Coding
Coding
REV.NO. R0 R1 ISSUE
CONTENTS
1.0 SCOPE 1
2.0 PURPOSE 1
3.0 RESPONSIBILITY 2
APPENDICES
2. SERVICE/FLUID CODES 13
3. INSULATION CODES 15
ISSUE
R1
REVISION STATUS
R0 96.04.10 -----
ISSUE
R1
1.0 SCOPE
1.1 This document describes the systems to be followed for designating lines, tagging
valves and specialities and specifying piping material codes for non-chemical and
chemical projects. Chemical projects also include industrial projects.
1.2 Where a client or a collaborator has a specific system of designation or tagging, the
same is to be followed. IBR and non-IBR systems have to be separately identified.
2.0 PURPOSE
2.1.1 The purpose of allotting a line number is to uniquely identify the line during
engineering so that the attributes given to the line and the line conditions can be
described and used for further engineering. These data may be operating and
design pressure and temperatures, field leak test data, insulation requirements as
well as any special requirements such as steam-out etc.
2.1.2 The line number also helps in making bills of materials line-wise for procurement
as well as helping in material control at site and during fabrication, installation,
testing and commissioning of piping systems.
2.2.1 The purpose of giving tag numbers is to identify the valve or speciality. This is
intended to facilitate procurement and installation.
2.2.2 As far as possible, tag numbers without serial numbers are recommended in order to
simplify design office work and field installation. If serial numbers are essential
from the operational point of view, these numbers shall be given later.
2.3.1 The intent of giving material specification code as a part of line designation number
is to uniquely identify the relevant piping material specification.
2.3.2 Piping material codes are classified based on the basic material of construction
(carbon steel, alloy steel, stainless steel, HDPE etc.), the pressure class (150, 300
etc.) and statutory requirement (IBR).
ISSUE
R1
3.0 RESPONSIBILITY
3.1 The responsibility for allotting line numbers and preparation of line designation
schedules is as follows :
Piping Group in Mechanical Department – for all projects other than chemical and
for the utility systems in chemical projects.
3.2 The responsibility of identifying valve and speciality tag numbers lies with the
group generating the P and I Diagrams (P&I Ds) with the guidance of piping group
as required.
3.3 The responsibility of identifying the right piping material specification code rests
with the piping group. However, the chemical engineer or system designer are
responsible in providing right information regarding the basic material of
construction and the design parameters affecting the selection.
ISSUE
R1
LINE NUMBER, A
MININUM OF THREE
DIGITS
INSULATION CODE
AS PER APPENDIX-3
PIPING MATERIAL
SPECIFICATION CODE
AS PER APPENDIX-1
This shall be as per Appendix-2, unless the client or collaborator has stipulated a
specific system to be followed.
This shall be nominal size in millimetres. Inch units for line sizes may be followed
based on client’s or collaborator’s specific requirement. As far as possible the same
units shall be followed throughout a project.
4.5.1 The service/fluid codes for non-chemical and chemical projects shall be generally
as per Appendix-2. Where applicable, service/fluid codes given by the client or
collaborator shall be followed.
4.5.2 Use of ‘s’ and ‘r’, in the fluid code, for supply and return lines shall be avoided.
4.5.3 It is recommended that line numbers be uniquely given and not related to any fluid
or service. However, if any difficulty is encountered in following this practice, then
for each service/fluid code, serial numbers can start from unity. With the latter
ISSUE
R1
practice, a line is completely identified only if both the service/fluid and the number
are known. Process and non-process lines shall have separate sequence of numbers.
4.5.4 For chemical projects, a block of serial numbers shall be allotted for each P&I D.
Numbers allotted, numbers used, number deleted and unused numbers may be
shown in the form of a block above the title block.
4.5.5 As far as possible, line numbers may be assigned only to lines carrying flow away
from an equipment. Lines carrying flow to an equipment shall be numbered at their
point of origin.
4.5.6 For the sake of uniformity, numbering may be started from the left side of a P&I D
and proceeded towards the right side. Also around an equipment, numbering of the
lines may be done in a counter-clockwise direction.
