Introduction To Surveying PDF
Introduction To Surveying PDF
Surveying – Introduction
Introduction to Surveying
Surveying is the art of determining the relative positions of different objects on the surface and
below the surface of the earth by measuring the horizontal and vertical distances between them
and by preparing a map to any suitable scale. Thus in discipline, the measurements are taken in
the horizontal plane alone.
Levelling is the art of determining the relative vertical distances of different points on the surface
of the earth. Therefore, in levelling, the measurements are taken only in the vertical plane.
Objective of surveying
The aim of surveying is to prepare a plan or map to show the relative positions of the objects on
the surface of the earth. The map is drawn to some suitable scale .It shows the natural features of
a country such as towns, villages, roads, railways, rivers, etc. Maps may also include details of
different engineering works, such as roads, railways, irrigation, canals, etc.
Uses of surveying
To prepare a topographical map which shows the hills, valleys, rivers, villages, towns, forests
,etc. of a country.
To prepare a cadastral map showing the boundaries of fields, houses, and other properties.
To prepare an engineering map showing details of engineering works such as roads, railways,
reservoirs, irrigation canals, etc.
To prepare a military map showing the road and railway communications with different parts of
a country. Such a map also shows the different strategic points important for the defence of a
country.
To prepare a contour map to determine the capacity of reservoir and to find the best possible
route for roads, railways, etc.
Surveying
The practice of measuring angles and distances on the ground so that they can be accurately
plotted on a map
2. To locate a new station by at least two measurements (linear or angular) from fixed reference
points.
According to the first principle, the whole area is first enclosed by main stations (i.e. controlling
stations) and main survey lines (i.e. controlling lines). The area is then divided into a number of
parts by forming well conditioned triangles. A nearly equilateral triangle is considered to be the
best well-conditioned triangle. The main survey lines are measured very accurately with a
standard chain. Then the sides of the triangles are measured. The purpose of this process of
working is to prevent accumulation of error. During this procedure, if there is any error in the
measurement of any side of a triangle, then it will not affect the whole work. The error can
always be detected and eliminated.
But, if the reverse process (i.e. from the part to the whole) is followed, then the minor
errors in measurement will be magnified in the process of expansion and stage will come
when these errors will become absolutely uncontrollable.
According to the second principle, the new stations should always be fixed by at least two
measurements (linear or angular) from fixed reference points. Linear measurements refer to
horizontal distances measured by chain or tape. Angular measurements refer to the magnetic
bearing or horizontal angle taken by a prismatic compass or theodolite.
In chain surveying, the positions of main stations and directions of main survey lines and
check lines.
CLASSIFICATION OF SURVEYING
Generally, surveying is divided into two major categories: plane and geodetic surveying.
PLANE SURVEYING is a process of surveying in which the portion of the earth being surveyed
is considered a plane. The term is used to designate survey work in which the distances or areas
involved are small enough that the curvature of the earth can be disregarded without significa nt
error. In general, the term of limited extent. For small areas, precise results may be obtained with
plane surveying methods, but the accuracy and precision of such results will decrease as the area
surveyed increases in size. To make computations in plane surveying, you will use formulas of
plane trigonometry, algebra, and analytical geometry.
A great number of surveys are of the plane surveying type. Surveys for the location and
construction of highways and roads, canals, landing fields, and railroads are classified under
plane surveying. When it is realized that an arc of 10 mi is only 0.04 greater that its subtended
chord; that a plane surface tangent to the spherical arc has departed only about 8 in. at 1 mi from
the point of tangency; and that the sum of the angles of a spherical triangle is only 1 sec greater
than the sum of the angles of a plane triangle for a triangle having an area of approximately 75 sq
mi on the earth’s surface, it is just reasonable that the errors caused by the earth’s curvature be
considered only in precise surveys of large areas.
In this training manual, we will discuss primarily the methods used in plane surveying rather
than those used in geodetic surveying.
