Tut-126 Program

1) The document provides details on the well plan for well TUT-126, including well objectives, location, and drilling programs through various hole sections. 2) It outlines minimum HSE requirements for drilling operations such as well control equipment testing frequencies, BOP stack requirements, and safety meeting and drill requirements. 3) Potential drilling hazards are identified for each hole section to be drilled, along with recommended solutions to mitigate risks such as maintaining good hole cleaning, minimizing connection times, using lost circulation materials, and adjusting mud weights.

Uploaded by

hamdi1000
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
260 views

Tut-126 Program

1) The document provides details on the well plan for well TUT-126, including well objectives, location, and drilling programs through various hole sections. 2) It outlines minimum HSE requirements for drilling operations such as well control equipment testing frequencies, BOP stack requirements, and safety meeting and drill requirements. 3) Potential drilling hazards are identified for each hole section to be drilled, along with recommended solutions to mitigate risks such as maintaining good hole cleaning, minimizing connection times, using lost circulation materials, and adjusting mud weights.

Uploaded by

hamdi1000
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 28

TO : OPERATION GENERAL MANAGERS & TWO MANAGING

DIRECTORS.
FROM : DRILLING GENERAL MANAGERS.
DATE : FEB. 25, 2019
SUBJECT : WELL PLAN FOR TUT-126 (DEVELOPMENT/VERTICAL)

ATTACHED IS THE WELL PLAN TO ASSIST DRILLING WELL TUT-126


THIS WELL IS A (DEVELOPMENT/VERTICAL)WELL LOCATED IN THE KHALDA CONCESSION.
THE PRIMARY OBJECTIVE OF THIS WELL IS K2BM-TS
THE SECONDRY OBJECTIVE OF THIS WELL IS AEB-3D

THE ANTICIPATED FORMATIONS AND LIT


HOLOGY ARE BASED ON SEISMIC AND THE REFERENCE WELLS DATA (TUT-119& TUT-52).

PREPARED BY: CHECKED BY:

_____________________ ___________________
SHADY A.WAHAB ABEDL RAHMAN SHOUKRY
SENIOR DRLG ENGINEER DRLG DEP. HEAD

RECOMMENDED BY:

_______________________ ______________________
SAM HAMPTON MOHAMED ABDEL MAGEED
DEP. DRLG. GENERAL MANAGER DRLG. GENERAL MANAGER

APPROVED BY:

________________________ ________________________
SAID ABD ELMONIEM KEN LEONG
DEP. OPERATIONS MANGER OPERATIONS GENERAL MGR.

________________________ _________________________
DAVID JENNETTE KHALED MOWAFI
GENERAL MANAGER CHAIRMAN
WELL DATA SUMMARY

CONTENTS

ORDER DOCUMENT

1ST WELL INFORMATION

2ND HSE

3RD WELL PLAN OUTLINE

4TH GEOLOGICAL DATA

5TH AUTHORIZATION FOR EXPENDITURE

6TH DAYS VS DEPTH CURVE

7TH COST VS DEPTH CURVE

8TH GENERAL DRLG. HAZARDS

9TH  17 ½” HOLE DRILLING PROGRAM


 13 3/8” CASING PROGRAM
 13 3/8” CEMENT PROGRAM
10TH  12 1/4” HOLE DRILLING PROGRAM
 9 5/8” CASING PROGRAM
 9 5/8” CEMENT PROGRAM
11TH  8 1/2” DRILLING PROGRAM
 7” LINER PROGRAM

12TH WELL HEAD PROGRAM SUMMARY

13TH MUD PROGRAM

TUT-126 (DEVELOPMENT/VERTICAL) 2
WELL INFORMATION
WELL NAME TUT-126

CLASSIFICATION DEVELOPMENT

COUNTRY EGYPT

REGION WESTERN DESERT

CONCESSION KHALDA

OPERATOR KHALDA PETROLEUM COMPANY


APACHE 50%
PARTNERS EGPC 50 %

3D SURVEY IN LINE / CROSS LINE : 7024 / 14871


X: 698279.738
Y: 282366.213
SURF. COORDINATES Deg. Min. Sec.
Lat: 30° 51’ 51.476”
Long: 27° 35’ 52.412"
X: 757183
Y: 296425
BTM. COORDINATES Deg. Min. Sec.
Lat: 30° 44’ 34.708”
Long: 26° 58’ 55.328"
WELL PROFILE VERTICAL

RIG EDC-57

RKB-GL 30 FT

GL-MSL 694 FT
RKB-MSL 724 FT
PROPOSED T.D. 13,000 FT [ ± 493' INTO YAKOUT FM]
PRIMARY OBJECTIVES K2BM-TS
SECONDRY OBJECTIVES AEB-3D
OFFSET WELL TUT-52& TUT-119

TUT-126 (DEVELOPMENT/VERTICAL) 3
HSE

1.1. KHALDA MINIMUM HSE EQUIREMENT FOR DRILLING OPERATION


 KHALDA CONTROL KICK BY HARD SHUT SO KEEP CHOKE LINE CLOSED,
AND CLOSE B.O.P, RECORD SIDPP AND SICP.
 B.O.P, CHOKE MANIFOLD, KILL LINE AND TIW VALVE AND ALL WELL
CONTROL EQUIPMENTS HAS TO TEST EVERY 21 DAYS.
 ALL ABOVE MUST FUNCTION TEST EVERY WEEK
 MINIMUM B.O.P STACK TWO RAM AND ONE ANNULAR PREVENTER
 KOOMEY UNIT MUST BE ABLE TO CLOSE, OPEN AND CLOSE POWERLESS.
 B.O.P CONTROL UNIT, ONE IN RIG FLOOR, ONE KOOMEY UNIT AND ONE
CLOSE TO STP OFFICE.
 B.O.P DRILL, H2S AND FIRE DRILL MUST BE PERFORMED IN WEEKLY BASIS
AND HAS TO RECORD IN IADC REPORT
 WIND SOCK AND ASSEMBLY POINT.
 TIW VALVE AND GRAY VALVE WITH SUITABLE CONNECTION TO DRILL STRING
ALL TIME IN RIG FLOOR.
 ENOUGH BARITE OR CALCIUM CARBONATE STOCK TO INCREASE` M.WT
WITH 2 PPG.
 MIXING SYSTEM VOLUME ENOUGH FOR 1 ½” HOLE VOLUME.
 MIXING SYSTEM ABLE TO MIX KILL FLUID AS HOLE CONDITION
 ALL RIG KEY PERSONNEL MUST HAVE VALID IWCF CERTIFICATE.
 TRIP SHEET AND WELL CONTROL SHEET UPDATED.
 B.O.P, CHOKE MANIFOLD AND KILL MANIFOLD TO BE TESTED.
 PIPE RAM AND CASING RAM FOR 5”, 3 1/2'” DP AND 9 5/8” AND 7” CASING.
 HOLD SAFETY MEETINGS PRIOR TO COMMENCING DRILLING ANY SECTION
OF THE WELL, AND TRIPPING ESPECIALLY THROUGH 8 ½” SECTION
ENSURING THAT ALL INVOLVED PERSONALS UNDERSTAND THE FORTH
COMING OPERATIONS AND RISKS.
 RECORD SLOW CIRCULATING RATES EVERY TOUR, AND EVERY BIT AND BHA
CHANGE OR MUD WEIGHT CHANGE.
 KILL SHEET READY WHILE DRILLING, TRIPPING AND RUNNING CASING AS
PER POLICY.
 REPORT ALL TESTS ON IADC AND DAILY DRILLING REPORTS.
 ALL PERSONNEL ON RIG SHOULD BE TRAINED FOR STOP CARDS INCLUDING
SERVICE COMPANIES.

TUT-126 (DEVELOPMENT/VERTICAL) 4
GENERAL DRILLING HAZARDS
17 1/2” Hole Drilling Hazards:
Potential Solution
Cause
Hazard
HIGH  HI-VIS, SWEEPS W/ LCM.
POTENTIAL
FRACTURED  CMT PLUGS IF LOSSES NOT TOLERABLE.
L.O.C. IN
FORMATION
(MARMARICA. &  AVOID LOADING HOLE WITH CUTTINGS AND CONTROL DRILL
MOGHRA FM) IF NECESSARY

 MAINTAIN GOOD HOLE CLEANING & MIN. REQUIRED MUD WT.


PIPE STUCK ANN. PACK  MINIMIZE CONNECTION TIME.
(DABAA) OFF
 MINIMIZE SHALE EXPOSURE TIME (DRILL SURFACE HOLE IN
THE LEAST TIME POSSIBLE)

12 1/4” Hole Drilling Hazards:


Potential Solution
Cause
Hazard
 MAINTAIN GOOD HOLE CLEANING & MIN. REQUIRED MUD WT.
 MAINTAIN SLIGHT DRILL STRING ROTATION WHILE MAKING UP
CONNECTIONS.
 KEEP CONNECTION TIME AS SHORT AS POSSIBLE TO AVOID
ANN. PACK DIFF. STUCK.
PIPE STUCK
OFF & DIFF.  STORE ±100 BBL FRESH WTR ON LOCATION PRIOR KHOMAN
(KHOMAN)
PRESSURES FM. FOR POSSIBLE USE IF HAVE DIFF. STUCK.
 KEEP RIG DIESEL STOCK FULL PRIOR KHOMAN FM. FOR
POSSIBLE USE IF HAVE DIFF. STUCK.
 MUD COMPANY SHOULD HAVE ENOUGH PIPE FREEING
CHEMICALS ON LOCATION PRIOR KHOMAN.
 INCREASING MUD WT. IN CASE OF STRESSED SHALE
SHALE
ACTIVE &
 USING SHALE INHIBITION & ENCAPSULATING CHEMICALS TO
PROBLEMS MUD SYSTEM.
STRESSED
(A/R-G, DAHAB  USING HI-VIS. SWEEPS TO CLEAN ANN. & TO AVOID STRING
SHALE
& AEB FM.) STUCK.
 PLAN FOR WIPER TRIPS TO CONDITION THE HOLE
ERATIC  MITIGATE DRILLING PARAMTERS
INTERBEDDED
TORQUE IN FORMATIONS  USE SLICK ASSY. W/ROLLER REAMER
A/R GROUP
 USE MOTORIZED BHA (OPTIONAL)
HIGH
POTENTIAL  HI-VIS, SWEEPS W/ LCM.
FRACTURED
L.O.C IN  CMT PLUGS IF LOSSES NOT TOLERABLE.
FORMATION
ALAMIEN
DOLOMITE
 RUN CSG & CMT SAME.

8 1/2” Hole Drilling Hazards:


Potential
Cause Solution
Hazard
TUT-126 (DEVELOPMENT/VERTICAL) 5
Potential
Cause Solution
Hazard
POSSIBLE  HI-VIS, SWEEPS W/ LCM.
L.O.C. IN FRACTURED
MASAJID FM FORMATION  CMT PLUGS IF LOSSES NOT TOLERABLE.
 RUN CSG & CMT SAME.
GAS FLOW HIGH  USING ADEQUATE MUD WT. ( PRIMARY CONTROL)
SAFA & RESREVOIER  MINIZING SURGE & SWAP EFFECT WHILE TRIPPING.
ZAHRA FM. PRESS.
 MEANTAIN GOOD HOLE CLEANING.
ERATIC  MITIGATE DRILLING PARAMTERS
INTERBEDDED
TORQUE IN FORMATIONS  USE BACKED BHA
AEB GROUP
 USE MOTORIZED BHA
 INCREASING MUD WT. IN CASE OF STRESSED SHALE
SHALE
ACTIVE &
 USING SHALE INHIBITION & ENCAPSULATING CHEMICALS TO
PROBLEMS MUD SYSTEM.
STRESSED
SHALE  USING HI-VIS. SWEEPS TO CLEAN ANN. & TO AVOID STRING
STUCK.
 PLAN FOR WIPER TRIPS TO CONDITION THE HOLE

DRILLING PROCEDURES

20” CONDUCTOR CASING


1. PRE-SET AND CEMENT ONE JOINT 20” (94PPF, K-55, BTC) CONDUCTOR AT + 7 FT BELOW THE
CELLAR FLOOR PRIOR TO THE RIG ARRIVAL ON LOCATION.

