ITP Elektrical Instrument
ITP Elektrical Instrument
: SP-203/PG0300/2014-SO
PEMBANGUNAN PIPA TRANSMISI GAS DARI Main Contractor : KWRK Date :
GRESIK - SEMARANG Project Owner : PERTAGAS Report No. :
Document No. : GRSM-00-QAC-PLAN-003 Page : 9 of 9
Responsibility
No DESCRIPTION INSPECTION METHOD ACCEPTENCE CRITERIA VERIVIED DOCUMENT
KWRK PMC PTG PJIT
1 Pre-Inspection Meeting Attend - Minute of Meeting
2 TRANSFORMER
2.1 Preparation
a. Location /Area Classification Visual IFC Drawing QI-E.01.01 M W R
b. Foundation as per Civil Data Visual IFC Drawing - M W R
c. Check Name plate and Rating Visual IFC Drawing QI-E.01.01 M W SW
d. Tools / Equipment Tester Calibration/Review Engineering Spec. QI-E.01.01 M W SW
2.2 Installation
a. Visual & dimensional Visual IFC Drawing QI-E.01.01 M W R
b. Seals of bushing Visual Engineering Spec. QI-E.01.01 M W R
c. Valves and pipe plugs Visual IFC Drawing QI-E.01.01 M W R
d. Cables, bells and connections Visual IFC Drawing QI-E.01.01 M W R
e. Sealing the terminal boxes Visual Engineering Spec. QI-E.01.01 M W R
f. Bolting and gaskets Visual IFC Drawing QI-E.01.01 M W R
g. Neutral connection (bolting, clamping, etc.) Visual IFC Drawing QI-E.01.01 M W R
h. Setting and Alignment Visual Engineering Spec. QI-E.01.01 M W R
i. Transformer oil level Visual Engineering Spec. QI-E.01.01 M W R
j. Equipment grounding connection Visual IFC Drawing QI-E.01.01 M W R
k. Check breathing device Visual Engineering Spec. QI-E.01.01 M W R
2.3 Testing
a. Insulation resistance measurement Test Engineering Spec. QI-E.02 M W SW
b. Inspect Dielectric strength of the insulation oil Test (sample) Engineering Spec. QI-E.07 M W SW
c. Inspect the Tap Changer and setting switch Setting/ Test Engineering Spec. QI-E.01.01 M W SW
d. Transformer function test Test Engineering Spec. QI-E.08 M W SW
e. Polarity & vector group test Test Engineering Spec. - M W SW
f. Impedance & load loss measurement Setting/ Test Engineering Spec. - M W SW
g. No load loss & exciting current measurement Test Engineering Spec. - M W SW
Responsibility
No DESCRIPTION INSPECTION METHOD ACCEPTENCE CRITERIA VERIVIED DOCUMENT
KWRK PMC PTG PJIT
b. Foundation as per Civil Data Visual IFC Drawing - M W R
c. Check Name plate and Rating Visual IFC Drawing QI-E.01.02 M W R
d. Tools / Equipment Tester Calibration/Review Engineering Spec. QI-E.01.02 M W R
3.2 Installation
a. Visual & dimensional Visual IFC Drawing QI-E.01.02 M W R
b. Board assembly and bolting Visual Engineering Spec. QI-E.01.02 M W R
c. Busbars bolted connection Visual IFC Drawing QI-E.01.02 M W R
d. Fuse ratings and gauge rings Visual IFC Drawing QI-E.01.02 M W R
e. Contact alignment of draw-out mechanism Visual Engineering Spec. QI-E.01.02 M W R
f. Cable glands, clamping and termination Visual IFC Drawing QI-E.01.02 M W R
g. Tag & wire number Visual IFC Drawing QI-E.01.02 M W R
h. Check grounding connections Visual IFC Drawing QI-E.01.02 M W R
i. Check rating and capacity of CT, PT Visual Engineering Spec. QI-E.01.02 M W R
j. The relays have complete final setting Visual IFC Drawing QI-E.01.02 M W R
3.3 Testing
a. Insulation resistance measurement Test Engineering Spec. QI-E.02 M W SW
b. Test anti-condensation heater Test Engineering Spec. QI-E.01.02 M W SW
c. PT's polarity & phase rotation Visual Engineering Spec. QI-E.11 M W SW
