Turbine Operating Procedure
Turbine Operating Procedure
2 of 32
REV
TABLE OF CONTENT
COVER 1
TABLE OF CONTENT 2
1 Purpose 3
2 Reference document 3
3 Test equipment 3
4 Safety Precautions 3
5 Pre-requisite 4
Description of the System and Equipment
6 4
Specification
7 Turbine and Auxiliaries Equipment Stipulation 5
8 Commisioning and Sequence Start-up 7
9 Main steam heating/warming up 8
10 Start up steam turbine 8
C. Control operation 19
1. Purpose
3 of 32
REV
The purpose of this document is to present the Steam Turbine start up,
shutdown, and trouble shooting to ensure the equipment and system can
be put into operation in an orderly way.
2. Reference Document
Design Drawing
Steam Turbine Operating Manual
3. Test Equipment
DCS and Local meters
4. Safety Precautions
Ensuring for all of authorized personal has been provided for “Personal
protective equipment” (Safety shoes, safety helmet, safety glass, ear
plug and / or other safety requirements).
Ensuring labeling / Marking for all inspected electrical equipment, tools
or appliances that era safe for use before issuing them workers.
All construction machinery, mechanical equipment and electrical
appliances shall by inspection and tested safe for use by competent
person for non-statutory equipment. And by an approved person for
statutory equipment. In addition all construction equipment must be
checked by competent / authorized personal before commencement of
work at site.
Provide “Warning line” erected around all sides of work area for the
purpose of preventing disturbing form unauthorized personal during
commissioning.
When work is performed on electrically powered equipment and
associated circuit, the electrical lock-out / Tag-out shall be applied
prior to work commencement.
No one shall change, alter or modify any electrical equipment, tools or
instrument except authorized electrician / technician.
5. Pre-requisite
Check name plate, cleanliness, labeling, and grounding point of the
equipment, such as motor, pump (if any) and etc.
Check all equipment has been installed completely.
All instruments have been calibrated.
4 of 32
REV
All the lubricating oil pumps as part equipment of the Turbine have
completely installed and have been commissioning.
Generator have installed completely.
Generator system have installed completely.
All I&C for Steam Turbine have installed completely and operable.
All I&C for Generator have installed completely and operable.
DCS have installed completely and operable.
Boiler main steam ready to supply turbine
Cooling system ready to supply water cooling for condenser and
equipment auxiliary.
Taking Over Package (TOP) has been issued by construction team that
system is ready for commissioning.
6. Pre-requisite
SPECIFICATION OF TURBINE
Model : N3.5-3.83
Type : Single cylinder, medium tempe-
ratute, intermediate pressure,
impulse condensing turbine
Governing Mode : Nozzle governing
Rated power : 3500 kW
Speed : 5600 rpm
Working grid frequency : 50 Hz
Rated Inlet pressure : 3.83 MPa
Rated Inlet temperature : 435 C
Inlet steam flow : 36.8 t/h
Exhaust pressure at rated condition : 0.0103 MPa
Stage number for Feed Water : Deaerator
Temperature of Feed water : 150 C
Critical Speed : 1750 rpm and 2500 rpm
Trip Speed : 3300 rpm dan 3330 rpm
Vibration bearing at rated speed : ≤ 0.03mm
Vibration bearing at critical speed : ≤ 0.15mm
Speed variation : ≤ 15%
Speed regulation : 4.5%, adjustable
Insensitivity of speed governing : ≤ 0.5%
Cooling water temperature : 32 C
Rotation direction : Clockwise when viewed toward
steam flow direction
7.1. The normal variable range of the parameters of the steam ahead of
Main Steam Valve (MSV) are as followings:
1) The pressure of steam before MSV : 4,9MPa; max. 5,1MPa, min.
4.6MPa.
2) The temperature of steam before MSV : 470C; max. 480C,
min. 455C.
7.2. The steam turbine is still allowed to operation in long term with
rated electric power under the following circumstances:
1) The steam pressure drops to no less than 4.6MPa, the steam
temperature falling to no less than 455C, and the cooling water
inlet temperature not exceeding 25C.
