INSTRUCTION MANUAL - PMT Menard - Roctest
INSTRUCTION MANUAL - PMT Menard - Roctest
PRESSUREMETER
Model GAM-II
This product should be installed and operated only by qualified personnel. Its misuse is potentially dangerous. The Company makes no warranty as to the
information furnished in this manual and assumes no liability for damages resulting from the installation or use of this product. The information herein is
subject to change without notification.
Tel. : 1.450.465.1113 • 1.877.ROCTEST (Canada, USA) • 33 (1) 64.06.40.80 (Europe) • www.roctest.com • www.telemac.com
E1001C-10042011
TABLE OF CONTENTS
1 GENERAL .................................................................................................. 1
1.1 DEFINITION AND PURPOSE OF TEST ................................................................. 1
1.2 PRINCIPLE OF TEST ...................................................................................... 1
1.3 RESULTS AND THEIR USE .............................................................................. 1
2 TESTING EQUIPMENT ............................................................................... 3
2.1 GENERAL .................................................................................................. 3
2.2 PROBE ...................................................................................................... 3
2.3 CONTROL UNIT ........................................................................................... 5
2.4 COAXIAL TUBING ......................................................................................... 5
3 TEST PROCEDURE .................................................................................... 6
3.1 GENERAL .................................................................................................. 6
3.2 THE PROBE ASSEMBLY AND DISASSEMBLY........................................................ 6
3.2.1 Assembly ..................................................................................................... 6
3.2.2 Disassembly ................................................................................................ 7
3.3 FILLING THE CONTROL UNIT AND SATURATING OF SYSTEM ................................... 9
3.4 CALIBRATIONS ............................................................................................ 9
3.4.1 General ........................................................................................................ 9
3.4.2 Probe inertia calibration ............................................................................ 10
3.4.3 Calibration due to intrinsic volume expansion of Complete system .......... 11
3.5 EXECUTION OF THE PRESSUREMETER TEST .................................................... 11
3.5.1 General ...................................................................................................... 11
3.5.2 Low pressure testing (0-2500 kPa)............................................................ 11
3.5.3 High pressure testing (0-10000 kPa) ......................................................... 11
3.5.4 Measuring cell and guard cell pressure systems ...................................... 12
3.5.5 Differential pressure.................................................................................. 13
4 OPERATIONS ...........................................................................................14
4.1 CHOICE OF GAGES ................................................................................... 14
4.2 FILLING THE PRESSUREMETER ..................................................................... 14
4.3 SATURATION OF TUBING AND PROBE ............................................................. 14
4.4 DIFFERENTIAL PRESSURE VALVE ADJUSTMENT ................................................ 15
4.5 CALIBRATION LOW PRESSURE 0-2500 KPA ..................................................... 17
4.6 TESTING ................................................................................................. 18
4.7 CONVERSION TO HIGH PRESSURE (10 000 KPA) .............................................. 18
4.7.1 Pressure gage ............................................................................................ 18
4.7.2 Pressure regulator spring .......................................................................... 19
4.8 CALIBRATION HIGH PRESSURE (0-10000 KPA) ............................................... 19
4.9 TESTING HIGH PRESSURE (0-10000 KPA) ...................................................... 20
4.10 CYCLIC TEST ........................................................................................... 20
4.11 WINTER USE ............................................................................................ 21
4.12 TESTS AT GREAT DEPTHS ........................................................................... 21
5 READINGS AND INTERPRETATION ..........................................................22
6 MAINTENANCE ........................................................................................23
6.1 FILTER ................................................................................................. 23
6.2 PRESSURE REGULATOR ....................................................................... 23
6.3 DIFFERENTIAL VALVE ................................................................................ 23
6.4 TROUBLE SHOOTING ................................................................................. 24
7 PART LIST AND ILLUSTRATIONS .............................................................25
E1001C-10042011 GAM-II
1 GENERAL
1.1 DEFINITION AND PURPOSE OF TEST
The pressuremeter test is a load test carried out in-situ in a borehole. An inflatable
cylindrical probe is set at testing depth in a pre-drilled borehole within a soil or rock mass
or by direct driving into the mass. The method in depends on the materials’
characteristics.
The Pressuremeter uses a pneumatic/hydraulic control unit to load and monitor the tested
material’s response. The data collected defines the stress-strain relationship of soil and
rock with depth.