PRIOR TO ACCEPTING THE RIG FOR OPERATIONS, ENSURE THAT:-


 THE RIG IS FULLY OPERATIONAL AND TESTED.
 MAST IS ALIGNED TO THE ROTARY TABLE AS WELL AS TO THE CELLAR CENTRE.
 ENOUGH AMOUNT OF WATER IS AVAILABLE IN THE TANKS TO DRILL THE SURFACE
HOLE.
 ALL DRILLING DOWNHOLE EQUIPMENT HAS BEEN INSPECTED AND IN GOOD
WORKING CONDITION.
 SOLIDS CONTROL EQUIPMENT IS IN GOOD WORKING ORDER.
 SUFFICIENT LOST CIRCULATION MATERIALS SHOULD BE AVAILABLE ON LOCATION.

DRLG 17 1/2” HOLE X 13 3/8’’ SURFACE CSG


SPUD-IN THE WELL (REPORT TIME, DATE, MOVE DISTANCE & DIESEL CONSUMED WHILE R/M
IN THE DAILY DRILLING REPORT) & ACCEPT RIG AS PER KHALDA PROCEDURES.
1. P/U AND M/U 17 ½” BIT AND BHA AS FOLLOWS :-

17 ½” M.T BIT + B.SUB WITH F.V + 9 1/2" SH. SUB WITH TOTCO
SEAT + 1 X 9 ½” NMDC (MONEL) + 3 X 9 ½” D/C’s + X/O + 9 X 8
1/4” D/C’s + 8” JAR + 3 X 8 1/4” D/C’s + X/O + 12 X 5’ HW D/P’S.
TUT-126 (DEVELOPMENT/VERTICAL) 6
AIR WEIGHT BELOW JAR 69,000 LB’S
BUOYED WEIGHT BELOW JAR 59,500 LB’S (IN 8.8 PPG WTR)
TOTAL BHA AIR WEIGHT 94,000 LB’S
TOTAL BHA BUOYED WEIGHT 81,500 LB’S (IN 8.8 PPG WTR)

 RE-CHECK UPDATED INSPECTION REPORT FOR ALL DRILLING STRING BEFORE M/U.
 SEND COPY FOR ALL BHA PLAN TO RIH BEFORE USE IT WITH ENOUGH TIME TO CAIRO OFFICE.
 USE 8” JAR WITH 100,000 LB UP LATCH SETTING AND 45,000 DOWN LATCH SETTING.
 DON’T EXCEED 45 K-LB W.O.B.
 USE FLOAT VALVE.
 USE MONEL D/C IN BHA.

2. DRILL 17 ½” HOLE TO (± 50 FT INTO MOGHRA FM.).


 USE SPUD MUD WITHOUT ANY ADDED DIESEL TO DRILL MARMARIICA SECTION.
 SWEEP HOLE WITH 30 BBLS HI.-VIS PILL EVERY TWO STANDS TO ENSURE ADEQUATE HOLE
CLEANING AND CIRCULATE OUT EACH PILL BEFORE PUMPING ADDITIONAL ONE.
 START DRILLING WITH REDUCED W.O.B. (10-15 K-LB) AND HIGH R.P.M. (130-140) TO KEEP HOLE
VERTICAL.
 THERE IS A POSSIBILITY OF HAVING L.O.C. IN MARMARICA AS EXPERIENCED IN THIS FORMATION.
 USE MAXIMUM GPM ONCE BHA PASSED 300 FT.

 SO, IF LOSSES IS ENCOUNTERED AND CAN BE TOLERATED, SKIP TO STEP # 4 AND


PROCEED OTHERWISE PROCEED AS FOLLOWING:

a) DRILL AHEAD WITHOUT RETURN UNTIL THE PENETRATION RATE INDICATES A CHANGE IN
FORMATION.
 IN ORDER TO FACILITATE DETECTING ANY CHANGE IN FORMATION, ALWAYS MAINTAIN CONSTANT
DRILLING PARAMETERS
 SWEEP HOLE WITH H.V.P LOADED WITH LCM (60-80 PPB) DURING THE INITIAL BLIND DRILLING AND
IF LOSSES BECAME TOLERATABLE SKIP TO STEP NO. 4 AND PROCEED, OTHERWISE PROCEED WITH
THE NEXT STEP.

b) POOH TO ± 50 FT ABOVE THE THIEF ZONE AND SPOT +/- 100 BBL HI-VIS PILL LOADED WITH (60-
80 PPB) LCM. CONTINUE POOH TO SURFACE.

c) RIH WITH O.E.D.P. TO ± 50 FT ABOVE THE THIEF ZONE. SET BALANCED CEMENT PLUG AS
FOLLOWING :

CLASS “G” CEMENT +


CMT PLUG PROPERTIES

NEAT CEMENT CLASS “G”

SLURRY DENSITY 15.8 PPG


SLURRY YIELD 1.16 CU.FT./SK
MIXING WATER 5.10 GAL/SK
THICKENING TIME 02:15 (HRS:MINS) @ 70 UC

TUT-126 (DEVELOPMENT/VERTICAL) 7
CHEMICALS
+ 2.0 % (BWOC) CACL2
+ 0.003 GAL/BBL DEFOAMER
+ 5.10 GAL/SK FRESH WATER (≥ 800 PPM CHLORIDE CONTENT)
 MAX CMT SLURRY SHOULD BE PUMPED FOR EACH CMT PLUG IS 100 BBL’S CMT SLURRY, THEN
POOH & MONITOR THE WELL FOR LOSSES WHILE WAIT ON CMT.
 PREFERED TO USE THE OPTION OF SLURRY DENSITY 15.8 PPG.
 A REVISED LAB TEST WILL BE FOLLOWED BASED ON THE DRILL WATER SALINITY (IF NEEDED).

d) POOH AND OBSERVE WELL FOR LOSSES WHILE WAIT ON CEMENT FOR +/- 4 HR’S (CHECK
SURFACE SAMPLES), AFTER THAT FILL HOLE WITH D.WTR IF SEVER LOSSES IS OBSERVED RIH
AGAIN WITH O.E.D.P +/- 50 – 100 FT ABOVE THIEF ZONE AND SET ADDITIONAL CMT PLUG,
OTHERWISE PROCEED AS FOLLOWS.

e) RIH WITH 17 ½” BIT AND BHA. TAG T.O.C. WITH CIRCULATION AND +/- 10 K-LB AND CLEAN OUT
THE CEMENT.
 MAX. WOB WHILE D.O.C IS 10 KLB.
 IF CEMENT TAGGED BELOW THE DEPTH AT WHICH FIRST LOSSES WAS ENCOUNTERED AND STILL
HAVING THE SAME LOSSES (EITHER WITH OR WITHOUT D.O.C.), REPEAT FROM STEP (b) TO (e).

3. CONTINUE DRILLING. 17 ½” HOLE TO THE SURFACE CSG POINT TO +/- 3,000 FT ( ± 84 FT INTO
APOLLONIA FM ).
 STRATING FROM DABAA FM SWEEP HOLE WITH 30 BBLS HI-VIS PILL EVERY TWO STD’S THEN SWEEP
HOLE WITH 30 BBLS D.D/ANTI BALLING FOR THE NEXT TWO STD’S TILL C.P
 D.D/ ANTI BALLING PILL (CAUSTIC SODA + DD + NUT PLUG )
 IF A PROBLEM OF BIT BALLING APPEARS ( REDUCED ROP & HIGH TORQUE,…) IMMEDIATELY SWEEP
HOLE WITH 30 BBLS D.D/ANTI BALLING WHILE INCREASE RPM TO 140 AND DECREASE FLOW RATE
TO 500 GPM WHILE THE ANTI BALLING PILL IS AROUND THE BHA TO INCREASE THE PILL CONTACT
TIME (7-10 MIN’S) THEN RETURN TO MAX FLOW RATE.
 DON’T DRILL MORE THAN +/- 100 FT INTO APOLLONIA FM.
 DRILL W/MAX GPM (850-950)&MAX PUMP PERSS FOR THE USED LINER SIZE

4. AT CSG. POINT, SWEEP AND CIRCULATE 1 X 50 BBLS SUN SWEEP PILL (0.25 PPB) TO
CONDITION MUD/HOLE AND MAKE SHORT TRIP TO BHA (DC’s) DEPTH TO CHECK FOR TIGHT
SPOT, RIH TO BOTTOM, SWEEP AND CIRCULATE 1 X 50 BBLS SUN SWEEP PILL (0.25 PPB) ,
SPOT +/- 50 BBL HI-VIS PILL, DROP THE MULTI SHOT SURVEY THEN. COOH WITH SLM TO
SURFACE.

 REMOVE D/P’S SCREEN BEFORE PUMP SUN SWEEP PILL (NO NEED TO REMOVE THE SUCTION PUMP
SCREEN ).
 REPORT ANY TIGHT SPOT DEPTH IF ENCOUNTERED DURING THE WIPER TRIP.
 RECEPROCATE DP WHILE CIRC. AND COND. TO ENHANCE HOLE CLEANING.
 ARRANGE TO TAKE MULTI SHOT SURVEY EVERY 100 FT WHILE COOH FOR CSG. AND SEND SAME TO
CAIRO OFFICE
 L/D 9 ½” MONEL AND STAND BACK THE D/C’s TO BE USED IN THE NEXT HOLE.

13 3/8’’ SURFACE CSG PROGRAM

R/U CSG EQUIPMENT AND RUN 13 3/8” CASING ( 68 PPF, K-55, BTC ) AS PER CSG PROGRAM.
TUT-126 (DEVELOPMENT/VERTICAL) 8
A) CASING DESIGN

DEPTH HOLE CSG. CSG GRADE CONN. COLLAPSE BUSRST BODY $/FT
(FT) SIZE SIZE PPF (PSI) (PSI) YEILD (LB)

0- 3,000’ 17 ½” 13 3/8” 68 K-55 BTC 1950 3450 1,069,000 25.37

B) CASING ACCESSORIES AND PLACEMENT:


CASING ACCESSORIES QTY. ACCESSORIES PLACEMENT
1- FLOAT SHOE (SINGLE VLV) 1 CASING END.
2- FLOAT COLLAR (SINGLE VLV) 1 2 JOINTS ABOVE THE FLOAT SHOE.
3- BOW CENTRALIZERS 3 1 PER JOINT ON THE FIRST 3 JOINTS.
4- STOP COLLAR WITH NAILS ONE IN MIDDLE OF EACH BOW CENTRALIZER.

C) MISCELLANEOUS:
 HAVE AVAILABLE IN LOCATION 13 3/8” BTC CIRCULATING HEAD AND SPIDER ELEVATOR.
 HAVE AVAILABLE IN LOCATION +300 FT OF 1” MACARONI TBG. ON LOCATION IN CASE OF A TOP CMT
JOB IS REQUIRED.
 HAVE CMT BASKET AVAILABLE ON LOCATION FOR 13 3/8" CSG JOB IF LOSSES INCOUNTERD.

NOTES:
 CENTRALIZE CASING AS PER PROGRAM.

D) RUNNING PROCEDURE:
 CLEAN ALL 13 3/8” CASING JOINT THREADS AND DRIFT SAME WITH 12.259” API RABBIT.
 CHECK FLOAT EQUIPMENT BEFORE RIH.
 MAKE UP AND THREAD LOCK THE FLOAT SHOE AND THE FLOAT COLLAR TO THE CASING ON THE
PIPE RACK & CHECK SAME BEFORE RIH.
 MONITOR LOSSES WHILE RIH WITH CASING & REPORT SAME.
 TORQUE UP THE CASING CONNECTIONS TO THE TRIANGULAR MARK & REPORT THE TRQ. VALUE IN
DMR.
 THREAD LOCK THE FIRST TWO JOINTS AND THE CONNECTION ABOVE THE FLOAT COLLAR (USING
CASING DOPE WITH FRICTION FACTOR 1 ON THE REMAINING JOINTS).
 FILL CASING WHILE RIH.
 ACCORDING TO SURGE AND SWAB RUNS WILL BE ISSUED LATER
 CIRCULATE BTM/UP’s TILL SAKER CLEAN (AT LEAST 1.5 CSG CAPACITY)
 SPACE OUT CSG:
SPACE OUT BEFORE RIH TO BE ABLE TO INSTALL AND WELD THE SLIP ON CASING HEAD
WITH THE TOP OF ITS FLANGE LEVELED WITH THE GROUND LEVEL.