2) The temperature of cooling water inlet rises to 33C, but the
following conditions must be meet:
a. The steam parameters shall be not less than the rated
values
b. The condenser shall keep the calculated water consumption
c. The quantity of feeding water that enters the HP heater is
not more than 105% of the total steam flow into turbine
under the condition.
7.3. When the pressure of the steam ahead of the MSV is 5.1 MPa
(absolute) or the steam temperature is 485 C, the turbine unit
running shall not exceed 30 minutes. Annual accumulative total
must not exceed 20 hours.
7.4. When the pressure of the steam ahead of the MSV is less than 4.6MPa
(absolute) or the steam temperature is less than 455C, it should be
reduced load operation according to regulations.
1. Boiler has been starting and minimal condition of main steam header
pressure > 3,0 Mpa and temperatur > 350 °C. Main steam pipe line
warming up can start with boiler pressure increasing process to 5,3 Mpa.
2. Main steam supply valve from Boiler close position
3. All drain valves of main steam pipe open position.
4. Main steam isolation valve of turbine close position.
5. Start heating the main steam pipe with open by pass valve of main steam
supply valve from boiler, step by step.
6. Monitor pressure and temperatur of pipe line, incraesing pressure rate 0,1
– 0,15 MPa /minute.
7. Heating is completed around 45 minuts and the pipe tempratur > 400 °C
The turbine start-up method is decided by the metal temperature at the lower part of
casing at the control stage, divided:
10 of 32
REV
9. Open valve step by step for steam extraction #1, steam extraction #2,
steam extraction #3 and turbine drain valve.
10. LP heater drain valve open and condensate recirculation valve to
condenser is close.
11. HP heater drain valve open and condensate recirculation valve to
deaerator is close.
12. Expansion tank, open drain valve step by step from inlet steam pipe,
extraction #1, drain from turbine, extraction #2, xtraction #3.
13. Start gland heater fan.
14. Start condensate pump and recirculation the water from condenser to
LP heater by adjusting control valve. Analisysed the water, if the water
quality is out of specification than some water drained and keep
condenser level is NWL by make up from demin water.
15. Open manual steam valve to surge tank step by step and start surge
tank fan. Keep surge tank pressure 0,1010 – 0,1275 Mpa.
16. Adjusted steam temperatur sealing to rear of turbine by open
condensate spreay valve.
17. Open condenser vacuum valve and start steam air ejector start up by
open the steam valve for starting steam ejector. Main steam pressure ±
1,2 Mpa and condenser vacuum ≤ -0,04 Mpa.
18. Open MSV for turbine and governor valve shlud be close position.
19. Open by pass valve of isolation motor valve step by step and start
heating of MSV and inlet steam pipe. Heating is finished after
temperatur >400 C.
20. Local site – reset trip buthon valve
21. TSI panel on normal operation the interlock swicth shall ‘on’ position for
below items :
a. Shutdown at generator breaker protection action or trip position
b. Shutdown at turbine over speed 3300 rpm and 3330 rpm
c. Shutdown at lubricating oil pressure 0,04 Mpa
d. Shutdown at vacuum prssur -0,04 Mpa
e. Shutdown of rotor axial displacement 0,7 mm
f. Shutdown at bearing lubrication return oil temperatur > 70 °C
g. Shutdown at bearing temperatur > 100 °C
h. Shutdown at bearing vibration > 70m
i. Shutdown at 505 governor control trip
j. Shutdown from boiler trip
k. Manual shutdown from control room
l. Main interlock swicth
22. Confirm that turbine trip lamp is off.
23. Confirm that main alarm is off
24. Confirm that AC and DC lube oil pump swicth position is auto.
25. Start turbine to 600 rpm from woodward 505 panel by push (increasing
speed rate 100 rpm/minuts) :
11 of 32
REV
- Reset
- Run
- Speed
- Select
- Input speed 600
- Enter
26. Turning gear motor auto stop/manual stop after rotor speed > 200 rpm.
27. Monitor the temperatur of and lower casing :
increasing rate less than 3-4C/minute.