d. Inspect interlock & control correctly operate Test Engineering Spec. QI-E.08 M W SW
e. Test indicating and signaling lamps or devices Test Engineering Spec. QI-E.01.02 M W SW
f. Switchgear / MCC function test Test Engineering Spec. QI-E.08 M P SW
g. Earthing resistance measurement Test Engineering Spec. - M P P
4 DIESEL ENGINE GENERATOR
4.1 Preparation
a. Location /Area Classification Visual IFC Drawing QI-E.01.08 M R R
b. Foundation as per Civil Data Visual IFC Drawing M W R
c. Check Name plate and Rating Visual IFC Drawing QI-E.01.08 M W R
d. Tools / Equipment Tester Calibration/Review Engineering Spec. QI-E.01.08 M W R
4.2 Installation
a. Visual & dimensional Visual IFC Drawing QI-E.01.08 M W R
b. Check bolting connection Visual IFC Drawing QI-E.01.08 M W R
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI Contract No. : SP-203/PG0300/2014-SO
PEMBANGUNAN PIPA TRANSMISI GAS DARI Main Contractor : KWRK Date :
GRESIK - SEMARANG Project Owner : PERTAGAS Report No. :
Document No. : GRSM-00-QAC-PLAN-003 Page : 9 of 9
Responsibility
No DESCRIPTION INSPECTION METHOD ACCEPTENCE CRITERIA VERIVIED DOCUMENT
KWRK PMC PTG PJIT
c. Check termination cable and wiring number Visual IFC Drawing QI-E.01.08 M W R
d. Check grounding connection Visual Engineering Spec. QI-E.01.08 M W R
e. Check fuel oil consumption Visual Engineering Spec. QI-E.01.08 M W R
f. Check lubricant system Visual Engineering Spec. QI-E.01.08 M W R
4.3 Testing
a. Insulation resistance test Test Engineering Spec. QI-E.02 M W SW
b. Inspect protection system Test Engineering Spec. QI-E.09 M W SW
c. Inspect sequence test Test Engineering Spec. QI-E.11 M W SW
d. Inspect operation / function test Test Engineering Spec. QI-E.08 M W SW
e. Automatic Synchronization & interlock test Test Engineering Spec. QI-E.08 M W SW
f. Load measurement Test Engineering Spec. By Vendor M W SW
5 CABLE INSTALLATION
5.1 Preparation
a. Location /Area Classification Visual IFC Drawing QI-E.01.04 M W R
b. Cable Trench/ Cable Trays accepted Visual IFC Drawing QI-E.01.15 M R R
c. Aboveground conduit accepted Visual IFC Drawing QI-E.01.16 M R R
d. Tools / Equipment Tester Calibration/Review Engineering Spec. QI-E.01.04 M W W/R
5.2 Installation
a. Visual inspection during pulling cable Visual IFC Drawing QI-E.01.04 M R R
b. Check cable size and installation Visual IFC Drawing QI-E.01.04 M R R
c. Check cable route markers Visual IFC Drawing QI-E.01.04 M R R
d. Check cable end seal and cable gland Visual IFC Drawing QI-E.01.04 M R R
e. Check the cable protection Visual IFC Drawing QI-E.01.04 M R R
f. Check underground cable jointing Visual IFC Drawing QI-E.01.04 M R R
g. Check cable termination and connection Visual IFC Drawing QI-E.01.04 M R R
h. Check grounding connection Visual/ Test IFC Drawing QI-E.01.04 M R R
i. Check cable marker Visual IFC Drawing QI-E.01.04 M R R
5.3 Testing
a. Continuity test Test IFC Drawing QI-E.06 M R R
b. Insulation resistance measurement Test Engineering Spec. QI-E.02 M R R
c. High Voltage test (MV Cable) Test Engineering Spec. QI-E.03 M R R
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI Contract No. : SP-203/PG0300/2014-SO
PEMBANGUNAN PIPA TRANSMISI GAS DARI Main Contractor : KWRK Date :
GRESIK - SEMARANG Project Owner : PERTAGAS Report No. :
Document No. : GRSM-00-QAC-PLAN-003 Page : 9 of 9
Responsibility