13 3/8” CSG PRELIMINARY CEMENT PROGRAM

13 3/8” SURFACE CSG CEMENT (3,000’ – SURFACE) ONE STAGE


a) PREFLUSH:

TUT-126 (DEVELOPMENT/VERTICAL) 9
+ 100 BBL’S FRESH WATER W/4 % KCL

b) LEAD SLURRY ( 2,400’- SURFACE )2400’


DYCKERHOFF CLASS “G” CMT. 12.7 PPG

c) TAIL SLURRY ( 3,000’ – 2,400’)600’


DYCKERHOFF CLASS “G” CMT. 15.8 PPG

DETAILED LAB TEST WILL BE ISSUED LATER


PROCEDURES:-
a) R/U CEMENT HEAD (LOADED WITH TOP & BOTTOM WIPER PLUGS) AND LINES. TEST SAME TO + 3000
PSI AND CIRCULATE WHILE PREPARING FOR CMT JOB.

 COMPANY MAN TO VERIFY PLUGS LOADED IN CEMENT HEAD PROPERLY.


 RECIPROCATE CASING WHILE CIRCULATION (3-5 FT/STROKE).
 CONFIRM NORMAL CIRC. IS ESTABLISHED PRIOR TO CEMENTING.
 MONITOR WELL FOR LOSSES WHILE CIRC. AND REPORT SAME.
 AT THE END OF CIRC. , CIRC. FOR 5 MIN’S W/ LOW GPM +/- 2 BPM & RECORD THIS CIRC. PRESS. IN
DDR.

b) PUMP THE PRE-FLUSH W/ 8 BPM AND RELEASE THE BOTTOM PLUG. MIX AND PUMP THE LEAD
SLURRY W/ 5-7 BPM AND TAIL SLURRY W/ 4-5 BPM.

 RECIPROCATE CASING WHILE MIX AND PUMP THE CEMENT SLURRY.


 MONITOR WELL FOR LOSSES WHILE MIX AND PUMP CEMENT SLURRY. AND REPORT SAME.

c) RELEASE THE TOP PLUG AND DISPLACE THE SLURRY AT +/- 8 BPM. SLOW DOWN TO +/- 2 BPM FOR
THE LAST +/- 15 BBL’S PRIOR TO BUMPING THE PLUG. BUMP THE PLUG GRADUALLY WITH +/- 1000
PSI OVER THE FINAL DISPLACEMENT PRESSURE FOR 10 MIN’S (MAX 2500 PSI).

 USE ISOLATE TANK FOR THE DISPLACEMENT MUD VOLUME TO AVOID OVER DISPLACEMENT.
 RECIPROCATE CASING WHILE ALL CEMENTING JOB (3-5 FT/STROKE).
 IF SLACK OFF WT INCREASE WHILE RECIPROCATE, SET CSG (1’-3’) OFF BTM & LEAVE IT THERE
WHILE COMPLETE CMT JOB.
 MONITOR & CALCULATE LOSSES WHILE CIRCULATION, PUMPING CEMENT, DISPLACMENT, ALSO
WHEN CEMENT START TO BE IN ANNULUS AND REPORT ANY LOSSES IF OBSERVED.
 CALCULATE THE DISPLACEMENT VOLUME AT WHICH THE SLURRY STARTS TO EXIT TO THE HOLE &
AT THIS POINT COUNT THE LOSSES STARTING FROM THIS STAGE SEPARATELY & REPORT SAME IN
THE D.M.R.
 FROM THE F.D.PRESS. & THE CALCULATED LOSSES , ESTIMATE THE EXPECTED T.O.CMT & REPORT
SAME IN THE DMR.
 IF PLUG DOES NOT BUMP AFTER THE CALCULATED DISPLACEMENT VOLUME, CONTINUE TO
DISPLACE, BUT DO NOT EXCEED ONE CSG JOINT CAPACITY.

d) BLEED OFF PRESSURE GRADUALLY TO CHECK THE FLOAT EQUIPMENT.

 IF THE FLOAT EQUIPMENT DOES NOT HOLD WAIT ON CEMENT UNDER THE FINAL DISPLACEMENT
PRESSURE, TILL THE CEMENT HAS INITIAL SET AND RECHECK FOR ANY BACK FLOW.

TUT-126 (DEVELOPMENT/VERTICAL) 10
MISCELLANEOUS:
 CEMENT VOLUME CALCULATION IS BASED ON 25% EXCESS OVER THE 17 ½” GAUGE HOLE IF
NORMAL LOSSES ARE ENCOUNTERED & USE 50% IF HIGH LOSSES ARE ENCOUNTERED.
 THE PERCENT OF EXCESS MAY BE INCREASED DEPEND ON LOSSES STATUS WHILE DRLG SURFACE
HOLE.
 IT IS DESIRED TO BRING THE TAIL SLURRY TO + 600’ ABOVE THE 13 3/8” CASING SHOE AND THE
LEAD SLURRY TO SURFACE.
 PERFORM TOP CEMENT JOB IF NO RETURN IS OBSERVED WHILE PUMPING AND DISPLACING THE
CEMENT SLURRY OR NO CMT LEVEL AT SURFACE.
 SEND DRY CEMENT SAMPLE AND DRILL WATER FOR SLURRY DESIGN AND A REVISED CEMENT
SLURRY LAB TEST WILL BE SENT LATER IF NEEDED.

e) AFTER PLUG IS BUMPED AND FLOATS CONFIRMED HOLDING, SLACK OFF 13-3/8" CASING WEIGHT TO
SET CASING ON BOTTOM. R/D CEMENTING EQUIPMENT. N/D FLOW LINE. CUT OFF 20" CONDUCTOR
PIPE AT CELLAR FLOOR.

f) INSTALL GUSSETS / BRACES BETWEEN 13 3/8" CSG AND 20" CONDUCTOR TO ALIGN 13 3/8" CSG
WITH ROTARY TABLE.
 GUSSETS / BRACES MUST BE WELDED T/ 20” CONDUCTOR CSG NOT 13 3/8” SURFACE CSG.

g) COLD & FINAL CUT 13 3/8” CASING ( TO BE ABLE TO WELD CASING HEAD WITH ITS TOP FLANGE
LEVELED WITH THE GROUND LEVEL ).

 OBSERVE CEMENT LEVEL IN 20" X 13-3/8" ANNULUS. IF NO CEMENT AT SURFACE, PERFORM TOP
CEMENT JOB WITH MACARONI TUBING.
 PERFORM ADDITIONAL TOP CEMENT JOBS AS REQUIRED UNTIL CEMENT REMAINS AT SURFACE.

TOP CMT JOB:-

1. IF LOSSES ENCOUNTERED OR CEMENT DID NOT RETURN TO SURFACE, RIH WITH


MACARONI PIPES INTO ANNULUS BETWEEN CASING AND OPEN HOLE TO PERFORM TOP
CEMENT.
2. MIX AND PUMP 15.8 PPG NEAT CEMENT THROUGH THE MACARONI PIPES UNTIL ANNULUS
IS FILLED WITH CEMENT. PULL AND FLUSH OUT THE MACARONI TUBES.
3. DO NOT ALLOW WATER OR DRILLING FLUID TO FILL THE ANNULUS.
4. OBSERVE CEMENT LEVEL, IF LEVEL DROPPED, REPEAT TOP JOB BY GRAVITY OR BY
MACARONI TUBING AS REQUIRED.
5. AFTER EACH CEMENT JOB, FLUSH WELLHEAD VALVES WITH CLEAN WATER.

WELL HEAD & BOP`S PROGRAM


1. INSTALL AND WELD THE 13 5/8”-5000 PSI “CIW” TYPE “S” CASING HEAD WITH 2 1/16”-5000 PSI
WING VALVE AND 1X2” LP BULL PLUG USING ELECTRIC TECHNIQUE FOR WELDING AND
TESTING SAME.
A. TEST PROCEDURE:
TESTING PROCEDURE AND PRESSURE MAGNITUDE TO BE AS PER midco REPRESENTATIVE
INSTRUCTIONS (FOR 15 MIN’s).
 AVOID ANY FLUID DROPS ON CSG HEAD WELDED AREA TILL NORMALY AIR COOLED
 OBSERVE CEMENT LEVEL IN 20’’ X 13 3 /8" ANNULUS. IF NO CEMENT AT SURFACE , PERFORM
ADDITIONAL TOP CEMENT JOB WITH MACARONI TUBING IF NEEDED.

TUT-126 (DEVELOPMENT/VERTICAL) 11
 RE-CHECK ALIGNMENT WITH ROTARY TABLE.

2. N/U 10,000 PSI X 13 5/8” SHAFFER BOP STACK WITH REQUIRED D.S.A, BELL NIPPLE, FLOW
LINE, KILL LINE, CHOKE LINES & CHOKE MANIFOLD.

3. RUN AND SET 13 5/8” NOMINAL “CIW” TEST PLUG ( FOR TYPE “S” C.H.) IN PLACE.

4. TEST BOP STACK AS FOLLOWS:

RAMS 500/5000 PSI


CHOKE/KILL LINES & VALVES 500/5000 PSI
HYDRIL 250/2500 PSI
CHOKE LINES & CHOKE MANIFOLD 500/5000 PSI
 P/T TEST PUMP TO 500/5500 PSI BEFORE START TESTING BOP’S.
 CHECK PRE-CHARGE PRESS. FOR EVERY N2 BOTTLE & MENTION IN DMR.
 ENSURE CSG IS FULL TO OBSERVE LEAK IF FOUND ANY.
 OPEN CASING HEAD WING VALVE WHILE TESTING BOP STACK TO MONITOR FOR TEST PLUG
LEAKAGE.
 TEST ALL CHOCK MANIFOLD VALVES( UP-STREAM & DOWN STREAM )
 TEST INSIDE BOPS TOOL TO + 500/ 5000 PSI IN CASE OF NEED.
5. PULL THE TEST PLUG. INSTALL 13 5/8” NOMINAL “CIW” WEAR BUSHING (FOR TYPE “S” C.H.)
 MENTION THE ID & CONDITION OF THE WEAR BUSHING IN THE D.M.R.

DRLG 12 1/4” HOLE X 9 5/8’’ INTERMEDIATE CSG


1. M/U & RIH WITH 12 ¼” PDC BIT AND SLICK BHA W/ 12 1/4” R.REAMER AS FOLLOWS:-

12 ¼’’ BIT, 9 ½’’ +Bit Sub + 9 ½’’ Drill Collar + 9 ½’’ MWD + 3x9 ½’’
Drill Collar + 9 ½’’ X-O Sub + 8 ¼’’ PBL + 9x8 ¼’’ Drill Collar + 12 ¼’’
Reamer Roller + 1 X 8 ¼’’ Drill Collar + 8" Jars + Drilling + 2x8 ¼’’
Drill Collar + X-O Sub + 12 x 5’’ HWDP
AIR WEIGHT BELOW JAR = 77,000 LB’S
BUOYED WEIGHT BELOW JAR = 65,000 LB’S (IN 10 PPG WTR)
TOTAL BHA AIR WEIGHT = 109,000 LB’S
TOTAL BHA BUOYED WEIGHT = 93,000 LB’S (IN 10 PPG WTR)
 RE-CHECK UPDATED INSPECTION REPORT FOR ALL DRILLING STRING BEFORE M/U.
 SEND COPY FOR ALL BHA PLAN TO RIH BEFORE USE IT WITH ENOUGH TIME TO CAIRO
OFFICE.
 USE FLOAT VALVE.
 RE-CHECK RIG ALIGNMENT TO ENSURE D/P’S IS CENTERED OVER WELL HEAD

