin, 2000.
This article is based in interviews with M Larraín, Overview El Teniente Di-
vision, Presentation to MBA Students M Larraín, P Maureira, Plan de Desar-
management from El Teniente and the
following papers: Vanderbilt University USA, 2002. rollo 2000, Division El Teniente, UGA
MINCO, Executive Summary, 2000.
P Yanez and R Molina, New Mine M Barranza and P Crorkan:
Level Project at El Teniente. Massmin Esmeralda Mine Exploitation Project.
2004. Massmin, 2000.
www.atlascopco.com
Boxhole Boring at El Teniente
Introduction Robbins
53RH Transportation level
Codelco, renowned for its refined
copper output, is also the second ranked
world supplier of molybdenum, as well Ventilation level
as being a major producer of silver and
sulphuric acid, both of which are by-
products of its core copper production. Mining method at El Teniente.
The El Teniente mine, located high
in the Andes at an elevation of 2,100 m,
has been producing copper since 1904.
The orebody is 2.8 km-long by
The 3.6 x 3.6 m operating limits at
1.9 km-wide, and is 1.8 km-deep, with the mine work sites demanded an
proven reserves of some 4,000 million t, extremely low reamer design with
sufficient for a mine life of 100 years. a quickly detachable stinger.
Approximately 2,800 miners work This reamer is bolted onto the
seven levels on a 24 h/day, 7 day/ week machine when not in use.
operation. When piloting, the stinger is
El Teniente production increased si- removed from the reamer, to allow
gnificantly in 2005, when its new Es- the drill string to be fed through.
meralda section came on line, using the In reaming mode, the stinger is
pre-undercut panel caving method. Over- refitted using the pipe loader,
all mine output has increased by 31,000 and the locking bolts are
t/day, with 45,000 t/day coming from tightened manually.
the Esmeralda Project, making it the
most important sector in the mine. The
two new boxhole boring systems sup-
plied by Atlas Copco Robbins are a
vital part of this production system.
Conclusion
The application environment in the El
Teniente mine placed high demands
on the boxhole boring equipment sup-
plier, both in size constraints, and in
operation of the equipment. The mine
personnel also had aggressive perfor-
mance expectations, in keeping with
the established high productivity of
the mine. Robbins 34RH.
Atlas Copco chose to offer its proven
34RH and 53RH boxhole machines with features were focused on accommoda- After thoroughly monitoring the ca-
customized features to meet the special ting the restrictive work environment pabilities of both machines, the project
needs of El Teniente. Most of these and high performance expectations. in El Teniente has provided important
input to future development of boxhole Rock Type Composition Density UCS Young’s Poisson’s
boring technology. With production re-
[%] [ton/m3] [MPa] Modulus Ratio
sults exceeding expectations, it has also [MPa] [---]
proved to be a new milestone in the ap- Andesite Fw 36 2.75 100 55 0.12
plication of boxhole boring machines. Andesite Hw 24 2.75 125 55 0.17
Anhydrite Breccha 20 2.70 115 55 0.17
Acknowledgement Andesite Breccha 12 2.70 100 50 0.12
Diorite 8 2.75 140 60 0.15
Atlas Copco is grateful to the manage-
ment and staff at El Teniente for their
Rock properties at El Teniente.
help and assistance with this article.
Geology mineralization is intermittent through a tent of copper and silver -lead- zinc
4 kms
W44 Shaft
Storage Pit
M64 Shaft
R67 Shaft
H70 Shaft
M73 Shaft
H75 Shaft
ShaftR62Shaft
S50 Fill Pass
X41 Shaft
L44 Shaft
I54 Shaft
Y59 Shaft
U62 Shaft
P63 Shaft
U47 ShaftM48Shaft
51U ShaftStoragePit
P61
R60Shaft
M61
Black Rock Black StarOpenCut
Open Cut
ISA
4/L
Black Star 5/L
6/L
Rio Grande & 7/L
Orebodies Black Rock LEAD 9/L
& Racecource
400 Orebody Black Star 10/L
Orebodies Orebodies 11/L
13C 12/L
COPPER MINE 13/L
14/L
16/L MINE 15/L
17/L
2 kms
orebodies have been established by ex- History and development problems of isolation, mine flooding
ploration drilling from the surface and and shortage of capital.
underground. Despite the depth of the John Campbell Miles discovered silver- Lead-zinc-silver production was the
mines, stresses in the ground are not lead ore at Mount Isa in 1923. Although original focus of Mount Isa Mines.
as great as at some shallower mines in mining began in 1924, Mount Isa Mines Although short periods of copper pro-
other regions of Australia. didn’t make a profit until 1937, due to duction had occurred during World War
II, parallel production of copper did not
begin until 1953, after extensions to the
Simba H4353 long hole drill rig with COP 4050 rock drill.
mining operations. The development of
copper orebodies in the late 1960s and
early 1970s, as well as improvements to
the Company’s Townsville refinery,
greatly increased copper production.
The Mount Isa group comprises se-
veral mines. The Hilton lead-zinc-
silver mine, 20 km north of Mount Isa,
opened in 1989, and is now incorpo-
rated into the George Fisher Mine. The
next large development came in the
late 1990s, when close to $1bn was
invested in projects, including the new
George Fischer lead-zinc-silver and
Enterprise copper mines, as well as
expansion of the copper smelter and
the Townsville refinery.
The Enterprise is an extension of
the Mount Isa mine, in the deep 3000
and 3500 orebodies lying beneath
existing mining zones.
4500N
5500N
5000N
1500E
3 1 3 1 3
2 3 2 3 2 3 2
3 1 3 1 3 1 3 1 3
Advance south 3 2 3 2 3 2 3 2 3 2 3 2
1 3 1 3 1 3 1 3 1 3 1 3
3 2 3 2 3 2 3 2 3 2 3 2
1 2 1 2 1 2 1 2 1 2 1 2
3 2 3 2 3 2 3 2
1 Primary Stope
2 Secondary Stope
3 Tertiary Stope
The new orebodies, 1,500-1,800 m ore by 2004.The other main copper In the Mount Isa copper mine ore-
below the surface, are accessed by de- resources at Mount Isa are the 1900 bodies, sub-level open stoping, coupled
clines from the bottom of the main U62/ and 1100 orebodies, the latter known with secondary and tertiary stoping is
R62 Mount Isa shaft complex. Central to also as the X41 mine named after the used to extract the ore. Blocks of ore 40
Enterprise is the new ore handling shaft that reaches the 21 level. m -wide, 40 m-long at full orebody
system, including a 2 km underground MIM Holdings’ lead-zinc-silver height are removed. To do this, 5.0 m x
conveyor (V63 and M62) and a 713 m- comes from the company’s lead mine at 5.0 m drilling sublevels are devel-oped
deep, 5.3 m-diameter internal shaft (the Mount Isa (Racecourse orebody, etc) at 40 m intervals. At the bottom of the
M62), which is boosting capacity to and its George Fischer mine. At these stope, a number of drawpoints are mined
extract the high-grade ore. A 2.13 m x mines the lead-zinc-silver ore is mined, and equipped to extract the ore.