No DESCRIPTION INSPECTION METHOD ACCEPTENCE CRITERIA VERIVIED DOCUMENT
KWRK PMC PTG PJIT
6 GROUNDING SYSTEM
6.1 Preparation
a. Location /Area Classification Visual IFC Drawing QI-E.01.05 M R R
b. Cable Trench/ Excavation accepted Visual IFC Drawing QI-E.20 M W R
c. Tools / Equipment Tester Calibration/Review Engineering Spec. QI-E.01.05 M W R
6.2 Installation
a. Visual inspection during pulling cable Visual IFC Drawing QI-E.01.05 M R R
b. Check cable size and installation Visual IFC Drawing QI-E.01.05 M R R
c. Check underground cable jointing Visual IFC Drawing QI-E.01.05 M R R
d. Check construction electrodes Visual IFC Drawing QI-E.01.05 M W R
e. Check cable clamp and layout Visual IFC Drawing QI-E.01.05 M W R
f. Check protective measurement Visual IFC Drawing QI-E.01.05 M W R
g. Check grounding connection Visual IFC Drawing QI-E.01.05 M W R
6.3 Testing
a. Grounding continuity test Test IFC Drawing QI-E.04 M W SW
b. Inspect resistance of each electrodes & grounding system Test Engineering Spec. QI-E.05 M W SW
c. Insulation Resistance Measurement Test Engineering Spec. QI-E.02 M W SW
Responsibility
No DESCRIPTION INSPECTION METHOD ACCEPTENCE CRITERIA VERIVIED DOCUMENT
KWRK PMC PTG PJIT
f. Check the mounting system Visual IFC Drawing QI-E.01.06 M W R
7.3 Testing
a. Test operation and setting of time switches photoelectric. Setting / Test Engineering Spec. QI-E.01.06 P W SW
b. Continuity Test Test IFC Drawing QI-E.06 P W SW
c. Insulation resistance measurement Test Engineering Spec. QI-E.02 P W SW
d. Lighting circuit test Test Engineering Spec. QI-E.10 P W SW
e. Illumination quality check Test Engineering Spec. QI-E.18 P W SW
f. Inspect phase sequence of receptacle Test Engineering Spec. QI-E.11 P W SW
Responsibility
No DESCRIPTION INSPECTION METHOD ACCEPTENCE CRITERIA VERIVIED DOCUMENT
KWRK PMC PTG PJIT
- Performance Test Test Engineering Spec. QI-E.17 M W SW
- Sequence and Alarm Test Test Engineering Spec. QI-E.08 M W SW
- Insulation Resistance Measurement Test Engineering Spec. QI-E.02 M W SW
- Noise Level Measurement Test Engineering Spec. QI-E.01.09 M W SW
c. Inverter
- Performance Test Test Engineering Spec. QI-E.17 M W SW
- Sequence and Alarm Test Test Engineering Spec. QI-E.08 M W SW
- Insulation Resistance Measurement Test Engineering Spec. QI-E.02 M W SW
- Noise Level Measurement Test Engineering Spec. QI-E.01.09 M W SW
d. Safety & Alarm Test Test Engineering Spec. M W SW
9 FIRE ALARM SYSTEM
9.1 Preparation
a. Location /Area Classification Visual IFC Drawing QI-E.01.10 M W R
b. Pulling cable accepted Visual IFC Drawing QI-E.01.04 M W SW
c. Condition of material accepted Visual Engineering Spec. QI-E.01.10 M W SW
d. Tools / Equipment Tester Calibration/Review Engineering Spec. QI-E.01.10 M W SW
9.2 Installation
a. Visual and dimensional Visual IFC Drawing QI-E.01.10 M W SW
b. Inspect personal safety device Visual IFC Drawing QI-E.01.10 M W SW
c. Check board assembly and bolting Visual IFC Drawing QI-E.01.10 M W SW
d. Check the mounting system Visual IFC Drawing QI-E.01.10 M W SW
e. Check grounding connection Visual IFC Drawing QI-E.01.10 M W SW
f. Check termination and wiring number Visual IFC Drawing QI-E.01.10 M W SW
9.3 Testing
a. Continuity test Test IFC Drawing QI-E.06 M W SW
b. Insulation resistance measurement Test Engineering Spec. QI-E.02 M W SW