2. RIH W/ 12 ¼” DRLG. ASSY. AND TAG THE TOP OF CEMENT ( REPORT SAME IN THE DAILY
DRILLING REPORT). DOUBLE CHECK ALLIGNMENT OF RIG WITH WELL BORE AND WITH D/P IN
HOLE.
3. IN CASE IF WE DIDN’T BUMPED PLUG, P/T CSG TO + 2000 PSI.
TUT-126 (DEVELOPMENT/VERTICAL) 12
4. DRILL-OUT CEMENT PLUGS, THE FLOAT COLLAR, AND CEMENT TO + 10 FT ABOVE FLOAT
SHOE& PUMP HI.VIS & CIRC. HOLE CLEANING , PRESSURE TEST CASING TO + 2000 PSI.
5. DRILL- OUT CEMENT, THE FLOAT SHOE, AND +/- 10 FT. OF NEW HOLE. CIRCULATE AND COND.
MUD WT. IN = MUD WT. OUT
 CONTROL PARAMETER ( WOB & RPM ) WHILE DRILL OUT CMT AND SHOE TRACK.
 CIRCULATE TILL MUD IN EQUAL MUD OUT & CONDITION THE HOLE.
 PLOT PRESSURE VS PUMPED BARRELS AS BASE LINE GRAPH.
6. PERFORM THE SHOE P.I.TEST WITH 11.5 ppg (EMW) (OPTIONAL DEPEND ON CMT HARDNESS)
 IN CASE OF HAD LEAK WHILE PERFORM PIT, ARRANGE TO SPOT H.V.P. W/ LCM ON BTM TO
PERFORMING P.I.T. & KEEP BIT ABOVE TOP OF H.V.P. W/LCM WHILE P.I.T.
 P/T SURFACE LINES BEFORE CONDUCT P.I.T
 USE CMT UNIT TO CONDUCT THE P.I.T
 WHILE PERFORMING P.I.T KEEP BIT INSIDE CSG SHOE.
 PLOT PRESSURE VS THE PUMPED BARRELS TO COMPARE P.I.T PLOT WITH THE CSG TEST BASE
LINE PLOT.
 INFORM CAIRO OFFICE IMMEDIATEY IF THE LEAK-OFF OCCURED BELOW 11.5 PPG EMW FOR
POSSIBLE CEMENT SQUEEZE JOBS.
 COMPLETE THE P.I.T. FORM AND SEND SAME TO CAIRO OFFICE.
7. DRILL 12 1/4” HOLE TO 3,650’ (+/- 100 FT ABOVE A/R A FM.) USING SPUD MUD AND SWITCH
OVER TO 9.1 PPG KCL POLY MUD (CONTROLLED FLUID LOSS 3-4 CC/30 MIN BEFORE A/R-C). W/
+ 3-5 % KCL AS PER MUD PROGRAM.

 PUMP MAXIMUM GPM ONCE THE BHA IS BELOW SURF CSG (850 – 900 ) MAX PUMP PRESS FOR THE
USED LINER SIZE
 CONTROL ONLY RPM WHILE DRLG & TILL ROLLER REAMERS PASS BELOW CSG SHOE. THEN DRLG
WITH FULL PARAMETERS GPM 850-900 ,W.O.B. (40-45 K-LB) AND R.P.M. (130-140).
 SWEEP HOLE WITH HI-VIS PILL TO ENSURE ADEQUATE HOLE CLEANING AND CIRCULATE OUT EACH
PILL BEFORE PUMPING ADDITIONAL ONE.
 MAINTAIN THE MUD WEIGHT AS CLOSE AS POSSIBLE AS PER MUD PROGRAM, UNLESS THE HOLE
CONDITION DICTATES.
 IF PUMP OUT OF HOLE, USE SAME GPM'S AS WHILE DRILLING & CIRC. HOLE CLEANING BEFORE
POOH
 MONITER BOTH DRILLING AND TRIP LOSSES, MENTION IT IN DMR.
MAINTAIN GOOD HOLE CLEANING & MIN. REQUIRED MUD WT.
MAINTAIN SLIGHT DRILL STRING ROTATION WHILE MAKING UP
CONNECTIONS.
KEEP CONNECTION TIME AS SHORT AS POSSIBLE TO AVOID DIFF. STUCK.
PIPE STUCK ANN. PACK OFF & STORE ±100 BBL FRESH WTR ON LOCATION PRIOR KHOMAN FM. FOR
(KHOMAN) DIFF. PRESSURES POSSIBLE USE IF HAVE DIFF. STUCK.
KEEP RIG DIESEL STOCK FULL PRIOR KHOMAN FM. FOR POSSIBLE USE IF
HAVE DIFF. STUCK.
MUD COMPANY SHOULD HAVE ENOUGH PIPE FREEING CHEMICALS ON
LOCATION PRIOR KHOMAN.

8. CONT. DRLG 12 1/4” HOLE T/ 9,500 FT (+/- 48 FT INTO AEB-3G) CASING POINT USING KCL POLY.
MUD WITH 3-5 % KCL AS PER MUD PROGRAM.

 CONSULT CAIRO OFFICE BEFORE STOP DRILLING TO CHECK IF THERE ARE ANY OIL SHOES
 TAKE MWD SURVEY EVERY 3 STD’S, IF FOUND SEVERE CHANGE IN INCLINATION OR VERTICAL
SECTION, CONSULT CAIRO OFFICE FOR POSSIBLE DECREASE RECORDING FREQUENCY.
TUT-126 (DEVELOPMENT/VERTICAL) 13
 ACCORDING TO ROP, PLAN TO WASH UP, REAM DOWN ONE STD IN CASE OF HIGH ROP & WASH UP &
REAM DOWN ONE JT IN CASE OF SLOW ROP
 IF ROP HIGHER THAN 100 FT/HR: WASH UP/REAM DOWN 1 STD
 IF ROP 100-40 FT/HR: WASH UP/REAM DOWN 1 JT
 IF ROP LESS THAN 40 FT/HR: CHECK P/U 5-10 FT
 SURGE AND SWAB RUNS WILL BE ISSUED LATER
 ARRANGE TO ENTER A/R-G FM. W/ MIN. MUD WT. +/-9.8 PPG WHILE DRLG.
 ARRANGE TO ENTER DAHAB FM . W/MIN.MUD WT. +/-10.2 PPG WHILE DRLG.
 ARRANGE TO RAISE MWT T/10.4 PPG WHILE DRLG AEB FM T/10.4 PPG AS HOLE DEDICATES TILL
C.P.
 INCASE OF HAVING HUGE CAVED SHALE, SWEEP THE HOLE 1ST & CONSULT CAIRO OFFICE BEFORE
INCREASING M.WT, IF NORMAL AMOUNT OF CAVED SHALE CONT’D DRLG.
 DOUBLE CHECK SOLID CONTROL EQUIPMENT, SPECIALLY SHALE SHAKERS CONDITION & SCREEN
DAMAGED RAPIDLY OR NORMAL.
 IN CASE OF INCREASE IN SOLID CONTENT IN THE MUD, USE CENTRIFUGE AND REPORT SAME IN
DDR.
 CHECK WEAR BUSHING EVERY 21 DAYS WITH B.O.P TEST.
 IF PUMP OUT OF HOLE, USE SAME GPM'S AS WHILE DRILLING & CIRC. HOLE CLEANING BEFORE
POOH.
 ARRANGE TO END DRLG THIS SECTION. W/ MAX.MUD WT. 10.2 PPG OR AS HOLE DEDICATE.
 MAINTAIN THE MUD WEIGHT AS LOW AS POSSIBLE AS PER MUD PROGRAM UNLESS THE HOLE
CONDITION DICTATES.
 PLAN TO PERFORM WIPER TRIP @BTM KHARITA FM. TILL SURFACE TO CHANGE THE BIT (DOUBLE
CHECK WITH CAIRO OFFICE) &RAISE MWT T/10.2 PPG BEFORE WIPER TRIP
 BEFORE WIPER TRIP SWEEP AND CIRCULATE ONE BTM UP (HOLE CLEAN), PUMP OUT OF HOLE THE
FIRST STAND, THEN CONT POOH ON ELEVATORS

THERE IS A POSSIBILITY OF HAVING L.O.C. IN ALAMIN DOL.


IF LOSSES IS ENCOUNTERED, PROCEED AS FOLLOWING:-
A. SWEEP HOLE WITH HI-VIS PILLS LOADED WITH LCM WHILE DRLG SINGLE BY SINGLE ( DON`T DRILL
THE NEXT SINGLE UNLESS THE FIRST ONE IS CURED )
B. PREPARE IN LOCATION L.C.M (F&M&C) TO BE READY FOR USE ( 40 -60 LB/BBL )
C. PUMP LCM AFTER OPEN PBL SUB IN CASE OF USED SAME.
D. IF LOSSES NOT CURED OR TOLERATED, A CEMENT PLUG LOADED W/ FIBER OR HYDRO PLUG WILL
BE RECOMMENDED (CONSULT CAIRO OFFICE FOR CONFIRMATION AND SLURRY DETAILS).
E. IF LOSSES NOT CURED OR TOLERATED, AFTER CEMENT PLUG (CONSULT CAIRO OFFICE FOR RIH W/
9 5/8” CSG.).

9. AT CSG. POINT, CIRCULATE ONE BTM UP (HOLE CLEAN )AND MAKE SHORT TRIP TO CHECK
FOR ANY TIGHT SPOT. RIH TO BOTTOM, SWEEP AND CIRCULATE ONE BTM UP (HOLE CLEAN).
SPOT 50 BBL HI-VIS PILL . COOH FOR LOGGING & CASING WITH SLM.

12 ¼’’ LOGGING PROGRAM (OPTIONAL)


10. R/U LOGGING UNIT AND RUN OPEN HOLE LOGS AS PER THE FOLLOWING PROGRAM. THEN
R/D LOGGING UNIT.
LOGS COMMENT

DLL,MLL,CAL , SP , G.R TD-SURF. CSG, (GR-SURF.)

MSFL TD - 250' ABOVE TOP BAH

DENSITY, NEUTRON TD -100' ABOVE AR-E


TUT-126 (DEVELOPMENT/VERTICAL) 14
FORMATION PRESSURE OVER SELECTED INT.

 TEMPERATURE DATA REQUIREMENTS FOR ALL LOGS :


 TIME SINCE LAST CIRCULATION STOPPED.
 TIME SURVEY OFF BOTTOM.
 MAX. RECORDED B.H.T. USING THREE THERMOMETERS.
 A CONDITION TRIP IS RECOMMENDED IF ANY HOLE PROBLEM IS ARAISED WHILE LOGGING. ALSO
BEFORE RUNNING RFT LOG (CONTACT CAIRO OFFICE FOR CONFIRMATION ).
 SEND IMMEDIATE COPIES OF THE OPEN HOLE LOGS TO CAIRO OFFICE.
 DOUBLE CHECK WITH CAIRO DRILLILNG OFFICE & EXPLORATION FOR POSSIIBLE 12.25” HOLE
LOGGING CANCELLATION

11. RIH FOR CONDITIONING TRIP TO BOTTOM AND CIRCULATE TO CONDITION MUD OF THE HOLE.
& SPOT HI-VIS PILL ON BTM BASED ON HOLE CONDITION.

NOTES:
 REPORT ANY TIGHT SPOTS DEPTH IF ENCOUNTERED DURING THE COND. TRIP.
 REDUCE THE NUMBER OF D/C'S IN CONDITION TRIP (SHORT BHA)

12. COOH FOR CASING TO SURFACE L/D BHA AND 12 1/4” BIT.

13. RETRIEVE THE WEAR BUSHING CHECK SAME AND CHANGE TOP PIPE RAM TO 9 5/8”.
FUNCTION TEST PIPE RAMS & PRESSURE TEST BONNET SEALS TO 5000 PSI.

 REPORT THE CONDITION & THE ID OF THE WEAR BUSHING

9 5/8” INERMEDIATE CASING


R/U CSG. EQUIPMENT AND RUN 9 5/8” PRODUCTION CASING (43.5 PPF, N-80, BTC) AS PER CSG.
PROGRAM.
A- CASING DESIGN
DEPTH HOLE CSG. CSG. GRADE CONN. COLLAPSE BUSRST BODY $/FT
(FT) SIZE SIZE PPF (PSI) (PSI) YEILD
(LB)
0’ – 8,170’ 12 ¼” 9 5/8” 43.5 N-80 BTC 3810 6330 1005000 19.34

B- CASING ACCESSORIES AND PLACEMENT


CASING ACCESSORIES QTY ACCESSORIES PLACEMENT

1- FLOAT SHOE (SINGLE VLV) 1 CASING END.