4.5.7 It is recommended that a few line numbers be left unassigned for future use.
4.5.8 To facilitate, generation of bill of materials for trim piping of an equipment (inlet of
piping of safety valves mounted on equipment, equipment instrumentation etc.) it is
advisable to give a “miscellaneous” line number for an equipment. This number
shall have the correct identification of the piping specification code depending on
which portion of the equipment, the item is connected to.
4.5.9 Avoid giving line numbers to bypass piping of control valves, steam traps etc.
4.5.10 Line number shall be maintained even if there is a size or specification change
along the line. Provision to show all the sizes and all the specifications shall be
made in the line designation schedule.
4.5.11 When flow splits to two or more equipment, the line number changes, one carrying
the same number, others new numbers.
4.5.12 Where lines of different piping specifications join, the segregating valve shall be of
the higher or the more stringent specification.
ISSUE
R1
5.1.1 For gate, globe, check, ball and angle valves upto and including 50 mm size.
Size code
Valve type code
Valve material code
Pressure class code
5.1.2 For all valves above 50 mm size and for power-actuated valves of all sizes and
types including butterfly, rotary, slide, push bottom, Y type foot valve and pinch
valves.
Serial number
Valve material Code
Pressure class code
5.1.3 For all specialities like traps, strainers, safety valves, etc.
AAA-NNN
Serial number
Speciality code
ISSUE
R1
Cast iron CI
Carbon steel CS
Bronze BR
Stainless steel SS
Nickel NI
Monel MO
Inconel IN
Hastealloy B HB
Hastealloy C HC
Titanium TI
Aluminium bronze AB
Alloy Steel AS
Alloy cast iron AK
Other materials OM
ISSUE
R1
Gate 1
Globe 2
Check 3
Angle 4
Ball 5
Needle 6
Diaphragm 7
Plug cock 8
Size Code
mm inch
6 ¼ 1
15 ½ 2
20 ¾ 3
25 1 4
40 1½ 6
50 2 8
Type Code
Expansion joints E
Traps T
Strainer S
Safety and relief valves SV
Air release valves AV
5.2.1 Valves
A N N Suffix (A)
Valve type Valve Valve body For special
code. pressure material requirement
class code code
ISSUE
R1
5.2.2 Specialities
AA NNN
Speciality Serial Number
type code
G - Gate
T - Globe (Throttling)
C - Check
B - Ball
P - Lubricated plug
U - Butterfly
L - Sleeved plug valve
D - Diaphragm
N - Needle
R - Rotary
K - Piston (Klinger type)
1 - 125 class
2 - 150 class
3 - 300 class
6 - 600/800 class
9 - 900 class
1 - bronze
2 - cast iron
3 - carbon steel
4 - reserved
5 - reserved
6 - polypropylene
7 - SS 304
8 - SS 316
9 - SS 321
5.2.6 Suffix
I - IBR
G - Valves with grooved flanges
J - Jacketed
ISSUE
R1
5.2.7 Speciality
EJ - Expansion joint
ST - Steam trap
S - Strainer
AV - Air release valve
VB - Vacuum breaker valve
FA - Flame arrester
FB - Flush bottom valve
AL - Angle valve
FT - Foot valve
FL - Float valve
H - Hose
5.2.8 NOTES
For chemical jobs, if process collaborator has given the tagging system and
is already incorporated on the P & IDs, follow the same. As far as possible,
avoid giving serial numbers to valves, which increase the design and
erection time. If serial numbers are required from operational point of view
the same are to be given at a later date after completion of engineering.
ISSUE
R1
APPENDIX-1
ISSUE
R1
APPENDIX-1 (CONTD.)
APPENDIX-1 (CONTD.)
NOTES
1. The first character in the piping material specification codes indicates the material,
broadly as under :
ISSUE
R1
APPENDIX-2
SERVICE/FLUID CODES
ISSUE
R1
APPENDIX-2 (CONTD.)
NOTES
1. In case chilled brine at different temperatures is used in the same plant, it can be
designated as HBR, MBR, LBR, etc.
ISSUE
R1
APPENDIX-3
INSULATION CODES
n - no insulation
Ih - insulation (hot)
Ic - insulation (cold)
ISSUE
R1