Design Basis PDF
Design Basis PDF
DESIGN BASIS
0 06.12.2007
In the event of conflict between codes and standards being used, the most stringent
one has to be followed. Where Indian standards do not exist or equipment is supplied
by foreign manufacturer, relevant international standards shall be applicable.
OISD - 113
API-RP - 500
IS - 5572 / 5571
Incase of any conflict amongst the above, the more stringent shall be followed.
The following factors shall be considered for proper selection of equipments for use in
hazardous area:
- Gas group classification: The characteristics of the gas or vapor involved in relation
to the ignition current or minimum ignition energy and safe gap data.
The types of protections generally used for electrical equipments in hazardous areas
are as follows :
Zone 0 - Intrinsically Safe, Type of Protection “i”.
Zone 1 - Intrinsically Safe, Type of Protection “i”.
- Flameproof equipment, Type of protection ”d”.
- Pressurized enclosure, Type of protection “p”
- Sand filled equipment, Type of protection “q”.
- Other electrical apparatus specifically designed for zone 1,”s”.
Zone 2 - Protection as suitable for Zone-0 and 1.
- Increased Safety protection “e”.
Electrical equipments to be used in hazardous area shall possess type test certificates
from one of the following recognized testing and certifying authorities:
CMRI : Central Mining Research Institute.
CCE : Chief Controller of Explosives (Indian).
UL : Underwriters Laboratories Inc. (USA).
FM : Factory Mutual Research Corporation (USA).
BASEEFA : British Approvals Service for Electrical
Equipment in Flameproof Atmospheres.
PTB : Physikalisch Technische Boundesantalt (Germany).
RIIS : Research Institute of Industrial Safety (JAPAN).
All equipments falling in the hazardous area shall be intrinsically safe (type “i”), or
flameproof / explosion proof (type “d”). Only in case for any application, when
equipments of such protection classification are not available, other types of
protections can be considered as indicated in the table below:
In addition to above, the equipments to be used in classified areas must have type test
certificates from CMRI or any other testing agency as above and must also be
approved by DGMS. Any other statutory approval, if required in view of Clause 5.0 of
this document, will also be the responsibility of the contractor.
Besides all indigenous equipments to be used in classified areas shall have valid BIS
license as required by statutory authorities. The copies of the BIS certificates with the
DGMS approval certificates shall be furnished during documentation review. It is the
contractor’s responsibility to obtain all statutory approvals including the DGMS
approval for the plant.
Further the electrical system and equipment shall conform to the following amendment
to Rule 116, sub rule (1) of Indian Electricity Rules:
“In the interest of safety, appropriate equipment shall be suitably placed in the mines
for automatically disconnecting supply in any part of the system, where a fault,
including earth fault occurs. Fault current shall not be more than 750 milli-amperes in
550V/1100V system for underground / oil fields and 50A in 3.3kV /6.6kV system in
open cast mines. The magnitude of the earth fault shall be limited to those specified
values by employing suitably designed, restricted neutral system of power supply.”
The following relay protections shall be provided as minimum for electrical installation.
OUTGOING
TRANSFORMER MOTOR INCOMER
FEEDER
RELAY MV
(REF:- ANSI / IEEE HV HV MV PMCC HV PMCC
/ IEC 37.2) POWER DISTR. (650 V (650 V (250 V (650 V (250 V
< HV ≤ < HV ≤ < MV ≤ < HV ≤ < MV ≤
33 kV) 33 kV) 650 V) 33 kV) 650 V)
IDMTL O/C (51) YES YES - YES YES (4) YES YES (4)
YES
IDMTL E/F (51N) YES (7) NO - YES YES (4, 8) YES
(4,9)
BACK UP E/F
(51N)
YES YES - NO NO NO NO
(SECONDARY
SIDE NEUTRAL)
MOTOR
PROTECTION
RELAY WITH
LOCKED ROTOR NO NO YES NO NO NO NO
FEATURE
(50, 51, 50N, 46,
49, 50L/R)
INSTANT.
REST.E/F
YES NO - NO NO NO NO
SECONDARY
SIDE (50N)
INST.O.C (50) YES YES - NO NO NO NO
INSTANT.EF. (R)
YES (6) YES - NO NO NO NO
(50N)
DIFF. PROT.( 87) YES (1) NO YES (2) YES (3) NO NO NO
TRIPPING RELAY
YES YES YES YES YES (4) YES YES
(86)
TRIP CKT
SUPERVISION YES YES YES YES NO YES NO
(95)
TFMR AUX.
