Seismic Load Calculation

This document contains seismic load calculations for a proposed building according to the 1997 Uniform Building Code. It identifies the earthquake design parameters such as seismic zone, soil type, and structural system. It then calculates the base shear and design response spectra to determine the seismic forces for the building. Key values calculated include the structural period, control periods, and base shear. Design curves are provided to determine the spectral acceleration.

Uploaded by

joshua humirang
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
332 views

Seismic Load Calculation

This document contains seismic load calculations for a proposed building according to the 1997 Uniform Building Code. It identifies the earthquake design parameters such as seismic zone, soil type, and structural system. It then calculates the base shear and design response spectra to determine the seismic forces for the building. Key values calculated include the structural period, control periods, and base shear. Design curves are provided to determine the spectral acceleration.

Uploaded by

joshua humirang
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 6

Project Title: Sample Only Civil Engineer

Project Location: Sample Only Junas A. Ultra


Owner / Clients: Sample Only By: Chk By: Rev.:
Subject: Seismic Load Calculation

SEISMIC LOAD CALCULATIONS (1997 Uniform Building Code, Section 1630.2.1)


1.0 Earthquake Dessign Parameters:

Occupancy category; = Essential facilities . . . . . . . . . . . . . . . . . . . . . . . . . Table 16 - K


Seismic importance factor; I = 1.25 . . . . . . . . . . . . . . . . . . . . . . . . . Table 16 - K
Seismic importance factor; Ip = 1.50 . . . . . . . . . . . . . . . . . . . . . . . . . Table 16 - K
Siesmic zone map; = 4 . . . . . . . . . . . . . . . . . . . . . . . . .Figure 16 - 2
Siesmic zone factor; z = 0.40 . . . . . . . . . . . . . . . . . . . . . . . . . .Table 16 - I
Soil profile type; = SE . . . . . . . . . . . . . . . . . . . . . . . . . Table 16 - J
Seismic coefficient; Ca = 0.06 6 . . . . . . . . . . . . . . . . . . . . . . . . . Table 16 - Q
Seismic coefficient; Cv = 0.96 . . . . . . . . . . . . . . . . . . . . . . . . . Table 16 - Q
Seismic source type; = C . . . . . . . . . . . . . . . . . . . . . . . . . Table 16 - S
Closest distance to known seismic; = ≤ 2 km 4 . . . . . . . . . . . . . . . . . . . . . . . . . Table 16 - S
Near source factor; Na = 1.00 . . . . . . . . . . . . . . . . . . . . . . . . . Table 16 - S
Closest distance to known seismic; = ≤ 2km 2 . . . . . . . . . . . . . . . . . . . . . . . . . Table 16 - S
Near source factor; Nv = 1.00 . . . . . . . . . . . . . . . . . . . . . . . . . Table 16 - S
Basic structural system; = 4.0 Dual system . . . . . . . . . . . . . . . . . . . . . . . . . Table 16 - N
Lateral force resisting system description; = 4.8 Steel EBF - With steel SMRF . . . . . . . Table 16 - N
Numerical coefficient representative; R = 8.50 . . . . . . . . . . . . . . . . . . . . . . . . . Table 16 - N
Seismic force amplification factor; Ω = 2.80 . . . . . . . . . . . . . . . . . . . . . . . . . Table 16 - N
Height limit for seismic zone 3 & 4; Hn = N.L. . . . . . . . . . . . . . . . . . . . . . . . . . Table 16 - N
Building height; Ht = 45.00
For all other buildings; Ct = 0.0488

1.2 Base Shear Calculation and Design Response Spectra:

Eq. - - - - - - - - - (30 - 8) T = Ct Hn ¾ = 0.8479 1630.2.2 Structure period

Control periods; Ts = Cv / 2.5 Ca 6.4000 Figure 16 - 3 Design Response Spectra

Control periods; To = 0.20 T = 1.2800 Figure 16 - 3 Design Response Spectra

Eq. - - - - - - - - - (30 - 4) V = [ Cv I / R T] W = 0.1197 W 1630.2 Static Force Procedure

Eq. - - - - - - - - - (30 - 5) V = [ 2.5 Ca I / R ] W = 0.0221 W 1630.2 Static Force Procedure

Eq. - - - - - - - - - (30 - 6) V = [ 0.11 Ca I ] W = 0.1320 W 1630.2 Static Force Procedure

Eq. - - - - - - - - - (30 - 7) V = [ 0.8 Z Nv I / R ] W = 0.0471 W 1630.2 Static Force Procedure


0.20
0.000 0.060
1.280 0.150
6.400 0.150
7.000 0.137
7.500 0.128
0.15 8.000 0.120
8.500 0.113
9.000 0.107
9.500 0.101
10.000 0.096
0.10 10.500 0.091
11.000 0.087
SPECTRAL ACCELERATION (g,s)

11.500 0.083
12.000 0.080
12.500 0.077
13.000 0.074
0.05
13.500 0.071
14.000 0.069
14.500 0.066
15.000 0.064
15.500 0.062
0.00 16.000 0.060
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0 16.500 0.058
PERIOD (SECONDS)
FIGURE 16 - 3 (DESIGN RESPONSE SPECTRA) Page 1 of 6
TRAL ACCELERATION (g,s)
0.05

Project Title: Sample Only Civil Engineer


Project Location: Sample Only Junas A. Ultra
Owner / Clients: Sample Only By: Chk By: Rev.:
Subject: 0.00 Seismic Load Calculation
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0
PERIOD (SECONDS) 17.000 0.056
FIGURE 16 - 3 (DESIGN RESPONSE SPECTRA) 17.500 0.055
18.000 0.053

Total weight of the building; W = 41000.00 kn The concentrated force at the top; = 226.10 kn
Total base shear; V = 904.41 kn

Floor Height
Floor Level Weight Per Level Height Per Level Weight x Height Wt x ht Shear Per Level
(ht Fh / Floor
(m) (Wt - kn) (hl - m) (Wt x ht) / Ʃwi x hi (V - kn)
in m)
15 3500 3 45.00 157500.00 0.165 904.41 338.34
14 2500 3 42.00 105000.00 0.110 904.41 300.93
13 2500 3 39.00 97500.00 0.102 904.41 295.58
12 2500 3 36.00 90000.00 0.095 904.41 290.24
11 2500 3 33.00 82500.00 0.087 904.41 284.89
10 2500 3 30.00 75000.00 0.079 904.41 279.55
9 2500 3 27.00 67500.00 0.071 904.41 274.20
8 2500 3 24.00 60000.00 0.063 904.41 268.86
7 2500 3 21.00 52500.00 0.055 904.41 263.51
6 2500 3 18.00 45000.00 0.047 904.41 258.17
5 2500 3 15.00 37500.00 0.039 904.41 252.83
4 2500 3 12.00 30000.00 0.032 904.41 247.48
3 2500 3 9.00 22500.00 0.024 904.41 242.14
2 2500 3 6.00 15000.00 0.016 904.41 236.79
2 2500 3 3.00 7500.00 0.008 904.41 231.45
1 2500 0.25 2.75 6875.00 0.007 904.41 231.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00

Page 2 of 6
Project Title: Sample Only Civil Engineer
Project Location: Sample Only Junas A. Ultra
Owner / Clients: Sample Only By: Chk By: Rev.:
Subject: Seismic Load Calculation

0.00 0.00 0.000 0.00 0.00


0.00 0.00 0.000 0.00 0.00
0.00 0.00 0.000 0.00 0.00
Sum 41000.00 45.25 951875.00 4522.06