The pressuremeter test data is used to determine the limit pressure (10 MPa max) and
pressuremeter modulus (5 GPa) max. The limit pressure is used to calculate the bearing
capacity. The pressuremeter modulus is used to evaluate absolute and differential
settlements for specific foundation designs.
1
E1001C-10042011 GAM-II
i) From P = 0 to P = P0
This portion of the curve corresponds to the probe seating against the borehole
wall. The wall disturbance induced by drilling or driving the probe into place has
considerable influence on this segment of the curve. The difference in borehole
and probe diameters also affects this segment.
ii) From P = P0 to P = Pf
This segment represents the pseudo-elastic behavior of the tested material. The
probe is in contact with the borehole walls. The loading is uniform along the probe
length. This segment is linear and defines E, the deformation modulus of the
tested material. E, in turn is used to evaluate settlement. Should the probe be in
contact with the borehole walls before applying pressure, the mass would exhibit
pseudo-elastic behavior from the outset.
iii) From P = Pf to P = PL
Pf by definition is the pressure at which the mass enters a plastic state. Above P f,
the loaded mass’ deformation accelerates up to the complete failure point. The
pressure that defines failure is the limit pressure PL. This fundamental
mechanical characteristic of the mass is used to evaluate the stability of
foundations in accordance with pressuremeter methods.
2
E1001C-10042011 GAM-II
2 TESTING EQUIPMENT
2.1 GENERAL
The pressuremeter apparatus consists of three distinct devices:
- The probe, the loading device, goes inside a borehole at the desired test elevation;
- The control unit, mounts on a tripod at surface, controls the test and displays test
parameters and data. The pressure source, a compressed gas cylinder
- The coaxial tubing delivers pressurized gas and liquid from the control unit to and
from the probe.
2.2 PROBE
The pressuremeter probe is a hollow metal cylinder threaded at both ends and designed to
accept and seal the inner rubber membrane and the outer rubber or metallic sheath. The
outer protective sheath mounts concentrically over the centrally located internal rubber
membrane. The protective sheath extends over the total length of the probe. It is this
sheath that is in direct contact with the borehole walls when the probe is pressurized.
Figure below shows a longitudinal cross section of a pressuremeter probe.
The metallic sheath has longitudinal steel strips fixed to its outer surface. The strips
overlap such that when inflated, the increased surface area of the sheath remains
protected. The metallic sheath is the most frequently used. In certain soils, depending on
the conditions, the pressuremeter tests are run with rubber sheaths.
The central rubber membrane contains the pressurized water and is the probe’s measuring
cell. Its deformation mirror the soil's deformation under load. The loads are applied
using the control unit. The sight tube indicates the volume change of the central
measuring cell. Pressure and volume readings are plotted, as shown in Figure on page 1.
PL and E are the calculated values are applied to the foundation design.
As mentioned above, the inner rubber membrane in which water pressure is applied
occupies the central parts of the probe. In the mathematics behind the interpretation of
the results the assumption is made that the material loaded by the central cell is in a state
of plane deformation. Practically, in order to obtain such a state of deformation it is
necessary to extend the loaded zone on both sides of the central cell. This is accomplished
by allowing gas pressure to be applied to the outer protective sheath which extends over
the total length of the probe. Therefore to transmit load to the material tested the inner
rubber membrane has to be in contact with the outer protective sheath. We then have
three separate chambers under pressure: the central cell under water pressure and the
two guard cells under gas pressure. Figures below schematically show the two pressure
systems of the probe.
3
E1001C-10042011 GAM-II
The GAM-II pressuremeter probe is available in three different sizes to fit the standard
borehole diameters. Table below lists the available probes’ diameters and their
corresponding standard drill hole diameters. Table below also shows the acceptable
tolerances on standard borehole sizes within which a satisfactory test can be expected.
A 44 46 52
B 58 60 66
N 70 74 80
4
E1001C-10042011 GAM-II
5
E1001C-10042011 GAM-II
3 TEST PROCEDURE
3.1 GENERAL
The following sections lists the specific instructions for the different stages required to
execute a successful pressuremeter test. They are, in chronological order:
Note: It is strongly suggested to use a bench vice and the probe to vice
adaptor to hold the probe during the following operations.
3.2.1 ASSEMBLY
Step 1 The two membrane internal tapered rings (32) are slid over the metal body (28) of
the probe and are left in place at mid-section. The internal face of each ring is in
the shape of a truncated cone and care must be taken so that the thickest
extremity (the base) is oriented towards the center of the probe.