Temperatur difference between upper and lower of casing wall at
control stage shall be less than 50C.
28. Close all drain valve of main steam pipe.
29. Close drain valve of turbine inlet steam pipe.
30. Keep for 5=10 minuts and monitor the speed, temperatur, vibration and
displacement.
31. Obsevation if any mall function stop the start up and investigation,
normal condition go to next step.
32. Incrase the speed to 900 rpm from woodward 505 by push (increasing
speed rate 100 rpm/minuts) :
Speed
Select
Input speed 900
Enter
33. Keep for 10 minuts and monitor the speed, temperatur, vibration and
displacement.
34. Adjust the steam sealing by increase opening steam valve
35. Keep condensor vacum -0,04 MPa, by adjusting opening steam to
ejector (maximal 1,2 Mpa).
36. Check opening valves of extraction #1, extraction #2, extraction #3
and turbine drain valve, if valves opening is so large than reduce
opening valves.
37. Obsevation if any mall function stop start up and investigation, normal
condition go to next step.
38. Incrase the speed to 1200 rpm from woodward 505 by push
(increasing speed rate 100 rpm/minuts) :
Speed
Select
Input speed 1200
Enter
39. Keep for 45-60 minuts and monitor the speed, temperatur, vibration
and displacement.
40. Adjust the steam sealing by increase opening steam valve
12 of 32
REV
13 of 32
REV
Cold start up
3500
3000
2500
Speed (RPM)
Time (minut)
1. Ensure condenser ready to operation, inlet and outlet of water cooling are
open.
2. Oil cooler is ready to operation, air release valve close position, intlet and
outlet for water and oil are open position
3. Air cooler is ready to operation, air release valve close position, intlet and
outlet for water are open position.
4. Start cooling tower system, basin water level is + 10 cm from NWL, start
cooling tower fan and cooling water pump.
5. Oil filter shall be clean and ready to operation, open inlet and outlet valve
.
6. Start high pressure oil pump and ensure discharge pressure ± 0,834 Mpa.
7. Start oil tank exhaust fan.
8. Start turning gear,
9. Open valve step by step for steam extraction #1, steam extraction #2,
steam extraction #3 and turbine drain valve.
10. LP heater drain valve open and condensate recirculation valve to
condenser is close.
14 of 32
REV
a. Speed
b. Select
c. Input speed 3000
d. Enter
46. Start two stage steam ejector, by open steam valve and condenser inlet
valve. Adjust condenser vacuum is -0,08 Mpa and maximum steam inlet
pressure is 1,2 Mpa.
47. High pressure oil pump auto stop/manual stop
48. Keep for 5 minuts and monitor the speed, temperatur, vibration and
displacement.
49. Adjust the steam sealing by increase opening steam valve, and steam
sealing temperatur for rear turbine controlled by condensate spray.
50. Obsevation if any mall function stop start up and investigation, normal
condition go to next step.
51. Steam turbine ready to syncronize.
52. The 0,6 MW electric load should be loaded immediately after connections
with power grid, increasing load speed 0,3 MW/minuts :
53. To 2 MW and kee for 10 minuts
54. To 4 MW and keep for 8 minuts
55. After water quality from condenser is suitable with requirement standard
boiler water than condenser drain valve is closed.
56. LP Heater - Open condensate valve to condenser, open steam valve to
condensor and close drain valve.
57. HP Hater - Open condensate valve to deaerator, open steam valve to
condensor and close drain valve.
58. Close drain valve from extraction #1, exraction #2, extraction #3 and
drain valve from turbine is closed after turbine normal operation
Hot start up
4000
3000
Speed (RPM)
Time (minut)
C. Control Opration
Parameter should be controled :
17 of 32
REV
8. Condenser vacuum :
a. Unit load is more than 40% of the rated load, vacuum should be
less than -0,065 Mpa
b. Unit load is 20-40% of the rated load, vacuum should be less than
-0,06 Mpa.
c. Unit load is less than 20% of rated load, vacuum should be less
than -0,04 Mpa
A. Boiler follow
Generating of power is depend on boiler steam out put, if steam pressure
and temperatur change so the steam flow will be change also than
the pressure and temperatur table.