GEODETIC SURVEYING is a process of surveying in which the shape and size of the earth are
considered. This type of survey is suited for large areas and long lines and is used to find the
precise location of basic points needed for establishing control for other surveys. In geodetic
surveys, the stations are normally long distances apart, and more precise instruments and
surveying methods are required for this type of surveying than for plane surveying. The shape of
the earth is thought of as a spheroid , although in a technical sense, it is not really a spheroid. In
1924, the convention of the International Geodetic and Geophysical Union adopted 41,852,960 ft
as the diameter of the earth at the equator and 41,711,940 ft as the diameter at its polar axis. The
equatorial diameter was computed on the assumption that the flattening of the earth caused by
gravitational at traction is exactly 1/297. Therefore, distances measured on or near the surface of
the earth are not along straight lines or planes, but on a curved surface. Hence, in the
computation of distances in geodetic surveys, allowances are made for the earth’s minor and
major diameters from which a spheroid of reference is developed. The position of each geodetic
station is related to this spheroid. The positions are expressed as latitudes (angles north or south
of the Equator) and longitudes (angles east or west of a prime meridian) or as northings and
castings on a rectangular grid.
Classifications of Surveying
Based on the purpose (for which surveying is being conducted), Surveying has been classified
into:
• Control surveying :
• Land surveying :
To determine the boundaries and areas of parcels of land, also known as property survey,
boundary survey or cadastral survey.
• Topographic survey :
To prepare a plan/ map of a region which includes natural as well as and man-made features
including elevation.
• Engineering survey :
To collect requisite data for planning, design and execution of engineering projects. Three broad
steps are
1) Reconnaissance survey :
2) Preliminary survey :
To collect adequate data to prepare plan/map of area to be used for planning and design.
3) Location survey :
To set out work on the ground for actual construction/execution of the project.
•Route survey :
To plan, design, and laying out of route such as highways, railways, canals,pipelines, and other
linear projects.
Construction surveys :
Surveys which are required for establishment of points, lines,grades, and for staking out
engineering works (after the plans have been prepared and the structural design has been done).
•Astronomic surveys :
To determine the latitude, longitude (of the observation station) and azimuth (of a line through
observation station) from astronomical observation.
•Mine surveys :
To carry out surveying specific for opencast and underground mining purposes
SPECIAL SURVEYS
As mentioned earlier in this chapter, SPECIAL SURVEYS are conducted for a specific purpose
and with a special type of surveying equipment and methods. A brief discussion of some of the
special surveys familiar to you follows.
establish the exact location, boundaries, or subdivision of a tract of land in any specified area.
This type of survey requires professional registration in all states. Presently, land surveys
generally consist of the following chores:
1. Establishing markers or monuments to define and thereby preserve the boundaries of land
belonging to a private concern, a corporation, or the government.
3. Rerunning old land survey lines to determine their lengths and directions. As a result of the
high cost of land, old lines are re-measured to get more precise measurements.
5. Calculating areas, distances, and directions and preparing the land map to portray the survey
data so that it can be used as a permanent record.
CONTROL SURVEYS provide "basic control" or horizontal and vertical positions of points to
which supplementary surveys are adjusted. These types of surveys (sometimes termed and
traverse stations and the elevations of bench marks. These control points are further used as
References for hydrographic surveys of the coastal waters; for topographic control; and for the
control of many state, city, and private surveys.
Lesson 3. Chain Surveying
The principle of chain surveying is triangulation. This means that the area to be surveyed is
divided into a number of small triangles which should be well conditioned. In chain surveying
the sides of the triangles which should be well conditioned. In chain surveying the sides of the
triangles are measured directly on the field by chain or tape, and no angular measurements are
taken. Here, the tie lines and check lines control the accuracy of work.
It should be noted that plotting triangles requires no angular measurements to be made, if the
three sides are known.
For example,
For example,
A map having an RF of less than 1/500 is considered to be large-scale. A map of RF more than
1/500 is said to be small-scale.
A triangle is said to be well-conditioned when no angle in it is less than 30 0 or greater than 1200 .
An equilateral triangle is considered to be the best-condition or ideal triangle
Well-conditioned triangles are preferred because their apex points are very sharp and can be
located by a single ‘dot’. In such a case, there is no possibility of relative displacement of the
plotted point.
A triangle in which an angle is less than 30 0 or more than 1200 is said to be ill-conditioned
Well - conditioned triangles are not used in chain surveying. This is because their apex points are
not sharp and well defined, which is why a slight displacement of these points may cause
considerable error in plotting.
