Technical Specification
Technical Specification
and
TENDER DOCUMENTS
PART 2 – REQUIREMENTS
Volume II
TECHNICAL SPECIFICATIONS
Chisinau, 2017
Volume II - Specifications
TABLE OF CONTENSE
PREAMBLE 12
TECHNICAL SPECIFICATIONS 13
0. GENERAL REQUIREMENTS 13
1. PREPARATORY WORKS 60
2. EARTHWORKS 69
3. PAVEMENT 84
The Contract may not fully describe every detail or contains specific allowances for all probable
occurrences, exceptions and contingencies. The Engineer has the authority to administer the
contract, to rule on discrepancies arising, to fulfil intentions, and to allow for construction needs
to ensure the performance and completion of the work.
The Contractor shall construct and complete the project in every detail as described in the
Drawings, the Specifications and the Bill of Quantities.
The Contractor shall consider the public interests as well as obligations and rights of all other
parties involved. The Contractor has to take full responsibility for the performance of the work
and agrees to furnish with labour, materials, equipment, tools, supplies, transportation, and
other incidentals necessary or convenient for a successful completion of the project.
0. GENERAL REQUIREMENTS
CHAPTER 001. ACCEPTANCE OF WORKS
001.00. Conformity with Contract and Project Requirements
Wherever reference is made in the Contract to specific standards and codes to be met by the
materials, Plant, and other supplies to be furnished, and work performed or tested, the
provisions of the latest current edition or revision of the relevant standards and codes in effect
shall apply, unless otherwise expressly stated in the Contract. Where such standards and codes
are national, or relate to a particular country or region, other authoritative standards which
ensure a substantially equal or higher performance than the standards and codes specified will
be accepted subject to the Engineer’s prior review and written approval. Differences between
the standards specified and the proposed alternative standards must be fully described in
writing by the Contractor and submitted to the Engineer at least 28 days prior to the date when
the Contractor desires the Engineer’s approval. In the event the Engineer determines that such
proposed deviations do not ensure substantially equal performance or that the deviations run
counter to the established legal requirements of the Employer’s country, the Contractor shall
comply with the standards specified in the documents.
The works shall be executed entirely in accordance with the requirements of the Contract,
including the requirements of this Specification. All works shall be executed in accordance with
the required lines, grades, cross - sections, dimensions, processes and material requirements
shown on the plans or specified in the contract or design documents.
The works shall be executed in compliance with the provisions of Law on quality in construction
No.271 dated February 2, 1996. The State Construction Inspectorate is empowered to initiate
controls on quality of works, laboratory tests, compliance with design, construction standards
and norms, and abovementioned Law.
Plan dimensions and contract specification values are to be complied with subject only to the
variances and tolerances specifically allowed for in this Specification. Works and materials shall
be uniform in character and meet the specified requirements.
The Engineer may inspect, sample or test all work at any time before final acceptance of the
project. When the Engineer tests work, copies of test reports are furnished to the Contractor.
Engineer's tests may or may not be performed at the work site.
Acceptable work conforming to the contract will be paid for at the contract unit bid price.
Methods of determining conformity and accepting work are described in Subsection 001.02 to
001.04 inclusive. The primary method of acceptance is specified in each Section of work.
Where appropriate, acceptance of work shall be in accordance with Sub-Clause 002.03 and
Sub-Clause 002.04 of Chapter 002.
Work shall be rejected at any time it is found not to comply with the specifications and drawings.
The initial acceptance of work does not imply that the work necessarily complies with the
Contract requirements. Work may be inspected and rechecked for conformity at any time and
work found not to conform shall be rectified or removed and replaced by the Contractor at no
cost to the Employer.
Work that does not conform to the project and contract requirements or to prevailing industry
standards where no specific contract requirements are noted, shall be removed and replaced at
no cost to the Employer.
Road Sector Program Support Project, Moldova
13
001.01. Technical Inspection
Acceptance is based on technical inspection of executed works to confirm compliance with the
contract documents and prevailing relevant technical standards. Payment for work during the
course of the project will be made as the work progresses provided it is in compliance with the
drawings and specifications.
The Contractor shall submit checking requests to the Engineer, giving a minimum period of
notice of at least 24 hours before the scheduled commencement of works in order to allow the
Engineer time to carry out a full and detailed inspection of the works. The checking request
signed by the Engineer shall be the basis for the payment certificate.
00501 Provide site laboratory including office for The Engineer Lump-sum
The Contractor shall, before placing any order for materials for incorporation in the Works,
submit for the information of the Engineer the names of the firms from whom he proposes to
obtain such materials. He shall give descriptions, manufacturer's specifications, the quality,
weight, strength and origin of the materials, as applicable, and confirm the quantities to be
procured. The Contractor shall provide the Engineer with samples of materials when requested,
details of the supplier's quality assurance system and, where appropriate, manufacturer's
certificates of recent tests carried out on similar materials. In accordance with Clause 7.3 of the
Conditions of the Contract the Engineer may require to visit the facilities of any manufacturer or
supplier.
The Contractor shall carry out trials of all concrete mixes, bituminous mixes and mixtures of
others materials to demonstrate that, not only are the constituents in compliance with the
Specifications, but that the resultant mixtures also comply. He shall show as part of the quality
assurance system the relationship between trial and job mixes and his proposals for maintaining
the quality of all mixes on site.
The Contractor shall keep a Non-conformity register and a Concession Request register that
shall be copied to the Engineer each month. Concession requests for materials or work that
does not meet the requirements of the Specifications (as recorded in the non-conformity
register) shall be forwarded to the Engineer as a part of the routine Quality Assurance
inspection system (Request for Inspection System). Requests for Inspection of the works shall
generally be forwarded to the Engineer not later than 17h00 for works to be carried out on the
following day, to enable the Engineer to allocate personnel to do the independent checking.
The Contractor shall provide a detailed programme according to Sub-Clause 8.3 of the
Conditions of Contract within 28 days of receiving the notice to commence the works. This shall
include the following:
• a detailed time schedule including allowance for the Contractor’s Documents
(Construction Drawings), materials approval and procurement, manufacture of
permanent Plant for the works (if any), delivery to Site, construction and testing;
• a time schedule that identifies the sequence, frequency and timing of tests required in
the Contract in conjunction with the item above;
• a general method statement for the Works;
• an estimate of the Pieces and class of Contractor’s Personnel and Contractor’s
Equipment required for each activity;
• a cash flow in conjunction with the first item above.
Failure to comply with this requirement will result to a penalty of 1000 EURO/ day calculated
from the end of the 28 days period, but should not exceed 0,5% of the Contract price.
At the time that possession of site is given, a site inspection shall take place , attended by
representatives of the Engineer, the Contractor and the Employer, to record the general
Road Sector Program Support Project, Moldova
28
conditions and locations of road signs, street furniture and any other items, and to determine the
measures necessary to safeguard such facilities.
In accordance with current legislation, the Contractor shall be held accountable for road
accidents on the Site (so far as the same is under his control) caused by non-compliance with
the contract provisions and the traffic management and road maintenance requirements during
the execution of the road works by the Contractor or his Subcontractors.
Measurement
Traffic management and road maintenance measures of all kinds as outlined above or as
necessitated by any other requirement of the Contract will be measured as monthly rates.
Road Sector Program Support Project, Moldova
30
Payment
The cost and expenses for traffic management and road maintenance will be paid monthly
throughout the construction period.
In the event of persistently inadequate traffic management measures under this item for any
month during the construction period the Engineer may deduct the monthly amount for that
month. Any such amounts deducted shall not be recoverable later.
In the event of persistently inadequate road maintenance measures under this item for any
month during the construction period the Engineer may deduct the monthly amount for that
month. Any such amounts deducted shall not be recoverable later.
Additionally, the Engineer may instruct the Contractor to execute any of the above road
maintenance measures which are urgently required. The Contractor shall comply with the
instruction within the time specified in the instruction. If the Contractor fails to comply with the
instruction, the Employer shall be entitled to employ and pay other persons to carry out the
work, and the Contractor shall pay to the Employer all costs arising from this failure.
Unit of
No. Item
Measure
Install, manage & maintain traffic measures
00701 Month
throughout the period of the works
Perform road maintenance measures for the full
00702 length of the Site (so far as the same is under his Month
control) throughout the period of the works
Payment
Pay item: Insurance Pay unit: Lump Sum
010.03. Storage
The right conditions for cement storage and protection against dampness must be provided.
Cement shall be stored in cool, dry, closed sheds. Cement shall not be stored in the open, on
the ground, or under plastic sheeting.
Under no circumstances shall cement showing any signs of the following damage or
mistreatment be used:
• partially hardened cement
• adulterated cement
• Cement from bags opened previously.
• cement from damaged bags.
Grade 60 – 90 90 – 130
For procurement of the Bitumen the Contactor shall submit Manufacturer’s test certificate with
other relevant documents of the company to get approval of the Engineer. Test certificates shall
be submitted to the Engineer for every delivery of the bitumen to site.
No test method is given for viscosity. Kinematic viscosity at 60°C and 135°C can, in theory, be
measured using Capillary viscoMetres, AASHTO test method T201. However, in practice only T
202 (dynamic viscosity by vacuum capillary) is suitable for penetration grade bitumen at 60°C.
More conveniently, dynamic viscosity can be measured using a rotating spindle type
mechanical viscoMetre; eg Brookfield viscoMetre.
For bitumens where penetration is specified with limits different to those quoted above the
viscosity requirements shall be determined by the Engineer based on a pro rata interpolation
from the above table.
Note that for bitumen acceptance purposes dynamic and kinematic viscosity may be equated on
the basis of 1Pa.s=1000 sq. mm/s
012.02. Crushed stone for road base, binder course and wearing course
The aggregates will result from durable crushed stone in accordance to SNiP 2.05.02-85, SM
GOST 25607-2010. Only crushed stone without organic additions or clay shall be used. Stone
susceptible to freezing-thaw cycle or liable to be blistered in moisture shall not be used.
The right size distribution of the aggregates will be provided under crushing, sizing and mixing
system. Small size aggregates, passing 4.75 mm screen will be natural or crushed sand.
012.04. Sand
The sand used for bituminous mixtures will be in accordance to SM GOST 8736-93.
The sand for the road base will be in accordance to SNiP 2.05.02-85.
012.05. Filler
The filler used for hot bituminous mixture will be in accordance to SM GOST 16557-78.
014.02. Paints
Unless otherwise indicated the protection of metallic elements will be done using paints in
accordance to SNiP 2.03.11-85.
014.03. Geotextiles
Geotextiles shall be in accordance with Chapter 902.
The Plan must include, but is not limited to, provisions to deal with the following problems,
hazards and requirements:
• Welfare measures at the site, including at the accommodation. The Plan shall include
access to fresh drinking water, washing facilities, toilets, shelters for use on breaks,
etc.
• Means of separation of working and traffic areas (Speed restrictions, marking, fencing,
etc.).
• Demolishing existing structures can entail exposure to high noise levels, vibration, dust
and falling debris. The Plan shall explain how machinery noise and vibration will be
mitigated and what personal protection measures will be taken. (Hearing protection
devices, dust masks, protective clothing, etc.).
• Handling raw materials (soils, aggregates, gravels, rock, etc.) and construction of
embankment, subgrade and pavement layers all entail exposure to dust, noise,
vibration and heavy manual handling. The Plan shall describe measures which will be
taken to minimise exposure to dust (watering, provision of masks), reduce noise and
vibration to a practicable minimum (the highest acceptable noise level shall be 85
dBA) and what mechanical equipment will be used to reduce manual handling. The
Plan should also define what level of manual handling will be required after all
mitigating measures have been implemented.