YES YES - NO NO NO NO
RELAY (63TX)
UNDERVOLTAGE
WITH TIMER - - YES - - YES (5) YES (5)
(27,2)
7.1 An earthing system as per IS 3043 shall be installed in each plant area for system
neutrals, all electrical equipments and steel frame buildings. Each earthing system
shall consist of G.I. pipe electrodes, G.I. earthing flats of sizes as required in a
common loop to interconnect all earth rods. All major structural steel, stacks, vessels
and process equipment likely to become charged with static electricity shall be solidly
connected to the earthing system. The overall resistance of earth grid shall be less
than 1.0 ohm. Soil resistively survey shall be carried out by the contractor for design of
earth grid. The earth network conductor shall be sized to carry maximum earth fault
current without undue rise in temperature. All electrical equipments shall have two
separate & distinct connections to earth grid.
7.2 Lightning protection system shall be provided for equipment, structures, Tankages
(Existing & New) and buildings as per OISD std.180 and IS 2309 with independent
earthing system of earth resistance less than 5 ohms.
7.3 For HV system each lightning arrestor shall be connected to a separate copper plate
earthing located as close as possible to it and within the fenced area of each set of
arrestors. The three numbers of earthings for each set of arrester shall be spaced
about 5 meters apart so that they are all within the enclosing fence. Each of these
earthings shall be interconnected.
7.4 An earthing schedule giving the type / sizes of earthing conductors for different
equipments is given below. Required sizes for earthing conductors shall have to be
established by design calculations. The sizes given below are indicative and minimum
only.
Utilization Category:
Electrical loads are divided into following three classes according to use:
Continuous Load - Which draws power at continuous rate.
Intermittent Load - Which draws power as per duty cycle for short duration.
Stand-by Load - Which is connected with power supply and ready to act as
and when required.
Load Assessment;
All electrical loads are to be developed by the contractor based on estimated load
identified in the equipment list. The data sheet should specify maximum power
requirement. In evaluating load summary, utilization category is applied as following:
Total Load:
i) Continuously Operating Equipment - 100 % of operating load
ii) Intermittent Load - 50 % of the total intermittent load or the
largest intermittent load whichever is
higher.
iii) Stand-by Equipment - 10 % of total ‘stand-by’ load or largest
stand-by load, whichever is higher.
Existing power supply to individual installations is availed from 33/11 kV sub stations
of CPPs (Captive power plants) located at Lakwa, Geleki and RDS through overhead
lines / UG cables. Otherwise for isolated installations power supply is availed from
state grid generally at following voltage levels. Under This Bid captive power plants
to meet the full power requirement is envisaged without any back up from SEB.
Frequency : 50 Hz ± 3%.
The shirt circuit levesl for all voltage levels shall be calculated and systems shall be
accordingly designed.
Reliable and trouble free performance for designed life of the installation.
Safety
Statutory Regulations.
Suitability for the specified requirement for use in outdoor and indoor locations.
Suitability for the corrosive effects of the saline and humid and extremely dusty
atmosphere.
All electrical equipments shall be suitable for installation in hot and humid
LT Switchgear : Indoor.
Two nos. of lighting transformers are required for each installation. Each lighting
transformer shall be sized to take care of the total lighting load of the plant with a
provision for 10% extra capacity. Lighting system of the complete installation shall be
as per DGMS guidelines as detailed later. Lighting transformers with the MLDB(s)
shall be located inside the MV switchgear room.
The substation building shall be sized to take care of all the present and future
requirements and to maintain adequate clearances between equipments for ease of
maintenance. A margin of at least 25% space shall be kept in switch gear rooms and
battery rooms for future expansion. HV/MV switch boards shall have provision for
future extension from both ends. The following minimum clearances around various
equipments and panels shall be maintained:
equipments - 2000 mm
Vertical clearance above the top of the highest equipment shall be minimum
1500mm from roof slab. For areas with false ceiling minimum clearance of 750mm
shall be provided between top of the equipment and the false ceiling.
All panels shall be single / double front, fully draw-out type. Compartments shall be
capable of withdrawing to a test position. This test position isolates the power cables
to allow the live commissioning of control circuit.
The MV switch boards are provided with a minimum 20% fitted spare motor starters
and feeder modules (subject to minimum 01 of each rating and type).
Each starter unit have component designed for Type – 2 co-ordination as per IEC /
IS – 13947. All load feeders shall be provided with earth leakage protection.
For the PMCC, feeders for more than 400 ampere rating shall be provided with ACB.
