0% found this document useful (0 votes)
85 views

04 Remb Net Metering

The document discusses the legal framework and mechanisms of net metering for renewable energy in the Philippines. It defines key terms related to net metering and distributed generation. It also outlines the setup, scope, qualifications and pricing methodology for net metering.

Uploaded by

Limuel Espiritu
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
85 views

04 Remb Net Metering

The document discusses the legal framework and mechanisms of net metering for renewable energy in the Philippines. It defines key terms related to net metering and distributed generation. It also outlines the setup, scope, qualifications and pricing methodology for net metering.

Uploaded by

Limuel Espiritu
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 36

e – DISKARTE MO

NET METERING
• Click to edit Master Fortunato
text styles S. Sibayan
• Second
Solarleveland Wind Energy Management Division
• Third level
• Renewable
Fourth level Energy Management Bureau
• Fifth level

e – Secure Mo
e – POWER MO e – Safety Mo
e – Diskarte Mo
7/13/2017
Department of Energy 1
Empowering the Filipinos
e – DISKARTE MO
LEGAL FRAMEWORK
RA 9513: Renewable Energy Act of 2008
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level

Accelerate the development of the country’s renewable energy resources by providing


fiscal and non-fiscal incentives to private sector investors and equipment
manufacturers, fabricators, suppliers.
7/13/2017
Department of Energy 2 2
Empowering the Filipinos
e – DISKARTE MO
POLICY MECHANISMS
Non-Fiscal Incentives
• Click to edit Master text styles
• Second
Creation
level of RE Market
• Third level
Renewable Portfolio Standard (RPS)
• Fourth level
 Off-Grid Development
• Fifth level

 Guaranteed long-term fixed price


 Feed-in Tariff
 Other Market Options
 Net Metering
 Green Energy Option

Power of Choice
7/13/2017
Department of Energy 3 3
Empowering the Filipinos
e – DISKARTE MO
LEGAL BASIS
Section 7 of RA No. 9513 Implementing Rules & Regulations (IRR)
defines:
• Click to edit Master text styles
• Second level
 Net Metering is a consumer-based RE incentive scheme (net-
• Third level
user only)
• Fourth level
• Fifth level
 Purpose : to encourage end-users to participate in RE
generation for own use
 Mandate : Upon request by distribution end-users, the DUs
shall, without discrimination, enter into a net-metering
agreements with qualified end-users who will be installing RE
system, subject to technical and economic considerations

Power of Choice
7/13/2017
Department of Energy 4
Empowering the Filipinos
e – DISKARTE MO
LEGAL BASIS
• Click to edit
Section 10Master of text styles9513 and Section 7 of its
R.A.
• Second level
Implementing
• Third level Rules & Regulations (IRR) provides that
• Fourth level
the Energy •Regulatory
Fifth level Commission (ERC), in consultation
with National Renewable Energy Board (NREB), shall
establish the net-metering interconnection standards
and pricing methodology.

Power of Choice
7/13/2017
Department of Energy 5
Empowering the Filipinos
e – DISKARTE MO
LEGAL BASIS
 ERC Resolution No. 9, Series of 2013 - A Resolution Adopting the Rules
• ClickEnabling
to edit Master text stylesProgram for Renewable Energy
the Net-Metering
• Second level
 Components:
• Third level
 •Rules
FourthEnabling
levelthe Net-Metering Program (Annex A)
• Fifth level
 Net-Metering Interconnection Standards (Annex A-1)
 Net-Metering Agreement Template (Annex A-2)

 Approved on May 27, 2013

 Effectivity on July 24, 2013

Power of Choice
7/13/2017
Department of Energy 6
Empowering the Filipinos
e – DISKARTE MO

NET METERING FOR RE


•• Click to edit Master text styles
Refers
• Second level
to a RE system, appropriate for
distributed
• Third level
• Fourth level
generation, in which distribution
grid user has a two-way connection to the
• Fifth level

grid and is only charged or credited, as the


case maybe, the difference (net) between its
import energy and export energy.

Power of Choice
7/13/2017
Department of Energy 7
Empowering the Filipinos
e – DISKARTE MO

DISTRIBUTED GENERATION
• Click to edit Master text styles
• • Refers
Second level to a system of small generation
• Third level
entities supplying directly to the distribution
• Fourth level
• Fifth level
grid, any one of which shall not exceed one
hundred kilowatts (100 kW) in capacity, as
defined in Section 4(j) of R. A. No. 9513.