2- FLOAT COLLAR (SINGLE VLV) 1 2 JOINTS ABOVE THE FLOAT SHOE.
3- CENTK CENTRALIZERS -AS PER CENTRALIZER PROGRAMS
4- STOP COLLAR WITH NAILS ONE ABOVE & BELOW EACH CENTRALIZER

C- MISCELLANEOUS:-
HAVE IN LOCATION 9 5/8” BTC CIRCULATING HEAD, SPIDER ELEVATOR AND FILL-UP TOOL.
TUT-126 (DEVELOPMENT/VERTICAL) 15
 CHECK FLOAT EQUIPMENT .
 CENTRALIZE CASING AS PER PROGRAM.

D- RUNNING PROCEDURE:-
 CLEAN ALL 9 5/8” CASING JOINTS THREADS AND DRIFT 43.5 PPF CASINGS WITH 8.599” API RABBITS
RESPECTIVELY.
 MAKE UP AND THREAD LOCK THE FLOAT SHOE AND THE FLOAT COLLAR TO THE CASING ON THE
PIPE RACK & CHECK SAME BEFORE RIH.
 ACCORDING TO SURGE AND SWAB RUNS, MAX TRIP –IN&OUT SPEED IS 30 STD/HR.
 MONITOR LOSSES WHILE RIH WITH CASING & REPORT SAME.
 TORQUE UP THE CASING CONNECTIONS TO THE TRIANGULAR MARK & REPORT TRQ. VALUE IN DMR.
 THREAD LOCK THE FIRST TWO JOINTS AND THE CONNECTION ABOVE THE FLOAT COLLAR (USING
CASING DOPE WITH FRICTION FACTOR 1 ON THE REMAINING JOINTS).
 FILL CASING WHILE RIH.
 SPACE OUT THE CASING TO HAVE THE SHOE ONE FT OFF T.D. WHILE NO CASING COLLAR AGAINST
THE CASING FINAL CUT POINT.
 SWITCH TO 350 TON SPIDER ELEVATOR AND SLIPS AND FILLUP TOOL PRIOR CSG ENTERING THE
OPEN HOLE.
 WASH DOWN LAST 3 JT’s AND CIRCULATE TILL SHAKER CLEAN (AT LEAST 1.5 CSG CAPACITY).

9 5/8” CSG PRELIMINARY CEMENT PROGRAM

 9 5/8” INTERMEDIATE CSG CEMENT (9,500’ – 5,000’ EXPECTED T.O.C.) ONE STAGE
 REVISED CMT PROG. / LAB TEST WILL BE ISSUED LATER BASED ON THE
INTERESTED INTERVALS AND THE STATIC DOWN HOLE TEMPERATURE.
PROCEDURE:
a) R/U CEMENT HEAD (LOADED WITH TOP & BOTTOM WIPER PLUGS) AND LINES. TEST SAME TO + 5000 PSI
AND CIRCULATE MINIMUM TWO HOLE VOLUMES.

 COMPANY MAN TO VERIFY PLUGS LOADED IN CEMENT HEAD PROPERLY.


 RECIPROCATE CASING WHILE CIRCULATION (3-5 FT/STROKE).
 CONFIRM NORMAL CIRC. IS ESTABLISHED PRIOR TO CEMENTING.
 MONITOR WELL FOR LOSSES WHILE CIRC. AND REPORT SAME.
 AT THE END OF CIRC, CIRC. FOR 5 MIN’S W/ LOW GPM +/- 2 BPM & RECORD CIRC. PRESS. IN DDR.

b) PUMP THE PRE-FLUSH W/ 8 BPM AND RELEASE THE BOTTOM PLUG. MIX AND PUMP THE LEAD SLURRY
W/ 5-7 BPM AND TAIL SLURRY W/ 4-5 BPM.

 RECIPROCATE CASING WHILE MIX AND PUMP THE CEMENT SLURRY.


 MONITOR WELL FOR LOSSES WHILE MIX AND PUMP CEMENT SLURRY. AND REPORT SAME.

c) RELEASE THE TOP PLUG AND DISPLACE THE SLURRY AT +/- 8 BPM. SLOW DOWN TO + 2 BPM FOR THE
LAST +/- 15 BBL’S PRIOR TO BUMPING THE PLUG. BUMP THE PLUG GRADUALLY WITH +/- 1000 PSI OVER
THE FINAL DISPLACEMENT PRESSURE FOR 10 MIN’S (MAX PRESSURES: 2500 PSI).

 USE ISOLATE TANK FOR THE DISPLACEMENT MUD VOLUME TO AVOID OVER DISPLACEMENT.
 RECIPROCATE CASING WHILE ALL CEMENTING JOB (3-5 FT/STROKE).
 IF SLACK OFF WT INCREASE WHILE RECIPROCATE, SET CSG (1’-3’) OFF BTM & LEAVE IT THERE
WHILE COMPLETE CMT JOB.
TUT-126 (DEVELOPMENT/VERTICAL) 16
 MONITOR & CALCULATE LOSSES WHILE CIRCULATION, PUMPING CEMENT, DISPLACMENT, ALSO
WHEN CEMENT START TO BE IN ANNULUS AND REPORT ANY LOSSES IF OBSERVED.
 CALCULATE DISPLACEMENT VOLUME AT WHICH THE SLURRY STARTS TO EXIT TO THE HOLE & AT
THIS POINT COUNT LOSSES STARTING FROM THIS STAGE SEPARATELY & REPORT SAME IN D.M.R.
 WHILE CIRCULATION BEFORE CMT JOB, AT LAST CIRCULATION REDUCE THE RATE TO 2 BPM &
RECORD CIRCULATION PUMPING PRESSURE TO COMPARE WITH THE F.D.P. AT CMT JOB.
 FROM THE F.D.PRESS. & THE CALCULATED LOSSES , ESTIMATE THE EXPECTED T.O.CMT & REPORT
SAME IN THE DMR.
 IF PLUG DOSE NOT BUMP AFTER THE CALCULATED DISPLACEMENT VOLUME, CONTINUE TO
DISPLACE, BUT DO NOT EXCEED ONE CSG JOINT CAPACITY.

d) BLEED OFF PRESSURE GRADUALLY TO CHECK THE FLOAT EQUIPMENT.


 IF THE FLOAT EQUIPMENT DOES NOT HOLD WAIT ON CEMENT UNDER THE FINAL DISPLACEMENT
PRESSURE, TILL THE CEMENT HAS INITIAL SET AND RECHECK FOR ANY BACK FLOW.
MISCELLANEOUS:
 CALCULATE CMT VOLUME ACCORDING TO CALIPER LOG PLUS 15% OVER CAL. LOG.
 SEND DRY CEMENT SAMPLE AND DRILL WATER FOR SLURRY DESIGN AND A REVISED CEMENT
SLURRY LAB TEST WILL BE SENT LATER IF NEEDED.

WELL HEAD PROGRAM


1. HANG BOP STACK AND SET 12” X 9 5/8” “CIW” TYPE “S” CASING HANGER IN PLACE. LAND
CASING WITH THE EXISTING HOOK LOAD.
 REPORT THE SET WEIGHT ON THE CASING SLIPS IN THE DAILY DRILLING REPORT.
 MAX. HANGING CAPACITY FOR CASING HANGER +/- 700,000 LB’S.
 SEND CASING SLIPS SETTING PHOTO TO CAIRO OFFICE.

2. CUT 9 5/8” CASING USING COLD CUTTER TECH. AND L/D CUT OFF JOINT.
 THE CUT SHOULD BE 6.5’’ ABOVE THE TOP OF CASING HEAD SPOOL (CHECK ACTUAL LENGTH OF
CUT OF LENGTH ON RIG SITE).
 POLISH THE CASING OUTSIDE SURFACE TO AVOID DAMAGING THE C.H.S. BUSHING.
 CHECK C.H SPOOL VISIUALLY WHEN YOU RECEIVE IT .

3. N/U 13 5/8”-5000 PSI X 11”- 10,000 PSI “CIW” C.H.S. WITH TWO 2 1/16”-5000 PSI “CIW” WING
VALVES. ENERGIZE SECONDARY SEAL AND TEST SAME TO +/- 3000 PSI AS PER WELL HEAD
PROGRAM.
TEST PROCEDURE:
A) AFTER N/U THE C.H.S., ENERGIZE THE BUSHING SEAL WITH PLASTIC STICKS.
B) SCREW THE HYDRAULIC TEST PUMP INTO ½” TEST PORT.
C) APPLY +/- 3000 PSI TO THE TEST CAVITY USING HYDRAULIC OIL (DO NOT EXCEED 80%
OF 9 5/8” [43.5 PPF] CASING RATING COLLAPSE PRESSURE). HOLD PRESSURE FOR 15
MIN’S.

 ENSURE CSG IS FULL TO OBSERVE LEAK IF FOUND ANY.


 KEEP THE CASING HEAD HOUSING WING VALVE OPEN WHILE TESTING.
IF PRESSURE DOES NOT HOLD:-

TUT-126 (DEVELOPMENT/VERTICAL) 17
 CHECK AROUND THE BOTTOM FLANGE FOR POSSIBLE RING GASKET LEAKAGE
 CHECK THE CASING HEAD WING VALVE FOR POSSIBLE CASING HANGER SEAL LEAKAGE.
 CHECK ALONG THE TOP OF THE CASING STUB INSIDE THE C.H.S. FOR POSSIBLE BUSHING SEAL
LEAKAGE.
D) AFTER TESTING, BLEED-OFF PRESSURE TO ZERO AND DRAIN THE TEST CAVITY.
E) PLUG THE TEST PORT WITH ½” PLUG.

4. N/U 10,000 PSI X 13 5/8” SHAFFER BOP STACK WITH REQUIRED D.S.A, BELL NIPPLE, FLOW
LINE, KILL LINE, CHOKE LINES & CHOKE MANIFOLD.

5. RUN AND SET 11” NOMINAL “CIW” TEST PLUG ( FOR TYPE “S” C.H.) IN PLACE.

RAMS 500/5000 PSI


CHOKE/KILL LINES & VALVES 500/5000 PSI
HYDRIL 250/2500 PSI
CHOKE LINES & CHOKE MANIFOLD 500/5000 PSI

6. TEST BOP STACK AS FOLLOWS:


 P/T TEST PUMP TO 500/5500 PSI BEFOR START TESTING BOP’S.
 CHECK PRE-CHARGE PRESS. FOR EVERY N2 BOTTEL & MENTION IN DMR..
 ENSURE CSG IS FULL TO OBSERVE LEAK IF FOUND ANY.
 OPEN CASING HEAD WING VALVE WHILE TESTING BOP STACK TO MONITOR FOR TEST PLUG
LEAKAGE.
 TEST ALL CHOCK MANIFOLD VALVES( UP-STREAM & DOWN STREAM )
 TEST INSIDE BOPS TOOL TO + 500/ 5000 PSI IN CASE OF NEED.

7. PULL THE TEST PLUG. INSTALL 11” NOMINAL “CIW” WEAR BUSHING (FOR TYPE “S” C.H.)
 MENTION THE ID & CONDITION OF THE WEAR BUSHING IN THE D.M.R.