• Working with bituminous materials, especially when hot, entails exposure to the risk of
severe burns and to fumes which, if inhaled will cause severe respiratory organ
Road Sector Program Support Project, Moldova
37
irritation and which are believed to be carcinogenous. Bitumen itself is a suspected
carcinogen and skin contact should be avoided even when cold. The Plan should
describe how contact will be minimised (protective clothing), how fumes will be
avoided (masks, working practices such as keeping upwind of hot bitumen), general
safety equipment (Piecess and locations of fire extinguishers) and the level of first aid
provision at the sites of bitumen transfer, preparationand application (spraying)
including presence of trained personnel, first aid supplies, first aid equipment and easy
access to clean water.
• Similar consideration must be given to the problems of working with more flammable
materials, especially fuels. In addition to first aid, etc. the Plan must detail safe
refuelling procedures to be employed for all static and mobile plant and vehicles.
• Handling of lime (especially quick lime), cement and other activators and additives is
potentially hazardous. The Plan must describe adequate measures which will be taken
to avoid eye and skin contact and inhalation (goggles, protective clothing and masks)
and to minimise manual handling.
• Maintenance of vehicles and machinery frequently involves contact with solvents. The
Plan should describe how skin and eye contact with and inhalation of solvents will be
minimised through the provision of protective clothing and good working practices.
• Wherever dust masks are to be provided these should preferably be of the type with
exhaust valves, making them easier to use. Rubber masks with removable filters are
preferable to paper masks as they generally fit better and they can be used with
different filters for different purposes (dust, solvents, etc.).
• To ensure that workers understand the occupational health and safety risks on the
work site, and that they are aware of the measures available to minimise these risks,
instruction and training must be given. The Plan must describe the instruction and
training to be given and explain how it will actually be delivered to the workforce.
• As a minimum, of direct relevance to operations on the site, instruction and training
must include the dangers of noise, vibration, dust, fumes, traffic, heavy equipment and
heavy manual handling and must explain what measures are available to minimise
these dangers, including the use of protective clothing, including protective footwear,
reflective vests, hard hats, hearing protection devices, protective eyewear, and gloves,
as may be necessary. The use of the required protective clothing shall be mandatory
for all employees on the Site.
In addition to the direct dangers resulting from working on a construction site, the other dangers
arising from living on the site must also be covered in the Plan which must explain how
information relating to everyday health matters will be comprehensively conveyed to the
workforce. Information to be disseminated must include, but is not necessarily limited to,
warnings concerning the health risks of malaria, bilharzias, yellow fever, hepatitis, meningitis,
hook worms, tape worms, intestinal worms, giardia, amoebae, venereal diseases, HIV-AIDS,
scorpions, snakes and stinging insects.
The Plan will acknowledge the Contractor’s responsibility for the health, safety and welfare of
his workforce and describe these responsibilities in detail.
As well as preparing the Plan for Health and Safety the Contractor shall provide, equip and
maintain adequate first aid stations throughout the Works, and he shall erect conspicuous
notice boards directing where these are situated and shall provide all requisite first aid transport.
The Contractor shall comply with the government medical or labour requirements at all times
and provide, equip and maintain first aid stations in easy reach of all his operational areas and
Road Sector Program Support Project, Moldova
38
wherever else directed and shall at all times have experienced persons trained in first-aid
available throughout the Works for attending to minor injuries.
016.01. Revegetation
All cutting and embankment slopes spoil heap and borrow pit slopes and areas of camps and
other temporary works must be revegetated with plants, shrubs and grasses approved by the
Engineer. At the Completion of the Works there shall be no exposed, unvegetated soils
remaining on either the permanent or the temporary works, including the sites of camps, work
stations, etc. On embankments in excess of 3 metres in height the revegetation measures shall
include provision of continuous screening using shrubs and bushes at the back of the soft
shoulder to a height of at least 1.5 metres.
016.05. Dust
Unpaved roads shall be regularly watered to restrict dust caused by construction traffic. Regular
watering means watering at a sufficient frequency to ensure that the running surface is always
damp while the roads are in use by construction traffic.
016.07. Emissions
Construction equipment shall be properly maintained to ensure that emissions are within the
manufacturers published tolerances. Asphalt plants shall be fitted with dust filtering equipment
and no significant emissions of dust will be permitted.
In the event of persistently inadequate environmental management measures under this item
for any month during the construction period the Engineer may deduct the monthly amount for
that month. Any such amounts deducted shall not be recoverable later.
.
No. Item Unit of
Measure
01601 Compliance with environmental management plan requirements Month
GOST 23457-86* Traffic control equipment: road signs, marking, traffic lights,
Replaced by parapets and guiding devices. Application.
94 GOST R 52289-2004 Mijloace tehnice de dirijare a circulatiei rutiere: indicatoare rutiere,
SM GOSTR marcajul, semafoare, parapete, dispozitive de orientare. Reguli de
52289:2009 aplicare.
Asphalt concrete mixtures for road and aerodromes and asphaltic
concrete. Specifications.
95 SM STB 1033-2008
Amestecuri de beton asfaltic pentru drumuri si aerodromuri si beton
asfaltic. Conditii tehnice
Oil bitumens for road pavement wearing course. Specifications.
96 SM STB 1062-2008 Bitumiri de petrol pentru stratul superior al imbracamintei rutiere.
Conditii tehnice.
Asphalt concrete mixtures for road and aerodromes and asphalt
concrete. Methods of testing.
97 SM STB 1115-2008
Amestecuri de beton asfaltic pentru drumuri si aerodromuri si beton
asfaltic. Metode de incercari.
Modified road bitumens. Specifications.
98 SM STB 1220-2008
Bitumiri rutiere modificate. Conditii tehnice.
Cubical crushed stone from dence mountain breeds. Specifications.
99 SM STB 1311-2008
Piatra sparta de forma cubica din roci de munti tari. Conditii tehnice.
Crushed stone-gravel-sand mixtures and soils, treated by inorganic
binder for road and aerodrome construction. Specifications
100 GOST 23558–94* Amestecuri de piatra concasata – prundis-nisip si soluri, prelucrate
cu lianti anorganici pentru constructia drumurilor si aerodromurilor.
Conditii tehnice
Water for concrete and mortar. Specifications.
101 GOST 23732-79
Apa pentru beton si mortar. Conditii tehnice
102 GOST 24143-80 Soils. Laboratory methods for swelling and subsidence
Road Sector Program Support Project, Moldova
50
No./ Type of Standard/
Title Definition / Definitie titlu/denumire
Nr. Tipul normativului
2. Engineer’s Offices
Engineer's offices specified in Chapter 004 shall consist of:
Office 1 20 s q. m.
Office 3 15 sq. m.
Office 4 15 sq. m.
Shower 1 no
Note that the Laboratory accommodation (including covered car parking) is for the exclusive use
of the Engineer. The Contractor must allow for such additional space as he requires for his own
staff.
Drawing stools 1
Saucepans 2 2
Clothes stand 3 1
101.02. General
The Contractor is required to carry out all survey works required for the execution oif the Works.
Basic data in respect of key setting out points and levels will be provided by the Engineer. All
further setting out is the responsibility of the Contractor.
If no changes to the design or contract drawing, then the Engineer pass the Construction
Drawings for the Employer approval, but if there are changes to the design or contract drawings
then the parties should follow GCC 13.1 – 13.3 as applicable and (subject to the approval of
the Employer) issued to the Contractor as ‘Approved for Construction’.
Following the completion of the review/approval process the Contractor shall prepare the Final
Construction Drawings.
Moldovan Law No. 721, on Quality in Construction,
Art. 13. - (1) of Law No. 721, dated 2nd February 1996, on Quality in Construction, requires that
construction works, as well as modernization, change, transformation, consolidation and repair
can be done only based on a project elaborated by natural or legal persons licensed in this field
and checked by State Service for Verification and Expertise of Projects and Constructions.
It is the responsibility of the Contractor to ensure that the final Construction Drawings are
elaborated by natural or legal persons licensed in the respective field, and to resolve non-
conformities and discrepancies reported by the State Service for Verification and Expertise of
Projects and Constructions.
It is the responsibility of the Employer to present the final Construction Drawings for verification
to the State Service for Verification and Expertise of Projects and Constructions.
The time period for the Employer to review of the final Construction Drawings is 14 days from
the date of submission of the final Construction Drawings by the Contractor. Subsequently, the
time period for the Employer to obtain the verification of the final Construction Drawings from
the State Service for Verification and Expertise of Projects and Constructions and to issue the
verified final Construction Drawings to the Contractor is 30 days from the date of Employer’s
approval of the final Construction Drawings.
102.02. Generalities
Wherever the Works require terrain clearing, including removal of shrubs and bushes, removal
of topsoil, and the removal of trees, having a diaMetre exceeding 200 mm at a height of 1 metre
above the ground, such works shall be executed under this Chapter. Topsoil shall be removed
at locations and to a depth to be indicated by the Engineer.
Roots and stumps shall be removed to a depth of at least 1 metre below finished ground or
subgrade level.
Topsoil shall be set aside in areas selected by the Contractor and approved by the Engineer for
reuse in soiling areas of cut and embankment slopes. It shall be carefully preserved and shall
not be mixed with other material. The material must not contain harmful impurities, hard
particles, clay, garbage, stones etc, and shall be used according to SNiP 3.06.03-85 and SNiP
2.05.02-85.
Trees will be removed only where specifically directed by the Engineer. Where trees are
removed the roots and stumps will be extracted to a depth of at least 1.00 m below finished
ground level or below subgrade level as appropriate. The holes will be filled and compacted, in
layers not greater than 20 cm, in accordance with the requirements of Chapter 203.
105.02. Materials
Materials for temporary signs shall comply with the following requirements
• Dimensions of traffic signs for the construction period: SM GOST 10807-78.
• Reflective foils: appendix 3 to SM GOST 10807-78.
• Signposts made of reinforced concrete: SM GOST 25459-82.
105.03. Generalities
Directing and diverting traffic, and separation of the working area shall be carried out in
accordance with the requirements of chapter 007 [Traffic Management] and of the traffic
regulations in VSN 37-84.
During the working period the following requirements shall be observed:
a) The positioning of signposts, barriers, cones and other marking devices will be
proposed by the Contractor and approved by the Engineer before the work starts.
b) Signs, diversions, barriers and other markings shall be limited to those required for the
works actually in progress.
c) The location of temporary signposts, diversions, barriers and other markings will be
changed as needed.
d) The signs, diversions, barriers and other markings which are not required for the
current stage of work will be dismantled or covered.
e) The Contractor will repair or replace any damaged or defective signs, diversions,
barriers and other markings at his own cost immediately upon receipt of a request from
the Engineer to rectify them.
105.04. Barriers
Barriers shall be erected in accordance with Sub-Clause 105.03. Barriers may be of metal,
wood or plastic and shall be erected wherever traffic is required to be diverted from its normal
location on the road. They shall be used in conjunction with cones to separate traffic moving in
opposite directions and to separate work areas from moving traffic.
105.05. Cones
Cones shall be erected in accordance with Sub-Clause 105.03 and shall be used in conjunction
with barriers for the purposes stated in Sub-Clause 105.04 above.
105.13. Acceptance
The execution of the temporary roads and traffic directing installations will be accepted only
when the work is done according to the drawings and the specifications and has been
approved by the Engineer.
Measurements
Measurement of the works required for the provision of authorised diversion roads will be made
in Metres of diversion authorised to be constructed.