1.98 m jaw crusher reduces the ore crushed and hauled to the surface. Ore Blast hole drilling is carried out using
down to less than 400 mm pieces at a from the George Fischer mine is taken a variety of Atlas Copco Simba rigs, in-
rate of up to 1,000 t/h. The 378 m-long via an off-highway haulage road to the cluding models H4353, H1354, 366, 269
V63 conveyor carries the crushed ore to Mount Isa facility for processing. and 254. On the extraction level,
the M62 shaft, where it is hoisted to the The total extent of the Mount Isa upholes in a ‘V’ shape are used to shape
20 level. The hoist is controlled from a mine workings is now 5 km in length the trough. On the drilling sublevel, the
surface control room, and operates at up and 1.2 km in width, with the deepest Simba rigs are used to drill holes in a
to 16.8 m/s. From there the ore is loaded radiating fan shape. A slice of ore the
point (Enterprise mine) approximately
onto the M62 conveyor for delivery to height of the stope is extracted first,
1,800 m underground.
the existing U62 copper ore handling exposing an open area along one side of
the stope, into which progressive bla-
shaft via a short orepass. Commercial Mining methods sting is carried out.
production began from Enterprise in
The zinc-lead-silver orebodies and The fleet of Simba rigs covers a wide
July, 2000 following five years of
development work. The ore has a high copper orebodies are mined separately, range of hole lengths, diameters and
grade of 4% copper, justifying using slightly different methods, al- orientation possibilities for flexible ore-
development at such depths. The devel- though all operations use forms of open body exploitation capabilities. Holes can
opment is predicted to provide ore for stoping. In open stoping, blocks of ore be drilled accurately, with stringent to-
the smelter after 2020, as production that make up part of the orebody are re- lerances, for optimum fragmentation of
from the 1100 orebody declines. Annual moved one at a time, with the ultimate the ore, and minimal underbreak. Top-
production increased to 3.5 million t of goal of removing all of them. hammer or ITH (in-the-hole) hammer
Zinc-lead-silver extraction
Panel stoping and bench stoping are
used in the zinc- lead-silver mine,
although sublevel open stoping has been
introduced as well, where suit-able.
Whereas bench stoping involves mining
the orebody longitudinally, panel stoping
involves mining the orebody
transversely. Panel stoping is still an
open stoping method, and was consid-
Drawpoint ered more efficient for mining the wider
orebodies at George Fischer. Bench
stoping is still the preferred method for
the mine’s narrow orebodies.
Prior to the current benching
method being introduced in 1992-93,
cut-and-fill was used. In the cut-and-
fill method, a horizontal slice of ore
up to 4 m-high is extracted from the
length of the ore-body. Although very
General view of sublevel stoping at Mount Isa copper mine. selective in high-grade ores, the
method is also expen-sive.
drilling is possible for hole lengths of stope, and is extracted at the drawpoints Benching was introduced as a safer
over 50 m. Flexibility of use is pro- by diesel-powered LHD wheel loaders and more efficient method. The cut-
moted by the modular construction of with a 6.1 cu m bucket capacity. Then and-fill method requires a lot of
the rigs so that, for example, the feed the ore is either tipped directly into the ground support, as miners work in the
positioning system can be combined in passes to feed the crusher or, if the stope orebody itself. With open stoping,
different ways to obtain the required is a long way from the crusher, into workers are positioned outside the
hole positions and directions. Types of articulated haulage trucks. After orebody, in a much safer working
drilling that can be handled include crushing, the ore is sent via a 1.6 km environment. Despite the larger open
bench drilling, fan drilling within a cable belt to the U62 hoisting system, void, benching is more cost effective
90-degree sector, 360-degree ring where 36 t skips take it to the surface. as less support is required, and the ore
drilling, and parallel hole drilling. Mount Isa aims at 100% extraction can be extracted more effi-ciently.
The Simba H4353, for example, is an so, in this method, pillars between In benching, horizontal tunnels, or
all-hydraulic unit for large-scale ope- blocks also need to be recovered. To ‘sill drives’, are driven the length of the
rations, carrying out 90- degree fan achieve this, open ore stopes are filled orebody at regular vertical intervals. The
drilling, 360-degree ring drilling, or with a cement-based slurry and/or distance between sill drives depends on
parallel hole drilling at 1.5 m intervals. rock mixture. The slurry is a mixture local ground conditions, and is ty-pically
The feed beam can be inclined 20 of Port-land cement and concentrator 15 m. Blast holes are drilled vertically
degrees forward and 80 degrees back- tailings, whilst the rock is sourced down from one sill drive to the lower sill
wards. The hole diameter range is 89- from sur-face stockpiles, from the drive. Starting at one end of the bench, a
127 mm, to a maximum recommended heavy media rejects from the lead row of holes is blasted to remove the
hole depth of 51 m. Drilling control is concentrator, or slag waste from the rock between the two sill drives. The
automatic, using the Atlas Copco COP copper smelter. The mixture sets into a broken ore drops to the bottom of the
4050 rock drill. hard, rock-like formation, providing a
orebody, and is removed by LHD to the
ANFO is the main explosive, mixed stable face to enable extraction of the
orepass. It is necessary for the loader to
on site. It is not uncommon for it to be adjacent ore pillar.
go inside the stope to remove the ore, so
used to blast 100,000 t in a single firing. Over half of the site’s production dril-
fill is progressively introduced to the
The broken ore falls to the bottom of the ling units are Atlas Copco Simba rigs. cavity to add stability
(delay exposure).
LHD, operators can now handle up to Minimize remote mucking.
18B
Simplify stope extraction sequence.
three units by remote control from one
19C Delay exposing faults and fill masses.
location. This is an air-conditioned Safety considerations & hazard ID.
built in 1978, is 270 m-high. Copper is that Mount Isa has over 6 million t of
Ore processing contained copper still to be mined,
produced electrolytically in the form
Lead-zinc-silver ore from Mount Isa of anodes. Each weighs 375 kg and is more than has been extracted over the
and George Fischer mines is ground to past 60 years.
99.7% pure copper.
a fine powder at the Mount Isa facility, In more detail, the 2002 reserves and
after which a flotation process is used resource report gave a total of proved and
to separate waste, and produce lead-
Expansion plans probable ore reserves of approxi-mately 73
rich and zinc-rich concentrates. In the year ending June, 2002, record million t at 3.3% copper (previously 47
Lead concentrate from Mount Isa copper smelter production of 233,000 million t at 3.6% copper). The total
contains 50- 60% lead, and around 1 kg t of anode was achieved. This was up underground measured, indi-cated and
of silver/t. After smelting to remove from 207,000 t for the previous year. inferred resources, including reserves,
further impurities, blocks of material, A recent copper study to improve were approximately 116 million t at 3.3%
each containing approximately 3,984 kg reserves and efficiencies has resulted in copper (previously 88 million t at 3.7%
of lead and 10 kg of silver, are trans- an increase in reserves to 12 years. This copper). In addition there were a total
ported by rail to Townsville for ship- has led to a planned 40% expansion in open-cut indicated, inferred re-sources of
ment to MIM’s lead/silver refinery in copper production by 2006. A rate of 255 million t at 1.2% copper (previously
England. In 2001-2002, lead-zinc 400,000 t/y for up to 20 years from an inferred resource of 112 million t at
concentrator throughput and recovery Mount Isa and MIM’s Ernest Henry 1.6% copper).