Step 2 Slide the membrane (31) over the body of the probe (28) and under the tapered
rings (32). During this step keep the tapered rings at mid-section and center the
rubber membrane (31) with respect to the beads (30a).
Step 3 Manually move the tapered rings (32) outward until the leading edge of the rings
contacts the beads. Assemble the three shortest puller arms to the ring puller.
The longer arms are used to remove the tapered rings.
Install the ring puller (36) at one extremity of the probe using the proper sized
bushing to center the puller about the probe axis. Rotate the handle (37)
backwards until it is parallel to the probe axis. This will set the tapered ring in
the correct location. Release the puller by rotating the handle (37) forward.
Repeat the operation for the other ring. When mounting the tapered rings verify
that in doing so the rubber membrane is neither stretched beyond its natural
length, nor bunched up between the two tapered rings. Place a layer of black
electrical tape in order to cover most of tapered rings and a section of the rubber
membrane sticking out from the outward edge of these rings. Do not tape over
the opening that delivers the gas from the upper guard cell to the lower guard
cell. Pressurize the measuring cell (100 kPa approx.) and verify for leaks.
6
E1001C-10042011 GAM-II
Step 4 Place an o-ring (30b) in each of the two grooves. Spread a thin layer of molycoat
or appropriate rubber grease over the probe core and membrane. Pay particular
attention to coat the tape covering the inner tapered rings. Remove the
temporary tape that covers each metallic sheath extremity. Slide, while rotating
counter and clockwise, the outer protective sheath over the membrane (31) and
the body of the probe. Push the sheath forward holding it at the far end from the
probe. This will favor the opening of the sheath’s leading edge and facilitate the
installation.
Center the sheath with respect to the O-rings (30b). When centered, the sheath
should cover a few of the inside threads at the probe extremities. To ensure
that the two o-rings remained in place, lift each end of the sheath up and
physically inspect the location of each o-ring. Replace the electrical tape at
both extremities of the external sheath with the equivalent of 1 to 1.5 layers of
electrical tape. Apply the lubricant to both outer sheath extremities. Check the
inner membrane seal by inserting a 3X5 connector hooked up to position 10 on
the control unit. Place valve on 6 and increase the pressure to 100 or 200 kPa.
Close valve 10 and listen and look for leaks. The probe should remain inflated.
Slide the tapered retaining rings (Yellow Vulcolan or metallic rings) in place over
the ends of the outer sheath. Orient the tapered rings such that the thickest
extremity points outward. Screw the brass cover nuts (35) on to the body of the
probe. This will advance the outer tapered sleeves inward providing a seal
between the sheath and the o-rings. Continue to advance the brass nuts until
same length of thread is exposed beyond both the nuts. When advancing the
nuts verify that no relative movement between the sheath and probe body
occurs. This can be achieved by holding the outer sheath in position with two
screw clamps temporarily positioned on the outer sheath. Position one of the
clamps near the inner edge of the vulcolan collar. Position the other clamp over
the adjacent inner tapered ring. Tighten securely but do not overtighten to the
point of cutting the inner rubber layers.
3.2.2 DISASSEMBLY
Step 1 Stand the probe up in a 5-gallon pail of water. Clean the probe thoroughly with
a nylon bristle brush. Remove the probe shoe.
Step 2 Screw the probe to vice adaptor onto one extremity of the probe and clamp the
adaptor in a bench vice.
Step 3 Using a strap wrench, unscrew the brass knurled nut (35) at the free end of the
probe.
7
E1001C-10042011 GAM-II
Step 6 Remove the outer sheath (33). If required remove the tape holding the strips at
either extremity (replace with new tape upon reassembly).
Step 7 Remove the O-ring at the free end of the probe (30b).
Step 8 Install the long extension arms and bushing appropriate to the probe size, on
the puller.
Step 9 Place puller on the free extremity of the probe and grasp the membrane ring (32)
with the 3 claws (Ref step 3, figure A). Rotate the puller handle backwards.
This will free the membrane ring (Ref step 3, figure B).
Step 11 Slide the membrane rings towards the center of the probe and remove the
rubber membrane (31).
8
E1001C-10042011 GAM-II
When the control unit and central tube saturation are complete, proceed to the second
phase which is the filling and saturation of the probe itself.