No separate payment will be made for temporary traffic signs, barriers or any other measures
for traffic required for the temporary roads or for traffic diversions or for one-way traffic systems
required for the Works. All such traffic management provisions are deemed to be included in the
payment described in Chapter 007 or in the payment for diversion roads described below.
Payment
The provision of approved, authorised diversion roads for the execution of road or bridge works
will be paid by the Metre of diversion road provided at the rate or price per metre in the Bill of
Quantities. Payment will be made only for those locations and lengths of diversion road that are
specifically indicated in the Drawings. Any other diversion road which the Contractor decides to
construct shall be entirely at his own cost.
201.02. Earthworks
Earthworks consist of the following
a) Excavation
Excavation along the length of the road to the full construction profile, excluding the
removal of the topsoil which is stored and reused and which is described in chapter 102
and 203. Excavation includes the excavation, forming and enlargement of roadside drains.
b) The operation of borrow pits
If the volume of suitable material arising from the works of excavation is insufficient to
meet the requirements for construction of embankments, additional material shall be
provided from borrow pits.
c) Stockpiling of suitable material
Under some circumstances during the rectification of slip areas it will be impossible for the
Contractor to reuse material immediately in the embankment. In these cases material shall
be stored and reused at a later date.
d) Embankment construction
The embankments will be executed according to SNiP 2.05.02-85, SNiP 3.02.01-87, SNiP
3.06.03-85.
201.03. Material
The material shall comply with SNiP 2.05.02-85.
The materials for the embankment construction shall be free from “Unsuitable materials”.
Unsuitable material shall include material from swamps, marshes and bogs, peat, logs, stumps,
roots and other perishable or combustible material and highly organic clay and silt material
having a liquid limit above 65%, or more than 80% passing the 75 microns sieves to BS 410 or
such other material as the Engineer may decide.
All fill material for embankment construction, except the 300 mm below formation, shall have a
CBR of not less than 6% measured after a 4-day soak on a laboratory mix compacted to a dry
density of 95 % MDD (AASHTO T180), a swell of less than 1% and a Plasticity Index of less
than 17 and shall be compacted in accordance with NCM D.02.01:2015 Chapter 7.
The fill material in the layer 200 mm below formation (subgrade) in embankments shall have a
CBR of not less than 10% measured after a 4-day soak on a laboratory mix compacted to a dry
density of 95% MDD (AASHTO T180), a swell of less than 1%, сontent of dust particles less
than 50% and a Plasticity Index of less than 7, and shall be compacted in accordance with NCM
D.02.01:2015 Chapter 7.
Road Sector Program Support Project, Moldova
69
The materials for the embankment construction shall not contain oversize materials larger than
100 mm, and for the 300 mm layer below formation level shall not contain oversize larger than
50 mm.
The selected fill materials for shoulder construction shall have less than 30% passing the 75
micron sieve to BS 410, shall have a Plasticity Index less than 17 and shall have a soaked CBR
of not less than 15%, measured after a 4-day soak on a laboratory mix compacted to a dry
density of 95% MDD and shall be compacted to 98% MDD.
201.11. Compaction
During compaction this moisture of the compacted backfill must not vary from the optimum
moisture content by more than 2%. The optimum moisture content for compaction (OMC) and
density shall be determined by testing according to SM GOST 22733-2009 and approved by the
Engineer. Following approval moisture content of the material for compaction it shall not deviate
from the approved value by more than +/- 2%. In the event that soil conditions or type render
the approved OMC invalid a revised OMC shall be determined by new tests and approved.
The particle size distribution is determined according to SM GOST 12536-79. Having the
Engineer’s approval the rate of compaction is determined according to SM GOST 5180-84
using Kovaliov’s equipment.
The types of compaction equipment to be used and the amount of rolling to be done shall be
determined through compaction trials and shall be such as to ensure that the specified densities
are obtained without damage being done to lower layers or structures. During compaction the
layer shall be maintained to the required shape and cross-section, and all holes, ruts and
laminations shall be removed.
201.16. Geotextiles
201.16.01. Introduction
This work consists of furnishing and placing geotextile as a permeable separator or
permanent erosion control measure.
Geotextile types conform and are designated as shown in EN 13249.
201.16.02. General
Where placing a geotextile on native ground, cut the trees and shrubs flush with the
ground surface. Do not remove the topsoil and vegetation mat. Remove all sharp
objects and large rocks. Fill depressions or holes with suitable material to provide a
firm foundation.
Replace or repair all geotextile that is torn, punctured, or muddy. Remove the
damaged area and place a patch of the same type of geotextile overlapping 1 Metre
beyond the damaged area.
201.17.02. Materials
The materials used for these works must comply with the following requirements:
Crushed stone M GOST 8267-93***.
Geotextile (for filter function) item 014.03 of Technical specification.
Measurements
The measurements will be done as follows:
a) Embankment Construction using material from General Excavation or from
Borrow
Measurement will be in cubic Metres in final position to the lines and levels shown on the
drawings measured to the nominal ground level after removal of any topsoil to the depth
as instructed by the Engineer less any volume to be paid as embankment using material
from stockpile. The item includes the roadbed preparation of the in-situ ground below new
embankment. The Contractor will make any necessary adjustments to levels to allow for
settlement of the embankment or of the foundation on which the embankment is placed.
Fill to any areas where unsuitable material has been removed to the instructions of the
Engineer will be measured under this item.
b) Excavation
Excavation to existing shoulders, embankments or cutting slopes will be measured in cubic
Metres. The item will include for the excavation of any materials found with the exception
of rock. Suitable material from the excavation, approved by the Engineer for such use,
shall be incorporated in embankments, or if of suitable quality used as select fill to
shoulders, and all other material, unsuitable or surplus, shall be taken off-site and
disposed of in spoil areas in accordance with the Specification. (The removal of paved
areas is covered in Chapter 302 and foundations to paved areas are covered in Chapter
103). The item includes for the loading and transport of material from areas of cut to the
site of embankment, to shoulders or to spoil. Excavation of benches is included under
general excavation but will only be measured and paid for when the benches are greater
than 750 mm. In vertical height and are specifically called for in the drawings or are
instructed by the Engineer.
c) Borrow Materials
Materials obtained from borrow pits will be measured in cubic Metres as the volume of
material calculated as being required for incorporation into the Works. The item includes
for incidental work as detailed in Sub-Clause 201.07. The volume of material eligible for
payment as Borrow shall be the volume required to make good the required volume of
Embankment construction after deducting the volume of material available from
Excavation and from all other excavation works where excavated material is approved by
the Engineer for use in Embankments. The item includes for the loading and transports of
material from borrow pits to the site of embankment.
d) Shoulders
Select fill for shoulders shall be measured in cubic metres of material required to conform
to the standard cross sections. The rate shall include for sourcing the material, loading,
Payment for the formation of embankment will be made in full when the embankment has been
placed, compacted to Specification and trimmed to shape.
Payment for excavation will be made in full for excavated materials to be placed in Embankment
when the compacted embankment is approved by the Engineer.
For excavated materials directed to be run to spoil, either as unsuitable material or as surplus to
requirements, or to be otherwise disposed of, payment will be in two parts: one half of the
payment due will be made when the material is removed from site and the other half of the
202.03. General
The ditches will be executed according to the project design and, if necessary, any detail design
required on site and the additional instructions of the Engineer, specifying the ditch dimensions,
the bottom grade and the horizontal location.
The ditches will be cleaned periodically and kept in such conditions that water flow in the
ditches is wholly unobstructed.
Where directed by the Engineer or called for in the drawings the material arising from ditch
excavation shall be placed on the downhill side of the ditch as a bund to increase capacity and
provide additional protection to downhill areas. Such bunds shall be constructed with a constant
level difference between crest of bund and invert of ditch. Material will be transported along the
line of the ditch as necessary to meet this requirement. Bunds shall be compacted to 95% of the
theoretical maximum requirement determined by SM GOST 22733-2009.
At the end of the execution and before the issue of the Taking-over certificate, all ditches will be
completely cleaned of tree branches, debris, silt and any other obstructions of whatsoever
nature.
Materials arising from the excavation of ditches shall be used in the construction of
embankments unless utilised in bunds or unsuitable or surplus to requirements. ´
20201 Excavation of ditches outside the road cross section Cubic Metre
Payment for the excavation of ditches shall include for the transportation of material to
embankment sites or to approved spoil areas and for the incorporation of the material into the
embankment or for the making good of spoil areas as appropriate and for the construction of
bunds as described above. Payment shall be made in full for excavated materials placed in
embankment or in bunds when the compacted embankment is approved by the Engineer. For
excavated materials directed to be run to spoil or to be otherwise disposed of, payment will be
in two parts: one half of the payment due will be made when the material is removed from site
and the ditch properly shaped and accepted and the other half of the payment due will be made
when the spoil areas or other disposal sites have been completely made good in accordance
with the requirements of this Specification.
203.03. Preparation
The ground will be without vegetation and the remaining materials shall be in accordance to
Chapters 101, 102, 103 and SNiP 3.02.01-87.
203.04. Generalities
The excavation works for trenches, or foundation pits shall be carried out to the level indicated
in the drawings without disturbing the underlying materials. This excavation shall include for any
bedding required for the structure.
203.06. Bedding
Where shown on the drawings or directed by the Engineer bedding material shall be placed
beneath the structures. Depth of excavation shall take into account the required thickness of
any bedding. Bedding shall be a granular, free draining material conforming to SNiP
2.05.02-85.
a) Structures other than culverts
Place, shape, and compact bedding materials confirming to the specified standard in
layers not exceeding 150 mm.
b) Culverts
The bottom of the excavation shall be compacted to 92% MDD (AASHTO T180) prior to
the placement of granular bedding layer or concrete foundation. The granular bedding
layer, in the thickness as specified in the drawings, shall be compacted to 95% MDD
(AASHTO T180), and in layers not exceeding 150 mm. Bedding shall be according to VSN
81-90, SNiP 2.05.03-84 and typical Album 3.501.1-144, also VSN 24-88. Where
applicable, recess the shaped bedding to receive the joints according to SNiP 2.05.03-84.
203.08. Compaction
Compaction shall be obtained through the use of mechanical equipment such as rubber tired
rollers, vibrating rollers (steel wheeled), sheepsfoot rollers, hand operated plate vibratory
machines, and mechanical or hand tamping in very restricted areas.
Compaction Requirements are as follows:
• Under structures:
95% of maximum density (according to SNiP 2.05.02-85)
• Structures and trenches in roadway or beside roadway:
93% of maximum density
• Structures and trenches in right of way but not part of travelled way:
90% of maximum density
• Trenches off right of way:
Not less than 90% of maximum density.
Only materials meeting the backfill requirements standard shall be used.
203.09. Acceptance
The work will be accepted for payment providing that it has been built in conformance to the
drawings and specifications and approved by the Engineer including Chapter 001.
Measurement and Payment
Structural excavation, bedding, foundation fill, backfill and temporary support of excavation will
not be measured for payment. These costs shall be included in the cost of the structure.
204.02. Materials
Depending on the method adopted, materials shall conform to the requirements of:
Hydroseeding
ENIR E2-1-45
Seeding
ENIR E18-45
Bushes
Bushes and shrubs shall be selected from locally available stock and approved by the
Engineer. Approved bushes shall have a height, when fully grown, of some 1.5 to 3.0
Metres and shall be of species which exhibit a strong and extensive root system with
dense foliage.
204.06. Fertilization
According to ENIR E2-1-45 or ENIR E18-24.
205.02. Materials
Materials shall be deciduous trees and large shrubs, such as poplar and willow trees, which
experience has shown will be suitable for the locations in which they are to be planted.