DRLG 8 ½” HOLE
M/U 8 1/2" PDC BIT WITH PACKED W/MTR & TWO R.REAMERS BHA AS FOLLOWS:

8 1/2" BIT (PDC) + 6 3/4” MOTOR(ZERO B.H) + 8 1/2” ROLLER REAMER + 6 3/4'' F.SUB
+ 6 3/4” MWD + 8 1/2” ROLLER REAMER + 15 X 6 1/2” D/C + 6 1/2” DRILLING JAR
+ 2 X 6 1/2” D/C + 21 X 5” HWDP.
AIR WEIGHT BELOW JAR = 53,000 LB’S
BUOYED WEIGHT BELOW JAR = 45,000 LB’S (IN 10.6 PPG MUD)
TOTAL BHA AIR WEIGHT = 88,000 LB’S
TOTAL BHA BUOYED WEIGHT = 77,000 LB’S (IN 10.6 PPG MUD)
 RE-CHECK UPDATED INSPECTION REPORT FOR ALL DRILLING STRING BEFORE M/U.
 SEND COPY FOR ALL BHA PLAN TO RIH BEFORE USE IT WITH ENOUGH TIME TO CAIRO OFFICE.
 USE 6 ½” FULL HYD JAR.
 THE SAFETY CLAMP MUST NOT BE REMOVED UNTIL THE JAR HAS BEEN MADE UP IN THE
DRILLSTRING.
 THE SAFETY CLAMP MUST BE INSTALLED ONTO THE JAR WHEN THE JAR IS AT SURFACE AND PRIOR
TO THE JAR BEING DISCONNECTED FROM THE STRING AND RACKED IN THE DERRICK.
 USE A LIFT SUB TO PICK UP THE HDJ AND A THREAD PROTECTOR.
TUT-126 (DEVELOPMENT/VERTICAL) 18
 DON’T EXCEED 45 K-LB W.O.B.
 USE FLOAT VALVE.
 RE-CHECK RIG ALIGNMENT TO ENSURE D/P’S IS CENTERED OVER WELL HEAD
 SHALLOW TEST ALL DIRECTION & SURVEY TOOLS ON SURFACE & REPORT SAME
 CONSULT W/ CAIRO OFFICE THE SIZE, POSITION & TYPE OF STRG. STB. & ROLLER REAMERS IN THE
NEXT RUNS BEFORE M/U.
 IN CASE OF USE PBL SUB, FUNCTION TEST SAME ON SURFACE & REPORT ACTIVATING &
DEACTIVATING PRESSURES IN D.D.R
1. RIH AND TAG THE TOP OF CEMENT ( REPORT SAME IN THE DAILY DRILLING REPORT).
DOUBLE CHECK ALLIGNMENT OF RIG WITH WELL BORE AND WITH D/P IN HOLE.
2. BEFORE 10 FT OF THE FLOAT COLLAR PRESSURE TEST CASING 2000 PSI.
3. DRILL- OUT CEMENT, THE FLOAT SHOE, AND +/- 10 FT. OF NEW HOLE. CIRCULATE AND
COND. MUD WT. IN = MUD WT. OUT.
 CONTROL DRLG PAREMETER WHILE DRLG W.O.B. (10-15 K-LB) AND R.P.M. (10-20 + MTR).
 CIRCULATE TILL MUD IN EQUAL MUD OUT & CONDITION THE HOLE.
 PLOT PRESSURE VS PUMPED BARRELS AS BASE LINE GRAPH.

4. PERFORM THE SHOE P.I.TEST WITH 11.5 PPG ( EMW )(OPTIONAL DEPEND ON CMT
HARDNESS).
 IN OFFSET WELL TUT-119 PERFORMED P.I.TEST W/ 11.5 PPG E.M.WT
 P/T SURFACE LINES BEFORE CONDUCT P.I.T
 USE CMT UNIT TO CONDUCT THE P.I.T
 WHILE PERFORMING P.I.T KEEP BIT INSIDE CSG SHOE.
 PLOT PRESSURE VS THE PUMPED BARRELS TO COMPARE P.I.T PLOT WITH THE CSG TEST BASE
LINE PLOT.
 INFORM CAIRO OFFICE IMMEDIATEY IF THE LEAK-OFF OCCURED BELOW 11.5 PPG EMW FOR
POSSIBLE CEMENT SQUEEZE JOBS.
 COMPLETE THE P.I.T. FORM AND SEND SAME TO CAIRO OFFICE.

 DRILL 8 ½” VERTICAL HOLE TO 13,000’ (+/- 493 FT INTO YAKOUT FM.) USING KCL POLY MUD (
5 % KCL) AS PER MUD PROGRAM.

 CONTROL ONLY RPM WHILE DRLG & TILL MOTOR/ROLLER REAMERS PASS BELOW CSG SHOE. THEN
DRLG WITH FULL PARAMETERS GPM 500-550 ,W.O.B. (35-40 K-LB) AND R.P.M. (60-70 + MTR).
 SURGE AND SWAB RUNS WILL BE ISSUED LATER
 TAKE MWD SURVEY EVERY 3 STD’S, IF FOUND SEVERE CHANGE IN INCLINATION OR VERTICAL
SECTION, CONSULT CAIRO OFFICE FOR POSSIBLE DECREASE RECORDING FREQUENCY.
 TARGET TOLERANCE IS 50 m. RADIUS.
 ACCORDING TO ROP, PLAN TO WASH UP, REAM DOWN ONE STD IN CASE OF HIGH ROP & WASH UP &
REAM DOWN ONE JT IN CASE OF SLOW ROP
 IF ROP HIGHER THAN 100 FT/HR: WASH UP/REAM DOWN 1 STD
 IF ROP 100-40 FT/HR: WASH UP/REAM DOWN 1 JT
 IF ROP LESS THAN 40 FT/HR: CHECK P/U 5-10 FT
 SURGE AND SWAB RUNS WILL BE ISSUED LATER
 ARRANGE TO ENTER U.SAFA FM . W/MIN.MUD WT. +/-10.6 PPG WHILE DRLG.
 INCASE OF HAVING HUGE CAVED SHALE, SWEEP THE HOLE 1ST & CONSULT CAIRO OFFICE BEFORE
INCREASING M.WT, IF NORMAL AMOUNT OF CAVED SHALE CONT’D DRLG.
TUT-126 (DEVELOPMENT/VERTICAL) 19
 INCASE OF DOWNHOLE VIBRATION, OPTIMIZE DRILLING PARAMETERS TO ELIMINATE VIBRATION &
REPORT SAME IN D.D.R IF ANY
 REPORT ANY TIGHT SPOT DEPTH IF ENCOUNTERED DURING THE WIPER TRIP.
 ROTATE STRG WHILE CONNECTIONS DUE TO HIGH DEPLETION IN ALL 8 ½’’ SECTION AND
RECEPROCATE D/P WHILE CIRC. AND COND. TO ENHANCE HOLE CLEANING.
 HAVE ON LOCATION DIFFIRENT SIZES OF STABILIZERS TO BE ABLE TO SELECT WHAT WE NEED.
 IF PUMP OUT OF HOLE, USE SAME GPM'S AS WHILE DRILLING & CIRC. HOLE CLEANING BEFORE
SWITCHING TO POOH
 CHECK WEAR BUSHING EVERY 21 DAYS WITH B.O.P TEST.

IF LOSSES IS ENCOUNTERED, PROCEED AS FOLLOWING:-


 SWEEP HOLE WITH HI-VIS PILLS LOADED WITH 40 PPB (FINE & MEDIUM) LCM WHILE DRILLING
SINGLE BY SINGLE (DON'T DRILL THE NEXT SINGLE UNLESS THE FIRST ONE IS CURED)
 CHECK WITH DIRECTIONAL CREW FOR THE TYPE, SIZE & CONCENTRATION OF LCM MATERIAL
PUMPED THROUGH DIRECTIONAL TOOLS
 OPEN PBL SUB ,SPOT (80-100 PPB) LCM PILL ON BTM, POOH 10-15 STD's FOR PILL SOAKING THEN
CIRCULATE AND CHECK DYNAMIC LOSSES.
 IF LOSSES NOT CURED OR TOLERATED, CONSULT CAIRO OFFICE BEFORE POOH TO SURFACE TO
L/D DIRECTIONAL TOOL.
 BE PREPARED W/DIA SEAL PLUG CHEMICALS ON LOCATION
 PERFORM KICK DRILL EVERY SHIFT TO ENSURE CREW ABILITY TO DETECT & SECURE THE WELL
INCASE REQUIRED
 MONITOR BACK GROUND GASES, CONNECTION GASES & TRIP GASES & CONFIRM WITH CAIRO
OFFICE BEFORE INCREASE M.WT
 ENSURE STATUS OF WELL CONTROL EQUIPMENT BEFORE DRLG THIS SECTION
 CONTROL TRIP OUT SPEED TO AVOID SWABBING KICK

FOR ANY TRIPS FOR BIT CHANGE OR WIPER TRIPS


 CIRCULATE HOLE CLEAN BEFORE POOH.
 ROTATE AND RECIPROCATE STRING WHILE CIRCULATION TO ENHANCE HOLE CLEANING.
 FLOW CHECK WHILE TRIPPING OUT IS REQUIRED PRIOR TO TRIPPING OUT OF HOLE & AT CSG SHOE
& PRIOR TO L/D BHA.
 BEFORE POOH FOR BIT CHANGE CIRCULATE ONE BTM UP,(TILL HOLE CLEAN), PUMP OUT OF HOLE
ONE STAND THEN CONT ON ELEVATORS
 REPORT ANY TIGHT SPOTS DEPTH AND LOSSES ENCOUNTERED DURING THE WIPER TRIP.
 FOR ANY PUMP OUT, USE SAME GPM'S AS WHILE DRILLING WHILE PUMP OUT, MONITOR P.
PRESSURE TO AVOID FM. BREAKDOWN IN CASE OF BACK-OFF
 DIRECTIONAL TOOLS SHOULD BE CHECKED AFTER EACH BIT RUN AND BACK UP TOOLS SHOULD
BE AVAILABLE ON LOCATION.
 AVOID SLACK OFF MORE THAN 10 KLB's WHILE RIH BACK, WASH & REAM DOWN TILL FREE
 PRECAUTIONARY WASH & REAM LAST 3 STD’s TO BOTTOM WHILE RIH.

5. AT TD. POINT CIRCULATE TO CONDITION ONE BTM UP AND MAKE SHORT TRIP TO CHECK
FOR ANY TIGHT SPOT. RIH TO BOTTOM SWEEP AND CIRCULATE ONE BTM UP. SPOT 50 BBL
HI-VIS PILL (IF NEEDED) COOH FOR LOGGING T/ SURFACE WITH SLM.
 REPORT ANY TIGHT SPOT DEPTH IF ENCOUNTERED DURING THE WIPER TRIP.
 ROTATE AND RECEPROCATE D/P WHILE CIRC. AND COND. TO ENHANCE HOLE CLEANING.

6. R/U LOGGING UNIT AND RUN OPEN HOLE LOGS AS PER THE LOGGING PROGRAM. R/D
LOGGING UNIT.

TUT-126 (DEVELOPMENT/VERTICAL) 20
 A CONDITION TRIP IS RECOMMENDED IF ANY HOLE PROBLEM IS ARAISED WHILE LOGGING. ALSO
BEFORE RUNNING RFT LOG (CONTACT CAIRO OFFICE FOR CONFIRMATION ).
 SEND IMMEDIATE COPIES OF THE OPEN HOLE LOGS TO CAIRO OFFICE.
 LWD OPTION IF FAILED TO RECORD WIRE LINE O.H.LOGS DUE TO HOLE CONDITION

8 ½’’ LOGGING PROGRAM


1. R/U LOGGING UNIT AND RUN OPEN HOLE LOGS AS PER THE FOLLOWING PROGRAM.THEN
R/D LOGGING UNIT.
LOGS COMMENT

(TD- 9 5/8’’ CSG)

DLL,MLL,CAL , SP , G.R
(GR 200' INSIDE CSG OR TO SURFACE)

MSFL TD-9 5/8''. CSG


DENSITY , NEUTRON TD - 9 5/8''. CSG

FM PRESS. OVER SELECTED INT.

TEMPERATURE DATA REQUIREMENTS FOR ALL LOGS :


 TIME SINCE LAST CIRCULATION STOPPED.
 TIME SURVEY OFF BOTTOM.
 MAX. RECORDED B.H.T. USING THREE THERMOMETERS.

 A CONDITION TRIP IS RECOMMENDED IF ANY HOLE PROBLEM IS ARAISED WHILE LOGGING. ALSO
BEFORE RUNNING RFT LOG (CONTACT CAIRO OFFICE FOR CONFIRMATION ).
 SEND IMMEDIATE COPIES OF THE OPEN HOLE LOGS TO CAIRO OFFICE.

RUNNING AND CEMENTING PROGRAM


OF 7” LINER HANGER WITH TOP PKR ISOLATION

PROCEDURES:-
1. A) CHANGE TOP PIPE RAMS TO 7”, FUNCTION TEST THE BOP'S & BONNET SEAL TEST FOR 7" RAM.
B) R/U CASING EQUIPMENT, M/U AND RIH WITH 7” (29 PPF, N-80, BTC) LINER AS FOLLOWING.
DEPTH HOLE CSG. CSG. GRADE CONN. COLLAPSE BUSRST BODY $/FT
(FT) SIZE SIZE PPF (PSI) (PSI) YEILD (LB)
9,300’ – 13,000’ 8 1/2” 7” 29 N-80 BTC 7020 8160 676000 12.76

 7” FLOAT SHOE W/ DUAL VALVE & DOWN JETS.