The step-by-step procedure related to the two phases of filling and saturation is described
in detail in Section 4.
3.4 CALIBRATIONS
3.4.1 GENERAL
The deformability of the different materials submitted to a pressuremeter test varies over a
wide range. Materials previously tested include soft and stiff soils, glacial till, soft rocks,
ice, frozen ground and boulders.
- The pressure calibration of the probe performed at ground level, beside the control
unit, unconfined, to establish its own pressure-volume relationship. This is a measure
of the probe inertia.
- The volume calibration of the complete system including the probe, coaxial tubing and
control unit circuitry. The probe is confined by placing it in a steel casing. The
pressure-volume relationship of the system is determined. This calibration is a
measure of the intrinsic volumetric expansion of the components under pressure.
The first calibration applies to low to medium rigidity soils. The second calibration is used
when testing highly rigid soils and soft rock.
In the first case a relatively low pressure (100 to 300 kPa) is necessary to inflate the probe
to its maximum capacity. However, in the second case, high pressures (6000 kPa) are
necessary. The coefficient of the system’s deformation is calculated between 3000 kPa and
6000 kPa. Small volumes of water are injected in the probe (from .07 to .15 cc/100 kPa).
The value depends on the probe diameter and the tubing length; an 80 meter tubing length
with the N probe is between .12 to .15 cc/100 kPa. Should the volume coefficient lie
significantly (>50%) above the specified range, it generally signals a faulty system.
The combined deformation of the coaxial tubing, the control unit circuits and the probe
itself is significant in high-pressure testing relative to the total deformation measured. In
most soil testing, this combined deformation is negligible with respect to the total
deformation.
The significance of the volume coefficient and the repeatability of measurement of the
system expansion increase exponentially with increasing modulus values. Ultimately the
system deformation approaches the tested material’s deformation limiting the instrument
to moduli of 5 GPa (700 000 psi).
Either one or both of the calibration tests described above should be performed when any
one of the following conditions is met:
9
E1001C-10042011 GAM-II
- If a membrane and/or protective sheath are replaced. In this case, before proceeding
with the inertia calibration it is advisable to inflate the probe several times.
- If the same membrane and protective sheath have been used for a large number of
tests, the calibration should be checked.
- If the coaxial tubing has to be changed.
- If the ambient temperature at the test location or in the borehole is substantially
different than the temperature that prevailed during the last calibration.
It should be emphasized that calibration tests are important if one wants to arrive at
representative results. It is recommended to calibrate regularly.
As mentioned previously the probe inertia calibration is done with the probe at ground
level, beside the control unit and unconfined. The calibration is carried out following the
instructions in Section 4 under low pressure calibration. The probe is inflated in 25 kPa
increments to a volume of approximately 75% of Vo. The pressure-volume relationship is
plotted for the pressure read on the pressure gage. Figure below shows a typical pressure-
volume data plot obtained from an inertia calibration. This curve is subsequently used for
data interpretation.
10
E1001C-10042011 GAM-II
When a pressuremeter test is performed, the volume variations measured on the control
unit are a combination of the volume changes due to the materials’ deformation, to the
slight deformation undergone by the coaxial tubing, to the expansion of the control unit
circuits and finally, to the compressibility of the rubber membrane and the protective
sheath. In high-pressure testing performed on stiff soils or rock, the former represent a
significant proportion of the total deformation.
The GAM-II pressuremeter has two standard pressure ranges. They are:
The limit pressure is first estimated to relate expected limit pressure to a known soil
parameter. Eight to 12 pressure levels are required to adequately define the pressuremeter
curve and parameters for the tested material. To determine the pressure increment size
divide the estimated limit pressure by 10. The pressure is increased incrementally
approaching the pressure from below and maintained for 1 minute. The ramp up period
between intervals is from15 to 30 seconds increasing with the pressure increment size.
The volume readings are recorded 30 and 60 seconds after reaching the pressure level. The
volume scale is in cm3 or .02 cm3 when knob under sight tube is unscrewed and valve 4 is
set at high sensitivity. This knob is located under the water reservoir. One may get access
to this knob after opening front panel. The ‘’high sensitivity’’ position increases the volume
readings’ resolution. This is generally necessary when testing rock at pressures above
3000 kPa.
Once the 60 second reading is recorded, the pressure is increased by one increment and
the sequence repeated. It is preferable, so as not to disturb the differential pressure, not to
decrease pressure once the pressure setting is reached. Instead record the actual pressure
level and the corresponding volume.