increased, and there was improved plant Mine is predicted by MIM. The improved lead-zinc concentrator
reliability at the lead smelter. MIM is planning to expand copper performance and smelter reliability in
Around 51% zinc concentrate is also production by developing the 1900 ore- 2001-2002 contributed to an increase in
railed to Townsville for refining, or ship- body, the Enterprise Mine 3000 and production from 140,000 t to 161,000 t
ment to overseas customers. MIM cur- 3500 orebodies, and the surface open pit and reduced operating costs. Still, MIM
rently produces approximately 190,000 t mines in and around existing orebod-ies. is planning to reduce off-site realization
of lead bullion and 500,000 t of zinc The aim for 2003 was to increase Mount costs such as transport and smelting,
concentrate each year. Isa copper production to 245,000 t, which represent up to 60% of total pro-
At the Mount Isa processing facility, improve the recovery rate in the con- duction costs at present.
there is a chimneystack at the copper centrator following an upgrade, and
smelter, built in 1955, which is 155 m- increase plant utilization by improving Acknowledgements
high, and at the lead smelter the stack, maintenance practices. It is estimated
Atlas Copco is grateful to the man-
Table: Mount Isa mine life production statistics agement of Mount Isa Mines, and in
Resource Tonnage (million t) particular to Jim Simpson, General
Total lead-zinc ore mined and processed 100 Manager Mining, Lead Zinc, for
Total copper ore mined and processed 200 writing this article which first
Total copper resource remaining 400 appeared in Underground Mining
Total lead-zinc resource remaining 200 Methods, First Edition.
Long history
Stawell Gold Mine, located about 250
km west of Melbourne, was first
mined in 1853. It was closed in 1926,
and stayed dormant for more than 50
years. It then re-opened in 1982, and
has been in operation ever since.
From 1992 until 2005, Stawell was
owned by MPI Mines, who instituted a Visual inspection of a Minetruck MT5010 with full load near Stawell portal.
plan to increase gold production from
100,000 oz/yr to 130,000 oz/yr by end- This is because the MT5010 has the
2006. However, the mine recently
Faster is better greatest power-to -weight ratio of any
changed hands, and is now operated by Stawell is a very deep mine with in- truck in its class, giving it the highest
Leviathan Resources, who have adopted cline access. Inevitably, the adit is the possible travel speeds per tonne.
the same objective. To meet these tar- bottleneck in the production operation, Based on the success of the site’s
gets, bench stoping with cemented rock because it limits the size of truck that first MT5010, commissioned in 2003,
fill pillars in primary stopes is used. can be employed hauling ore to the mine subsequently ordered another
With this mining method, approxi- surface. However, within the normal three, with the latest arriving on site in
mately 80% of the ore is recovered from under-ground speed constraints, the early January, 2005. Together, the new
the stopes. Remote-controlled loaders shift faster the trucks, and the cleaner they fleet has helped Stawell to its medium
the ore out of the stopes, from where a run, the greater will be the amount of term objectives while reducing the mi-
fleet of four Atlas Copco Minetruck ore that gets to surface. ning cost/tonne to the lowest it has
MT5010 trucks is employed hauling it to At Stawell, getting the ore to surface
ever been.
the surface along a gravel roadbed involves an 8-9 km drive, which, even
maintained by two graders in continu-ous with the MT5010, involves a round trip Comfortable power
operation. Stawell management is of 100 minutes. On the 1:8 gradient, its
convinced that the MT5010 is the best speed under full 50 t load is 12 km/h, The Atlas Copco Minetruck MT5010 is
truck on the market in terms of load some 2-3 km/h faster than the next fast- currently offered with the Cummins
capacity and performance. est truck on the current market. QSK-19-C650 engine as standard. This
PORPHYRY
FAULT BLANK
500m
1000m
1500m
Getting the ore out at Stawell involves an incline of 1:8 to the 400 m level and then 1:10 to surface.
water-cooled diesel provides an MSHA configuration. It is designed for maxi- 30% longer life after the engine’s first
power rating of 485 kW (650 hp) at 2,100 mum utilization with minimum main- rebuild. Oil seals have been
rpm, has a displacement of 19 litres tenance. The articulated pistons are engineered so they are never exposed
(1,159 cu in) and a six-cylinder, in-line made to last 30% longer, and also give to contami-nants.
The MT5010 is equipped with an air-
conditioned ROPS/FOPS - appro-ved
One of the four MT5010 mine trucks at Stawell Mine with manager Bill Colvin and driver Bruce Mclean.
cabin with forward-facing seat and back-
up video monitor, and has an active
hydraulic suspension system for im-
proved operator comfort and handling.
Indeed, Stawell operators report that the
MT5010 suspension is the most com-
fortable in their experience and pro-
vides a much softer, smoother ride. They
observe that, when working 12-hour
shifts, this makes a huge difference. The
cab is also set up for efficient operation,
with good driver visibility, clear instru-
ments, and all controls easy to reach.
One of the most noticeable and impres-
sive features of the MT 5010 truck is its
power. The Cummins engine delivers
torque of more than 3,000 Nm through
the six- speed automatic transmission.
From a standing start under load it pulls
extremely well, whereas vehicles from
the previous fleet struggled. It also has
The Minetruck MT5010 exits from the Stawell portal after a 9 km uphill drive.
www.atlascopco.com/rock
Woomera, south australia
Sublevel stoping at
Olympic Dam
Rapid expansion Darwin
Northern
Since discovery of the massive Teritory
Olympic Dam orebody in 1975, and Western Queensland
the establishment of the mine in Australia
Brisbane
1988, the complex has been New South
through a series of rapid expan- South Australia
Perth Wales
sion programmes. Owned and op- Victoria Sydney
Lake Eyre
erated by BHP Billiton, it is the lar- Coober North
Melbourne Canberra Pedy Lake Eyre
gest single underground mine in South
Australia, with a production rate of Tasmania Hobart OLYMPIC DAM
30,000 t of ore per day to produce Lake
around 185,000 t of copper product Torrens
annually and significant quantities Port
1999 at a cost of Aus$1,940 million. ber, 2000, ore reserves were predicted the grade and volume of the ore; the
They included an automated electric rail to be 707 million t, with average grad- mine’s production requirements.
haulage system (based on that at the ing of 1.7% copper, 0.5 kg/t uranium This type of mining is most suitable
LKAB Kiruna mine), a new under- oxide, and 0.5 gm/t gold. for large ore zones that are character-
ground crusher station, a third haulage The mine’s revenue is made up from ized by relatively regular ore-waste
shaft (the Sir Lindsay Clark), a substan- sales of copper (75%), uranium (20%) contacts and good ground conditions. At
tial increase in ventilation capacity, a and gold and silver (5%). Copper cus- Olympic Dam, the method features the
new smelter, and an enlarged hydromet- tomers are based in Australia (26%), development of sublevel drives, us-ually
allurgical plant. The Sir Lindsay Clark Europe (16%), northern Asia (28%) and at 30-60 m vertical intervals. From these
shaft is fitted with the largest mine win- sublevels, a 1.4 m-diameter raise hole is
south-east Asia (30%). Uranium is sold
der in Australia, both in terms of power excavated by contracted raise boring.
to the United States (54%), Japan (23%),
(6.5 MW) and hoisting capacity (13,765 This extends the whole vertical extent of
Europe (22%) and Canada (1%).