205.04. Planting
Trees shall be planted out in pits suitable for the seedlings dimensions and species. Pits shall
be dug by excavators or by earth augur machines, in cases where the sites are inaccessible to
equipment; pits shall be dug by hand. Edges of machine pits will normally require hand
trimming.
Each pit shall be partially filled with fertile soil with added compost, humus and fertiliser as
required and appropriate for the species being planted. For plants with bare or spreading roots
the initially charge of soil shall be formed into a hillock at about half the hole depth and for
plants with root balls into a pillow. Pits shall then be filled in layers with further fertile soil, each
layer being carefully and firmly compacted. Before planting the tree roots shall be trimmed and
the crown pruned as appropriate for the species. Trees shall be planted at spots indicated by
the Engineer or, for general tree cover at about 8 Metre spacing or such other spacing as may
be suitable for the species.
205.05. Watering
Immediately after planting, the tree shall thoroughly watered with about 25 litres of water soaked
into the planting soil. Thereafter the newly planted trees shall be carefully monitored for signs of
wilting or drying out and additional watering carried out as necessary depending on the climatic
conditions and the condition of the plants. Watering shall preferably be carried out in the late
afternoon or evening.
3. PAVEMENT
CHAPTER 301. COLD RECYCLING OF THE ASPHALT
CONCRETE PAVEMENTS
PART A: GENERAL
This section of the specification includes requirements for the Cold Recycling of Asphalt
Concrete Pavements (CRACP) and related work as indicated on the drawings and as
hereinafter specified. The work consists of furnishing all plant, labour, equipment and materials
to perform all operations as required for the construction of CRACP as part of the pavement
base material.
Notwithstanding the information provided in the drawings, the Contactor shall perform a site
reconnaissance and document the actual pavement condition and perform all necessary
verification pavement coring and analyses to determine the prevailing conditions for optimal
pavement mix design. The cost of these investigations shall be borne by the Contractor.
The Contractor shall submit a detailed work plan describing his proposed construction
equipment, procedures, and schedules. This shall include, but not be limited to, the following:
Listing of supervisory personnel: Name and experience of the various persons,
their role and primary responsibilities.
Equipment set-up and site use layout: Including storage areas, mixing plant
locations, haul roads, and work platform.
CRACP equipment specifications, including milling, mixing, spreading and
compacting machines to be used in the project.
Construction means and methods: Listing of equipment and capabilities,
construction steps, control of surface storm drainage, spills, wastes, pollutions,
etc.
A layout drawing showing the limits of the CRACP zones both horizontally and
vertically along with the planned sequence of construction.
A quality control plan describing all testing, sampling, reporting forms, methods,
responsible persons, non-conformance procedures, and all other means to
ensure the quality of work.
Schedule: A bar chart schedule showing all major activities and durations.
In addition to the Work Plan, the following specific information shall be submitted prior to the
start of CRACP construction:
Sampling Plan: A description of the methods and locations of all samples used in
the design mix testing. Description of the materials and method used to restore
the disturbed pavement and roadway areas where asphalt pavement samples
were collected.
Source of all imported material, including aggregates, mix water, cement, and
any additives. Shipment of materials to the site shall be accompanied by the
vendor's written certification of the quality or specification of the material.
301.05 JOB-MIX FORMULA (JMF)
Road Sector Program Support Project, Moldova
86
A pre-construction, laboratory design mix program is required to determine appropriate
materials and material proportions for the required CRACP performance. The Contractor shall
furnish the JMF for approval to the Engineer, for verifcation to the Employer (State Roud
Administration Laboratory in Chisinau) for review and acceptance at no later than 21calendar
days prior to date when the Contractor intends to commence execution of the rehabilitation of
the pavement . The formula will indicate the gradation of the imported aggregate, recycled
asphalt and a definite percentage of water, recycling agent, and cement to be added to the
mixture. The JMF shall establish the minimum curing period for all proposed mix design.
The general percentage by weight of individual constituents of the mixture is as follows:
Portland Cement (Slag Portland Cement) 4-5%
Recycled Asphalt concrete granules 40 – 50 %
Crushed Stone As indicated by the Engineer
Sand and Fillers As indicated by the Engineer
Water 2-6%
Select the optimum cement content to provide the properties indicated in Section 301.06.1
Physical Property.
301.05.1 Physical Property
The following minimum physical properties are required:
Flexural Strength (ODMD since 27.06.2002) = 1.7 MPa
Unconfined Compressive Strength (ODMD
since 27.06.2002) = 2.0 MPa
Minimum Density (ODMD since 27.06.2002) = 98 %
Water saturation by volume,% not more than
(ODMD since 27.06.2002) = 12 %
Coefficient of water resistance, not less than
(ODMD since 27.06.2002) = 0.6 %
Four (4) sets of batch trial samples for each proposed JMF shall be made available to the
government for independent testing and verification. The samples shall be made in accordance
with GOST 12801-98 (ODMD since 27.06.2002 p.7.12 to 7.16) and shall be compacted and
properly cured in accordance with GOST 12801-98.
The JMF may be adjusted during construction by the Contractor to improve paving mixture.
Written consent from the Engineer will be required for changing the JMF. The proposed revised
JMF shall satisfy the physical property requirement indicated in this section.
301.06 QUALITY ASSURANCE
301.06.1 Sampling and Testing
The Contractor shall perform sampling and testing using his own facilities approved by the
Engineer or by using a commercial testing laboratory approved by the Engineer. No work
requiring testing will be permitted until the testing facilities have been inspected and approved.
301.06.2 Samples
The Contractor shall take :-
95- 65- 54- 42-88 30-65 25-65 18-65 12-65 8-40 5-22 2-8
100 100 100
301.09 EQUIPMENT
301.09.1 General
All plant and equipment shall be supplied and operated in such a manner as to recycle in-place
material to the specified depth and construct a new layer, all in accordance with the
requirements of the specifications. All plant and equipment deployed on the site shall be of
adequate rated capacity and in good working order.
The Contractor shall allow the the Engineer access at any time to all equipment used to
produce the cold-recycled mixture. This can involve checking the adequacy and the operation
of the equipment used. Plant, machines, tools, and miscellaneous equipment to be used in the
successful demonstration test sections shall be used for the production and placement of the
cold recycled mixture. Changes in the plant, machines, tools, and miscellaneous equipment
shall be approved by the Engineer.
301.09.2 Central Plant Mixing
The mixing plant designed, coordinated, operated to produce mixture within the job mix formula
(JMF), shall be capable of producing recycled mixture at a minimum rate of 150 tons per hour.
The plant shall be equipped with positive means to control the amount of cement, water, and
time of mixing.
301.09.3 In-Place Mixing
Equipment used for in-place mixing construction shall be designed, coordinated, and
maintained to produce mixture within the JMF. The mixing equipment used shall be equipped
<150 mm 12
200 mm to 250 mm 19
>250 mm 24
The operating speed of the primary roller shall not exceed 3 km/h and the number of passes
applied over the full width of each cut shall be sufficient to achieve the specified layer density.
PART C: EXECUTION
301.10 PREPARING THE SURFACE
Before any recycling work commences, the surface of the existing road shall be prepared by:
Clean all vegetation, garbage and other foreign matter from the full road width,
including any adjacent lanes or shoulders that are not to be recycled
Remove any standing water
Pre-mill where high-spots are to be removed (if required)
Accurately mark the proposed longitudinal cut lines on the existing road surface.
Remove all road marking features that will be destroyed by recycling
Identify pavement areas with obvious underlying structural deficiencies
(settlement, lateral spreading of embankment). Propose fixing methods to the
Government for approval.
301.11 MILLING OF THE EXISTING PAVEMENT
The milling of the pavement during the process of cold recycled asphalt shall be carried out in
compliance with CHAPTER 302. MILLING ASPHALT PAVEMENT of this specification.
The contractor shall take all necessary steps to ensure that the gradation that results from the
recycling process conforms to the gradation established in the JMF. The forward speed of the
recycling machine, rate of rotation of the milling drum and the positioning of the gradation
control beam shall be set so that the in-place material is broken down to an acceptable
gradation. When required by the Engineer, samples of in-place materials shall be collected and
tested for particle size and gradation requirements.
The actual milling depth shall be measured at interval no longer than 100 m along the milling
cut length using the same survey references that will be used to achieve final surface grades.
Longitudinal joints between successive milling cuts shall overlap by a minimum of 150 mm.
Transverse joints between successive milling cuts shall overlap by a minimum of 500 mm.
The speed of advance shall be checked and recorded at least once every 200 m of cut to
ensure conformity with the planned production rate and on-going compliance with the recycling
process. Acceptable tolerance limits shall be dependent on the type of recycler and material
being recycled, but shall not be less than 4 m/min nor greater than 12 m/min.
301.12 CONSTRUCTION METHOD
301.12.1 Central Plant Mixing
The central mixing plant shall be capable of producing a uniform blend of the AG, aggregate,
cement, and water. The required amount of cement material for each batch, or calibrated
amount of continuous mixing, shall be introduced into the mixer to meet the requirements of the
JMF. The mixing process shall provide a uniform dispersion of the cement and water to achieve
Road Sector Program Support Project, Moldova
91
a thorough coating (visually) of all aggregate particles. As a minimum, when the recycled
mixture contains fine particles passing the 4.75 mm sieve, the mixing process shall provide a
thorough coating of these particles.
301.12.2 Test Section - Central Plant Mixing
The Contractor, prior to the start of the recycling in the Works shall prepare a sufficient quantity
of mixture to construct a test section at least 200 meters long, two spreader widths wide and of
thickness to be used in the project by placing, spreading, and compacting the mixture with the
equipment to be used in the Works and in accordance with requirements specified above. This
test section will be tested and evaluated as a lot conforming to all specification requirements. If
approved by the Engineer, the test section shall be located in one of the less critical areas of
the in the normal course of embankment construction Works pavement construction otherwise,
it shall be located outside the project paving. If tests results are satisfactory if constructed in the
area of the Works pavement the test section shall remain in place as part of the completed
pavement. If tests indicate that the pavement does not conform to specification requirements,
the test section of pavement shall be removed and material disposed of offsite at the
Contractor's cost.
In case test section does not conform to the Specification, the Contractor shall make necessary
adjustments to the plant operations and rolling procedures immediately, and construct another
test section, at no additional cost to the Employer. Other additional test sections, as necessary
and as directed, shall be constructed and will be sampled and tested for conformance with
specification requirements. Full production with the recycled mixture shall not commence
without approval of the Engineer.
Note:
a. The density of the sample is determined by dividing the average density to the apparent
density, being expressed in %.
b. The coefficient of compaction is determined by dividing the average density of the cores
to the density of the specimens remoulded from the cores (cl. 4.16 GOST 12801-98).
302.03. Milling
The existing bituminous pavement is made from different asphalt and gravel shall be milled and
processed by at least sieving (if necessary) to meet the requirements for re-use in the regulating
layer. If the existing bituminous pavement material does not conform to any given grading, but
consists locally of larger gravel and finer material then it shall be re-used or disposed as
instructed by the Engineer.
Milling and removal of existing pavement layers shall be conducted during dry weather
conditions. Milling and removal shall be conducted on small sections only as approved by the
Engineer. Construction of new pavement layers in such disturbed sections shall be completed
as soon as possible. Only after the completion of new pavement layers, except the final surface
course, shall another section for removal is approved by the Engineer.
The existing pavement shall be milled at a depth as specified with a minimum milling width of
1.5 m. A traffic lane should be processed to its full width, and the cross-section of the newly
obtained surface should be even The evenness of the surface shall be measured with a 3-m
straight-edge, the gap between the straight-edge and the road surface should not exceed 20
mm, and shall be in accordance with SNiP 3.06.03 – 85.
