Check List For AFC
Check List For AFC
HYDROTEST:
TUBE TEST
PRESSURE (Kg/cm2g) 69KG/CM2
TEST DATE 31/12/13
RETUBING OF THE BUNDLE REQUIRED IN THE NEXT OUTAGE: PARTIAL COMPLETE NII
ACTION REPORT ISSUED: NO. __________________.DATED: __________________
OBSERVATIONS
1. HEADER BOX (FRONT) :
FOUND SATISFACTORY
Condition of plug threads (internal)
FOUND SATISFACTORY
Condition of Inlet & Outlet and any other nozzles (including serrations):
FOUND SATISFACTORY
FOUND SATISFACTORY
EXTERNAL :
FOUND SATISFACTORY
Condition of Inlet & Outlet and any other nozzles (including serrations):
4. TUBE SECTION :
FOUND SATISFACTORY