Steam flow change will given effect to generator out put.
B. Turbine follow
Generating of power is depend on turbine setting input by operator, boiler
shall be supplied the steam that turbine required for generating the
power.
One or several items of parameter have alarm, but don’t reach to the stopping and
the unit does not want to stop, the unit is running in abnormal condition. Try
to find the cause of abnormal parameter. Stop the unit if the abnormal
parameter going to reach of the limit and can’t slove.
Item Inspection
1. Axial displacement 1. Check axial bearing pad temperatur and
return oil temperatur to ensure is no wearing
with the bearing pad
2. Check the inlet steam parameters and
vacuum to avoid sharp change
2.Differential 1. Check the expantion direction
Expansion 2. Maintain the load to minimum the change of
inlet steam temperatur and the exhaust
temperatur.
3. Reduce or increase the load gradually,
according the diffrential expantion recording
and shall be normal range.
19 of 32
REV
exhaust.
e.The casing expantion and difference
expantion.
f. Measure the vibration spectrum.
3. Don’t let the unit near the critical speed if
the vibration is violent during start up. Stop
rising load if the vibration is violent during
rising load, and operate the unit with the
former load. The unit can’t raise load until
the violent vibration has been eliminated.
Stop the unit to check if the vibration is
violent during eccelerating, operating the
unit with reducing speed is forbidden in this
condition.
Lube oil pressure low 1. Check the level in main oil tank
2. Check whether the main oil pump or oil
injectors are working well
Higher temperatur of 1. Check inlet oil pressure of turbine bearing
radial bearing 2. Check lube oil quality/cleanness to ensure
pad and return there is no impurities in lube oil.
oil 3. Check turbine inlet lube oil temperatur, shall
be normal range.
4. Check any steam leaking from gland seal
system that mean so much steam or so high
steam temperatur.
5. Check bearing pads temperatur, shall be
normal range.
Higher temperatur of 1. Check the axial displacement, shall be
axial bearing normal range.
pads and 2. Check the lube oil quality/cleanness to
return lube ensure that is no impurities in oil.
3. Check turbine inlet lube oil temperatur, shall
be normal range.
4. Check bearing pads temperatur, shall be
normal range.
Higher/lower level in 1. Check any leakage at oil tank and lube oil
mail oil tank pipe line when the oil level is lower.
2. Check any water leakage in oil coolers.
Lowering vacuum of 1. Check the exhaust temperatur, should be in
exhaust normal range.
2. Check the vacuum braker and accident blow
valve are working well.
3. Check inlet steam pressure to gland sealing
20 of 32
REV
1. Inform to Boiler operator and electrical that steam turbine will be stoped.
2. Reduce generator load to minimal load (± 2 MW), reducing rate 0,3 – 0,5
MW/minuts.
3. Monitor some parameters, vibration, displacement
4. Maintance the water balance, so daerator not over flow
5. Keep condenser vacuum is -0,06 Mpa by adjusting steam ejector.
6. Maintaince Steam temperatur gland sealing is high enough to avoid
negative expansion difference.
7. Open syncrone the generator
8. Shut down turbine by push ‘stop button’ at woodward 505.
9. Ensure AC electric oil pump runing, auto if the lube oil pressure is 0,04
Mpa. ( if auto not runing, put swich on manual and start)
10. All valve extraction will automaticaly closed
11. Close steam valve to surge tank
12. Close steam to ejector system
13. Close main steam isolation valve
14. Close main steam header valve
15. Open all drain valve of main steam inlet pipe of turbine
16. Open all drain valve of main steam line.
17. Stop condensate pump
18. Cooling tower fan stop
19. Make sure that turning gear is runing after turbine rotor rotation
completely stop. Turning gear will operation for 8-10 hours until the rotor
is cold.