Before the commencement of any survey work, the area to be surveyed is thoroughly examined
by the surveyor, who then thinks about the possible arrangement of the framework of survey.
This primary investigations of the area is termed as reconnaissance survey or reconnoitre.
During reconnaissance survey, the surveyor should walk over the area and note the various
obstacles and whether or not the selected stations are intervisible. The main stations should be so
selected that they enclose the whole area. The surveyor should also take care that
The neat hand sketch of the area which is prepared during reconnaissance survey is known as the
‘index sketch’ or ‘key plan’. The index sketch shows the skeleton of the survey work. It indicates
the main survey stations, sub-stations, tie stations, base line, arrangement for framework of
triangles and the approximate positions of different objects. This sketch is an important
document for the surveyor and for the person who will plot the map. It should be attached to the
starting page of the field book
A. Survey Stations
Survey stations are the points at the beginning and the end of a chain line. They may also occur
at any convenient points on the chain line. Such stations may be:
1. Main stations
3. Tie stations
2. Main stations Stations taken along the boundary of an area as controlling points
are known as ‘main survey lines’. The main survey lines should cover the whole
area to be surveyed. The main stations are denoted by ‘ ’ with letters A, B, C, D,
etc. The chain lines are denoted by “__ … __ ... __...__...__...__”.
3. Subsidiary stations Stations which are on the main survey lines or any other
survey lines are known as “Subsidiary stations”. These stations are taken to run
subsidiary lines for dividing the area into triangles, for checking the accuracy of
triangles and for locating interior details. These stations are denoted by ‘’ with
letters S1 ,S2 ,S3 , etc.
4. Tie stations These are also subsidiary stations taken on the main survey lines.
Lines joining the tie stations are known as tie lines. Tie lines are mainly taken to
fix the directions of adjacent sides of the chain survey map. These are also taken
to form ‘chain angles’ in chain traversing, when triangulation is not possible.
Sometimes tie lines are taken to locate interior details. Tie stations are denoted by
‘’ with letters T 1, T2, T3. Etc.
B. Base Line
The line on which the framework of the survey is built is known as the ‘base line’. It is the most
important line of the survey. Generally, the longest of the main survey lines is considered the
base line. This line should be taken through fairly level ground, and should be measured very
carefully and accurately. The magnetic bearings of the base line are taken to fix the north line of
the map.
C. Check Line
The line joining the apex point of a triangle to some fixed point on its base is known as the
‘check line’. It is taken to check the accuracy of the triangle. Sometimes this line helps to locate
interior details.
D. Offset
The lateral measurement taken from an object to the chain line is known as ‘offset’. Offsets are
taken to locate objects with reference to the chain line. They may be of two kinds -
perpendicular and oblique.
1. Perpendicular offsets When the lateral measurements are taken perpendicular to the chain
line, they are known as perpendicular offsets
(a) By setting a perpendicular by swinging a tape from the object to the chain line. The point of
minimum reading on the tape will be the base of the perpendicular
(c) By setting a right angle with the help of builder’s square or tri-square
Suppose AB is a chain line and p is the corner of a building. Two points ‘a’ and ‘b’ are taken on
the chain line. The chainages of ‘a’ and ‘b’ are noted. The distances ‘ap’ and ‘bp’ are measured
and noted in the field book. Then ‘ap’ and ‘bp’ are the oblique offsets. When the triangle abp is
plotted, the apex point p will represent the position of the corner of the the building.
3. Number of offsets The offsets should be taken according to the nature of the object. So, there
is no hard and fast rule regarding the number of offsets. It should be remembered that the
objects are to be correctly represented and hence the number of offsets should be decided on the
field. Some guidelines are given below:
(a) When the boundary of the object is approximately parallel to the chain line, perpendicular
offsets are taken at regular intervals
(b) When the boundary is straight, perpendicular offsets are taken at both ends of it
(c) When the boundary line is zigzag, perpendicular offsets are taken at every point of bend to
represent the shape of the boundary accurately. In such a case, the interval of the offsets may be
irregular
(d) When a road crosses the chain line perpendicularly, the chainage of the intersection point is
to be noted
(e) When a road crosses a chain line obliquely, the chainages of intersection points ‘a’ and ‘b’
are noted. Then at least one offset is taken on both sides of the inter-section points. More offsets
may be taken depending on the nature of the road. Here, perpendicular offsets are taken at ‘c’
and ‘d’
(f) When the building is small, its corners are fixed by perpendicular or oblique offsets and the
other dimensions are taken directly on the field and noted in the field book.