t/h). These facilities increased the an - the designated stope. Production
nual production capacity to 200,000 t of blastholes of 89-155 mm-diameter are
refined copper, 4,300 t of uranium
Mining method then drilled in ringed fans, or rows
oxide, 75,000 oz (2.33 t) of gold and A carefully sequenced and monitored parallel to the ore limits. Plan-ning
850,000 oz (26.44 t) of silver. method of sublevel open stoping is em- engineers, in consultation with the drill
Further expansion under the Optimi- ployed to extract the ore. This was chosen -and-blast engineer, develop the patterns
sation Phase 3 plan in 2003 increased chiefly on the basis of: the depth of the using the Datamine Rings soft-ware
copper production to 235,000 t/year. orebody and volume of overburden; the package. The normal hole para-meters
Since 1988, more than 100 km of un- large lateral extent of the orebody; the are 3 m overburden and 4 m toe spacing.
derground development has taken place geotechnical attributes of the ore (see
to facilitate the production of more than above), the host rock and barren materials, A powder factor of 0.25 kg of explo-
17 million t of mined ore. As of Decem- as well as their geological distribution; sives per tonne of ore is generally main-
tained. Blasts range in size from about
World ranking of Olympic Dam mine 500 t, when opening an undercut slot, to
250,000 t for the maximum stope ring
Metal Resource ranking Production ranking % of world production
Copper No.5 No.17 1.4% firing. There are six to ten blasts/week.
Uranium No.1 No.2 11% Charging is carried out by two 2-man
crews, working 14 shifts/week. Firing is
STOPE
STOPE DRAWPOINT
DRIVE
UNDERCUT
EXTRACTION
MUCKING
ExtractionDrive
DUMPING DRAWPOINT
LOADER
TRAMMING
Dumping Overview
MOBILE ROCK
BREAKER LOADER TRAMMING
Tramming Overview
FINGER PASS TO ORE PASS GRIZZLY
STOPE TRUCK
GRIZZLY
HAULING
TO ORE PASS ORE PASS
GRIZZLY
EXTRACTION
DRIVE
IVE
N
DR
IO
CT
A
R
T
EX
R
IVE
D
N
IO
CT LOADER TRUCK DUMPING
RA
XT
INTO FINGER PASS ORE PASS
E
TRAMMING TO GRIZZLY
TO TRAIN LEVEL
ORE PASS <250 M AWAY
Activity overview showing mucking, tramming and dumping of ore from a typical stope.
carried out by a remote initiation system generally domed to maximize stability. data such as drill-and-blast design lay-
using an electromagnetic field link con- Perimeter drives are located a minimum outs, firing sequences, ground support
trolled by PEDCALL software from a of 1.5 m away from stopes. designs, backfill design, ore grades,
desktop computer. Called BlastPED, the The stopes are laid out by mine de- structural controls, and ventilation se-
system has improved the reliability and sign engineers in consultation with the
quencing.
safety of blasting. The maximum trans- area mine geologist, and then presented
verse width (across strike) and length of to the operating personnel. This is in-
the stope have been determined as 60
Extraction and filling
tended to gain formal approval from
and 35 m respectively. underground production, development WMC employs Atlas Copco Simba
The stope length (along strike) is ge- and services departments, so providing a 4356S electro-hydraulic rigs for down-
nerally based on mineralization, geolo- forum for continuous improvement. A ward blasthole drilling, whilst upholes
gical discontinuities, and other geotech- final document incorporating any re- are avoided as much as possible. Mining
nical issues such as in-situ stress distri- commendations is then issued, so that usually commences at one end of the
bution, possible stope geometry and everyone is aware of the agreed stope stope, and from one sub-level to the
stope filling. The stope crowns are development procedure and all relevant next, until the stope is completed. Once
CAF fill
CAF fill
Tertiary
Primary
Primary
Secondary
Secondary
Unmined
Unm
ined
Unm
ined
Unmined
Unmined
Designed stopes
Unmine
d
Unmined
Primary stope extracted
CAF filled due to unmined adjacent stopes
ROCK fill
CAF fill 2nd Primary stope extracted
CAF filled due to adjacent unmined stopes
CAF fill ROCK fill
Unm
ined
Unmined
ROCK fill
Unmined
drilling is complete, the stope is fired tation and minimum dilution of ore. bored hole, and then subsequent blasts
in stages to ensure maximum fragmen- First the slot is formed around the raise- peel away the ore into the void. Suffi-
cient broken ore has to be removed by
loader from the bottom sublevel of the
Ore progression from stope to train level. stope at the footwall to allow for swell-
ing of the rock and the next firing
FINGER PASS GRIZZLY stage.
450 m B.S.L. 400 m B.S.L. The extraction process continues in
this way, and then all broken ore is re-
moved leaving a roughly rectangular
Loaders and Trucks dump ore prism-like vertical void, which is then
into the Ore Pass Grizzly's. ORE PASS backfilled. The broken ore is transferred
The Grizzly is essentially a large to one of the permanent, near vertical,
steel grate designed to stop orepasses linking the extraction levels
large rocks getting into the ore pass.
These large rocks are broken up 520 m B.S.L. with the rail transport level. These load
by a Mobile Rock Crusher. minecar trains, which carry the ore to
Ore slides down the ore passes the underground crusher and shaft hoist
into the Surge Bin. 550 m B.S.L.
system.
SURGE BIN The optimum geotechnical dimen-
sions of the unsupported open stope are
FINGER PASS usually insufficient for complete extrac-
tion of the suitable ore at that position,
570 m B.S.L. so a series of secondary, and maybe
650 m B.S.L. tertiary, stopes have to be developed
FINGER PASS adjacent to the primary stope. This ne-
The Ore is loaded onto the Train. cessitates a substantial structural fill for
The Train continues to the Crusher, the primary stope, to ensure the struc-
TRAIN LEVEL
dumps the ore which is crushed
tural security of the adjacent stopes
and hauled to the surface
36 tonnes at a time. without leaving a pillar. This comprises
a cement aggregate fill (CAF) produced
Pride of Simba rigs Simba 4356S longhole drill rig with COP 4050 tophammer rock drill.
Atlas Copco has had a fleet of Simba
4356S machines at Olympic Dam since
1992, and has had a service contract on Olympic Dam mining and production statistics
site supporting and maintaining the fleet Description Amount
since 1994. The machines consist-ently Underground development drives (2000) 1,100 m/month
achieve high levels of productivity and Producing stopes each month (2000) 24
availability at a minimal cost. The Average stope size (2000) 300,000 tonne
Simba rigs are predominantly used to
Average stope production rate (2000) 30,000 tonne/month
drill downhole production blast holes for
Average stope production time Ten months
the stopes. Their average mechani-cal
availability is 88-92%, and they drill Average stope filling time One month
between 8,629 m and 9,359 m/month. Average stope fill curing time Three months
Drill-and-blast methods are also Copper production (2002) 178,523 tonne
used for main drive developments, and Uranium Oxide production (2002) 2,890 tonne
for roof bolting as necessary, or in the Gold production (2002) 64,289 oz
rehabilitation of old mining areas re-
Silver production (2002) 643,975 oz
entered.
Improved results at
Meishan iron ore mine
Bright future
China is rich in natural resources,
and is already the fourth largest
gold producer in the world. This
vast country has abundant depos-
its of copper, lead, zinc, iron and
other minerals, not to mention huge
reserves of coal, oil and gas. As
more mines adopt mechaniza-tion,
China’s potential as a world-class
mining nation continues to grow.
