Elect 01 Method Statement For Testing of MV Cables Rev 2.0
Elect 01 Method Statement For Testing of MV Cables Rev 2.0
Method Statement
Rev: 02
Testing MV Cables at Um-Qasr
xxxxxxxxxxxxx Doc. Cat. EXT
Method Statement
Testing MV Cables at Um-Qasr
1 OF 7
IRAG GATES CONTRACTING COMPANY
Method Statement
Rev: 02
Testing MV Cables at Um-Qasr
XXXXXXXXXXXXX Doc. Cat. EXT
TABLE OF CONTENTS
1. Introduction
2. Definitions
3. Abbreviations
4. Methodology
5. MTO
6. HSE Requirements
7. Attachments
2 OF 7
IRAG GATES CONTRACTING COMPANY
Method Statement
Rev: 02
Testing MV Cables at Um-Qasr
XXXXXXXXXXXXX Doc. Cat. EXT
Method Statement
Testing MV Cables at Um-Qasr
1. Introduction
As part of BGC development plan, Work Order (WO-026) to perform Refrigerated Export
Project (Testing MV Cables at Um-Qasr) at Um-Qasr Storage Terminal has been issued to
IGCC.
This Method Statement, aims to provide sufficient definition for Refrigerated Export Project
(Testing MV Cables at Um-Qasr) Storage Terminal. Its intent is to also facilitate
implementation in a safe and efficient manner and for all involved parties to understand the
risks, roles and responsibilities associated with the Testing MV Cables at Um-Qasr.
2. Definitions
COMPANY BGC (Basra Gaz Company)
WORK Shall mean all and any of the work andor services andor materials
required to be provided by the CONTRACTOR under contract with
COMPANY.
3. Abbreviations
Abbreviation Definition
3 OF 7
IRAG GATES CONTRACTING COMPANY
Method Statement
Rev: 02
Testing MV Cables at Um-Qasr
XXXXXXXXXXXXX Doc. Cat. EXT
4. Methodology
4.1 Engineering Phase
- Preparation and Submission of Method Statement.
4 OF 7
IRAG GATES CONTRACTING COMPANY
Method Statement
Rev: 02
Testing MV Cables at Um-Qasr
XXXXXXXXXXXXX Doc. Cat. EXT
4.4.2.3 IR Test
- By utilizing calibrated Megger tester, IR test will be performed
by qualified electrician
- IR Testing voltage shall not exceed the cable operating voltage;
for 3.3KV cables the test will be done at 2.5KV and the 11KV
cables will be tested at 5KV
- Record the measured value on related ITR form
4.4.2.4 Hi-Pot Test
- By utilizing calibrated Hi-Pot Very Low Frequency (VLF) tester,
Hi-Pot test will be performed by qualified electrician
- Hi-Pot DC voltage is not to be used, under any circumstances
- VLF voltage must not exceed the nominal / operating voltage
- As an alternative of VLF Hi-Pot testing, may be applicable the
“soak test” at nominal voltage and frequency
- Record the Hi-Pot measured value on related ITR form
Method Statement
Rev: 02
Testing MV Cables at Um-Qasr
XXXXXXXXXXXXX Doc. Cat. EXT
5. MTO
N/A
6. HSE Requirements
Site Induction.
Where it is not possible to isolate the cable from other equipment, ensure that Surge
Arresters and VT’s are disconnected from the cable
The ‘Cable Tester’ must be the authorized tester who has been appropriately trained
and authorized to conduct Testing of HV Cables in accordance with accepted
standards. It is the responsibility of the ‘Cable Tester’ to have a clear understanding and
comply with the requirements of this ‘Voltage Testing of HV Cables’ technique
6 OF 7
IRAG GATES CONTRACTING COMPANY
Method Statement
Rev: 02
Testing MV Cables at Um-Qasr
XXXXXXXXXXXXX Doc. Cat. EXT
Job Risk Analysis must be done by the work team before commencing any switching and
tests near the underground cables and all parties concerned are in agreement upon that
assessment
The tester in charge shall ensure that drawings are made available to familiarize himself
with the work area and equipment locations prior to commencing work
Ensure to connect a local earth on the test equipment, if practicable. The case earth
must remain connected to the system earth in order to maintain an acceptable single
earth potential
After the cable is tested (SI, IR and VLF) cable cores must be then discharged. If
applicable, close the Earth switch and then the test set leads may be removed
PPE Requirement:
Use suitable barriers, barricades and warning signs on both sides of the cable to prevent
access to the cable by persons not involved with the testing. If there is any danger of
exposing the public or staff to energized conductors or equipment a safety observer must
be used.
Housekeeping.
7 OF 7