The transition between the milled asphalt lane and the existing pavement shall have a smooth
transition to ensure safety of the travelling public.
Before opening the milled surface to traffic all loose asphalt, particles and other loose material
shall be removed.
302.04. Acceptance
The acceptance of the asphalt milling shall be in accordance with the drawings and
Specifications and approved by the Engineer.
Measurement
The milling of the existing asphalt pavement shall be measured either in cubic Metres to any
depth or in square Metres to depths as specifiedin the Bill of Quantities.
Payment
The accepted works shall be paid according to the rates as specified in the Bill of Quantities.
The payment shall be done for the payment items listed below, and which are contained in the
bid. The indicated payment is the full amount of remuneration for the works under this chapter.
The payment shall be for the following items:
303.02. Materials
The materials used for the construction or reconstructions of pavements have to meet the
following requirements:
Geotextile EN 13249
Following acceptance of the subgrade a drainage layer of approved ballast material shall be
placed and compacted using vibratory rollers or vibrating plate compactors. Top of ballast layer
after compaction shall be correct for level in all areas within a tolerance of +0
to -35 mm.
The ballast layer shall be extended beyond the limits of the carriageway beneath the shoulder to
meet the side drain or the embankment face.
Following acceptance of the ballast layer a subbase of approved material, crushed limestone
complying of SM GOST 25607-2010 with the following grading requirements:
63.0 100
40.0 70 – 100
20.0 50 -85
10.0 40 – 75
4.75 30 – 60
2.36 20 – 45
1.18 15 – 37
0.075 4 – 15
30302.1 Base course of mixture of Lime Stone Nr.5, h - 220 mm Square metre
304.02. Materials
The materials used have to be in accordance to the following standards:
• Вitumen SM GOST 22245-90.
• Cutback Road bitumen, GOST 11955-82
• Bituminous emulsion SM GOST 18659-81.
304.03. Equipment
• Self-propelled bitumen distributor.
• Mechanical rotary brush.
• Compressor (for particularly dusty base layers).
305.02. Materials
The materials will be in accordance to the following standards:
Bitumen content as determined by testing shall not vary from the approved design mix in binder
courses and regulating asphalt by more than +/-0.3% and in wearing courses by more than +/-
0.2%.
If tests show that the mix being produced does not comply with these requirements all asphalt
work will cease immediately the problem is noted and no further asphalt will be laid until, either
the causes of the fault with the existing mix have been established and rectified or until a new
mix design has been prepared and approved following the procedures above.
The thickness and the density of the asphalt course being laid will be checked by coring.
At least one 100 mm diaMetre twin core for each 800 m2 of asphalt mix laid shall be tested for
density, thickness and voids.
With an absolute minimum of 3 cores being taken for any day’s work. Cores will be checked for
thickness of layer as the average of three uniformly spaced thickness measurements by caliper
round the circumference of the core. The compacted asphalt in the field shall achieve a density
in accordance with Chapter 305.14.
The grading and specific gravity of the cold aggregates will be tested as directed by the
Engineer but normally not less than once per day.
305.011. Mixing
The proportioning of bitumen and aggregates in the mixer shall be according to the approved
mix design formula.
The mixing period shall be sufficient to achieve a complete coating of the aggregates with
bitumen and the complete mixing of filler with bitumen and shall in no case be less than the
mixing period recommended by the plant manufacturer.
305.012. Transport
Mixed asphalt material shall be transported from the mixing plant to the laying site in tipping
trucks specially reserved and designated for this purpose.
Trucks shall be metal bodies, insulated and equipped with insulated tarpaulin covers. Covers
shall be deployed at all times when the truck is being used for the transport of asphalt.
Trucks for the transport of asphalt shall be equipped with ports in each side of the body for the
measurement of load temperatures. The Contractor shall supply and maintain suitable heavy
duty thermoMetres (Rototherm or similar or other approved type) at the delivery point, able to
measure temperatures at 1 Metre penetration into the load, for checking asphalt temperatures
prior to discharge into the finisher.
Limited quantities of approved release agent may be used to prevent asphalt material hanging
in, or adhering to the body during discharge. Release agents shall be subject to the approval of
the Engineer both as regards type and rate of application. Under no circumstances will agents
which react with or which are miscible with the binder be permitted. Any members of the
Contractors staff found applying such agents will be subject to immediate and automatic
removal from the site with an absolute prohibition on their re-employment on the project at any
time in any capacity. The Contractor shall ensure that this provision is brought forcefully to the
attention of all staff involved in asphalt work.
305.014. Compaction
The compaction of the mixture will be done according to SNiP 3.06.03-85.
The Contractor shall provide sufficient rollers of adequate size and weight to achieve the
specified compaction. Prior to commencing the laying of bituminous mixes in the permanent
works the Contractor shall carry out site trials to demonstrate the adequacy of his plant and to
determine the optimum method of use and sequence of operation of the rollers.
Rolling shall be carried out parallel to the axis of the road with transverse movement of rollers
being accomplished by gradual diagonal rolls not varying by more than 15 degrees from the
axial direction. Sharp turning movements of rollers on fresh asphalt shall not be permitted. The
Contractor shall be responsible the repair of any and all damage which may result from the
improper or careless use of rollers. The only exception to the use of rollers in an axial direction
shall be when the need arises to compact transverse joints. In these cases the rollers shall be
turned off the asphalt surface and shall be used at right angles to the axis of the road. All
exposed edges of the lane/layer shall be adequately supported by the use of suitable timbers so
that the roller(s) may move onto and off the asphalt without deforming the edges. Rolling shall
be commenced before the mix temperature falls below 120°C and final compaction shall be
accomplished before the temperature falls below 80°C. No further rolling will be allowed if the
temperature falls below 80°C. In general the pattern of rolling shall be started from edge/down
side and procced towards center/upper line. In case of joint rolling should commenced first at
the joint.
The compacted asphalt in the field shall achieve a coefficient of compaction in accordance with
SNIP 3.06.03-84 and SM STB 1115-2008.
Coefficient of compaction shall be determined comparing the density of the core with the density
of the remolded sample and with the average density of the laboratory samples taken on the
same day. If any of the above coefficients of compaction are less than requirement in SNiP
3.06-03-84 and SM-STB 1115-2008 then that area of pavement shall not be accepted.
306.02. Materials
The materials to be used in the reconstruction of shoulders shall be:
307.05. Transport
Asphalt shall be transported in dedicated trucks complying with the requirements of
Sub-Clause 305.12.
Unit of
No. Item
Measure
Asphalt concrete SMVg-III / 2,0 SM STB 1033:2008 Square
30701
h- 30 mm Metre
308.02. Materials
Portland cement and water according to Specifications, curing seal shall be emulsified asphalt
and the granular material shall not contain gravel or stone retained on a 50 mm sieve or more
than 45 percent retained on a 5.0 mm sieve.
308.06. Finishing
After final compaction, the surface shall be smooth and free from cracks, ridges and loose
material. Any ridges or undulations are removed by planing with a motor grader, and the
resulting loose material removed from the area. The finishing and construction operations shall
be completed before six (6) hours has elapsed from the time of addition of water to the mix.
The surface of the compacted base course shall be kept moist until a curing seal has been
applied. Water shall be applied in a fine spray which does not segregate the cement from the
soil particles.
308.07. Curing
A curing seal of emulsified asphalt shall be applied to the dampened surface at a temperature of
20ºC - 50ºC, and at a uniform rate of 2.5 litres per square Metre. The seal covers the full width
of the roadway and shall be allowed to cure thoroughly before the Engineer grants permission
to continue further works.
308.08. Maintenance
The Contractor shall, within the Limits of Contract, maintain the soil-cement base course in
good condition. Faulty areas are replaced for the full depth of the base course with fresh
soilcement mixture or concrete. Surface depressions are brought up to proper grade by
patching with asphaltic concrete prior to the application of the asphaltic surface course. Areas
Road Sector Program Support Project, Moldova
118
where the curing seal is removed by traffic or otherwise, shall be resealed immediately, at the
Contractor’s expense.
Measurements
The volume of work is measured in tons.
Payment
The works measured as indicated above and confirmed by the Engineer will be paid at the rates
provided in the contract against those items that are shown in the bid schedule. The payment
under these items shall be the whole of the payment due for the completion of all works
indicated in the present chapter.
309.02. Aggregate
The aggregate shall consist of crushed rock or crushed gravel of angular shape and of such
character that it will compact and interlock under rolling. It shall be of reasonably uniform quality
throughout and free from clay, earth, dust or other deleterious matter.
309.03. Bitumen
The binder shall be Gudron as specified in the SNiP or ordered by the Engineer.
Payment
The works measured as indicated above and confirmed by the Engineer will be paid at the rates
provided in the contract against those items that are shown in the bid schedule. The payment
under these items shall be the whole of the payment due for the completion of all works
indicated in the present chapter.
Payment will be made under the item below:
310.02.
The Contractor shall not be able to commence with asphalt concrete wearing course until the
Engineers approves the testing company or laboratory and the proposed IRI profiling
equipment, and the Quality Control (QC) plan submitted by the Contractor as per Appendix B.
Any delays in asphalt concrete wearing course construction caused by the Engineer’s
determination of inadequate qualifications of the testing company, the profiling equipment,
and/or the QC plan will be the sole responsibility of the Contractor.
310.03.
All roughness measurements and reporting costs shall be the responsibility of the Contractor.
311.02. Materials
The materials used shall be compliant with these Specifications and standard norms,
as follows: ther non-organic binders shall be compliant with the requirements of GOST 10178-
85* and SMV ENV 13282:2010, the crushed stone - with the requirements of GOST 8267-93*,
the natural sand must be clean with no clay content or organic inclusions according to GOST
8736-93, the water shall be compliant with the requirements of GOST 23732-79. The soil used
for works shall have pH 4,5<pH<9,5, moisture content of 3% to 5% less than optimal moisture
and the density of 0,85 to 0,90 of the maximal density, according to GOST 25100. The
requirements for stabilized soils shall be those from GOST 23558-94. It is not admissible to use
soils of Plasticity Index higher than 12 and soils with more than 10% of passings of fines grains
through the 0.063 mm sieve.
The granular materials used for mixtures shall not contain rounded, elongated or soft gravel; it
should be of an approximately cubical form. The grading curve envelopes must be compliant
with the requirements of Table 2 in the GOST 23558-94. It is desirable to select and use of
homogeneous materials for use in the implementation of the stabilized base layers. It is
preferable to select and use consistently homogeneous materials for stabilized base courses.
311.06. Compaction
The mixture shall be transported, spread and compacted within an interval of two (2) hours after
the addition of water. Any stabilized materials with hydraulic binders, which is not compacted
and finished, shall not remain undisturbed for more than thirty (30) minutes. At the
start of compaction, moisture in the mixture shall be within two (2) percentage points of the
specified optimum moisture content.
Prior to the beginning of compaction, the mixture shall be in a loose condition for its full depth.
Compaction shall be carried out on the loose material until it has attained a uniform density
of >98% of the Maximum Design Density. Compaction may be obtained by steel wheel, grid or
pneumatic rollers, vibratory or sheepfoot packers or any other means approved by the
Engineer. Following initial compaction, the mixture shall be shaped to the required grade and
cross-section. Where necessary the surface shall then be scratched to remove compaction
planes which may have developed during compaction. Final compaction to the specified density
shall be done with steel wheel or pneumatic rollers, or vibratory packers. If the specified density
is not attained, the Contractor, at his own expense, shall complete one of the following
operations as instructed by the Engineer.