Feeders up to 400 ampere rating shall be provided with MCCB. All lighting / auxiliary
/ power panel main incomers will be MCCB. All lighting sub-distribution board
incomers up to 63 amperes shall be MCB and beyond 63 amperes MCCB shall be
provided. Bus bar and isolating devices are rated at 125% of total design load. Bus
bars are generally identified as R, Y & B with phase coloured as red, yellow and
blue. All the switchgears are industrial grade equipment installed in freestanding
sheet metal cubicles of modular design. All the switchgears are to be installed in a
All equipment and switchgear ratings are decided based on actual design
calculations (actual requirement) and 10% spare capacity (if spare capacity is not
particularly mentioned).
Cable entry to all panels of H.T. & L.T. switchgear and control panels shall be from
bottom.
Switch board components such as breakers, MCCBs, horizontal and vertical bus
bars shall be designed to withstand design fault current or maximum fault current at
the point of installation, which ever is higher for a minimum period of 1 sec.
11.4 MV Incomers
Incomer feeders shall be withdrawable, four pole, air circuit breakers with charging
motor, spring release and close mechanism. Breaker close / trip solenoid are fed
through 110 Volt D.C. There shall be three positions for the draw out trolley, “Full-in”,
“Test” and “Full-out”.
MV Capacitor banks
415 V, indoor type, delta connected capacitor bank for p.f. control complete with
over voltage protection, microprocessor based automatic p.f. correction relay and
switching contactors.
Capacitor units shall be dry type, mixed di-electric, low loss, long life with over
pressure protection device.
11.6 Motors
All the motors required by mechanical packages shall meet the requirement of
relevant National / International standards. The voltage ratings for motors shall be as
below:
Rated Voltage in kV ( UN) Minimum rated output (kW)
415 ≤160
3.3 ≤ UN ≤ 6.6 > 160 and < 1000
6.6≤ UN<11 ≥1000
Also all electric motors installed outdoor shall meet the criteria for the hazardous
area requirement and the below mentioned criteria in addition to the standard
specifications and data sheet for same:
Starting torque and minimum torque of the motor shall be compatible with the speed
torque curve of driven equipment under specific operating conditions. For DOL start
applications, HV motors shall be suitable for starting with 80 % of the rated voltage
at the terminals and MV motors with 75 % of the rated voltage at the terminals. For
heavy duty drives such as reciprocating compressor, agitator, crusher etc. high
starting torque motors (minimum 150 % of rated torque) shall be provided to limit
starting current and time.
UPS and DC supply shall be provided as per project requirement. Separate battery
room is to be provided in all switch gear rooms. Generally, the following shall be
required:
11.7.3 DC supply
DC supply system shall be provided with charger, SMF batteries, Lead acid and DC
distribution board. DC supply shall be sized during detail engineering.
To cater to specialty lighting, i.e. critical and exit lights, breaker controls /
instrument supply etc.
To cater to instrument / control supply, Process and control PLC, Fire and Gas
detection system etc.
c) Output : 24 V DC
To cater to the starting requirement of Emergency Gen. sets, Fire water pumps.
Emergency generator driven by battery started diesel engine with AMF panel shall
be provided in all installations. The electrical loads to be fed by emergency generator
shall consist of the following as minimum:
• All utilities including air compressor, UPS, DC battery and charger system,
Potable water, Service water, Bore well water, etc.
• Fire fighting equipment including jockey pump but excluding main fire water
pumps
• Loads critical for process (as defined in basic bid work), plant and personnel
safety
• 10 % margin for future expansion shall be considered while sizing the generator
set.
Gas engine generator shall be sized to meet full power requirement of the
installation as follows.
i) Continuously Operating Equipment - 100 % of operating load
ii) Intermittent Load - 50 % of the total intermittent load or the
largest intermittent load, which ever is
higher
The total load for sizing of generator shall be sum of i), ii) and additional 10% margin
for future.
All LT power cables shall be armored, heavy duty, XLPE insulated with copper
conductor, ISI marked & conforming to DGMS requirements.
Control cables shall be of copper conductor, heavy duty, armored, XLPE insulated,
ISI marked & conforming to DGMS requirements.
All the above cables are indented to be used in mines and shall accordingly be
identified on outer sheath as per IS.
Cable entry:
HT Switchgear : Bottom
LT Switchgear : Bottom
Control Panels : Bottom
Voltage Rating:
• DC Cables : 150 V DC
Cable sizing:
During detailed engineering all power and control cables are to be identified and
sized according to the requirements of Indian and International standards. The sizing
calculation takes into account the following factors:
• System Voltage
• Connected Load
• Voltage Drop
• Laying conditions
Wherever possible, power cables and control cables are to be routed separately or
with adequate spacing to minimize the effects of de-rating.
De-rating of cables due to ambient air temperature, ground temperature, grouping &
proximity of cables, method of laying (air / underground), thermal resistivity of soil
etc. shall be taken into account. De-rating factor of 0.6 or less shall be considered
for sizing of all cables.
