Sample Letter For Variation Order

The contractor requests a 60-day time extension for the construction project 18D00071: CONSTRUCTION OF LAUREL EVACUATION CENTER AT BARANGAY LAUREL, SAN PASCUAL, BATANGAS PROVINCE. The time extension is needed due to the removal and redesign of a center column at the second floor of the Accommodation Building to suit actual field conditions. The contractor requires additional time to prepare and compute the structural design analysis for the new design of the Accommodation Building.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
4K views

Sample Letter For Variation Order

The contractor requests a 60-day time extension for the construction project 18D00071: CONSTRUCTION OF LAUREL EVACUATION CENTER AT BARANGAY LAUREL, SAN PASCUAL, BATANGAS PROVINCE. The time extension is needed due to the removal and redesign of a center column at the second floor of the Accommodation Building to suit actual field conditions. The contractor requires additional time to prepare and compute the structural design analysis for the new design of the Accommodation Building.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Engr. Noel P.

Ebiao, Jr
DPWH, Region IV-A
EDSA Quezon City

Sir :

Greetings of Peace!

This is to request from your good office for the Time Extension of my contract for
18D00071: CONSTRUCTION OF LAUREL EVACUATION CENTER AT BARANGAY
LAUREL, SAN PASCUAL, BATANGAS PROVINCE. Due to the removal of center column
of located at the second floor of the Accommodation Building to suit actual field condition.

This letter of time extension needs Additional 60 CD, due to waiting of the the
Preparation and Computation of Structural Design Analysis of the new design of the
Accommodation Building.

Favorable action will be highly appreciated.

Thank You.

W. RIVERA CONSTRUCTION & EQUIPMENT


RENTALS Name of Business Firm

WILFREDO A. RIVERA
Authorized Managing Officer