Contoh Remaining Work

This document provides a status update on remaining civil field work in the utility area. It lists various infrastructure items and their status, including pipe racks, buildings, shelters, ponds, and pump stations. Many items are still outstanding or ongoing, with pilecaps, pedestals, structures, and finishing work remaining. Installation of equipment is also holding up related support work for items like pipe supports and trenches.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
282 views

Contoh Remaining Work

This document provides a status update on remaining civil field work in the utility area. It lists various infrastructure items and their status, including pipe racks, buildings, shelters, ponds, and pump stations. Many items are still outstanding or ongoing, with pilecaps, pedestals, structures, and finishing work remaining. Installation of equipment is also holding up related support work for items like pipe supports and trenches.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

REMAINING WORK CIVIL FIELD (UTILITY AREA)

No. ITEM PEKERJAAN Qty Status KETERANGAN


A Pipe Rack D Boiler to STG
1 Pilecap 5 Outstanding
2 Pedestal 14 Outstanding
3 Fabrication structure Finished
4 Erection Structure Outstanding
B Pipe Rack E Boiler to STG
1 Pilecap 1 Outstanding
2 Pedestal 2 Outstanding
3 Fabrication structure Finished
4 Erection Structure Outstanding
C Pipe Rack H
1 Erection Structure 2 Outstanding
D STG Building
1 Brick masonry (hebel) On going - Sisi utara ruang panel kurang ±1 m
-
Sisi selatan ruang panel belum
dikerjakan
-
Di atas pintu sisi utara belum bisa
dikerjakan
- Sisi timur sebagian harus dibongkar,
menyesuaikan drawing terbaru
2 Plastering Outstanding
3 Ceiling + Frame Outstanding
4 Finishing Floor Outstanding
5 Painting Outstanding
6 Door + Frame 4 Holded - Frame sudah terpasang sebagian
- Pintu sudah difabrikasi
- Kendala keluar-masuk equipment
7 Ventilation (kawat ayam) Outstanding
8 Platform and support STG Outstanding - Menunggu STG equipment terinstall
Pilecap cooling tower to STG - Menunggu STG equipment terinstall
9 4 Holded
pipe support
Pedestal cooling tower to STG - Menunggu STG equipment terinstall
10 8 Holded
pipe support
11 Cable Trench STG Holded - Menunggu STG equipment terinstall
Excavation underground pipe - Menunggu STG equipment terinstall
12 Holded
13
Outstanding
Excavation Atmospheric Tank
E Compressor STG Shelter
1 Brick masonry (hebel) On going
2 Plastering Outstanding
3 Painting Outstanding
4 Ventilation (kawat ayam) Outstanding
5 Install BRC Outstanding
6 Roof Outstanding
F Spray Pond Pump Shelter
1 Foundation Outstanding
2 Stucture Outstanding
G Spray pond
1 Platform On going
2 Biotray 350 On going
3 Drainase existing Holded
H Pipe Support Cooling Tower to STG
1 Pilecap 2 Outstanding
2 Pedestal 6 Outstanding
3 Fabrication structure Outstanding
4 Erection Structure Outstanding
5 Pipe Sleeper 4 Outstanding
I P807 A/B and P808 A/B Pump Shelter
1 Foundation Outstanding
2 Structure Outstanding
J P805 A/B and P806 A/B Pump Shelter
1 Foundation 6 Finished
2 Structure Outstanding
K P809 A/B Pump Shelter
1 Foundation Outstanding
2 Structure Outstanding
L P804 A/B Pump Shelter
1 Foundation Outstanding
2 Structure Outstanding
M P801 A/B Pump Shelter
1 Foundation Outstanding
2 Structure Outstanding
N P810 A/B Pump Shelter + P6 Pump
1 Foundation Outstanding
2 Structure Outstanding
3 P6 pump foundation Outstanding
O Pit Netralisasi (WTP)
1 Slab Finished
2 Wall Finished
3 Drainase from WTP area to Pit
Outstanding
Netralisasi
P DEG Shelter
1 Stucture Outstanding
Q Control Room Boiler
1 Plestering On going
2 Ceiling + Frame ?
3 Painting Outstanding
4 Finishing Floor Outstanding
5 Window Outstanding
R Compressor Boiler Shelter
1 Painting On going
S WWTP
1 Install pipe sleeper aeration
On going
tank
2 Blower existing foundation ?

4 Handrail and stairway/ladder Outstanding

3 Aeration existing walk way Outstanding


T Baggase Supply Structure
U Baggase Return Structure