An operation that typifies the trend
in productivity and effi-ciency
improvements is the Meishan
underground iron ore mine, near
Nanjing. Having been a limited
producer for many years, Meishan
is now showing signifi-cantly
improved results, thanks to
enlightened management, backed
by Atlas Copco equipment.
–186 m
–198 m –198 m
–213 m
–228 m
–243 m –258 m
–330 m
–447 m
Number of drill rigs 4 4 4 5+1 backup 6+1 backup 6+1 backup 5+2 backup
Output of iron ore (Mt) 2.84 3.18 3.33 3.46 3.87 4.00 3.91
Drill metres (x1,000 ) 203 248 350 380 375 290 280
www.atlascopco.com
Rustenburg, South Africa
m
4m
A-A
~ ~~ ~ ~ ~ ~
5m5
A A C C
7m 7m7m7m ~ ~
m
~ ~ ~
4 m 6m
A A
5m
14
4m 10 m B-B
B D
5m 10 m
A-A C-C
B
7m B
~ ~~ ~ ~ ~ ~
~ ~ ~ ~~
4 m 10 m 7 m 7 m 14 m
8 m 10
10
7m
m m
12m
m
75˚
14 m
60˚ 75˚ 60˚
4m 10
7m
C-C
B-B D-D
~
~ ~ ~ ~ ~ ~~
7m
C
7m
9,5 m
10 M
C 7m7m 14 m
~ ~~ ~
14 m 14 m 14 m
purpose of the shaft. The most modern the exploitation of roof caving, two each of the pillars, beginning from the
shaft in Rudna mine is Koepe hoist eq- stages of excavating pillars were used. In abandoned line, was cut into many
uipped with two twin-skip hoisting the first stage, the area was divided into smaller pillars. From the viewpoint of
installations. Each of the skips has 300 25 m x 35 m pillars. In the second stage, rockburst risk, the two-stage method is
kN capacity and 20 m/s transportation
velocity. The depth of the loading General mining layout for 3 m thickness at Polkowice-Sieroszowice Mine.
level is 1,022 m. Each skip is powered
by a four-line hoisting machine with
Backfill module 7m 7m
5.5 m-diameter transmission using 14m
7m
3,600 kW motors. Timber post
Deposits 5 to 7 m-thick
Until recently, the deposits over 5 m-
thick used to be mined entirely with
backfilling. The newest technology to 7
m-thick is based on the hypothesis of
advance - fracturing and post-failure
capacity of pillars. The roof opening
reaches 150 m, and the longest edges of
the pillars are located perpendicular to
the exploitation front line.
Within caved areas, the upper layers
of roof are not fully supported with bro-
ken rock. Such a situation creates real 1 5 3 2 4
Underground mining of
limestone and gypsum
Trading costs for
profit makes mining
more attractive
Limestone in its various forms is
in such great demand, both as
high quality roadstone and as the
raw material for cement and steel
manufacture, that its mining is
fre-quently carried out
underground. Gypsum is needed
as an additive to the cement-
making process, and is also a
major input to build-ing plaster
and plasterboard pro-duction.
Closeness to the market, or
availability of a suitable mineral
deposit, may be the driver, but eco-
nomic extraction is the deciding
factor. In essence, the underground
limestone and gypsum mines are
trading off the savings in surface Rocket Boomer L1 C-DH drilling the face at Auersmacher limestone mine.
transportation costs by being clo-
ser to the point of use, against the of 6-8 m/min. Each V-cut round of 35
marginal difference in production Auersmacher, holes produces up to 340 t, and takes
costs between surface and under-
ground working.
Saarland, Germany only an hour to drill.
Where these are approxima- Since 1936, almost 20 million t of lime- The Rocket Boomer L1C-DH rig drills
tely in balance, an underground stone have been produced at Auers- the entire daily production output in a
mine can be profitable, as the macher, a border town in Saarland, single shift, returning very favour-able
following examples show. In all operating and wear costs. Mine output is
cases, Atlas Copco drill rigs are the Germany. The mining area covers al-
most 4 sq km, with overburden of ap- currently 350,000 t/year, for which the rig
key to economic success.
proximately 50 m in thickness and an is drilling six rounds on each dayshift. The
average mining height of some 6 m. The rest of the mine works two 8 h shifts/day, 5
Triassic strata comprises a shelly lime- days/week on pro-duction, with a Saturday
Case studies morning shift for non-production work if
stone, which is excellently suited as an
The major characteristic of a success-ful aggregate for the local steel industry. required.
underground mining operation is its The mine is working a room and Experience with the diesel
efficiency, and the single greatest factor pillar system of extraction in the hori- hydraulic unit has shown it to be
affecting this is the cost of drilling and zontal deposit, and the normal face is economic on fuel, and to exhibit low
blasting. Atlas Copco drill rigs are 5 m -high and 6.5 m -wide. The length exhaust gas emis-sions.
bringing down this cost by a combina- of a room plus pillar is about 100 m, The Rocket Boomer L1C-DH diesel
tion of drilling speed and accuracy with in which some limestone is left to engine consumes only about 19 litres of
low maintenance and longevity. form the permanent roof. dieseline for each percussion drill-ing
Matching the drill rig to the job ensures A diesel- powered computerized hour, and can complete two shifts on a
that, whatever the mining situation, Atlas Copco Rocket Boomer L1C-DH single tank of fuel. The excellent exhaust
economic long-term production can be hydraulic drill rig is used because there emission values are very impor-tant in
achieved, sometimes with the whole is no electricity supply installed to the underground mining, where ven-tilation
operation dependent upon a single ma- faces. It is equipped with a COP 1838 can be costly. Due to the very good drilling
chine. The following case studies from rock drill with 22 kW output. As a re- and flushing characteri-stics using water
four very different locations serve to sult, blast holes of 51 mm diameter can mist, drill rod losses are negligible. Water
underline this point. be drilled to depths of 3.4 m at a rate consumption varies
Obrigheim,
Veiw from the driver´s seat of the Rocket Boomer L1 C-DH.
Neckarzimmern, Germany
Heidelberg Cement employs some
from 2-5 lit/min depending upon rock Drilling is carried out exclusively 37,000 people at 1,500 sites in 50
conditions, and a full tank lasts a with Atlas Copco shank adapters and countries, a truly international company
week. The water mist mix is adjusted drill rods, and the very good dampening with sales in excess of EUR6.6 billion.
by the operator. With too little water, it and anti-wear properties have resulted in Since 1905, the company has been
is im-possible to drill, and with too enormously long service lives, despite operating an underground mine in
much, the cuttings become slurried. the high work capacity. For example, the Obrigheim producing gypsum and an-
The rotation speed has a profound approximate service life of drill bits is hydrite. This operation is only possible
effect on penetration rate. In the lime- 3,200 m, rods 10,000 m, and shank thanks to the use of percussion drilling
stone rock at Auersmacher, the opti- adapters, 18,500 m. technology provided by an Atlas Copco
mum speed is 400 rev/min. Dropping Secoroc shank adapters and steels computerized Rocket Boomer L1C drill
it to 300 rev/min reduces the are used with 51mm ballistic bits. A rig introduced in 2003. Training for ope-
penetration rate by 2 m/min. couple of years ago the mine switched rators covering drilling, systems and
maintenance was provided by Atlas
Rocket Boomer L1 C drilling 4.5 m-long blastholes at Obrigheim. Copco, leading to excellent results and
high utilization.