Power of Choice
7/13/2017
Department of Energy 8
Empowering the Filipinos
e – DISKARTE MO
INTERCONNECTION SET-UP
Two-way connection
Two uni-directional meters
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Import

Export

Max. Capacity = 100 kW


Situated within the premises of Third meter
a qualified end-user (QE)

7/13/2017
Department of Energy 9
Empowering the Filipinos
e – DISKARTE MO
NET METERING SETUP
Two-way connection
Bi-directional meter
• Click to edit Master text styles
• Second level
• Third level
• Fourth level Import
• Fifth level

Export

Max. Capacity =100 kW


Situated within the premises of
a qualified end-user (QE) Second meter

7/13/2017
Department of Energy 10
Empowering the Filipinos
e – DISKARTE MO
Scope, Applicability, & Qualification
• Click
Applicable to on-grid RE systems
to edit Master text styles
 End-user
• Second level should be in good credit standing in the
• Third level
payment • Fourthoflevelelectric bills to the distribution utility (DU).
• Fifth level
 RE systems such as wind, solar, biomass or biogas
energy systems or such other RE systems capable of
being installed within the qualified end-user’s premises
are eligible to participate in the net metering program.

Power of Choice
7/13/2017
Department of Energy 11
Empowering the Filipinos
e – DISKARTE MO
Scope, Applicability, & Qualification
• Click
Theto editRE Master System must be compliant with the
text styles
• Second level
standards
• Third level
set in the Philippine Electrical Code (PEC),
Philippine
• Fourth levelDistribution
• Fifth level
Code (PDC), Distribution
Services and Open Access Rules (DSOAR) and the
Net-Metering Interconnection Standards (NMIS).

Power of Choice
7/13/2017
Department of Energy 12
Empowering the Filipinos
e – DISKARTE MO
Pricing Methodology
 Interim (temporary/provisional) pricing for export
• Click to edit Master text styles
• energy
Second levelis the DU’s monthly charge based on its
blended
• Third level generation cost.
• Fourth level
• Fifth level
 This cost shall be automatically included in the
DU’s total generation cost to be recovered from all
its customers as part of the adjusted generation
rate pursuant to Section 2 of ERC Resolution
No. 19, Series of 2009

Power of Choice
7/13/2017
Department of Energy 13
Empowering the Filipinos
e – DISKARTE MO
Pricing Methodology
Export rate

• Click to edit Master text styles P4.9101/kWH


• Second level
• Third level
• Fourth level
• Fifth level

Generation Transmission

P9.4291/kWH
Import rate
Power of Choice
7/13/2017
Department of Energy 14
Empowering the Filipinos
e – DISKARTE MO
Net Metering Charge
• Click
Netto editmetering charge is equivalent to
Master text styles
•PhP/customer/month
Second level supply and metering rates;
• Third level
plus • the ERC-approved PhP/kWh metering rate
Fourth level
• Fifth level
based on export energy.

 DUs may file for a different net metering charge, if


necessary.

Power of Choice
7/13/2017
Department of Energy 15
Empowering the Filipinos
e – DISKARTE MO
Billing Charge
Billing Charge:
• Click to edit Master text styles
PhP for import energy
• Second level
Less: •PhP export energy
Third level
• Fourth level
PhP credited
• Fifth level in previous month
Net/Difference in Php (+ or -)

If positive: QE shall pay this amount to DU


If negative: DU shall credit this amount to QE’s next bill

Power of Choice
7/13/2017
Department of Energy 16
Empowering the Filipinos
e – DISKARTE MO
HOW TO OPTIMIZE A NET METERING CONNECTION?
• It shall displace relatively high consumer rate (import cost) of the DUs , that is:
• Click to edit Master text styles
• Annual gross benefit of the project is equivalent to the annual savings generated. It is
• Second
computed level
by multiplying the annual total generation with the import cost
• Third level
• Fourth level
• Type of usage : •Net user on a monthly basis
Fifth level

- Capacity (kWp) can supply the minimum daytime consumption even during low
irradiation months (July to January);
- generation during the high irradiation months is less than the maximum daily energy
requirement

• The system is used to displace the minimum daily energy requirement.

Power of Choice
7/13/2017
Department of Energy 17
Empowering the Filipinos
e – DISKARTE MO
SAMPLE CALCULATION
• Site is Manila (NAIA) • Economic life : 20 years
• The system is to be used 12/7 annually; • 100% loan at annual interest rate of 10%
• Click
• Daily to edit
minimum Master(daytime)
electricity text styles payable in 5 years
need :• 10 kWH/day
Second level • Annual amortization : P55,397.47
• Minimum•Irradiation
Third level : 4.5 kWH/m
2
• Displaced cost (MERALCO consumer price
• Global Irradiation : 1 kWH/m
• Fourth level 2
of electricity) : P11.00/kWH
• Optimum capacity• (kWp) : 3 kWp
Fifth level • Projected annual savings : P46,253.00
• Annual generation at 16% capacity • NPV : P647,896.00
factor : 8,410 kWH • Project IRR : 14%
• Installed Cost/kWp : P70,000.00/kWp x • Breakeven Year : 7th year
3 = P210,000.00 • The levelized cost of electricity (LCOE) :
P1.41/kWH