(g) When the building is large, zigzag in shape and oblique to the chain line, then the corners are
fixed by perpendicular or oblique offsets. Then the full plan of the building is drawn on a
separate page along with all the dimensions. This page should be attached with the field book at
the proper place.
(h) When the object is circular, perpendicular offsets are taken at short and regular intervals
4. Limiting length of offset The maximum length of the offset should not be more than the
length of the tape used in the survey. Generally, the maximum length of offset is limited to 15m.
However, this length also depends upon the following factors:
(c) The maximum allowable deflection of the offset from its true direction and
Problem 1 An offset was laid out 5 0 from its true direction and the scale of the map was 20 m to
1 cm. Find the maximum length of offset for the displacement of a point on the paper not to
exceed 0.03 cm.
Solution Let AB be the actual length of offset which was laid out 50 from its true direction. So,
BC is the displacement of the point.
= 6.884 m
Therefore, the maximum length of offset should be 6.884 m.
Problem 2 The length of the offset is 15 m and the scale of the plan 10 m to 1 cm. If the offset
is laid out 30 from its true direction, find the displacement of the plotted point on the paper
Solution Let AB be the actual length of offset, which is 15 m long and deflected by 3 0 from its
true direction.
Here,
(i) CD = AD – AC = AB - AC
= 15 – 15 cos 30
E. Degree of Accuracy
Degree of accuracy is determined before the starting of any survey work. It is worked out
according the following factors:
(a) Scale of plotting
During reconnaissance survey, the length of the main survey lines are approximately determined
by the pacing method. One pace or walking step of a man is considered to equal 80 cm. When
the length of the survey lines or the extent of area to be surveyed is approximately known, the
scale of the map may be assumed. Again, the permissible error in plotting may be obtained from
the concerned department. Then the degree of accuracy in measurement is ascertained.
Suppose the scale of plotting is 5 m to 1 cm and the allowable error is 0.02 cm.
The following points should be remembered during the selection of survey stations:
1. The stations should be so selected that the general principle of surveying may be
strictly followed.
3. The stations should be selected in such a way that well-conditioned triangles may be
formed.
4. The base line should be the longest of the main survey lines.
5. The survey lines should be taken through fairly level ground, as far as practicable.
6. The main survey lines should pass close to the boundary line of the area to be
surveyed.
7. The survey lines should be taken close to the objects so that they can be located by
short offsets.
8. The tie stations should be suitably selected to fix the directions of adjacent sides.
9. The subsidiary stations should be suitably selected for taking check lines.
10. Stations should be so selected that obstacles to chaining are avoided as far as
possible.
11. The survey lines should not be very close to main roads, as survey work may then be
interrupted by traffic.
2. Arrows = 10 nos.
5. Offset rod = 1 no
6. Clinometer = 1 no
11. Mallet = 1 no
The notebook in which field measurements are noted is known as the ‘field book’. The size of
the field book is 20 cm x 12 cm and it opens lengthwise. Field books may be of two types:
2. Double-line.
1. Single-line field book In this type of field book, a single red line is drawn through the middle
of each page. This line represents the chain line, and the chainages are written on it. The offsets
are recorded, with sketches, to the left or right of the chain line. The recording of the field book
is started from the last page and continued towards the first page. The main stations are marked
by ‘’ and subsidiary stations or tie stations are by ‘’
2. Double-line field book In this type of field book, two red lines, 1.5 cm apart, are drawn
through the middle of each page. This column represents the chain line, and the chainages are
written in it. The offsets are recorded, with sketches, to the left or right of this column. The
recording is begun from the last page and continued towards the first. The main stations are
marked by ‘’ and subsidiary or tie stations by ‘’ This type of field book is commonly used.