Production is by room and pillar, with
10 m-wide x 5.5 m-high drives. A 4.5 m-
deep round comprises four cut-holes of
89 mm-diameter and 60 blastholes of 45
mm- diameter. Much work has been put
in by both the mine and Atlas Copco to
optimize the drill pattern to maximize
the pull of each round.
The rig is equipped with a heavy duty
COP 1838HF rock drill, and hydraulic
systems and onboard compressor are
driven by a 75 kW electric motor. The
diesel engine is used to move the rig
around the mine. A water tank with
water admixture device provides the
flushing medium for drilling.
Penetration rates vary considerably
due to the large range of compressive
strengths of gypsum and anhydrite,
Josefstollen,
Trier, Germany
Josefstollen mine was opened in 1964
and produces some 600,000 t/y of raw
dolomite primarily for the building
ma-terials industry. Operating
company TKDZ has some 40 million t
of reserves at its disposal, enough for
another 40 years of mining.
The dolomite is of excellent quality,
with a compressive strength of 130 -150
Mpa, and optimized underground pro-
duction allows the products to be placed
on the market at competitive prices.
Mining is by conventional room and
pillar at two gallery levels in the bottom
and central beds. The production area is
initially opened up by mining hori-
zontal galleries, with ramp access to the
individual beds. Room widths are 5 m in
the bottom bed and 5.5 m in the cen-tral
bed, with heights of 5.0-5.5 m.
Each blasting round comprises 29
off 3.3 m -deep x 45 mm-diameter
holes with a Vee cut. Around 13 faces/
day must be drilled to keep pace with
demand.
Drilling is carried out by a diesel-
hydraulic Rocket Boomer L1 C-DH
rig equipped with COP 1838HF rock
drill and air-water mist flushing. The
rock drill takes around 25-30 seconds
to drill each hole, at a penetration rate
of 8 m/min. Total drilling time is about
30 minutes for each round.
Rocket Boomer L1 C-DH with COP 1838HF rock drill achieves 8 m/min at Josefstollen.
The dolomite is difficult to drill be-
cause it is not a continuously compact slack time as a reserve against any in- The strata is a middle limestone
formation, so the computerization on the mem-ber of the Gabsan formation in
creased production demand.
drill rig, which controls both the the upper palaeozoic Pyeongan super
hammer and feed, plays a vital role. As a Yongjeung, Jechon, Korea group of minerals. The geological
result, most of the required drilling is structures are mainly controlled by a
completed on a single shift, with the Yongjeung limestone mine is situated NW-SE trend-ing, with westerly
second shift offering flexibility for drill- in Jechon city in the Choongbook overturned folds and thrust faults.
ing awkward places and for performing province of South Korea, some 150 Reserves confirmed by drilling are
maintenance. The mine also sees this km southeast of capital city Seoul. over 12 million t, of which it is expected
Conclusions
Where there is no suitable electricity
supply to the mining areas to power an
7m Pillar
electro -hydraulic rig, as at Auersmacher
and Yongjeung, diesel-driven hydraulic
9m
rigs offer a means of upgrading mining
Pillar
efficiency without excessive capital
expenditure. At these mines, drilling
Vertical benching of bottom parts rates doubled with the introduction
of the Rocket Boomer L1C-DH, and
round depths increased significantly.
These machines, equipped with water
tanks and water mist flushing, operate
Principle mining method at Yongjeung. efficiently despite the absence of mains
supplies of water and electricity. They
that over 5.5 million t will eventually drilling 4 m-long x 51 mm- diameter are also adaptable, performing on both
be mined. Average chemical analysis holes. Generally, 50 holes are drilled in production and development, and han-
of the limestone bed is CaO 54.4%, each face, and three faces are drilled in dling rockbolt and ancillary drilling.
SiO2 0.78%, MgO 0.53%, Al2O3 each 8 h shift. This affords a capacity of Production and efficiency gains
0.03%, and Fe2O3 0.17%. 3,000 t/day or 70,000 t/month. When have been recorded wherever the
Around 25,000 t/month of drilling, the rig’s diesel engine operates Rocket Boomer L1C-DH has been
limestone is produced for markets that for around 1 min/drilled metre, con-
introduced, making it a boon to mines
include companies operating plants for suming 0.31 litres of fuel. Returns from
where every penny counts.
the manufacture of desulphurization rig consumables are: rods 975 m; bits
prod-ucts, quicklime, calcium 750 m; shanks 3,900 m; and sleeves
1,950 m.
Acknowledgements
carbonate and chicken feed.
The limestone bed is mined in three An Atlas Copco ROC D5 crawler rig Atlas Copco is grateful to the manage-
steps, starting with 15 m-wide x 7 m-high is used for downhole drilling of the ments at Auersmacher, Heidelberg,
room and pillar, followed by a 9 m bench. bottom bench. This rig has a long fold- TKDZ and Yongjeung for their inputs
A Rocket Boomer L1C-DH diesel powered ing boom which allows the operators to to this article and for permission to
drill rig is the main production machine in drill at a comfortable 5.5 m from the publish.
the room and pillar faces, edge of the crater, a major improvement
Rocket Boomer L1 C-DH on demonstration at Yongjeung limestone mine. Atlas Copco ROC D5 drilling the bench at Yongjeung.
Production
Production loading
N 55
Charging – production holes
N 65
Production drilling
N 75
Mucking out
N 85
Charging
N 95
Scaling
Development
N 105
Drilling
N 115
Shot
N 125
creting
and, in the few cases when the orebody is of the orebody. The vertical distance blast holes, which have a diameter of
horizontal, open stoping is the pre-ferred between sublevels varies from 14 m to 51 mm and a burden of 2.2 m. At the
method. Both methods are safe, with 30 m. Production drilling is upwards, same time, they are studying the pos-
currently acceptable dilutions. However, using a fan pattern. The broken ore is sibility of changing to 76 mm-
the management has started looking for loaded using LHDs, and is hauled diameter holes and 2.8 m burden, in
suitable alternative methods that will from the production levels to the order to re-duce costs.
reduce the dilution in future. For surface using rigid frame trucks. The fleet of production drill rigs in-
longitudinal sublevel caving, produc-tion In terms of production, the company cludes an Atlas Copco Simba H254 and
drifts are developed in the footwall drills 180,000 m/year of production a Simba 253, both electro- hydraulic
The locations of drifts and drill patterns are adapted to the ore-waste boundaries.