Power of Choice
7/13/2017
Department of Energy 18
Empowering the Filipinos
e – DISKARTE MO
SAMPLE CALCULATION
• Site is Manila (NAIA) • Economic life : 20 years
• The system is to be used 12/7 annually • 100% loan at annual interest rate of 10%
• Click
• Daily to edit
minimum Master
electricity text styles
(daytime) need : payable in 1.5 years
• Second level
1 kWH/day • Annual amortization : P23,645.84
• Third level: 4 kWH/m2
• Minimum Irradiation • Displaced cost (MERALCO consumer price
• Fourth level of electricity) : P11.00/kWH
• Global Irradiation : 1 kWH/m2
• Fifth level
• Optimum capacity (kWp) : 350 Wp • Projected annual savings : P5,396.16
• Annual generation at 16% capacity factor : • NPV : P41,034.00
490.56 kWH • Project IRR : 11%
• Installed Cost/kWp : P100,000.00/kWp x .35 • Breakeven Year : 8th year
= P35,000.00 • The levelized cost of electricity (LCOE) for
20 years : P0.94/kWH

Power of Choice
7/13/2017
Department of Energy 19
Empowering the Filipinos
e – DISKARTE MO

Net Metering
• Click to edit Master text styles
• Second level
Interconnection Standards
• Third level
• Fourth level
• Fifth level

Annex A-1

Power of Choice
7/13/2017
Department of Energy 20
Empowering the Filipinos
e – DISKARTE MO
Interconnection Standards
 General Guidelines
• Click to edit Master text styles
• Second level Application for Interconnection
• Third level
 level
• Fourth System Parameters
• Fifth level
 System Protection
 Operations & Maintenance
 Metering
 Testing and Commissioning

Power of Choice
7/13/2017
Department of Energy 21
Empowering the Filipinos
e – DISKARTE MO
General Guidelines
 Design, installation, operations and maintenance shall be in consultation
•with
Clickthe
to DU,
editsince
Master all text styles
specifications shall be of DU’s standards.
• Second level
 System requirements shall be met at the Connection Point.
• Third level
 The DU shall only
• Fourth levelallow interconnection of RE facilities with up to 100kW
capacity per •QE Fifth level
account.
 The DU shall conduct inspections and shall remove the generation from
DU system at any time due to maintenance, test, repair and emergency
conditions.
 QE to be liable for any damages of the DU should the QE execute changes
to the RE facilities without first informing the DUs.

Power of Choice
7/13/2017
Department of Energy 22
Empowering the Filipinos
e – DISKARTE MO
Application for Interconnection
QE to
QE to complete and
send DU to
file an application.
a•letter
Click to edit Master text styles
provide information
• Second
requesting DU level
for to QE.
• Third level
interconnection.
• Fourth level
• Fifth level

Ifyes:
Pro forma agreements
DU to determine DU to acknowledge
DU Application form
shall whether DIS and/or within ten (10)
provide• DescriptionDAS of proposed
is connection business days from
results of study.• Relevant Standard Planning Data
necessary. receipt.
• Other data required by DU
• Completion date
DU, with  Technical requirements
 Specifications QE and DU
QE to
to enter
 Listing of certified equipment
conduct
 Application fee into a Net-Metering
information
on-site
 Applicable rate schedulesAgreement.
inspection.
Department of Energy  Metering requirements
7/13/2017 23
Empowering the Filipinos
e – DISKARTE MO
System Parameters
 Voltage Level - should be the same level as the DU with automatic method
of disconnecting.
• Click to edit Master text styles
 Frequency – 60 Hz with automatic method of disconnecting.
• Second level
 Power• Quality
Third level
 Limitation
• Fourthoflevel
direct current (DC) injection – not to inject direct current
• Fifth level
greater than 0.5% of the full load rated output current at connection
point.
 Flicker severity – not to exceed 1.0 unit for short term (ST) and 0.8 units
for long term (LT).
 Harmonics – within limits in Sec. 3.2.4 of Philippine Distribution Code
(PDC)
 Power Factor – not less than 85% lagging measured at the Connection Point.

Power of Choice
7/13/2017
Department of Energy 24
Empowering the Filipinos
e – DISKARTE MO
System Protection
 Synchronization – QE to provide synchronizing devices with typical limits in
the Net Metering Standards.
 •Islanding
Click to edit
– QEMaster
systemtext styles
should detect islanding and disconnect within 2
• Second level
seconds from formation.
• Third level
 Integration withlevel
• Fourth DU’s Distribution System Grounding – shall be grounded in
accordance to • Fifth
Philippine
level Electrical Code (PEC).
 Protective Control Devices
 Disconnect device – visible for use by the DU within 10 feet from
connection point.
 Protective relays – protective relays provided in Net Metering (NM)
Standards
 Reclosing – immediate disconnection from the DU system when the
system is down.