Problem 1 While measuring a chain line AB, the following offsets are taken. How would you
enter the field book ?
(a) A telegraph post is 10 m perpendicularly from chainage 2.5 m to the right of the chain line.
(b) A road crosses obliquely from left to right at chainage 10 m and 14 m. Perpendicular offsets
are 2m and 3m to the side of the road from chainage 5m and 20 m respectively.
(c) A tube-well is 5m perpendicularly from chainage 30 m to the left of the chain line.
Problem 2 The base line AC of a chain survey is measured and the following records are noted.
Make the necessary entries in a field book.
(a) The corners of a building are 9 and 9,5m from chainage 7.5 and 18 m to the left of the chain
line. The building is 7m wide.
(b) A 4 m wide road runs about parallel to the right of the chain line. Offsets are 2,2.1,2.2, and
2.15m at chainages 0,20,40, and 55.5m respectively.
(c) A check line is taken from the sub-station at chainage 25 m to the left.
(e) The fore bearing and back bearing of the base line are 30 030’ and 21003C’ respectively.
Problem 3 Enter the field book according to the following field notes:
(b) The offsets to the pond at the left of chain line are as follows:
Chainage – 10,15,20,25,30 m
Offset – 16,12,10,14,20 m
(c) The offsets to the river at the right of the chain line are :
Chainage – 5,25,40,80 m
Offset -13,17,19,19.5m
2. Each chain line should be recorded on a separate page. Normally it should start from the
bottom of one page and end on the top of another. No line should be started from any
intermediate position.
6. Reference sketches should be given in the field book, so that the station can be located when
required.
8. If an entry is incorrect or a page damaged, cancel the page and start the entry from a new one.
10. The surveyor should face the direction of chaining so that the left-hand and right-hand
objects can be recorded without any confusion.
Field work of chain survey should be carried out according to the following steps:
1.Reconnaissance
Before starting survey work, the surveyor should walk over the whole area to be surveyed in
order to examine the ground and determine the possible arrangement of framework of survey.
During this investigation, he should examine the intervisibility of the main survey stations. He
should ensure that the whole area is enclosed by main survey lines, and also that it is possible to
form well-conditioned triangles. He should observe various objects and boundary lines carefully
and select the survey lines in such a manner that the objects can be located by short offsets. The
base line should preferably be taken through the centre of the area and on fairly level ground.
2.Index sketch
After preliminary inspection of the area, the surveyor should prepare a neat hand sketch showing
the arrangement of the framework and approximate position of the objects. He should note the
names of the stations on the sketch maintaining some order (clockwise or anticlockwise). The
field work should be executed according to this index sketch. The names and sequence of chain
lines should be followed as directed in the index sketch. The ‘base line’ should be clearly
indicated in the index sketch.
After reconnaissance, the stations are marked on the ground by wooden pegs. These pegs are
generally 2.5 cm square and 15 cm long, and have pointed ends. They are driven into the ground
firmly, and there should be a height of 2.5 cm above the ground. The station point is marked with
a cross so that it can be traced if the wooden peg is removed by somebody
4. Reference sketches
To take precautions against station pegs being removed or missed, a reference sketch should be
made for all main stations. It is nothing but a hand sketch of the station showing at least two
measurements from some permanent objects. A third measurement may also be taken
5.Taking measurements of survey lines and noting them in the field book
Ranging and chaining is started from the base line, which should be measured carefully. The
magnetic bearings of the base line are measured by prismatic compass. These measurements are
noted in the field book showing the offsets to the left or right according to their position. Then
the other survey lines are ranged and chained maintaining the sequence of the traverse. The
offsets and other field records are noted simultaneously. The check lines and tie lines are also
measured and noted at the proper place. The station marks are preserved carefully until field
work is completed.
In a map the objects are shown by symbols and not by names. So the surveyor should know the
following standard conventional symbols for some common objects.
4. Protractor
6. Instrument box
7. French curve
8. Offset scale
1. A suitable scale is chosen so that the area can be accommodated in the space available on the
map.
2. A margin of about 2 cm from the edge of the sheet is drawn around the sheet.
4. The north line is marked on the right-hand top corner, and should preferably be vertical. When
it is not convenient to have a vertical north line, it may be inclined to accommodate the whole
area within the map.