The test is stopped when the suggested limiting combination of values for pressure and
volume are reached.
The high pressure range is required to test from very stiff soil deposits to soft rock. It is
not uncommon for the glacial till or an over consolidated sand to show a limit pressure
“PL” above 5000 kPa. The pressure is increased in 500 kPa increments. Readings are
recorded 30 and 60 seconds after the pressure level is reached or when the readings have
stabilized, whichever comes first.
11
E1001C-10042011 GAM-II
1. The central measuring cell rubber membrane must always be in full contact
with the metallic sheath liner.
2. The membrane must not exhibit relative axial deformation with increasing
pressure.
These conditions are met if the pressure in the measuring cell less the cell membrane’s
inertia exceeds the gas pressure in the guard cells by a constant differential pressure.
This differential pressure must remain constant over the total test pressure range.
The pressure applied to the material by the central measuring cell at the probe level is
comprised of:
i. The gas pressure applied to the water reservoir in the control unit and
readout on gages 5, 6 or 17.
ii. The water pressure exerted by the water column between the probe center
and the ground surface elevations.
iii. The pressure decrease due to inertia of the probe. This pressure P i,
determined by the unconfined pressure loss calibration, decreases the net
pressure applied to the test material.
Where P net applied measuring = the pressure applied to the soil or rock
P gage 5, 6 or 17 = the gas pressure reading at gage 5, 6 or 17 on the
control panel
= the water density
h = the difference in elevation between the center of the
probe and the center of the control unit.
The gas pressure applied to the guard cells to the tested material above and below the
measuring cell is equal to:
12
E1001C-10042011 GAM-II
The differential pressure across the measuring cell membrane between the guard cell and
the measuring cell must remain constant. This pressure is set at 100 kPa for low pressure
(0-2500 kPa) for testing in soils and at 400 kPa for high pressure (0-10000 kPa) for test
stiff soils or soft rocks. These values were chosen to ensure that the measuring cell is
always in contact with the inner wall of the metallic sheath. They are a function of the
maximum error between the pressure gages with the same range.
With the probe at 1 meter below ground surface and a total differential pressure required
of 100 kPa, the pneumatic component of the differential pressure is +92 kPa. That is gage
5 must be set to lead gage 7 by 92 kPa. For each meter additional meter of probe depth
the pneumatic component of the differential decrease by 9.8 kilopascals.
At 10 meters depth, the pneumatic differential is 0 and the differential pressure at the
probe level is 100 kPa.
The above is valid for the high pressure gages, with the exceptions that the differential for
these gages calls for 400 kPa and valve 3 is placed on greater than 10 meters for all depths
below 40 meters.
13
E1001C-10042011 GAM-II
4 OPERATIONS
On the water circuit : a 0-2500 kPa, 0-6000 kPa, and 0-10000 kPa gage. A lower range
gage, for example 0-600 kPa, can be fitted to quick connector 17 to give more accurate
readings at these lower pressures for soils with weak stress-strain properties.
On the gas circuit : a 0-2500 kPa, and 0-10000 kPa gage. In the same manner, inlet 16
can be used to add lower pressure range gages.
WARNING : The gages plugged to quick connectors 16 and 17 are active no matter
what the position of valves 14 and 15 are. Take care to close these valves
or remove gages with low pressure ranges whenever necessary.
Once the gages have been chosen, check that they are set to zero, if not use the knurled
buttons or the screws on the gages to do so.
To drain the control panel, connect the filler funnel to outlet 12e. Turn valve 2 to "Water".
The water in the control panel empties out by gravity.
14
E1001C-10042011 GAM-II
When 300 cc of water have been injected in the probe, disconnect the 4 x 4 connector
from probe; water will be expulsed from probe with air bubbles. Repeat this operation
until the water ejected from the probe contains no air bubbles; then reconnect 4 x 4 to
probe.
In the execution of the latter phase, care should be taken not to let the water in the
reservoir drop below the 800 cc level. Otherwise, gas bubbles will get into water circuit. In
that case, refill the control panel, then saturate tubing and probe again.
At the end of the procedure, unscrew pressure regulator 9. Bleed the pressure in each
circuit with valve 2, and then reconnect the probe tubing onto the control panel. The quick
connectors are designed to prevent any air from entering the tubing.