20. Open drain valve of surge tank
21. Open drain valves of extraction #1, extraction #2, extraction #3 and
turbine drain valve.
22. LP Heater – open darin valve, close steam valve to condenser and close
condensate valve to condensor
23. HP Heater – open darin valve, close steam valve to condenser and close
condensate valve to deaerator
24. After turning gear stoped than electric oil pump shall stoped.
25. Oil tank fan still runing and stop after 24 hours
26. Stop cooling tower pump
The relationship between the feeding steam quantity of the steam turbine and
the electricity generation power shall be offered as the attached drawings,
it drew when the generator efficiency is 96.5% at rated steam inlet
pressure, rated steam temperature and rated backpressure of turbine.
And various correction curves with the change of inlet steam pressure,
inlet steam temperature and extraction pressure shall be offered the also.
In the practical application, not only revise the steam feeding quantity and power
according to the variation of the steam feeding pressure, temperature,
back pressure of the different operating mode of variation, but also revise
the power to the efficiency variation of different load in relationship
between the power and the efficiency of the generator. The relationship
22 of 32
REV
between the inlet flow and pressure after Curtis stage offered is only for
reference in operation.
23 of 32
REV
24 of 32
REV
Status
No Parameter
Not OK
Communication facilities should be ready, boiler operator,
1 turbine operator, electrical section and instrument
section should be easy to commonication
Prepare tools and meters from instrument, electric,
2
mechanical that ready to application
All equipments shall be inspected in detail and it is ensured
that the installation is completed. The turbine
3
generator set’s accessory equipments and the floor
around are clean.
All instrumentation sensors/meters had been installed,
callibrated and tested, shuch as temperatur sensor,
4
pressure sensor, vibration sensor, speed sensor
and displacement
Oil system
a. Oil tank level > 100 mm
b. Exhaust oil fan shall be normal
c. condition/ready to operation
d. Lubricating oil filter is clean
e. Control oil filter is clean
5 f. HP oil pump and valves is ready to
operation
g. AC electric pump and valves ready to
operation
h. DC oil pump and valves ready to
operation
i. Oil shall be equivalent to ISO-VG-46 a
and cleanness is maximal NAS 9
Cooling system
a. Cooling tower basin level is +10 cm
from NWL
6 b. Circulating water pumps and valves are
ready to operation
c. Cooling tower fans are ready to
operation
25 of 32
REV
Cooler systeam
A. Oil cooler system
a.Oil cooler and valves are ready to operation
1.4.
b.No oil leaking
7
B.Air cooler system
a.Oil cooler and valves are ready to operation
Expantion tank
1.15. 13 a. Expantion tank ready to operation
b. All inlet valve close position
Steam pipe line turbine section
1.16. 14
a. Isolation motor valve try to operation
26 of 32
REV
27 of 32
REV
POINT SETTING
NO
DESCRIPTIONS TAG NO. ALARM
.