5. A suitable position for the base line is selected on the sheet so that the whole area along with
all the objects it contains can be drawn within the space available in the map.
6. The framework is completed with all survey lines, check lines and tie lines. If there is some
plotting error which exceeds the permissible limit, the incorrect lines should be resurveyed.
7. Until the framework is completed in proper form, the offsets should not be plotted.
8. The plotting of offsets should be continued according to the sequence maintained in the field
book.
9. The main stations, substations, chain line, objects, etc. should be shown as per standard
symbols
10. The conventional symbols used in the map should be shown on the right-hand side.
11. The scale of the map is drawn below the heading or in some suitable space. The heading
should be written on the top of the map.
The inking should be begun from the left-hand-side towards the right-hand-side, and from the
top towards the bottom.
A. Cross-staff
The cross-staff is a simple instrument for setting out right angles. There are three types of cross-
staves.
1. Open
2. French
3. Adjustable
Open cross-staff
The open cross-staff consists of four metal arms with vertical slits. The two pairs of arms (AB
and BC) are at right angles to each other. The vertical slits are meant for sighting the object and
the ranging rods. The crossstaff is mounted on a wooden pole of length 1.5m and diameter 2.5
cm. The pole is fitted with an iron shoe.
For setting out a perpendicular on a chain line, the cross-staff is held vertically at the
approximate position. Suppose slits A and B are directed to the ranging rods (R, R 1) fixed at the
end stations. Slits C and D are directed to the object (O). Looking through slits A and B, the
ranging rods are bisected. At the same time, looking through slits C and D, the object O is also
bisected. To bisect the object and the ranging rods simultaneously, the cross staff may be moved
forward or backward along the chain line
B. Optical Square
An optical square is also used for setting out right angles. It consist of a small circular metal box
of diameter 5 cm and depth 1.25 cm. It has a metal cover which slides round the box to cover the
slits. The following are the internal arrangements of the optical square.
1. A horizon glass H is fixed at the bottom of the metal box. The lower half of the glass is
unsilvered and the upper half is silvered.
2. A index glass I is also fixed at the bottom of the box which is completely silvered.
3. The angle between the index glass and horizon glass is maintained at 45 0.
4. The opening ‘e’ is a pinhole for eye E, ‘b’ is a small rectangular hole for ranging rod B, ‘P’ is
a large rectangular hole for object P.
6. The horizon glass is placed at an angle of 120 0 with the horizon sight. The index glass is
placed at an angle of 105 0 with the index sight.
7. The ray of light from P is first reflected from I, then it is further reflected from H, after which
it ultimately reaches the eye E
Principle
According to the principle of reflecting surfaces, the angle between the first incident ray and the
last reflected ray is twice the angle between the mirrors. In this case, the angle between the
mirrors is fixed at 450. So, the angle between the horizon sight and index sight will be 90 0.
1. The observer should stand on the chain line and approximately at the position
where the perpendicular is to be set up.
2. The optical square is held by the arm at the eye level. The ranging rod at the
forward station B is observed through the unsilvered portion on the lower part
of the horizon glass.
3. Then the observer looks through the upper silvered portion of the horizon glass
to see the image of the object P.
4. Suppose the observer finds that the ranging rod B and the image of object P do
not coincide. The he should move forward or backward along the chain line
until the ranging rod B and the image of P exactly coincide
5. At this position the observer marks a point on the ground to locate the foot of
the perpendicular.
… … … … …
A P B
Lesson 4. COMPASS TRAVERSING
In chain surveying, the area to be surveyed is divided into a number of triangles. This method is
suitable for fairly level ground covering small areas. But when the area is large, undulating and
crowded with many details, triangulation (which is the principle of chain survey) is not possible.
In such an area, the method of traversing is adopted.
In traversing, the framework consists of a number of connected lines. The lengths are measured
by chain or tape and the directions identified by angle measuring instruments. In one of the
methods, the angle measuring instrument used is the compass. Hence, the process is known as
compass traversing.