c. Test indicating signaling lamps and devices Test Engineering Spec. QI-E.01.10 M W SW
d. Operation test by manual and automatic Test Engineering Spec. QI-E.08 M W SW
e. Alarm system test Test Engineering Spec. QI-E.08 M W SW
10 LIGHTING PANEL
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI Contract No. : SP-203/PG0300/2014-SO
PEMBANGUNAN PIPA TRANSMISI GAS DARI Main Contractor : KWRK Date :
GRESIK - SEMARANG Project Owner : PERTAGAS Report No. :
Document No. : GRSM-00-QAC-PLAN-003 Page : 9 of 9
Responsibility
No DESCRIPTION INSPECTION METHOD ACCEPTENCE CRITERIA VERIVIED DOCUMENT
KWRK PMC PTG PJIT
10.1 Preparation
a. Location /Area Classification Visual IFC Drawing QI-E.01.11 M W R
b. Foundation as per Civil Data/ Support accepted Visual IFC Drawing M W SW
c. Pulling cable accepted Visual IFC Drawing QI-E.01.04 M W SW
d. Check Name plate and Rating Visual IFC Drawing QI-E.01.11 M W SW
e. Tools / Equipment Tester Calibration/Review Engineering Spec. QI-E.01.11 M W SW
10.2 Installation
a. Visual & dimensional Visual IFC Drawing QI-E.01.11 M W SW
b. Board assembly and bolting Visual IFC Drawing QI-E.01.11 M W SW
c. Busbars bolted connection Visual IFC Drawing QI-E.01.11 M W SW
d. Check Fuse and Circuit breaker ratings Visual IFC Drawing QI-E.01.11 M W SW
e. Contact alignment of draw-out mechanism Visual IFC Drawing QI-E.01.11 M W SW
f. Cable glands, clamping and installation Visual IFC Drawing QI-E.01.11 M W SW
g. Tag & wire number Visual IFC Drawing QI-E.01.11 M W SW
h. Check grounding connections Visual IFC Drawing QI-E.01.11 M W SW
i. Check termination and wiring number Visual IFC Drawing QI-E.01.11 M W SW
10.3 Testing
a. Continuity test Test IFC Drawing QI-E.06 M W SW
b. Insulation resistance measurement Test Engineering Spec. QI-E.02 M W SW
c. Phase sequence test Test Engineering Spec. QI-E.11 M W SW
d. Operation test Test Engineering Spec. QI-E.08 M W SW
11 CCTV
11.1 Preparation
a. Location /Area Classification Visual IFC Drawing QI-E.01.12 M W SW
b. Pulling cable accepted Visual IFC Drawing QI-E.01.04 M W SW
c. Condition of material accepted Visual Engineering Spec. QI-E.01.12 M W SW
d. Tools / Equipment Tester Calibration/Review Engineering Spec. QI-E.01.12 M W SW
11.2 Installation
a. Visual and dimensional Visual IFC Drawing QI-E.01.12 M W SW
b. Inspect personal safety device Visual IFC Drawing QI-E.01.12 M W SW
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI Contract No. : SP-203/PG0300/2014-SO
PEMBANGUNAN PIPA TRANSMISI GAS DARI Main Contractor : KWRK Date :
GRESIK - SEMARANG Project Owner : PERTAGAS Report No. :
Document No. : GRSM-00-QAC-PLAN-003 Page : 9 of 9
Responsibility
No DESCRIPTION INSPECTION METHOD ACCEPTENCE CRITERIA VERIVIED DOCUMENT
KWRK PMC PTG PJIT
c. Check board assembly and bolting Visual IFC Drawing QI-E.01.12 M W SW
d. Check the mounting system Visual IFC Drawing QI-E.01.12 M W SW
e. Check grounding connection Visual IFC Drawing QI-E.01.12 M W SW
f. Check termination and wiring number Visual IFC Drawing QI-E.01.12 M W SW
11.3 Testing
a. Continuity test Test IFC Drawing QI-E.06 M W SW
b. Insulation resistance measurement Test Engineering Spec. QI-E.02 M W SW
c. Operation test Test Engineering Spec. QI-E.08 M W SW
12 CABLE TRAY
12.1 Preparation
a. Location /Area Classification Visual IFC Drawing QI-E.01.15 M W R