• Reprocess the same stabilized material within twenty-four (24) hours of the original
application of binder and water, with the addition of seventy-five (75) percent of the
original cement content.
• Reprocess the same stabilized material after the elapse of twenty-four (24) hours with
the addition of one hundred (100) percent of the original binder content.
• Remove the stabilized base course material and replace it with new approved material
processed in accordance with these Specifications.
• Complete the surfacing operation in two (2) lifts, applying a total average depth of 75
mm of asphaltic concrete.
311.07. Finishing
After final compaction, the surface shall be smooth and free from cracks, ridges and loose
material. Any ridges or undulations are removed by planing with a motor grader, and the
311.08. Curing
A curing seal of emulsified asphalt shall be applied to the dampened surface at a temperature of
20ºC – 50ºC, and at a uniform rate of 2.5 litres per square Metre. The seal covers the full width
of the roadway and shall be allowed to cure thoroughly before the Engineer grants permission
to continue further works.
311.09. Maintenance
The Contractor shall, within the Limits of Contract, maintain the binder-stabilized base course in
good condition. Faulty areas are replaced for the full depth of the base course with fresh
stabilized material or concrete. Surface depressions are brought up to proper grade by patching
with asphaltic concrete prior to the application of the asphaltic surface course. Areas of
removed curing seal due to traffic or otherwise, shall be resealed immediately, at the
Contractor’s expense.
Measurements
The volume of work shall be measured in square meters.
Payment
The works measured as indicated above and confirmed by the Engineer will be paid at the rates
provided in the contract against those items that are shown in the bid schedule. The payment
under these items shall be the whole of the payment due for the completion of all works
indicated in the present chapter.
Payment will be made under the item below:
Unit of
No. Item
Measure
Base course of mineral aggregates stabilized with
31101 Square Meter
cement or hydraulic binder, M60 h - 230 mm
Traffic Accommodation
During the entire construction period and independent of the weather, the traffic to be
accommodated permanent on all bridges.
Temporary roads, crossing the riverbed, to be constructed, are according the design drawings.
TECHNICAL SUPPORT
Working Drawings of the Bridges
The contractor shall provide working drawings according to the chosen construction system of
all bridges (e.g. but not limited to: topographic setting-out, geotechnical investigations,
reinforcement inc. steel-lists, pre-stress system, construction details) elaborated with CAD-
system and submitted as DXF-file to the client on CD-Rom and hard copy in 3 copies to the
Engineer for approval.
Structural analyses of the Bridges
Structural analyses for new construction parts of bridge, selected pre-stressed -system for pre-
cast beams (pre-stress forces and pre-stress-assignment), construction-stages, temporary
constructions and stability analyses. Corrections /amendments in 3 copies in English to the
Engineer on CD-Rom for approval.
MISCELLANEOUS
Illumination of Roads and Bridges
Roads and Bridges to be illuminated by street lights where shown in the drawings. Foundation
or fixation is detailed shown in the drawings. Dia 75 mm PVC lining/sleeve pipes are embedded
in the bridge caps to allow thread cables.
Type of street light according to clients detailed instruction.
402.02. Materials
The free draining granular soil, used for the works of this chapter shall have a filtration
coefficient not less than 2.00 m in 24 hours and must comply with Technical Report, SNiP
3.06.04-91. The filtration coefficient will be determined according to SM GOST 25584-90.
Washed out stream and river banks will be reinstated using normal soil of sandy clay.
403.02. Materials
The materials and the precast units for the works under this chapter must be compliant with the
following requirements:
The pier construction woks should be performed in compliance with the requirements of SNiP
3.06.04-91.
403.04. Equipment
The following equipment should be provided:
• Crane for mounting and dismantling of the formworks, for installation or reinforcing grids
and for concrete supply by a bucket;
• Excavator for excavation of foundation pits;
• Welding machine for welding works;
• Vibrator for compaction of the concrete, cast into a structure;
• Pump for water pumping from a pit.
403.09. Waterproofing
Waterproofing should be carried out in compliance with SNiP 3.04.03-85 and VSN 32-81. The
pier surfaces, buried in the ground, must be waterproofed by coating in two layers.
Waterproofing should be performed on a primed concrete surface. The surface to be
waterproofed must be dry and clean of oils, dirt and dust. Waterproofing Works should be
carried out at an outdoor temperature above plus 5°С.
404.02. Materials
All materials and pre-cast elements used for the works of this chapter must comply with:
404.03. Equipment
The following equipment will be required:
• Crane for the mounting of deck slabs, weight to 3 tons;
• Welding equipment for welding works;
• Vibrators for compaction of the concrete cast-in-situ;
• Concrete mixer with pumps.
405.04. Equipment
The following equipment will be required:
• Concrete mixer with pumps for concrete curing;
• Vibrators for compaction of the concrete cast-in-situ.
405.08. Waterproofing
The surface of the approach slabs must be waterproofed. The works must be executed as
described in the Clause 403.09.
407.02. Materials
The materials of the joint structure shall meet the following requirements:
(i) expansion profile
• elastomere (polymer SBR/BR)
• shore hardness A 58 ± 5 SHE
• tensile strength min. 14 N/mm²
• elongation at break min 400%
• ageing resistance (7 days at 70°C)
hardness + 8 SHE
tensile strength ± 15 %
elongation ± 25 %
• ozone resistance
0.5 pphm/48 h “0“, no visible cracks
• compression deformation
72 h/20°C max. 20 %
22 h/70°C max. 25 %
(ii) steel elements
• clamping profile fy = 360 N/mm²
• bolts high tensile
• anchors to concrete fy = 460 N/mm²
• corrosion protection 80 μm hot-dip galvanised, 2x80 μm iron-
oxide/epoxy-resin coats
407.05. Installation
The Expansion Joint shall be installed in the recesses of the deck slab and abutment/backwall.
The anchors (loops) of the joint structure are to be connected with the reinforcement of the
structure by stirrups or hooks and longitudinal bars passing through the loops of the anchors.
The gap between both sides of the joint structure is to be fixed dependent on the actual
temperature of the superstructure in accordance with manufacturer’s instructions.
The recesses have to be filled with well compacted concrete after alignment.
409.02. Materials
Materials and prefabricated units used for the works of this chapter have to be in accordance
with:
410.02. Materials
The materials and the precast reinforced concrete units used must be in accordance with the
technical specification and the Design type 503-09-7.84. The grid used on the outlets must
comply with this specification and the Design type 3.503.1-81. The metal must be painted in
accordance with SNiP 2.03.11-85 and SNiP 3.04.03-85.
Crushed stone for the bed underneath the stairs SM GOST 8267-93
Project Design, SM GOST 26633-91
Concrete and components
SNiP 3.06.04-91
Reinforcing bars and build-in elements Project Design, SM GOST 5781-82
Metallic handrails for the stairs Project Design
The materials used for reinforced concrete stairs shall comply with the requirements of chapter
402.
The handrails and all fixings and fittings shall be hot dip galvanised after fabrication in
accordance with the standards for guardrails.
The paints used shall comply with the requirements of SNiP 2.03.11-85 and design drawings
3.04.03-85.
412.02. Materials
The materials used for these works must comply with the following requirements:
Concrete and components SM GOST 26633-91**, SNIP 3.06.04-91 and Chapter 504
Reinforcement SM GOST 5781-82*****
Crushed stone SM GOST 8267-93***
Stone of 25 cm size SM GOST 8267-93***
413.02. Materials
The materials for use in the works of this chapter shall conform to the following requirements:
413.04. Shoulders
Where indicated on the Drawings or directed by the Engineer, shoulders to bridge embankment
approaches shall be protected with a 50 mm layer of asphalt on a base of crushed stone of 100
mm thickness. Base and asphalt to shoulders shall be in compliance with the requirements of
chapters 303, 305 and 307. Asphalt protection to shoulders shall be laid after the execution of
the safety guardrails and the drainage chutes.
414.02. Materials
The materials and elements shall comply with the following requirements:
Technical Specification,
Standard sections of metal pedestrian railing
Design type 3.503.1-81
SNiP 2.03.11-85, SniP 3.04.03-85,
Paints
CPE 04.03-2005 SM GOST 9.032-74
415.02. Materials
The materials used for the works described in this chapter shall be in accordance with the
following requirements:
415.03. Equipment
The following items of equipment are likely to be required:
• Jacking capacity adequate to lift the estimated superstructure weight with a factor of
safety of 1.3 (See Special Specifications for bridge details)
• Temporary works for installing and controlling jacking, providing support and load
distribution
• Grit blasting equipment for rust cleaning surfaces of steel rocker bearings
• Autocrane for assembly and dismantling of the temporary works.
416.02. Materials
Materials used for the works of this chapter shall be in accordance with the following
requirements:
416.04. Equipment
The following equipment will be required for works under this chapter:
416.05. Formwork
Formwork shall be in accordance with the requirements of SNiP 3.06.04-91.
416.06. Reinforcement
Reinforcing works are to be carried out according to SNiP 3.06.04-91. No reinforcement shall be
brought on to the site or used without a manufacture certificate certifying that it complies with
requirements. Any change or substitution in the category class, diaMetre, or type of the steel,
required by the Drawings or Technical Specification must be agreed by the Engineer.
Before use, all reinforcement must be cleaned of rust, mud, dust and grease; Lap joints of
reinforcing bars are to be executed by overlapping by a length of at least 40 bar diaMetres and
in compliance with requirements of the Technical Specification.
Where the welding of reinforcement and embedded elements is unavoidable the work shall be
executed in accordance with the requirements of SM GOST 14098-95. Welding of
reinforcement shall be avoided wherever possible and shall not be carried out without the
explicit permission of the Engineer.
417.02. Materials
The materials used for the works described in this chapter shall be in accordance with the
following requirements:
417.03. Equipment
The following items of equipment and special auxiliary installation are likely to be needed:
• Autocrane for assembly and dismantling of the auxiliary installation;
• Compressor for pneumatic hammer, cleaning /drying cracks;
• Concrete pumping equipment;
• Deep vibrator for concrete compaction;
• Injection concrete equipment, metallic brush or sandblasting equipment for the concrete
and reinforcement steel cleaning;
• Temporary scaffoldings, auxiliary piers, lifting equipment for repair works.
Measurement
The minor repair, consolidation, jointing and slope execution works described in this chapter will
be measured in cubic Metres of reinforced concrete or reinforced concrete with polymers, or
mortar with polymers, or sand cement mortar. Repair works and painting works will be
measured in square Metres of the surface covered with sand cement mortar or with liquid
suspension of cement with polymers.
Payment
The works measured as indicated above and confirmed by the Engineer will be paid at the rates
provided in the contract against those items that are shown in the bid schedule. The payment
under these items shall be the whole of the payment due for the completion of all works
indicated in the present chapter.
501.02. General
Culvert units and materials used for the works should meet SNiP 2.05.02-85,
OST 35-27.0-85, OST 35-27.1-85, OST 35-27.2-85, SM GOST 5781-82.
501.04. Pipes
Culvert pipes shall conform to SNiP 2.05.03-84, SM GOST 12586.0-83 and SM
GOST 12586.1-83. The length of culvert pipes shall be as stipulated in the Album of typical
drawings unless otherwise specified. Concrete pipe shall be 2.5 m in length unless otherwise
specified.
501.05. Generalities
The extension of the culverts shall be carried out using precast elements, indicated on the
drawings, the dimensions and location will be in accordance with the drawings.