4.2 DEFINITIONS
1.True meridian The line or plane passing through the geographical north pole, geographical
south pole and any point on the surface of the earth, is known as the ‘true meridian’ or
‘geographical merdian’. The true meridian at a station is constant. The true meridians passing
through different points on the earth’s surface are not parallel, but converge towards the poles.
But for surveys is small areas, the true meridians passing through different points are assumed
parallel.
The angle between the true meridian and a line is known as ‘true bearing’ of the line. It is also
known as the ‘azimuth’.
2. Magnetic meridian When a magnetic needle is suspended freely and balanced properly,
unaffected by magnetic substances, it indicates a direction. This direction is known as the
‘magnetic meridian’.
The angle between the magnetic meridian and a line is known as the ‘magnetic bearing’ or
simply the ‘bearing’ of the line
3. Arbitrary meridian Sometimes for the survey of small area, a convenient direction is
assumed as a meridian, known as the ‘arbitrary meridian’. Sometimes the starting line of a
survey is taken as the arbitrary meridian.
The angle between the arbitrary meridian and a line is known as the ‘arbitrary bearing’ of the
line.
4. Grid meridian Sometimes, for preparing a map some state agencies assume several lines
parallel to the true meridian for a particular zone. These lines are termed as ‘grid lines’ and the
central line the ‘grid meridian’. The bearing of a line with respect to the grid meridian is known
as the ‘grid bearing’ of the line.
5. Designation of magnetic bearing Magnetic bearings are designated by two systems :
(a) Whole Circle Bearing (WCB) The magnetic bearing of a line measured clockwise from the
north pole towards the line, is known as the ‘whole circle bearing’, of that line. Such a bearing
may have any value between 0 0 and 3600. The whole circle bearing of a line is obtained by
prismatic compass
For example,
WCB of AB = θ1
WCB of AC = θ2
WCB of AD = θ3
WCB of AE = θ4
For example, QB of AB = N
6. Reduced bearing (RB) When the whole circle bearing of a line is converted to quadrantal
bearing. It is termed the ‘reduced bearing’. Thus, the reduced bearing is similar to the quadrantal
bearing. Its value lies between 0 0 and 900, but the quadrants should be mentioned for proper
designation.
7. Fore and back bearing The bearing of a line measured in the direction of the progress of
survey is called the ‘fore bearing’ (FB) of the line.
The bearing of a line measured in the direction opposite to the survey is called the ‘back bearing’
(BB) of the line
For example, FB of AB = θ
BB of AB = θ1
(a) In the WCB system, the difference between the FB and BB should be exactly 180 0, and the
negative sign when it is more than 180 0. Remember the following relation:
BB = FB ± 1800
Use the positive sign when FB is less than 180 0, and the negative sign when it is more than 180 0.
(b) In the quandrantal bearing (i.e. reduced bearing) system, the FB and B3 are numerically
equal but the quadrants are just opposite.
8. Magnetic declination The horizontal angle between the magnetic meridian and true meridian
is known as ‘magnetic declination’.
When the north end of the magnetic needle is pointed towards the west side of the true meridian,
the position is termed ‘Declination West’ ().
When the north end of the magnetic needle is pointed towards the east side of the true meridian,
the position is termed ‘Declination East’
9. Isogonic and agonic lines Lines passing through points of equal declination are known as
‘isogonic’ lines.
The Survey of India Department has prepared a map of India in which the isogonic and agonic
lines are shown properly as a guideline to conduct the compass survey in different parts of the
country.
10. Variation of magnetic declination The magnetic declination at a place is not constant. It
varies due to the following reasons:
(a) Secular Variation The magnetic meridian behaves like a pendulum with respect to the true
meridian. After every 100 years or so, it swings from one direction to the opposite direction, and
hence the declination varies. This variation is known as ‘secular variation’.
(b) Annual Variation The magnetic declination varies due to the rotation of the earth, with its
axis inclined, in an elliptical path around the sun during a year. This variation is known as
‘annual variation. The amount of variation is about 1 to 2 minutes.
(c) Diurnal Variation The magnetic declination varies due to the rotation of the earth on its own
axis in 24 hours. This variation is known as ‘dirunal variation’. The amount of variation is found
to be about 3 to 12 minutes.