15
E1001C-10042011 GAM-II
1 90 1 390
2 80 2 380
3 70 3 370
4 0-10 m Pressure 60 4 360
on water circuit 0-10 m Pressure on
5 50 5 350
gage is greater water circuit gage is
6 than pressure on 40 6 greater than 340
gas circuit gage. pressure on gas
7 30 7 circuit gage. 330
8 20 8 320
9 10 9 310
10 0 10 300
11 10 11 290
>10m Pressure on 20 20 200
12 gas circuit gage is
20 greater than 100 30 100
pressure on water
25 circuit gage
150 40 0
30 200 50 100
>10m Pressure on
50 60 gas circuit gage is 200
greater than
70 pressure on water
circuit gage
16
E1001C-10042011 GAM-II
1) Disconnect tubing
from the control panel
2) Turn valve 3
to "0-11 m"
5) Read pressure
on gas circuit gage
no yes no
17
E1001C-10042011 GAM-II
4.6 TESTING
Valve 4 on closed.
Lower probe to the required elevation.
Adjust the pressure differential.
Valves 1 and 2 on test.
Make sure appropriate manometers are selected (valves 14 & 15).
Valve 3 on 0-11 m or >11 m according to test depth table
Valve 4 on test.
Water will flow by gravity from the reservoir into the probe.
Note the volume reading once the level in sight tube has stabilized.
With the pressure regulator, adjust the central cell pressure gage to the first pressure
step (one tenth of the expected limit pressure).
Note volumes reading 30 seconds and 60 seconds after the pressure step has been
reached.
The pressure is increased by equal increments to the limit pressure (700 cc of
injection). To avoid bursting the probe, it is recommended to stop injection around
75% of Vo.
To depressurize the system:
Reduce pressure to zero with regulator 9.
Valve 3 set horizontally (on ‘’bleed’’ i.e. > 11m).
Valve 2 set slowly on ‘’water’’
When manometer 7 (or 16) displays about 500 kPa, set valve 1 on closed.
When all water is back in water reservoir, set valve 4 on close, valve 2 on ‘’gas’’ and
at the same time valve 1 on ‘’test’’
Inflation of the probe must be done slowly to minimize risks of bursting the sheath
To use the pressuremeter above 2500 kPa, the following modifications must be made.
Connect the 0-10 000 kPa pressure gages and set valves 14 and 15 at gage 16 and
17.
18
E1001C-10042011 GAM-II
For tests in soft rock, the dilatation of the pressuremeter-tubing-probe system under
pressure is determined by calibrating the system with the probe placed in a rigid steel
casing. The procedure is as follows:
Fill and saturate pressuremeter and probe.
Adjust pressure differential to 400 kPa.
Valve 15 on gage 16.
Valve 14 on gage 17.
Put high pressure spring in the pressure regulator.
Valve 3 on 0-11 m.
Place probe in steel casing:
44 mm dia. probe - A size casing
60 mm dia. probe - B size casing
70 mm dia. probe - N size casing
Valve 1, 2 and 4 on test.
With pressure regulator, apply 500 kPa pressure to the central cell.
Note the volume reading when the water level in the sight tube has stabilized.
Increase pressure by 500 kPa increments taking volume readings when the water
level has stabilized.
When the volume changes become imperceptible, screw knurled knob located
underneath the sight tube and set valve 4 on ‘’ high sensitivity’’.
In this position, the volume changes are amplified 50 times (i.e. 1 scale unit - .02 cc).
Continue increasing the pressure to 6000 kPa in 500 kPa increments taking volume
readings at each step.
When calibration is completed, position set valve 4 on test and unscrew knurled
knob. The factor of correction due to dilatation of the pressuremeter system is a =
dv/dp.
19
E1001C-10042011 GAM-II
Consequently, depending on the depth, turn valve 2 slowly onto either "gas" or "water"
while watching either gage 7 - or that fitted into 16 -, or the gages 5 or 6 - or that fitted
into 17 - to realize the first negative pressure increment. The differential valve acts on the
other circuit to maintain differential pressure between the two circuits.
Repeat the same operation to unload to the next pressure level. Reloading is carried out as
in a standard test.
20
E1001C-10042011 GAM-II
During winter, it is necessary to use an antifreeze liquid instead of water. A mixture of 50%
Ethylene glycol - 50% water is recommended. It allows work to -23C. The use of windshield
washer liquid or “Prestone” is not recommended; this may induce deposits that could block
tubing and fittings, and is at the risk of the user.