The Metre measurement of culverts to side roads shall include the cost of providing appropriate
inlet and outlet structures of headwall and wingwalls. Any additional protection works required
shall be measured in Sq.m. and paid under the item for protection works where such an item is
listed in the Bill of Quantities. If no item is listed, then the costs of additional protection shall be
included in the liner metre rate for provision of the culvert.
Payment
The works measured as indicated above and certified by the Engineer will be paid at the rates
provided in the contract against those items that are shown in the bid schedule. The payment
under these items shall be the whole of the payment due for the completion of all works
indicated in the present chapter.
Payment will be made under some or all of the items below:
502.02. Materials
Concrete shall conform to Table 504-1 of this Specification. Before batching concrete submit the
proposed concrete proportions for approval to the Engineer. As a minimum, submit the
following:
(a) Type and source(s) of all material proposed for use.
(b) Material certification for all material proposed for use.
(c) Surface dry weight of the fine coarse aggregate per cubic Metre of concrete.
(d) Gradation of fine and coarse aggregate.
(e) Weight of mixing water per cubic Metre of concrete.
(f) Weight of cement per cubic Metre of concrete.
(g) Entrained air content of plastic concrete in percent by volume.
(h) Maximum slump of plastic concrete in cm.
Joint mortar use for concrete minor structure shall consist of the following:
a) One part hydraulic cement (see SM GOST 25192-87, SM GOST 26633-91). The
cement shall not contain lumps, be partially set, come from previously opened bag
or be subject to hydration.
b) Two parts fine sand free of clay or other deleterious materials.
c) Water as required to obtain a freely working mix capable of being forced into small
small openings, cracks or gaps.
503.02. Materials
Material shall conform to the requirements of this specification and to the materials stipulated in
the Drawings. Paved waterways of all types shall be constructed using B20 concrete having a
maximum aggregate size of 20 mm. Where mesh reinforcement is required it shall comply with
the relevant GOST standard.
503.03. Generalities
Excavation shall be performed accurately to line and level. The bed of the excavation shall be
parallel to the required finished surface of the waterway. Concrete mixes shall be designed and
approved in accordance with the requirements of Chapter 504.
504.02. Materials
1. Aggregate shall conform to SM GOST 10268-84 and shall consist of hard durable
particles of fragments of crushed stone, crushed slag or crashed gravel and shall be
subjected to the following tests: Sieve analysis, Strength, Wearing and amount of dust
particles.
2. Mortar - the joint filler used for concrete minor structures shall consist of the following:
a) One part hydraulic cement see SM GOST 10178-85 and table 3.1 of
SNIP 2.05.02-85.
b) Two parts fine sand free of clay or other deleterious materials.
c) The maximum water cement ratio shall be 0.5 as required to obtain
a freely working mix capable of being forced into small interstices.
3. Portland cement.
Portland Cement shall meet the following specifications: SM GOST 10178-85.
Do not use cement which has lumps, become partially set or is salvaged from previously
opened bags. Do not mix brands or types of cement from different mills without the
Engineer’s approval.
Concrete curbs can be cast-in-situ or prefabricated in unified block length.
504.04. Generalities
Excavation and backfill shall be performed in accordance with the requirements of chapter 203.
Forms shall be so designed and of sufficient strength that there is no loss of shape, bulging or
warping under site conditions or concrete pressure, and such that they permit of ready removal
without causing damage to the concrete.
Forms shall be of wood, metal, or other suitable material. They shall be kept clean and coated
with form release agent or form oil before placing concrete.
40 mm 100
30 mm 90 - 100
20 mm 65 - 90
10 mm 40 - 85
5 mm 30 - 80
2 mm 15 - 75
1 mm 12 - 60
0.5 mm 10 - 45
0.065 mm 0 - 10
Measurement
Payement as per running metre incl. excavation and disposal of excess material, geotextile and
permeable granular filling.
506.03. Riprap
Riprap shall consist of a course of packed large stones, bolders or lumps of rock placed on
bank slopes and outlets toes in stream and river beds and at other localities where protection of
this type may be required.
Depending on the slope and the expected stream, the size of stones/bolders is varying:
stones D50 <= 350 mm
stones 350 mm < D50 < 1000 mm
stones 1000 mm < D50 < 1500 mm
The alignment of the gabion shall be correct within a tolerance of 100 mm of the instructed
alignment and the level of any course of gabion shall be correct to within a tolerance of 50 mm
of the instructed level. In addition adjacent gabions shall not vary by more than 25 mm in line
and/or level from each other.
The pre-packed elements of gabions shall be of dimension 2.00x1.00x0.50 m and arranged as
shown on the standard drawings.
The surface upon which gabions are to be laid shall be compacted to a minimum dry density of
90% MDD (AASHTO T180) and trimmed to the instructed level or shape.
Joints in gabions shall be stitched together with 600 mm minimum lengths of binder wire, with at
least one stitch per 50 mm, and each end of the wire shall be fixed with at least two turns upon
itself.
Adjacent gabions shall be stitched together with binder wire along all touching edges.
507.02. Gabions
General: handling, fixing filling and fastening according to manufacturers instructions.
On earth touched sides a geotextile membrane shall be fixed onto the gabions. Gabions shall
be filled as instructed and with stones of appropriate size.
Measurement
Gabions shall be measured as per m3.
507.03. Matresses
General: handling, fixing filling and fastening according to manufacturers instructions.
On earth touched sides a geotextile membrane shall be fixed onto the gabions. Matresses shall
be filled with stones of appropriate size.
Measurement
Matresses shall be measured as per m2.
508.02. Materials
1. Precast concrete kerb units of the quality and dimensions are shown on the Drawings.
Where kerbing is required to follow a curve having a radius of less than 10 metres then
purpose made radiused kerbs shall be fabricated. Kerbs shall be made from concrete
having a maximum aggregate size of 20 mm and a minimum compressive strength of 35
N/mm2 at 28 days.
2. Portland cement mortar in accordance with Sub-Clause 504.02 above, as required.
3. Backing concrete having a maximum aggregate size of 40 mm and a minimum
compressive strength of 20 N/mm2 at 28 days.
Measurement
The Metre measurement will cover all works necessary, including any excavation, trimming or
backfilling, to place the kerbs and backing complete, as specified.
Payment
509.02. Materials
Materials have to be in accordance to:
601.02. Materials
Material shall conform to the following Section and Subsections:
• Concrete Chapter 504.
• Galvanized steel rail SM GOST 26804-86, and provisions of this Chapter.
• Paint for guardrail
If required on the drawings or indicated elsewhere in this specification Guardrail shall be
painted as shown. Paint shall conform to the requirements of Sub-Clause 014.02 of this
Specification; however the following preliminary treatment shall be applied:
604.02. Materials
• Concrete for the walls shall be according to GOST 26633-85
• Reinforcement shall comply with GOST 5781-82 and
• Reinforcing mesh shall comply with GOST 23279-85
• Filter surround materials for the drain - GOST 8267-93.
604.03. Reinforcement
Reinforcing works are to be carried out according to SNiP 3.06.04-91. No reinforcement shall be
brought on to the site or used without a manufacture certificate certifying that it complies with
requirements. Any change or substitution in the category class, diaMetre, or type of the steel,
required by the Drawings or Technical Specification must be agreed by the Engineer.
Before use, all reinforcement must be cleaned of rust, mud, dust and grease, Lap joints of
reinforcing bars are to be executed by overlapping by a length of at least 30 bar diaMetres and
in compliance with requirements of the Technical Specification.
Road Sector Program Support Project, Moldova
179
Where the welding of reinforcement and built-in elements is unavoidable the work shall be
executed in accordance with the requirements of GOST 14098-95. Welding of reinforcement
shall be avoided wherever possible and shall not be carried out without the explicit permission
of the Engineer.
701.02. Materials
Material shall conform to the following:
• All sign panels shall be manufactured according to SM GOST R52290:2009.
• Posts are to be manufactured according to Typical Album Serial # 3.503.1-89.
• Concrete to be according to Section 504.
701.03. Generalities
Furnish traffic control devices according to SM GOST R52289:2009, Technical Methods of
Organizing Traffic Movement. Submit the sign list, details of non-standard signs and details of
all marker posts for approval to the Engineer before ordering. The design of traffic signs and
their installation shall be approved by the Road Police.
702.02. Materials
a) General
The material to be used for road marking and striping shall be an approved road marking paint
applied to the pavement by mechanical means and reflectorised by the application of glass
beads (ballotini) sprayed onto the wet paint during the application process.
Following application and drying, the material shall produce an adherent reflectorised stripe of
specified thickness and width capable of resisting wear by traffic.
1) Air drying paint based on organic solvent of white or yellow colour, forming a
membrane when it gets dry.
2) Air drying paint based on solvent and water (ecological), of white or yellow
colour, forming a membrane when it gets dry.
3) Air drying paint of plastic type based on solvent and water (ecological), of
white colour.
4) Cold applied material of 2 components
These marking products ensure visibility during day-time and night-time, during dry weather and
rainy weather.
These marking products shall also create a rumble effect.
Fine or coarse glass beads may be used as such, but also in a mixture with beads for skid-
resistance.
b) Road Paint
Paint shall meet the requirements of SM GOST R51256:2009 for Ready-Mixed White and
Yellow Traffic Paints. The drying time shall not be more than 30 minutes.
All paint shall be shipped in strong containers plainly marked with the weight per gallon, the
volume of paint content in gallons, the colour, lot, batch and code Pieces. A true Statement of
the % composition of the pigment, the proportion of pigment to vehicle, and the name and
address of the manufacturer also shall be shown.
Any paint which, although inspected and approved at the point of manufacture, hardens or livers
in the containers so that it cannot be readily broken up with a paddle to a smooth, uniform
painting consistency, will be rejected. Any paint too thick for proper brush application will be
rejected, even though it conforms to these Specifications in all other respect. Paint shall be
used as supplied; under no circumstances will thinning of paint be permitted.
All paints shall be delivered to the project completely mixed, and ready to be used without
additional oil or thinner.
c) Colour
g) Test Certificates
The Contractor shall submit, for each consignment of paint and of ballotini delivered to site, the
Manufacturer's certificate to show that the materials comply in all respects with the relevant
product specifications.
At least 21 days before starting pavement marking application, the Contractor shall furnish a
written copy to the Engineer of the marking manufacturer′s recommendations for use. A field
demonstration may be required to verify the adequacy of recommendations.
Marking material shall be transported in appropriate containers plainly marked with the following
information as appropriate for the material being furnished:
• Manufacturer′s name and address
• Name of product
• Lot/batch Piecess
• Color
• Net weight and volume of contents
• Date of manufacture
• Date of expiration
• Statement of contents,
• Mixing proportions and instructions if mixing of components is required
• Safety information.
702.06. Tolerances
Road traffic markings shall be applied with an accuracy complying with the tolerances given
below:
a) Width
The width of lines and other markings shall not deviate from the specified width by
more than 5%.
b) Position
The position of lines, letters, figures, arrows, retro-reflective road studs and other
markings shall not deviate from the true position specified by more than 20 mm.
c) Alignment of Markings
The alignment of any edge of a longitudinal line shall not deviate from the true
alignment by more than 10 mm in 15 Metre.
d) Broken Lines
The length of segments, both of line and of break of broken longitudinal lines shall
not deviate from the specified length by more than 150 mm.
In broken lines, the length of segments and the gap between segments shall be as
indicated on the Drawings or as directed by the Engineer.
Lines lying on curves, whether broken or unbroken, shall not consist of chords but
shall follow the correct radius.