 1 X 7” (29 PPF, N-80, BTC) CASING JT.
 7” FLOAT COLLAR (SINGLE VALVE).
 1 X 7” (29 PPF, N-80, BTC) CASING JT.
 7” LANDING COLLAR.
 7” (29 PPF, N-80, BTC) CASING JT’S TO HAVE THE REQUIRED LENGTH (ACCORDING TO CSG TALLY).

TUT-126 (DEVELOPMENT/VERTICAL) 21
 7” X 9 5/8” HYDRAULIC SET ROTATING SOLID BODY LINER HANGER WITH 7” LINER TOP ISOLATION
PKR AS ONE SET.
 7” SETTING ADAPTER WITH RETRIEVABLE CEMENT BUSHING (RCB) & 10 FT TIE BACK RECEPTACLE.
 MODEL HYDRAULIC RELEASE SETTING TOOL WITH TAMPING DOG AND TAILED WITH LINER WIPER
PLUG.
 5” D/P’S GRADE “G & S” (IF NEEDED) TO SURFACE.
 CEMENT MANIFOLD LOADED WITH DART PLUG.

IMPORTANT NOTES TO BE CONSIDERED:-


 CONSIDER REAMER SHOE IN CASE IF NEEDED
 SEND THE LINER SKH., CSG. TALLY, DRILL PIPE TALLY & CMT. CALCULATION TO CAIRO OFFICE BEFORE
PERFORMING THE JOB.
 BE SURE THAT X/O (7" BTC P X 5" IF B) IS AVAILABLE ON RIG FLOOR FOR USING IN STRIPPING OPERATION IN
CASE OF KICK
 IT IS RECOMMENDED TO HAVE SAFETY MEETING WITH ALL INVOLVED PERSONNEL PERIOR LINER RUNNING.
 M/U THE CEMENT MANIFOLD TO 5” D/P SINGLE L/D SAME, THIS IS FOR FACILATE ACCESS ONCE LINER AT
THE DESIRED DEPTH & PRESSURE TEST SAME TO 4,000 PSI AGAINST TIW VALVE.
 CLEAN 7” CSG. THREAD AND DRIFT SAME WITH 6.059” API RABBIT.
 DRIFT THE LINER HANGER AND THE TBR WITH 6.184” API RABBIT.
 SPACE-OUT BEFORE RIH TO HAVE THE CSG SHOE AT 12,995 FT (± 5 FT OFF BTM) AND LINER HGR INCLUDE
ISOLATION TIE-BACK PKR’S WITH FINAL T.O.L @ ±8,000 FT-ORKB (170 FT OVER LAP).
 CHECK 9 5/8” CSG. TALLY TO AVOID SETTING LINER HANGER OR PKR. AGAINST CSG. COLLAR.
 ALL THE RUNNING ASPECTS TO BE SUPERVISED BY LINER ENG.
 TORQUE-UP CASING TO THE TRIANGULAR MARK & REPORT CSG M/U TORQUE IN D.M.R.
 CENTRALIZE CSG. WHILE RIH AS FOLLOWING:-
ITEM PLACEMENT

1) CENTEK CENRALIZER (TO BE PLACED ON  70 % STAND OFF


THE MIDDLE OF THE CSG. JT’S)

2) STOP COLLARS WITH NAILS  ONE ABOVE AND BELOW EACH CENTRALIZER.

 CHECK THE FLOAT COLLAR AND SHOE WHILE RIH.


 CHECK LINER HANGER BEFORE PICK UP. CHECK ALL LINER HANGER PARTS AND BE SURE THE HANGER SLIPS
AND ARMS DO NOT GET DAMAGED WHEN PICKING UP.
 FILL UP LINER TBR WITH VIS-POLYMER.
 FILL THE CSG. AND THE 5” D/P’S WHILE RIH.
 MONITOR WELL FOR LOSSES WHILE RIH (REPORT SAME).
 GREASE THE WIPER PLUG BEFORE INSERT SAME INTO THE 7” LINER.
 DRIFT 5” D/P’S WITH API RABBIT WHILE RIH AND CONFIRM RETRIEVE THE RABBIT.
 INSTALL HOLE COVER PERIOR TO REMOVING JUNK COVER & FILLING UP TIE BACK EXTENSION WITH HI-VIS.
POLYMER.

TUT-126 (DEVELOPMENT/VERTICAL) 22
 BREAK CIRCULATION AT THE 9 5/8” CSG. SHOE ONE AND HALF CASING VOLUME, RECORD P/U AND S.O.WT AND
REPORT SAME IN D.D.R.

8. M/U FLOAT SHOE W/ DUAL VALVE & DOWN JETS TO THE FIRST CASING JOINT, THREAD LOCK AND FILL UP THIS
JOINT, TEST THE FLOAT SHOE; MAKE SURE IT’S FUNCTIONING PROPERLY.

9. M/U FLOAT COLLAR (SINGLE VALVE) TO CASING JOINT, THREAD LOCK AND FILL UP THIS JOINT, TEST THE FLOAT
COLLAR; MAKE SURE IT’S FUNCTIONING PROPERLY.

NOTE:
 THE SHOE & LINER SHOULD BE FILLED W/ CLEAN MUD.
10. THREADS LOCK THE SHOE TRACK TO THE PIN OF THE LANDING COLLAR.

11. CONTINUE RIH W/ 7” LINER CASING JOINTS WHILE FILLING UP EVERY 3-5 JOINTS.

12. P/U & M/U THE 7” HYD. LINER HANGER W/ 7” LINER TOP ISOLATION PKR AS ONE SET & CIRCULATE 1.5 TIMES
THE LINER CAPACITY MAX. ALLOWABLE PRESSURE MUST NOT EXCEED 900 PSI AT SURFACE, TO MAKE SURE
THAT THE CEMENTING PACK OFF BUSHING IS NOT LEAKING.
NOTES:
 P/U THE LINER HANGER ASSY. VIA USING LIFTING BELT, SECURED BY SAFETY CLAMP).
 SET SLIPS ON THE LAST JOINT OF LINER. CAREFULLY, PICK UP THE LINER ASSEMBLY. INSTALL THE LINER
WIPER PLUG ONTO THE SLICK JOINT WHEN THE LINER HANGER ASSEMBLY IS HANGING ON THE
ELEVATORS IN THE DERRICK, IF THIS HAS NOT BEEN PREVIOUSLY DONE. APPLY DOPE OR GREASE ON THE
WIPER PLUG FINS AND SWAB CUPS RUBBER PRIOR TO INSERTING THEM INTO THE LINER. MAKE UP THE
LINER HANGER ASSEMBLY ONTO THE LAST JOINT OF LINER. APPLY THE CORRECT MAKE-UP TORQUE FOR
THE SPECIFIC CONNECTION.
 ENSURE DURING THE MAKEUP OF LINER HANGER ASSEMBLY CONNECTION THAT THE HANDLING SUB IS
FREE TO ROTATE IN THE ELEVATOR AND THAT THE SETTING TOOL ROTATES WITH LINER HANGER
ASSEMBLY.
 PICK UP LINER HANGER ASSEMBLY THREE TO FOUR FEET WITHOUT REMOVING SLIPS, MAKE SURE NOT
TO TAKE OUT THE SLIPS FROM ROTARY TILL IT CONFIRMED THAT RUNNING TOOL IS FULLY ENGAGED AND
THE STRING IS HANGED ON RUNNING TOOL.
 PULL CASING SLIPS OUT AND LOWER THE LINER HANGER ASSEMBLY UNTIL THE JUNK BONNET (JBT) IS AT
WAIST LEVEL. DO NOT PLACE SLIPS ON TBR.
 MAX. ALLOWABLE PRESSURE MUST NOT EXCEED 900 PSI AT SURFACE WHILE CIRCULATION TO
AVOID SETTING THE HYD. LINER.

13. RECORD THE P/U WT & THE S/O WT AND REPORT SAME IN D.M.R.

14. CONT. RIH W/ 7” HYD. LINER HANGER W/ 7” LINER TOP ISOLATION PKR AS ONE SET ON DRIFTED 5” DRILL PIPE
TO 9-5/8” CSG. SHOE.

15. AT 9-5/8” CASING SHOE, BREAK CIRCULATION; CHECK THE P/U WEIGHT & S/O WEIGHT.

TUT-126 (DEVELOPMENT/VERTICAL) 23
16. CONTINUE RIH 7” HYD. LINER HANGER W/ 7” LINER TOP ISOLATION PKR AS ONE SET, CSG ON 5” D/P T/ +/-
13,000 FT-MD (TD), WASH DOWN THE LAST 2 STD. TO THE TD.

NOTES:
 CHECK ROTATION BEFORE RUN IN OPEN HOLE
 MAX. ALLOWABLE PRESSURE MUST NOT EXCEED 900 PSI AT SURFACE WHILE CIRCULATION TO
AVOID SETTING THE HYD. LINER.
 WHEN REACHING THE TD CIRCULATE AT LEAST BOTTOM’S UP OR TILL THE SHAKERS ARE CLEAN TO
CONFIRM THE HOLE CLEAN, THEN P/U & M/U SMITH CEMENTING MANIFOLD
 REDUCE MUD YIELD AND PLASTIC VISCOSITY TO BE AS LOW AS POSSIBLE.
 RECIPROCATE THE CASING WHILE CIRC.
 MONITOR WELL FOR LOSSES WHILE CIRCULATION.
 SURGE AND SWAB RUNS WILL BE ISSUED LATER
 BREAK CIRC. BEFORE ENTERING OPEN HOLE & RECORD STRG. WT.
 FILL THE LINER CSG EVERY 1,000 FT WHILE RIH.
17. SPACE OUT THE DRILL PIPE TO ALLOW PROPER HANDLING OF THE CEMENT MANIFOLD, TAG BOTTOM MARK
THE PIPES, PICK UP 5 FT UP TO THE SETTING DEPTH, TO HAVE T.O.LINER @ +/- 8,000 FT LAST MOVEMENT
SHOULD BE UP NO SLACK IS REQUIRED.
18. DROP THE 1 3/4” SETTING BALL, AND CIRCULATE THE BALL DOWN TO BALL SEAT IN THE ST LANDING SUB,
PUMP BALL DOWN TO ROTATING BALL SEAT AT NO MORE THAN APPROXIMATELY 1-3 BPM OR AS
RECOMMENDED BY OPERATOR.
NOTE: DO NOT PRESSURE UP ON BALL SEAT AT THIS TIME.

19. AFTER LANDING THE BALL, PRESSURE UP TO +/- 1,600 PSI TO SET THE LINER HANGER, SLACK OFF THE LINER
WEIGHT PLUS 10,000 - 20,000 LBS FROM THE DRILL PIPE WEIGHT TO CHECK LINER SETTING.

20. BLEED THE PRESSURE, SLACK OFF ANOTHER 20,000 LBS. ON THE SETTING TOOL TO MAKE SURE THAT THE
SETTING TOOL UNDER COMPRESSION.
 IF A LOSS OF WEIGHT IS NOT INDICATED, THE LINER HANGER DID NOT SET AND THE PREVIOUS STEPS
SHOULD BE REPEATED INCREASING PRESSURE NO MORE THAN 250 PSI OVER ORIGINAL SHEAR
PRESSURE. REPEAT UNTIL HANGER IS SET. BLEED PRESSURE DOWN AFTER SETTING.
 THE SETTING TOOL IS READY FOR RELEASE ONCE THE HANGER HAS BEEN SET. THE DRILL STRING SHOULD
BE SLACKED-OFF ONTO THE SETTING. IMPORTANT: THE STHR RUNNING TOOL WILL NOT RELEASE IF
THERE IS ANY TENSION PRESENT IN THE DRILL STRING. ALSO THERE IS NO STROKE IN THE SETTING TOOL.
21. SLOWLY PRESSURE UP DRILL-PIPE TO THE PRESET SETTING TOOL SHEAR VALUE +/- 2,400 psi & HOLD FOR 1
MINUTE. BLEED PRESSURE DOWN

22. P/U NOT MORE 3 - 4 FT MAX. & CHECK THE P/U WEIGHT, (THE P/U WEIGHT SHOULD BE LESS THAN THE
WEIGHT ON BTM BY THE LINER WEIGHT).