Power of Choice
7/13/2017
Department of Energy 25
Empowering the Filipinos
e – DISKARTE MO
Operations & Maintenance
 Facility should operate in parallel with the DU.
• Click to edit Master text styles
 QE• Second
mustlevel inform the DU if it is going to synchronize.
• Third level
 If the• Fourth DUlevel system is down, the facility should
• Fifth level
automatically disconnect.
 QE to provide DU with contact numbers.
 QE shall maintain the facility in a safe manner as
approved by the DU.

Power of Choice
7/13/2017
Department of Energy 26
Empowering the Filipinos
e – DISKARTE MO
Metering
 MSP shall own and shall be responsible for the
•operations
Click to edit Master and text styles
maintenance of the meter in
• Second level
accordance
• Third level with Sec. 2.11 of Distribution Services and
• Fourth level
Open Access Rules (DSOAR).
• Fifth level

 QE to provide space for the metering facilities.


 Metering facilities shall be installed in an accessible
and visible area for reading and testing of both QE and
DU.

Power of Choice
7/13/2017
Department of Energy 27
Empowering the Filipinos
e – DISKARTE MO
Testing & Commissioning
 Commissioning test shall be Commissioning Test shall
• Click to edit
conducted Master
after thetext styles include the following:
• Second level system is
interconnection  Verification and
• Third level
installed. • Fourth level inspections
• Fifth level
 DU has the right to witness the  Production Test
testing and commissioning.  Response to
abnormal voltage
 RE facility shall be equipped with
 Response to
whatever equipment is required
abnormal frequency
to perform the test.
 Synchronization
 Unintentional islanding
functionality test
 Cease-to-energize
7/13/2017
functionality
28
test
Department of Energy
Empowering the Filipinos
e – DISKARTE MO

Net Metering Agreement


• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level

Annex A-2

7/13/2017
Department of Energy 29
Empowering the Filipinos
e – DISKARTE MO
Net Metering Agreement
Parties: DU and Qualified End-user (QE)
• Click to edit Master text styles
Mirrors
• Second the
levelprovision in the Rules Enabling the Net-Metering
Program (i.e.
• Third levelCompliance Standards, Interconnection Set-Up, DU
• Fourth level
Inspection, •MeterFifth level Readings, Pricing and Other Charges).

To be submitted to ERC, DOE & NREB within 5 days from


execution.

Deemed approved and effective upon submission to ERC.

Power of Choice
7/13/2017
Department of Energy 30
Empowering the Filipinos
e – DISKARTE MO
GOVERNMENT INITIATIVE
DOE Project: Net Metering Demonstration in Private Academic Institutions
• Click:toDisplace
Objective edit Masterdaytime textload
styles
Target Area
• Second: Metro
level Manila
Consumer•Electricity
Third level Rate : PhP 11.50
• Fourth level
Financing Scheme : PV Suppliers at no initial cost to the school
• Fifth level
Payment Scheme : PhP 9.500/kWh for 14 years
Status :
• Three (3) schools
1. La Consolacion College : 133 kWp
2. MLQU : 96 kWp
3. St. Scholastica College : 96 kWp

Total Capacity : 325 kWp


Power of Choice
7/13/2017
Department of Energy 31
Empowering the Filipinos
e – DISKARTE MO
WHERE ARE WE NOW?
• Click to edit Master text styles
•92%
Secondislevel
in
• Third level
MERALCO
• Fourth level
• Fifth level

7/13/2017
Department of Energy 32
Empowering the Filipinos
e – DISKARTE MO
WHERE ARE WE NOW?
• Click
ERCto edit - Master
engaged a consultant to conduct a
text styles
• Second level
net-metering study (on pricing methodology) on July
• Third level
2016 • Fourth level
• Fifth level

 The ERC came out with proposed amendments to


the Net-Metering Rules in August 2016

Power of Choice
7/13/2017
Department of Energy 34
Empowering the Filipinos
e – DISKARTE MO
WHERE ARE WE NOW?
 The following were the current issues covered in the
• Click
proposed Amendments:
to edit Master text styles
• Second level
• Third level
1. Whether
• Fourth levelor not the lifeline rate should apply to Qualified
End-users.
• Fifth level

2. Whether the mechanism of merely accumulating the


credits of net exports on the customer bill, is reasonable.

 The ERC will consolidate all amendments based on the study


and the comments gathered.

Power of Choice
7/13/2017
Department of Energy 35
Empowering the Filipinos
Thank You!

e-Diskarte Mo!
#KuryenteMo #eGenerateMo

(+632) 479-2900
[email protected]
www.doe.gov.ph
//doe.gov.ph
@doe_ph

Department of Energy
Empowering the Filipinos

You might also like