702.07. Faulty Workmanship or Materials
If any materials not complying with the requirements are delivered to the Site or used in the
Works, or if any sub-standard work is carried out, such material or work shall be removed,
replaced or repaired as required by the Engineer, at the Contractor's own cost. Rejected traffic
markings and paint or marking material that has been splashed or has dripped onto the
surfacing, kerbs, structures or other such surfaces shall be removed by the Contractor at his
own cost, in such a way that the markings or spilt paint will not show up again later and the
underlying bituminous surfacing is not damaged in any way.
703.02. Materials
Materials, items, and structures used for the works under this Section should meet the following
requirements.
• Sand asphalt concrete mix and materials SM STB 1033:2008.
• Aggregate for base of sidewalk SM GOST 8267-93.
• Ballast walk subgrade GOST 23735-79.
• Stairway structures according to the project.
• Cement-sand mixture according to the project.
• Concrete Paving Blocks according to the project.
Material for concrete sidewalk (if concrete is used for constructing sidewalks) should be in
accordance with Chapter 504 and, where kerbs are used, they shall be in compliance with
Chapter 505.
801.02. Materials
The materials used for protection or deviation of the installations belonging to one of the
organizations must correspond to the existing installations agreed by the representative of the
given organization.
802.02. Materials
The materials used for repair or deviation of the installations belonging to one of the
organizations must correspond to the existing installations agreed by the representative of the
given organization.
Payment
Unit of
No. Item
Measure
Arangement of underground comunication optic cable (as per
80201 linear Metres
drawings)
80202 Arrangement of aerial communication line including poles
80202.1 Arangement of aerial communication line (as per drawings) linear Metres
Arrangement of underground magistral gas pipes (as per
80203 linear Metres
drawings)
901.02. Materials
Materials for embankment construction shall comply with the requirements of SNiP 2.05.02-85
and with the provisions of chapter 201 and this chapter generally.
901.03. Excavation
Topsoil shall be stripped and stockpiled for reuse in accordance with the provisions of chapter
102. Material excavated from the top of the existing road embankment shall be excavated to the
depths shown on the Drawings and shall be used for the provision of new counterberms at the
toe of the embankment.
Slipped material shall be excavated to the shapes, lines and levels shown on the Drawings or
directed by the Engineer. Slip material shall be classified as unsuitable unless specifically
901.07. Geotextiles
Geotextile reinforcement to embankments and geotextiles to drainage works, as specified in
chapter 902, shall be placed as shown in the drawings.
901.010. Subgrade
The top of the finished embankment shall be finished to subgrade standard in accordance with
the requirements of chapter 201.13 to form the base for the reconstructed pavement.
Measurement
The various items of earthworks under slip remedial earthworks shall be measured throughout
in net cubic Metres except for the compaction of embankment prior to placing new material
which shall be measured in square Metres. The works of trimming, top soiling and seeding or
grassing shall be measured and paid under the relevant items of the Earthworks Bill.
Payment
The works measured as indicated above and confirmed by the Engineer will be paid at the rates
provided in the contract against those items that are shown in the bid schedule.
The payment under these items shall be the whole of the payment due for the completion of all
works indicated in the present chapter.
902.02. Materials
GEOTEXTILE Type 1 Geotextile for transverse subsurface drainage
This must be a mechanically bound material in a continuous way of 100% polypropylene, UV
stabilized, of highly resistant fibres of an approved inert material, manufactured by a specialized
producer of geosynthetical products as per ISO, and compliant with the following requirements:
The material used for construction of transverse subsurface drainage must be the one
recommended by the producer. Before the material is procured or supplied to the site to be
used for construction of transverse subsurface drainage, the Engineer must be submitted for
approval the patterns of material and the test results for the proposed patterns.
GEOTEXTILE Type 2. Geotextile used as a separating membrane, protection membrane
for embankments and a filter membrane for protection of ravine slopes and bottom and
for protection against erosion caused by runoffs.
This must be a mechanically bound material in a continuous way of 100% polypropylene, UV
stabilized, of highly resistant fibres of an approved inert material, manufactured by a specialized
producer of geosynthetical products as per ISO, and compliant with the following requirements:
The material used for stabilization of fine soil must be the one recommended by the producer.
Before the material is procured or supplied to the site to be used for protection of embankments
and slopes, the Engineer must be submitted for approval the patterns of material and the test
results for the proposed patterns.
The embankments and slopes shall be protected against scours caused by runoffs as shown on
the Drawings.
Geocomposite Type 1 for road pavement as SAMI (Stress Absorbed Membrane
Interlayer)/
This must be a highly strong geocomposite material of continuous fibres of 100%
polypropylene, UV stabilized, mechanically bound, reinforced with glass fibres, and
manufactured by a specialized producer of geosynthetical products as per ISO.
The products used for road pavement must be compliant with the following requirements related
to physical and mechanical properties:
The products to be used for road pavement, supplied by the producer, must be accompanied by
a Quality Certificate and Method Statement, which must be submitted to the Engineer. The
products must be supplied in protective packages against UV rays, abrasion and moisture.
Before the products are procured or supplied to the site to be used as a SAMI membrane for
road pavement, the Engineer must be submitted for approval the patterns of material and the
test results for the proposed patterns.
Filter Geocomposite Type 2 used for protection of banks, embankment slopes against
erosion caused by waves and streams.
This must be a mechanically bound material in a continuous way of 100% polypropylene, UV
stabilized, of 2 continuous layers of nonwoven geotextile: one filter layer and a second
protective layer against damage of the first layer, manufactured by a specialized producer of
geo-synthetical products as per ISO, and compliant with the following requirements:
Flow rate in the plan, 20 / 100 kPa [EN ISO 12958] 10-6 m²/s 4.0 / 1.1
Before the products are procured or supplied to the site to be used as a filter membrane, the
Engineer must be submitted for approval the patterns of material and the test results for the
proposed patterns.
Drainage Geocomposite Type 3.
The geocomposite used as a draining membrane shall consist of a core material of high
permeability, obtained from extruded synthetic monofilaments polypropylene, twisted and bound
with 2 filter geotextiles, fixed on it at hot temperatures. The geocomposite will be placed in the
area of a subdrain pipe intended to capture the water and to convey it to the proper direction,
manufactured by a specialized producer of geosynthetical products as per ISO, and compliant
with the following requirements.
Before the products are procured or supplied to the site to be used as a filter membrane, the
Engineer must be submitted for approval the patterns of material and the test results for the
proposed patterns.
For slope protection and stability against erosiuns can be used confinement systems, as
Geocells and Polymat (a 3D anti-erosion mattress).
Geocell is a product of polyethylene material of a high density, used on slopes, road
embankment slopes, reducing hydraulic energy and limiting the stress inside and underneath
the cells, increasing the original strength, protecting the root systems, serving as a directional
means for the surface drainage, preventing the ravines, avoiding loss of moisture.
Polymat is a 3D mattress for erosion control of monofilament extruded polypropylene, UV
stabilized, used on abrupt slopes, preventing soil erosion, stabilizing the surface soil layer and
ensuring a permanent support required for growth of vegetation.
The products used for slope stability must be compliant with the following requirements, related
to physical and mechanical properties:
Geocell Confinement Systems
Properties ParaMetres
No. of Cells/m2 35
Before the products are procured or supplied to the site to be used for slope stability, the
Engineer must be submitted for approval the patterns of material and the test results for the
proposed patterns.
903.02. Materials
Materials shall be at the Contractor’s option.
903.03. General Conditions
The Contractor shall make his own arrangements for necessary access to slip areas. He shall
construct such road ways and hard standings as he considers fit for the movement and
operation of his vehicles and equipment. He shall be solely responsible for locating and
acquiring/easing the required areas of lad for such accesses. Before undertaking construction of
such accesses he shall prepare carefully surveyed plans and submit them to the Engineer for
his approval. He shall demonstrate to the satisfaction of the Engineer that the requirements of
all owners and tenants of land affected by his proposed accesses are satisfied with the
arrangements made and that there are no objections from any quarter, including the local
authorities, to his plans.
When the accesses are no longer required, the Contractor shall completely remove all traces of
the accesses and of his presence and shall restore the land to its original condition. The only
Road Sector Program Support Project, Moldova
203
exception to this requirement shall be where affected land owner(s) require the access (es) to
be left in place and where it can be clearly shown that the approval of the local authorities to
such retention of the access (es) has been granted.
Payment of the lump sum for provision of access road(s) shall be made in two parts. 60% of the
sum shall be paid when the Engineer is satisfied that the Contractor has completed construction
of the approved access roads to the approved standard. The remaining 40% shall be paid on
completion of the remedial works and when the Engineer is satisfied that the Contractor has
discharged all his obligations in respect of their removal or handover under the Contract.
904.03. Piling
The Contractor shall carefully set out the required locations and levels of all piles complete with
well established reference points outside the area of the works which will be available
throughout the period of construction. The setting out shall be verified and approved by the
Engineer before any further works proceed.
Before drilling of pile holes, the Contractor shall have established a secure stable working
platform for his equipment at the designated location.
Before any drilling of any holes, the Contractor shall have on site the complete prefabricated
reinforcement cage required for those borings, ready for installed.
Drilling of pile holes shall be executed as rapidly as possible to minimise the possibility of
borehole collapse. The Contractor shall be responsible for taking all necessary measures to
avoid the collapse of boreholes based on the data available regarding ground water levels and
soil types shown in the Drawings. The contractor shall use temporary steel casing, drilling fluid,
or other measures to ensure that soil collapse does not occur.
If a pile location becomes unusable due to borehole collapse or any other reason associated
with the execution of the works and a rearrangement of the piling becomes necessary in
consequence, the contractor shall carry out any additional works required to implement such a
revised arrangement.
As boring proceeds, waste from the operation shall be removed from the site and disposed of in
accordance with the specification requirements. If the material is suitable it shall be run to store
and reserved for use in embankment, otherwise it shall be disposed of as spoil material. Any
slurry arising from the works shall not be discharged into watercourses but shall be settled until
liquids and solids can be disposed of separately.
On completion of the hole it shall be inspected and approved by the Engineer prior to placing of
the reinforcing cage. Reinforcing cages shall be checked prior to placing and marked by the
Engineer as checked and approved.
Concreting shall begin as soon as possible after cage placement and shall continue without
interruption until the casting is complete.
The concrete casting work will be done using a tremie pipe for placing concrete at depth and
with vibratory equipment for compaction and concrete flow. The work will be stopped only for
the removal of slurry, water or unsuitable concrete. In the top 3 metres of the piles additional
compaction will be provided using a poker vibrator. Concrete placement shall be carried out so
as not to move the reinforcement cage. The tremie pipe shall be raised gradually in stages such
that the end of the pipe is always at the level of the placed concrete
906.02. Materials
Concrete for the walls shall be according to GOST 26633-91*.
Reinforcement shall comply with GOST 5781-82*.
Reinforcing mesh shall comply with GOST 23279-85.
Filter surround materials for the drain - GOST 8267-93*.
906.03. Reinforcement
Reinforcing works are to be carried out according to SNiP 3.06.04-91. No reinforcement shall be
brought on to the site or used without a Quality Certificate from the producer, demonstrating the
compliance with the requirements. Any change or substitution in the category class, diaMetre,
or type of the steel, required by the Drawings or Technical Specification, must be agreed with
the Engineer. Before use, all reinforcement must be cleaned of rust, mud, dust and grease;
joints of reinforcing bars are to be executed by overlapping and in compliance with requirements
of the Technical Specification; the overlaps shall be equal at least to 30 bar diaMetres.
Where the welding of reinforcement and built-in elements is unavoidable, the work shall be
executed in accordance with the requirements of GOST 14098-91. Welding of reinforcement
shall be avoided wherever possible and shall not be carried out without the explicit permission
of the Engineer.