b. Foundation as per Civil Data / Support accepted Visual IFC Drawing QI-E.01.15 M W SW
c. Check enclosure and safety device Visual IFC Drawing QI-E.01.15 M W SW
d. Condition and type of material accepted Visual Engineering Spec. QI-E.01.15 M W SW
12.2 Installation
a. Visual and dimensional inspection Visual IFC Drawing QI-E.01.15 M W SW
b. Check support of cable tray Visual IFC Drawing QI-E.01.15 M W SW
c. Alignment of cable tray Visual IFC Drawing QI-E.01.15 M W SW
d. Check installation of separator Visual IFC Drawing QI-E.01.15 M W SW
e. Check tightening bolt & nuts Visual IFC Drawing QI-E.01.15 M W SW
f. Check grounding connection Visual IFC Drawing QI-E.01.15 M W SW
g. Check completely of cover with clamp Visual IFC Drawing QI-E.01.15 M W SW
13 ABOVEGROUND CONDUIT
13.1 Preparation
a. Location /Area Classification Visual IFC Drawing QI-E.01.16 M W R
b. Support or bracket accepted Visual IFC Drawing QI-E.01.16 M W SW
c. Check enclosure and safety device Visual IFC Drawing QI-E.01.16 M W SW
d. Condition and type of material accepted Visual Engineering Spec. QI-E.01.16 M W SW
13.2 Installation
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI Contract No. : SP-203/PG0300/2014-SO
PEMBANGUNAN PIPA TRANSMISI GAS DARI Main Contractor : KWRK Date :
GRESIK - SEMARANG Project Owner : PERTAGAS Report No. :
Document No. : GRSM-00-QAC-PLAN-003 Page : 9 of 9
Responsibility
No DESCRIPTION INSPECTION METHOD ACCEPTENCE CRITERIA VERIVIED DOCUMENT
KWRK PMC PTG PJIT
a. Visual and dimensional Visual IFC Drawing QI-E.01.16 M W SW
b. Check Support of conduit Visual IFC Drawing QI-E.01.16 M W SW
c. Alignment of conduit installation Visual IFC Drawing QI-E.01.16 M W SW
d. Check tightening bolt & nuts Visual IFC Drawing QI-E.01.16 M W SW
e. Make sure of conduit's clean and free damages Visual IFC Drawing QI-E.01.16 M W SW
f. Check bending radius of conduit Visual IFC Drawing QI-E.01.16 M W SW
Responsibility
No DESCRIPTION INSPECTION METHOD ACCEPTENCE CRITERIA VERIVIED DOCUMENT
KWRK PMC PTG PJIT
f. Operation / function test Test Engineering Spec. QI-E.08 M W SW
`
Prepared By, Checked/Reviewed By, Reviewed/Approved By, Reviewed/Approved By,
KWRK PMC PERTAGAS PJIT/MIGAS
5.1 Preparation
a. Conform material to specification Review Engineering Spec. Data sheet R R R R
5.2 Installation
a. Install instrument air supply piping Visual Engineering Spec. QI-J17 M W SW R
b. Hook-up drawing checking Visual Engineering Spec. QI-J17 M W SW R
c. Checking and Tighting all connection Visual Engineering Spec. QI-J17 M W SW R
5.3 Testing
a. Leak Test Test Engineering Spec. QI-J03 M W W R
SEQUENCE TEST INCLUDING SHUT DOWN SYSTEM & FIRE AND GAS
11
DECTECTOR SYSTEM
11.1 Preparation
a. Check termination Visual Engineering Spec. QI-J09, QI-J07 M W W R
QI-J04, QI-J11, QI-J14,
b. Check individual calibration report Visual Data Sheet QI-J15, QI-J16, QI- M R R R
J19
c. check interlock logic diagram Visual Data Sheet Logic Diagram - M R R R
d. I/O Check Test Data Sheet Logic Diagram - M R R R
e. Control/ alarm /trend Grouping chek Test Data Sheet Logic Diagram - M R R R
11.2 Test
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI Contract No. : SP-203/PG0300/2014-SO
PEMBANGUNAN PIPA TRANSMISI GAS DARI Main Contractor : KWRK Date :
GRESIK - SEMARANG Project Owner : PERTAGAS Report No. :
Document No. : GRSM-00-QAC-PLAN-003 Page : 6 of 6