NOTE:-
DO NOT PICK UP MORE THAN 3-4 FEET (EXCESSIVE PICK UP MAY CAUSE THE TAMPING DOG ASSEMBLY
TO COME OUT OF TBR OR CAUSE THE CEMENTING BUSHING OR PACK-OFF TO DISENGAGE.

23. SLACK OFF 15,000 LBS. ON THE SETTING TOOL & SHEAR THE BALL W/ + 3,100 PSI.

TUT-126 (DEVELOPMENT/VERTICAL) 24
24. CIRCULATE WHILE MIXING CEMENT SLURRY.

25. A) PUMP THE SPACER. MIX AND PUMP THE CEMENT SLURRY USING THE CEMENT UNIT (AS PER CEMENT LAB.
TEST).

NOTES:-
ROTATE LINER DURING CMT JOB
PUMP THE SPACER AND THE SLURRY INSIDE THE D/P WITH + 5 BPM.
CALCULATE THE CEMENT VOLUME BASED ON CALIPER HOLE PLUS 15% EXCESS.
USE THE BATCH MIXER TO PERFORM THE CEMENT JOB.
PLAN TO HAVE THE TOP OF CEMENT +/- 200 FT ABOVE THE TOP OF TIE BACK PKR.
MONITOR WELL FOR LOSSES WHILE PUMP THE CEMENT.
B) RELEASE DART PLUG BEHIND THE CEMENT SLURRY AND DISPLACE SAME WITH MUD USING THE CEMENT UNIT.
SHEAR-OUT THE WIPER PLUG.

NOTES:-
CHECK THE CMT LINES FLUSHING AFTER RELEASE THE PUMP DOWN PLUG WAS MADE INTO STRG
JUST AFTER PUMP DOWN PLUG.
CONTINUE DISPLACE THE SPACER AND THE SLURRY WITH +/- 5 BPM INSIDE THE D/P.
TO BE ABLE TO MONITOR THE WIPER PLUG SHEARING, REDUCE THE PUMPING RATE TO +/-2 BPM FOR THE
LAST 10 BBL’S PRIOR THE DART PLUG LATCH THE WIPER PLUG.
CHECK THE RATING SURFACE PRESSURE TO SHEAR THE WIPER PLUG & REPORT IN D.M.R.
START A NEW COUNT OF THE DISPLACEMENT VOLUME AFTER SHEARING THE WIPER PLUG AND THEN
INCREASE THE DISPLACEMENT RATE TO +/- 8 BPM.
MONITOR THE WELL FOR LOSSES WHILE DISPLACE THE CEMENT.

c) CONTINUE TO DISPLACE THE CEMENT SLURRY TILL BUMP THE WIPER PLUG AND TEST WITH 1000 PSI ABOVE
THE FINAL DISPLACEMENT PRESSURE FOR 10 MIN AS CSG P/T BLEED-OFF PRESSURE GRADUALLY TO CHECK
BACK FLOW.

NOTES:-
CONTINUE TO DISPLACE THE SLURRY WITH +/- 8 BPM AND TO BE ABLE TO MONITOR THE WIPER PLUG
BUMPING, REDUCE THE PUMPING RATE TO +/-2 BPM FOR THE LAST 10 BBL’S PRIOR BUMPING THE WIPER
PLUG
IF THE PLUG NOT BUMPED AFTER THE PRE-DETERMINED DISPLACEMENT VOLUME STOP PUMPING.

26. PICK UP LINER STRG TO PULL TAMPING DOG ASSEMBLY OUT OF THE TBR +/- 11 FT OR AS PER SMITH ENG.
RECOMMENDATION THEN SLACK OFF DRILL PIPE TO ACHIEVE THE MINIMUM SETTING LOAD AT THE PACKER,
OBSERVES PKR SETTING ON MARTIN DICKER AND RECORD SAME IN D.D.R.

NOTES:-
DO NOT SET THE TOP PKR IF YOU HAVE ABNORMAL OR COMPLETE LOSSE WHILE CEMENT JOB.
27. STING-OUT SLOWLY COMPLETELY JUST ABOVE T.O.L. (OBSERVE U-TUBE & MENTION IN D.M.R.)., L/D THE
CEMENT MANIFOLD.
TUT-126 (DEVELOPMENT/VERTICAL) 25
28. CIRC. REVERSE OUT FOR DRILL PIPE CLEANNING.

NOTE:-
 MONITOR PUMPING PRESSURE WHILE CLEAN OUT CMT , IF PUMPING PRESS. INDICATE
THAT CMT START TO BE THICK POOH RAPIDLY TO BE ABOVE T.O.CMT & RESUME CIRC.
REVERSE OUT
29. P/T ANNULUS SIDE T/+ 2000 PSI FOR 10 MIN.

30. RESUME POOH WITH LINER SETTING TOOL TO SURFACE.

NOTE:-
FILL HOLE EQUAL TO THE METAL DISPLACEMENT VOLUEM WHILE POOH.

WELL HEAD PROGRAM SUMMARY

A. 13 5/8”- 5000 PSI “CIW” TYPE “S” CASING HEAD WITH 2 1/16”-5000 PSI WING VALVE AND
1X2” LP BULL PLUG.

a. SPACE OUT:
SPACE OUT BEFORE RIH TO BE ABLE TO INSTALL AND WELD THE SLIP ON CASING HEAD
WITH THE TOP OF ITS FLANGE LEVELED WITH THE GROUND LEVEL.

b. TEST PROCEDURE:
TESTING PROCEDURE AND PRESSURE MAGNITUDE TO BE AS PER MIDCO
REPRESENTATIVE INSTRUCTIONS.

B. 12” X 9 5/8” “CIW” TYPE “S” CASING HANGER.

C. 13 5/8”- 5000 PSI X 11”-10,000 PSI “CIW” CSG HEAD SPOOL WITH TWO 2 1/16”-5,000 PSI
“CIW” WING VALVE.

1) SPACE OUT:
DRESS OFF 9 5/8” CASING STUB TO BE 6 1/2” ABOVE THE TOP OF THE CASING HEAD
FLANGE TO ACCEPT THE C.H.S. (CHECK ACTUAL LENGTH IN RIG SITE)

2) TEST PROCEDURE:
A) AFTER N/U THE T.H.S., ENERGIZE THE BUSHING SEAL WITH PLASTIC STICKS.
B) SCREW THE HYDRAULIC TEST PUMP INTO ½” TEST PORT.
C) APPLY +3000 PSI TO THE TEST CAVITY USING HYDRAULIC OIL (DO NOT EXCEED 80% OF 9
5/8” [43.5 PPF] CASING RATING COLLAPSE PRESSURE). HOLD PRESSURE FOR 15 MIN’S.

 KEEP THE CASING HEAD HOUSING WING VALVE OPEN WHILE TESTING.IF PRESSURE DOES NOT
HOLD:
 CHECK AROUND THE BOTTOM FLANGE FOR POSSIBLE RING GASKET LEAKAGE
 CHECK THE CASING HEAD WING VALVE FOR POSSIBLE CASING HANGER SEAL LEAKAGE.
 CHECK ALONG THE TOP OF THE CASING STUB INSIDE THE C.H.S. FOR POSSIBLE BUSHING SEAL
LEAKAGE .
TUT-126 (DEVELOPMENT/VERTICAL) 26
D. AFTER TESTING, BLEED-OFF PRESSURE TO ZERO AND DRAIN THE TEST CAVITY.

E. PLUG THE TEST PORT WITH ½” PLUG.

F. 11"-10,000 PSI "CIW" BLIND FLANGE

MUD PROGRAM

M. W. PH/ GEL
DEPTH (FT) DESC. MUD TYPE VIS PV YP W.L. VALUES
(PPG) E.S.

45 -
0 – 3,000’ CSG PT. SPUD MUD 8.5 – 9 - - - - -
55

3,000’ – 100' ABOVE 45 -


SPUD MUD 9 - 9.2 - - - - -
3,650’ A/R-C 55

100' ABOVE KCL POLY - 40 -


3,650 – 5,218’ 9.2 - 9.8 ALAP 20 - 28 3-4 9-10 8/10
A/R-G 3-5% KCL 50

+/- 100'
5,218’ – KCL POLY -
ABOVE 9.8 – 10.2 +/- 55 ALAP 22-28 3-4 9-10 8/10
7,834’ 3-5% KCL
DAHAB

7,834’ – 9 5/8” CSG. KCL POLY -


10.2-10.4 +/- 55 ALAP 22-28 3-4 9-10 8/10
9,500’ PT. 3-5% KCL

TUT-126 (DEVELOPMENT/VERTICAL) 27
+/- 100
9,500’ – KCL POLY 45 -
ABOVE 10.4-10.6 ALAP 18-22 3-4 9-10 9/11
11,400’ 5% KCL 55
U.SAFA

11,400’ – KCL POLY 45 -


TD 10.6 ALAP 18-22 3-4 9-10 9/11
13,000’ 5% KCL 55

NOTES:
 ARRANGE TO ENTER A/R-G FM. W/ MIN. MUD WT. +/- 9.8 PPG WHILE DRLG.
 ARRANGE TO ENTER DAHAB FM. W/MIN.MUD WT. +/- 10.2 PPG WHILE DRLG.
 ARRANGE TO ENTER U.SAFA FM. WITH MUD WT. +/- 10.6 PPG WHILE DRLG
 CONSULT CAIRO OFFICE TO ADD LUBRICANT TO MUD IF NEEDED.
 INCASE OF HAVING HUGE CAVED SHALE, SWEEP THE HOLE 1ST & CONSULT CAIRO OFFICE BEFORE
INCREASING M.WT, IF NORMAL AMOUNT OF CAVED SHALE CONT’D DRLG.
 DOUBLE CHECK SOLID CONTROL EQUIPMENT, SPECIALLY SHALE SHAKERS CONDITION & SCREEN
DAMAGED RAPIDLY OR NORMAL.
 INCASE OF INCREASE IN SOLID CONTENT IN THE MUD, CONSULT CAIRO OFFICE TO USE EXTRA
CENTRIFUGE.
 KEEP MUD WT. AS LOW AS POSSIBLE DUER TO THE FRACTURE RISK OF ALM/DOL & MASAJID
FORMATIONS AND ENSURE LOADING SYSTEM WITH BRIDGING MATERIALS.

HAVE AVAILABLE ON LOCATION THE FOLLOWING:

 LCM (OF DIFFERENT GRADES) SUPPLY


 ENOUGH SACKS OF BARITE FOR 2 PPG INCREASE IN MWT.
 6 DRUMS OF DETERGENT TO AID THE DISPERSION OF DIESEL.
 3 DRUMS OF OIL SOLUBLE SURFACTANT FOR USING IN CASE OF DIFFERENTIAL STUCK.

I. USE PRE HYDRATED HI-VIS SWEEP (20-40 SEC/QT > THE MUD VISCOSITY) WHILE DRILLING
17 ½” HOLE TO ENSURE HOLE CLEANING.
II. POLYMERS USED WHILE DRILLING BELOW 7000 FT SHOULD BE STABLE AT 250-400F.
III. RUN HTHP FILTRATE LOSS TEST AT 350F AND 500 PSI.
IV. MAKE SURE THAT ALL THE SOLID CONTROL EQUIPMENT IS RUN PROPERLY ALL THE TIME
WHILE DRILLING CONSIDERING THE FOLLOWING:-
 USE FEED PRESSURE OF 40 PSI TO OPERATE THE DESANDER AND MUD CLEANER.
 USE THE SMALLEST SHAKER SCREENS SIZE THAT AVAILABLE WITHOUT CAUSING SCREEN
PLUGGING.
 RUN THE CENTRIFUGE AND MUD CLEANER TO AVOID THE SOLID BUILD-UP.
 BACK FLUSHES THE CENTRIFUGE TO AVOID PLUGGING PROBLEMS.

V. MONITOR MUD WEIGHT WHILE DRILLING 12 ¼” & 8 ½” HOLE AND DILUTE THE ACTIVE
SYSTEM AS NECESSARY WITHOUT CHANGING THE RHEOLOGICAL PROPERTIES.

TUT-126 (DEVELOPMENT/VERTICAL) 28