Blast holes
Ore
Cable
Waste
Drift
2.2 m
Slot drilling at Ferbasa: The Simba M6 C in action and, (right), the perfectly finished row of holes.
rigs equipped with COP 1238ME rock advances of up to 6 m. Nowadays, this of up to 25 m length are successfully
drills, which drill 6,000 m/month to practice has been replaced with a fully achieved. The main advantages of the
achieve a productivity of 22 m/h. The mechanized method, increasing the method are personnel safety and speed
mine also has a Promec M195 pneu- speed and safety of drilling the open- in the drilling. Also, slot drilling is
matic rig equipped with COP 131EL ings. Looking for a solution to improve more precise and, in general, more
rock drill. These machines are also operator safety when drilling these pro- productive.
duction raises, technical personnel from A Simba M6 C drill rig equipped with
used to drill orebody definition holes,
Ferbasa visited LKAB’s Malmberget COP 64 DTH hammer and ABC Regular
and achieve 3,500 m/month.
iron ore mine in Sweden, where they system, as well as an on-board booster
compressor, has been acquired for drill-ing
Slot drilling studied the development of inverse drop
inverse drop raises with holes up to 10 in-
raises blasted in one single shot. After
One of the main challenges at Ferbasa’s the visit, Ferbasa started employing a diameter. Depending on the length of the
underground operations is the develop- slot drilling technique, and Ipueira and raise, and the quality of the rock mass, the
ment of inverse drop raises. These open- Medrado are now the most experienced slot drilling technique is used. If the length
ings, which are also called ‘blind raises’ of the raise is short, and the rock quality
mines in Brazil in its use. Slot drilling
because they don’t communicate with poor, the traditional technique with reamed
requires a row of 7.5 in -diameter inter-
the upper level, can only be accessed holes is used.
connected holes to be drilled using a
from the lower level. This limitation is Until the Simba M6 C arrived, Fer-
special guide mounted on a regular ITH
dictated by the mining methods. basa was carrying out slot drilling with
drill hammer. Thus, with an available
Previously these blind raises were de- only one machine. They chose the new
free face, drilling accuracy, and con-
veloped upwards by successive individual trolled blasting techniques, openings Simba rig because of its advanced tech-
nological and safety features. One of the
The slot drilling crew with their Simba. main advantages is the setup, which
only has to be carried out once at each
site.
The Simba M6 C machine is also easy
to operate, and the spacious, air-condi-
tioned cabin is an attractive feature.
The mine spent five years looking for
a solution to the opening of inverse drop
raises, and is pleased with its invest-
ment in technology and modernization
represented by the Simba M6 C.
Acknowledgements
Atlas Copco is grateful to the manage-
ments at both Ipueira and Medrado
mines for their contributions to this
article.
When you choose Secoroc DTH equipment, you decide what balance of technol-ogy,
performance, and investment is right for your drilling conditions. Atlas Copco Secoroc
has the broadest range of hammers, bits, and related equipment of any supplier in
the world. This means more choices for you. It means you can work with the
strongest support network in the industry, regardless of your equipment needs. It also
means that you can look to one reliable and time-tested source for all con-ceivable
applications.
Of course, you'd expect Atlas Copco Secoroc to have the most productive DTH ham-
mers in the world. And we do.
Your situation might call for the utmost in reliability. Or perhaps your application
demands technology that has been tested and proven through years of field use.
Whatever your needs, check out our many choices before settling for less. We are
the only manufacturer to offer both first and second choice solutions in every single
application.
You'll find it all here. At Atlas Copco Secoroc.
www.atlascopco.com/cmtportal
Zacatecas, Mexico
Mechanization pioneer
The official name of the Proaño mine
comes from Captain Diego Fernandez de
Proaño, who discovered the site and
developed the first mining works on the
hill that bears his name. The operation is Setting up Simba 1254 for blast hole drilling.
also known as Fresnillo mine because
of its proximity to Fresnillo city. It is run last 30 years there has been a steady increased its mining fleet with the pur-
by the Compania Fresnillo, SA de CV, increase in production. Products are chase of three Rocket Boomer 281 de-
which is 100% owned by Peñoles. With silver-lead concentrates and silver-zinc velopment drill rigs additional to its four
a history that can be traced as far back as concentrates. In 2005, Proaño existing units, another Simba M4 C
the 1550s in Pre-Hispanic times, Proaño production drill rig additional to its ex-
produced nearly 34 million troy
has gone through a number of phases, isting three units, five Scooptram
ounces, or 1,055 t, of silver.
which have left an important mark on ST1020 loaders to complement its
the mine. Its operations have been existing fleet of 17 units, and two
stopped due to economical and technical
Production expansion Minetruck MT2000 trucks to increase its
difficulties (1757 to 1830), as well as During the mine's long history it has had fleet to seven units. Atlas Copco has also
during the Mexican Revolution (1913 to to adapt to changes in the geology and started a service contract for the Simba
1919), and inevitably it has gone work parameters. For instance, the rigs, which re-quires the presence of
through several ownership as well as mining method has had to be funda- four technicians on site, and offers
technological changes. mentally changed several times, and similar assistance for the loaders.
From employing basic manual tools each time the appropriate technology Currently, the Proaño mining fleet
in the early days, the mine now employs and equipment has had to be introduced. represents a mix of old and new Atlas
modern mechanized units, including Atlas Copco has worked alongside the Copco technology. Amongst the old units
some of the most sophisticated mining mine management for several years to are Scooptram ST6C loaders, BBC 16
machinery available. adapt and innovate with primary equip- pneumatic rock drills, BMT 51 pusher leg
Embracing mechanization early on ment, service, training, inventory man- rock drills and DIP & DOP pneu-matic
has been one of the factors that has hel- agement and parts stock. The mine re- pumps. There are also Diamec U6, Diamec
ped Proaño cement its position as the cently implemented a substantial pro- 262 and Diamec 252 explora-tion drill
world's largest and most profitable silver duction increase, going from 4,500 t/day rigs, Boltec 235 bolting rigs, Rocket
mine. They started mechanizing opera- to 7,000 t/day. To support this produc- Boomer 104 drill rigs, Simba 1254
tions about 40 years ago, and during the tion expansion the company recently production drill rigs and Robbins
o
& Service Centre
(Caleras) Madero Mine G U LF O F MEXICO
Mining operations
r
n Zacatecas
The underground operations can be ac-
i cessed either through two shafts, Central
a Proaño Mine (Fresnillo)
Atlas Copco Mexicana Shaft and San Luis Shaft, or by one of
(Tlalnepantla) Mexico City the mine's several ramps. The mine has
seven levels and in Level 425 is the San
BELIZE Carlos orebody, which currently pro-
duces 67% of production.
GUATEMALA HONDURAS
Proaño carries out about 40,000 m
EL SALVADOR of development drilling a year. To sup-
port this work, there are three different
contracting companies: Mincamex, Jo-
Map of Mexico showing Atlas Copco bases and mine locations. margo and Mecaxa. All three compa-
nies own Atlas Copco equipment,
raise borers. Furthermore, the mine uses telescopic advance, which represent mainly Rocket Boomer drill rigs and
Secoroc drill steel on development and completely new technology. loaders.
production rigs. Likewise, Proaño owns two Diamec The mining method is cut & fill using
Proaño was the first mining opera- U6 APC deep hole drill rigs, the first upwards and downwards drilling. How-
tion in Mexico to employ the Boltec rigs mine in the Americas to use this type ever, the amount of drilling and the hole
and the Rocket Boomer 281 rig with of machine. diameter have changed over the years.
4915
4600
o
with electricity, water and air, from 380
where the sublevels are supplied.
Currently, the miners drill 25 to 32 m
downwards and 25 to 32 m upwards,
using a com-puterized Simba M4 C
DTH rig from a single set up.
This method provides better safety,
higher productivity and lower costs.
New operation
Located about 15 km north of the city of
Zacatecas, Francisco I. Madero (FIM) is
one of Peñoles' newest mines, having
started commercial production only in
2001. The mine's name comes from a
former Mexican President, Francisco
Ignacio Madero, killed during the Mexi-
can Revolution. Although a polymetallic
Introduction
Panasqueira mine is located at Barroca Grande in Portugal.