The minimum value of oxygen index for cables shall be 29 at 27± 20 C. The flame
retardance properties shall meet the requirements of IS – 7098 (1994) applicable to
C1 category of cables for all power and control cables (up to and including 1100
Volts).
All cables shall be without intermediate joints. The cable sizes selected shall meet
the following requirements of voltage drops.
Voltage drop:
• DC system - 3%
• The voltage drop at the worst affected pre-loaded bus is not to exceed 15% of
nominal voltage during start-up of the largest HV motor and 10% of nominal
voltage during start-up of the largest MV motor.
• Cables for capacitor banks shall be sized for 143% of the rated capacitor current.
One core shall be left as spare in control cables having up to 5 cores. From 7 cores
upward about 20% or minimum 2 cores shall be left as spare for future use. Control
wiring of the panels shall be carried out with flexible, 1.1kV grade, PVC insulated,
switchboard wire with stranded copper conductor of 2.5 mm2. For connecting relay
instruments, 1.5 mm2 copper conductors will be acceptable.
For Air-conditioner machine circuits 4.0mm2 (Copper conductor) PVC insulated wire
shall be used.
Industrial cable glands are not used on oil / gas installations. All cable glands are to
be type tested and certified by appropriate authorities for use in specified hazardous
area.
Cable transit frames are to be fitted where cables pass through outdoor trays /
trenches indoor areas or vice-versa.
Such cable transit frames are designed to include 25 % spare capacity for future
use. Cable transit frames are to be supplied with test certificates from an accredited
independent test authority to confirm adequate fire rating for areas where they are to
be installed.
b) The cable trays, racks & trenches shall be sized to allow for 20% future cables.
d) In addition the minimum distance between power / control wiring and electronic
signal wiring on prolonged cable route will be as follows:
f) The overhead cable trays are installed a minimum 2700 mm. (minimum) above
grade level. At road crossings overhead trays shall be installed at 7000 mm.
(minimum) above grade level.
For illumination of the complete outdoor area (e.g. open area, street lighting etc.)
coming under each plant area, motorized flood lighting high mast(s) (20 mtrs high
approximately) shall be provided. Each high mast shall have minimum 12 nos. of 2 x
400W HPSV fixtures. The number of fixtures in each mast including mast’s exact
location shall be worked out during detailed engineering.
The dark areas / shadows shall be illuminated with suitable street light / floodlight
fixtures.
The type and exact number of fixtures required for different locations shall be worked
out during detailed engineering and shall fulfill the minimum illumination level criteria.
The fixture selection (i.e. flameproof / non-flameproof) shall be based on the area
classification. Outdoor fittings in safe areas shall be of weather proof (i.e. IP 55)
construction. Corrosion resistant fixtures will be provided in places like chemical
storeroom and battery room.
A maintenance factor of 0.8 shall be considered for all illumination level calculations.
All ballasts shall be low loss type with copper winding and power factor improvement
capacitor.
The lighting fixtures of various circuits shall be suitably interlaced so that failure of
one circuit does not result in complete darkness.
Illumination in lux
Roads 20
Process Areas:
Non-Process Areas:
Laboratory 400
Cable cellar 70
Flare area 60
Injection header 60
Office 300
Stairs / corridors 70
Residential Area:
Canteen 150
Taller structures shall have aviation obstruction lighting as per statutory regulations
(D.G.C.A.).
Oil Mines Regulations, 1984 state that the lighting systems installed in the mine shall
comply with the provisions of the Indian Electricity Rules, 1956. Indian Electricity
Rules indicate additional precautions to be adopted in mines and oil fields. Additional
precautions for oil mines state that wherever electric lighting is used; the voltage
between phases shall not exceed 250 V if the neutral of the system is connected
with earth.
Lighting system shall be maximum 250 volts, 3-phase, 3-wire system with lighting
equipment connected between phases. It would also be essential to control all
lighting through-two-pole switches.
d) All lighting distribution boards and lighting panels shall have three phase buses
rated for 240 V, 3-phase and shall be without neutral bus.
f) All lighting fixtures and equipments shall be connected between two phases at
a voltage 240 V phase to phase.
g) Incase of lighting of building within the plant premises, double pole switches or
2-pole MCBs shall be used in the lighting circuits instead of conventional single
pole switches.
h) All 240 V, 1-phase sockets in plant area as well as in buildings shall also be
connected between phases at a voltage of 240 V phase to phase and
controlled by 2-pole MCBs or double pole switches.
• All metal surfaces for all equipments and panels shall be painted after proper
surface finish