H L
A Main Steam
1 Alarm of inlet main steam low pressure 21PI22_L <= 46 bar
2 Alarm of inlet main steam high pressure 21PI22_H >= 51 bar
3 Alarm of inlet main steam low temperature 21TI20_L <= 455 ⁰C
4 Alarm of inlet main steam high temperature 21TI20_H >= 480 ⁰C
5 Main stop valve close position 28ZS201
<= -
6
Alarm of Turbine Exhaust low pressure 28PS204A 0.07MPa
7 Shut down of Turbine Exhaust lower pressure 28PS204B
8 Alarm - 1 of Turbine Exhaust high temperaure 23TI02_H1 >= 100 ⁰C
9 Alarm - 2 of Turbine Exhaust high temperaure 23TI02_H2 >= 65 ⁰C
10 Alarm of turbine casing high differential temperature ∆23TI01_H ∆ 50 ⁰C
B Hot Well Condensor Water
<=
1
Alarm low - 1 of hotwell water level low alarm 22LI01_L +200mm
2 Alarm low - 2 of hot well water level lower alarm 22LI01_LL
3 Alarm high - 1 of hotwell water level high alarm 22LI01_H >=+550 mm
4 Alarm high - 2 of hot well water level higher alarm 22LI01_HH
5 hot well water level 22LI01 <= 400 mm
<= 0.2
6
Alarm of outlet condensor pump low pressure 22PI03_L MPa
C Extraction Valve
28 of 32
REV
<= 101
1
Alarm of Surge tank low pressure 23PI10_L kPa
>= 127.5
2
Alarm of Surge tank high pressure 23PI10_H kPa
3 Alarm of Surge tank low temperature 23TI10_L <= 190 ⁰C
11 Alarm of front bearing Lub. oil high temp._Turbine 29TI10_H >= 65°C
29 of 32
REV
12 Alarm of back bearing Lub. oil high temp._Turbine 29TI11_H >= 65°C
13 Alarm of front bearing Lub. oil high temp._Generator 29TI12_H >= 65°C
14 Alarm of back bearing Lub. oil high temp._Generator 29TI13_H >= 65°C
15 Shutdown of front bearing Lub. oil high temp._Turbine 29TI10_HH
16 Shutdown of back bearing Lub. oil high temp._Turbine 29TI11_HH
Shutdown of front bearing Lub. oil high
17
temp._Generator 29TI12_HH
Shutdown of back bearing Lub. oil high
18
temp._Generator 29TI13_HH
I Bearing Bush Temperature
1 Alarm of front bearing high temperature _ turbine 29TI03_H >= 85°C
2 Alarm of back bearing high temperature _ turbine 29TI04A/B_H >= 85°C
3 Alarm of front bearing high temperature _ generator 29TI05A/B_H >= 85°C
4 Alarm of back bearing high temperature _ generator 29TI06_H >= 85°C
5 Shutdown of front bearing high temperature _ turbine 29TI03_HH
1 Alarm of thrust pad high temperature _ turbine 29TI14A ~ J_H >= 85°C
2 Shutdown of thrust pad high temperature _ turbine 29TI14A ~ J_HH
K TSI
>= 3240
1 Alarm of turbine over speed 27SI251H
(8%) rpm
30 of 32
REV
L 505 DEH
1 Alarm at 505E governor control 505 ALARM
2 Shut down at 505E governor control 505 TRIP
505_SHUTDOW
3
Manual Emergency Push Button 505 N
M Generator & Cooling
Alarm of inlet air cooler for generator high
1
temperature 24TI05 >= 40°C
2 Alarm of Generator winding high temperature 29TI01A ~ F_H >= 80°C
3 Alarm of Generator core high temperature 29TI02A ~ F_H >= 80°C
4 Generator breaker protection action or trip position 28ZS203-DCS-C
N Cooling Water
1 Alarm of Inlet cooling water high temperature 03TI04_H >= 33°C
<= 0.17
2
Alarm of Inlet cooling water low pressure 03PI07_L MPa
O ETS For Turbine Shutdown
1 ETS Active for Turbine ETS_ACTIVED
2 Manual Emergency Push Button - Turbine PB_ETS
P Interlock From Boiler
1 Boiler Trip / MFT MFT_ACTIVED
2 Manual Emergency Push Button - Boiler PB_MFT
32 of 32
REV
K
TSI
>=
Shut down at turbine overspeed 3330
27SI251HH
(mechanical) (111%
1 ) rpm
3300
Shut down at turbine overspeed
(110%
(electrical)
)
Shut down of rotor axial >= 0.7
2 1.0 s
displacement 27ZI252HH mm
>= 70
3 1.0 s
Shut down of bearing vibration 27XI253HH um
L 505 DEH
2 Shut down at 505 DEH 505 TRIP OPENED
Manual Emergency Push Button 505 505_SHUTDOW
3
DEH N OPENED
O Manual Turbine Shutdown
Manual Emergency Push Button -
1
Turbine PB_ETS OPENED
33 of 32
JOB NO. : 97-8207
.
DOC. NO. :
CHD
DATE
APPD
BY