Production and Operations Management (Mba-G519) : Case Report On
Production and Operations Management (Mba-G519) : Case Report On
MANAGEMENT (MBA-G519)
CASE REPORT ON
Advanced Integrated Circuitry, Inc.—later renamed AIC Systems was established in Taiwan in the year 1992,
It was recognized as the producer of printed circuit board maker for the PC business. They had some expertise
in motherboards and graphics cards for the personal computer industry also.AIC also supplied branded
manufacturers of desktop and laptop computers such as Dell, HP, and Compaq.
By the year 2000, organization AIC had developed itself into an Original Design Manufacturer (ODM)
empowering advancement and the new era of outlines as well the company took the active role in innovating
and designing the new generation of components. Advanced Integrated Circuitry, Inc also protected its
position in the industry as the low-cost supplier by opening a new plant at Kaizhi in early 2001 when the
Taiwanese government relaxed restrictions on investments in the mainland China.
In the year 2007, the organization AIC broadened into the generation of Netbooks and embarked on a new
strategy: - diversifying the product portfolio to include consumer electronics, with a particular focus on
mobile technology as well.
In any case, AIC can't take care of demand within the present operations going in in the plant. The production
is neither proficient nor viable. The organization has a couple of alternatives to enhance sequential
construction system by either expanding the movements or the mechanical production systems. Each of these
choices will expand work cost for the organization yet encourage in meeting objectives production and
process duration.
Q1. How efficient is notebook assembly at kazhi plant?
Kazhi plant is efficient enough as we can see their monthly production and design of plant assembly. The
setup of this plant was due to relaxed government taxation. It also had an added advantage of having its
own warehouse for incoming material, outsourced parts & components.
As given in the case, by Nov 2008 each assembly line was producing 1 netbook in 50 seconds.
That brings monthly output of plant to:
(B). What is theoretical efficiency of the planned line, looking only at direct labor on
the assembly line?
Answer:
As, Chen & Lapen designed this process to give an output of 700 units per shift per line. Thus, planned
Cycle time for 8 working hours shift comes out to be:
Theoretical Actual
Task time 396 443
Effectiveness is defined as the degree to which something is successful in producing a desired result. The
current operations of AIC are not successful in producing desired results, what are the criteria that leads to
this are given below.
• NO, according to the design operations are not well appropriate to meet the design as according to
planned time cycle each line should produce 700 netbooks per 8 working hour shift with 1 hour of
relaxation.
They can produce monthly output of
= 700 * 2 * 4 * 6 * (52/12)
= 145,600 Netbooks/month
Where, Number of shifts = 2
Number of lines = 4
Number of working days in a week = 6
Number of weeks in a year = 52/12 = 4.33
The main bottleneck is formed on the station 2 & 6 as it takes 50 secs each to complete its operations.
The only ways to achieve this target are:
1. Either to increase the labor force so as to decrease extra time taken per station to meet planned
cycle time of 41.1 seconds rather than current actual cycle time of 50 seconds.
2. To setup an extra line to increase total production.
Q.3 What is the financial impact of bringing the operation closer to "full potential"
and achieving planned production levels?
(B). What is the financial impact of achieving the target cycle time?
Answer:
Actual: -
8 working hours shift = 28800 seconds,
Number of shifts in a day = 2,
Number of working days in a week = 6,
Number of assembly lines = 4,
Number of Netbooks produced per assembly line per shift per day = (28800/50)
= 576 Netbooks /line/shift/day
Number of Netbooks produced in total in a day = 576*2*4
= 4608 Netbooks/day
Targeted: -
Cycle time planned = 8*60*60/700 = 41.14 Seconds / Netbook
Therefore: -
8 working hours shift = 28800 seconds,
Number of shifts in a day = 2,
Number of working days in a week = 6,
Number of assembly lines = 4,
Number of Netbooks produced per assembly line per shift per day = (28800/41.1)
= 700 Netbooks /line/shift/day
Actual: -
Number of Netbooks produced per assembly line per shift per day = (28800/50)
= 576 Netbooks /line/shift/day
Assembly line worker costs $500 per month
Direct labor cost
Total deployment: - 12
Per person production per day per shift per line: - 576/12 = 48
Cost per month for direct labor = 500 * No of labor * No of shifts * No of line
= 500 * 12 * 2* 4 = $48000/month
Total deployment: - 10
Per person production per day per shift per line: - 576/10 = 57.6
Cost per month for direct labor = 500 * No of labor * No of shifts * No of line
= 500 * 10 * 2* 4 = $40000/month
Now,
Labor cost per unit = $ 4.80
Total labor cost with 12 labors (Direct labor + Indirect labor) = 4.8 * 119808(units/month)
= $575078.4/month
Total labor cost with 10 labors = 575078.4 – 8000 = $567078.4/month