The Panasqueira mine is located at
Bar-roca Grande in a mountainous in length, varying in width from 400 as much as 3-4 m over a very short
region of Portugal, 300 km northeast m to 2,200 m, and continues to at least distance.
of the capi-tal city of Lisbon, and 200 Blocks of ore are laid out initially in
500 m in depth.
km southeast of the port city of Porto. 100 m x 80 m sections by driving 5 m-
The mining concession lies in mod- wide tunnels, 2.2 m-high. Similar tun-
erately rugged, pine and eucalyptus co-
Production levels nels are then set off at approximately 90
vered hills and valleys, with elevations Access to the mine’s main levels is by degrees to create roughly 11 m by 11 m
ranging from 350 m above sea level in a 2.5 m x 2.8 m decline from surface, pillars, which are ultimately reduced by
the southeast to a peak of 1,083 m above with a gradient of 14%. The main slyping to 3 m by 3 m, providing an
sea level in the northwestern corner. levels consist of a series of parallel extraction rate of 84%.
The concession area is an irregular drives that are spaced 100 m apart, Blasted ore is loaded from the stopes
shape trending northwest-southeast, and and which pro-vide access to the ore by a fleet of six low-profile Atlas Copco
is approximately 7.5 km-long. It is 1.5 passes for rail transport, and connect Scooptram ST600LP loaders, tipping
km-wide at the southeastern end, and 5.0 with ramps for movement of drilling into 1.8 m - diameter bored raises con-
km-wide at the northwestern end, where and loading equip-ment. necting to the main level boxes.
the mine workings and mill facilities are There are seven veins between the 2nd Rail haulage with trolley locomotives
located. The geology of the region is and 3rd Levels, which are 90 m apart. The is used to transport the ore to the shaft
characterized by stacked quartz veins veins are almost flat, but occasion-ally on Level 3, and to the 900 t- capacity
that lead into mineralized wolfram- split or join together. They pinch and main orepass on Level 2 that provides
bearing schist. The mineralized zone has swell, and are usually between 10 and 70 storage for the 190 t/h jaw crusher lo-
dimensions of approximately 2,500 m cm-thick, and can plunge locally cated at the 530 m-level.
Crushed ore discharges onto the and a new compressor unit was East-west oriented tunnels are called
1,203 m-long, 17% inclined Santa installed underground in 2002. Drives, and those trending north-south
Bar-bara conveyor belt that connects The mine is supplied by 3.0 kV are called Panels. Drives and Panels are
with a 3,000 t- capacity coarse ore bin elec-trical power, which is reduced to driven 5 m-wide and, where they inter-
located beneath the mine office. sect, 1.8 m-diameter raises are bored
380 V for distribution to equipment.
Primary mine ventilation is provided between haulage levels to act as ore-
naturally by several ventilation raises. passes for all of the stopes. Chutes are
Airflow is controlled by curtains in main
Mining method installed in the bottoms of the orepasses
areas and assisted by axial flow fans The stoping process begins when spiral to facilitate the loading of trains.
where needed, particularly in the stopes. ramps are driven up to access the miner- The height of the stopes is nominally
Compressed air is needed for the alized veins, and the orebody is opened 2.1 m, but can increase to 2.3 m in areas
where ore bearing veins are more vari-
charging of the blast holes with ANFO, in four directions and blocked out.
able in their dip, strike or thickness.
Precise survey control is maintained,
Schematic of stope layout.
so that all final pillars are aligned ver-
tically. Experience has shown that the
stopes will usually begin to collapse
about 4 or 5 months after extraction,
which gives plenty of time to glean
any remaining fines from the floor.
Stope drilling is carried out by new
generation Atlas Copco Rocket Boomer
S1L low profile electric hydraulic single
boom jumbos. Rounds are drilled 2.2 m-
Initial pillar Final pillars deep, utilizing a Vee- cut, and 41 and 43
11 m 5m 3m 5m 3m Wolframite seam mm- diameter drill bits. Drilling is
carried out on two shifts, with about 28
holes required per 5 m-wide round.
ANFO is loaded pneumatically into
138
the blast holes, and electric delay deto- All drilling uses ballistic button bits, The recent addition of Rocket Boomer
nators along with small primers are of which the preferred 43 mm-diameter S1 L models to the fleet has resulted in a
used for blasting. Blasting takes place Atlas Copco Secoroc SR35 bits used by 50% increase in output/drill rig, while less
around midnight, and the mine then the COP 1838 rock drills are returning waste rock is generated due to the lower
ven-tilates throughout the night. 370 m/bit, while the 41 mm -diameter profile required for safe operation. This
Each blasted face produces about bits are returning 450 m/bit. In such drill rig will operate in a seam height as
60 -65 t of rock, and each rig can drill abrasive rock, bit wear has to be closely low as 1.3 m and is equipped with four-
up to 10 faces/shift, depending upon monitored to avoid an escalation in wheel drive for maximum trac-tability. The
the availability of working places. costs. Likewise, regrinding has to be to a COP 1838 rock drill has double reflex
After the blast, the muck pile is wa-
high standard. dampening for high-speed
shed down, and the back is scaled. Ore
is loaded and hauled by the Scooptrams
Core drilling in the levels.
from the headings to the orepasses.
Once the limits of the stopes are es-
tablished, then the final extraction
takes place with 3 m x 3 m pillars
created from the perimeter retreating
to the access ramp.
Drilling performance
The mine drill rig fleet comprises three
Atlas Copco Boomer H126 L drill rigs
mounted with COP 1238ME rock drills;
five Atlas Copco Rocket Boomer S1 L
low -profile drill rigs mounted with COP
1838ME rock drills; and three older drill
rigs retrofitted with COP 1238LP rock
drills.
drilling and excellent drill steel econ- round trip to tip, consuming 12 lit/h of mechanical breakout force of 8.7 t and
omy. dieseline. hydraulic breakout force of 9.3 t. For
Drilling is performed primarily on The ST600LP is an extremely robust visibility on the far side of the machine,
day and afternoon shifts on around 50 LHD designed specifically for demand- video cameras point forward and aft,
faces. These are maintained in close ing low seam applications where the reporting to a screen in the driver’s cab.
back heights are as low as 1.6 m. It has The model has gained a well-deserved
proximity to one another, to avoid
an operating weight of 17.3 t and a tram- reputation in the platinum, palladium
long moves for the drill rigs. and chrome mines of South Africa,
ming capacity of 6 t, equipped with a 3.1
where gradients are steep and rock is
Scooptram ST600LP cu m bucket. It is 8.625 m-long, 1.895
highly abrasive. The ST600LP is now
m-wide and 1.56 m from floor to top of
Each Scooptram ST600LP cleans 4 -6 proving itself in similar rigorous condi-
canopy. It is powered by a robust 6- tions at Panasqueira, where the roof is
headings/shift on a maximum 200 m cylinder diesel engine, providing a not well defined, and there are frequent
seam irregularities.
Main access ramp to level 2 at Panasqueira mine.
The mine currently operates at a
rate of 65,000 t/m with a recovered
grade of 0.2% WO3, which should
produce about 112 t of high grade and
20 t of low-grade concentrate. Some
150 people are employed underground
on two shifts, five days per week.
Acknowledgements
Atlas Copco is grateful to the directors
and management at Panasqueira for
their kind assistance in the production
of this article, and for providing access
to the mine statistics.
www.atlascopco.com
This is optimised productivity
www.atlascopco.com