When the control unit is used at very low temperatures, the Whitey valves with Teflon seal
may leak. To stop the leakage, remove the black handle of the valve with a 3/32" Allen key
and slightly screw the packing bolt with the special two-pin tool provided (tightening tool) in
1/8th turn increments. Usually, the first 1/8th turn will prove sufficient.
The spring in the differential valve has a 500-kPa range approximately. Consequently, for
tests in soil at depths exceeding 60 m, an additional differential valve must be mounted in
series in order to increase range of differential pressure. The additional differential valve is
installed between the main pressure regulator and the differential valve on the control
panel.
The borehole MUST be filled with drilling mud to limit the expansion of the probe before
the test starts.
The tubing and the probe must be perfectly saturated and be filled with specially de-aired
water to prevent air bubbles rising in the tubing. This would alter the value of the
hydrostatic pressure at in the probe.
Regulate the differential pressure before lowering the probe down the borehole, the hose
being disconnected.
Close water circuit valve 4 to prevent any expansion as the probe is lowered down the hole
with the risk of jamming it above the designated test depth. Re-open this valve just before
the start of the test.
Pressure increments must be obtained slowly. The readings at 30 and 60 seconds should
only be taken after the pressure reading on the gage has stabilized.
21
E1001C-10042011 GAM-II
The limit pressure PL corresponds theoretically to the pressure required to double the
volume of the initial cavity. The total injected volume is then equal to Vo plus twice the
volume injected in order that the probe contacts the walls of the borehole. This value is
generally obtained by extrapolation.
22
E1001C-10042011 GAM-II
6 MAINTENANCE
6.1 FILTER
Filter in the control panel prevent water and gas circuits from becoming contaminated with
foreign particles. This filter should be cleaned and changed periodically.
Unscrew back of differential valve 8, remove valve 4, and clean off the fine dust that
might have stuck to it, preventing seal 5 to tighten down correctly.
Reassemble the valve.
* the outlet connector is similar to the inlet connector without filter (6 1/8
connector).
23
E1001C-10042011 GAM-II
Problem: The regulated pressure continues to increase after lock-up and without
change in control knob position.
Possible cause:
1. Valve seat (22) needs replacement.
2. Sensor assembly needs cleaning and seal replacement.
Problem: Regulated pressure drops off sharply when flow is within regulator
capabilities.
Main valve seat (22) needs replacement.
24
E1001C-10042011 GAM-II
Control Panel
1 Rilsan tubing 5 mm X 3 mm
2 Tecalan tubing
3 Tecalan connector ass’y
4 10 mm Nut
5 10 mm Ferrule HP
6 4 x 3 connector
7 O-ring øi: 0.087” X w: 0.031”(Bunan)
1 Double connector
2 Internal tube
25
E1001C-10042011 GAM-II
Pressure Regulator
1 Plug button
2 Circlip
3 Hand knob
4 Bonnet
5 Screw
6 Thrust washer
7 Thrust spring
8 Thrust bearing
9 Thrust washer
10 Adjusting screw
11 Limit screw
12 Spring cap assembly
13 Vent valve rod
14 Load spring
15 Sensor assembly
17 O-ring
18 Connector
19 Main valve assembly
20 Regulator body
21 Retaining seat
22 Main valve seat
23 Back-up ring
24 O-ring
26 Main valve
27 Spring
28 Filter assembly
29 Spring pad
30 Sensor back up
31 Vent valve seat
33 O-ring
34 Vent Valve
35 Spring
36 Sensor
26
E1001C-10042011 GAM-II
Front panel
13 27 7 1 33 32
26
35 30
19
41
20
36 25
25 15
18
27
16
6
2
24
40
34
27
39
5 31
23 30
17
9
37 8
14
28
21
10
25 25
29
38
36 20 19 4 12 12 11 30 39
27
E1001C-10042011 GAM-II
Rear panel
1 11 27 26 25 4 12 17
21
19
11
11
28 20
1
24
5
29
11
12
2
17 19
17
11
20
13 15
30
15 11
15 4
3
2
31 23
11 17
32
19
11
33 11
15
7
6 22
34
42
15 20
35
18
8
36
18
41
20
37 17
38 16
19 9 10 1 11 39 40 15
15 15
28
E1001C-10042011 GAM-II
29
E1001C-10042011 GAM-II
Pressure regulator
30