(d) Irregular Variation The magnetic declination is found to vary suddenly due to some natural
causes, such as earthequakes, volcanic eruptions and so on. This variation is known as ‘irregular
variation’.
11. Dip of the magnetic needle If a needle is perfectly balanced before magnetisation, it does
not remain in the balanced position after it is magnetised. This is due to the magnetic influence
of the earth. The needle is found to be inclined towards the pole. This inclination of the needle
with the horizontal is known as the ‘dip of the magnetic needle’.
It is found that the north end of the needle is deflected downwards in the northern hemisphere
and that is south end is deflected downwards in the southern hemisphere. The needle is just
horizontal at the equator. To balance the dip of the needle, a rider (brass or silver coil) is
provided along with it. The rider is placed over the needle at a suitable position to make it
horizontal.
12. Local attraction A magnetic needle indicates the north direction when freely suspended or
pivoted. But if the needle comes near some magnetic substances, such as iron ore, steel
structures, electric cables conveying current; etc. it is found to be deflected from its true
direction, and does not show the actual north. This disturbing influence of magnetic substances is
known as ‘local attraction’.
To detect the presence of local attraction, the fore and back bearings of a line should be taken. If
the difference of the fore and back bearings of the line is exactly 180 0, then there is no local
attraction.
If the FB and BB of a line do not differ by 1800, then the needle is said to be affected by local
attraction, provided there is no instrumental error.
To compensate for the effect of local attraction, the amount of error is found out and is equally
distributed between the fore and back bearings of the line.
Observed FB of AB = 60 030’
(a) First Method The interior angles of a traverse are calculated from the observed bearings.
Then an angular check is applied. The sum of the interior angles should be equal to (2n – 4) x
900 (n being the number of sides of the traverse). If it is not so, the total error is equally
distributed among all the angles of the traverse.
Then, starting from the unaffected line, the bearings of all the lines may be corrected by using
the corrected interior angles. This method is very laborious and is not generally employed.
(b) Second Method In this method, the interior angles are not calculated. From the given table,
the unaffected line is first detected. Then, commencing from the unaffected line, the bearings of
the other affected lines are corrected by finding the amount of correction at each station.
This is an easy method, and one which is generally employed.
Note: If all the lines of a traverse are found to be affected by local attraction, the line with
minimum error is identified. The FB and BB of this line are adjusted by distributing the error
equally. Then, starting from this adjusted line, the fore and back bearing of other lines are
corrected.
The principle of compass surveying is traversing, which involves a series of connected lines. The
magnetic bearings of the lines are measured by prismatic compass and the distances of the lines
are measured by chain. Such survey does not require the formation of a network of triangles.
Interior details are located by taking offsets from the main survey lines. Sometimes subsidiary
lines may be taken for locating these details.
Compass surveying is not recommended for areas where local attraction is suspected due to the
presence of magnetic substances like steel structures, iron ore deposits, electric cables conveying
current, and so on.
4.4 TRAVERSING
As already stated in the last section, surveying which involves a series of connected lines is
known as ‘traversing.’ The sides of the traverse are known as ‘traverse legs’.
In traversing, the lengths of the lines are measured by chain and the directions are fixed by
compass or theodolite or by forming angles with chain and tape.
1. Closed traverse When a series of A connected lines forms a closed circuit, i.e. when the
finishing point coincides with the starting point coincides with the starting point of a survey, it is
called a ‘closed traverse’. Here ABCDEA represents a closed traverse. Closed traverse is
suitable for the survey of boundaries of ponds, forests estates, etc.
2. Open traverse When a sequence of connected lines extends along a general direction and
does not return to the starting point, it is known as ‘open traverse’ or ‘unclosed traverse’. Here
ABCDE represents an open traverse
Open traverse is suitable for the survey of roads, rivers, coast lines, etc.
1.Chain traversing Chain traversing is mainly conducted when it is not possible to adopt
triangulation. In this method, the angles between adjacent sides are fixed by chain angles. The
entire survey is conducted by chain and tape only and no angular measurements are taken. When
it is not possible to form triangles, as, for example, in a pond, chain traversing is conducted,
(a) First Method Suppose a chain angle is to be formed to fix the directions of sides AB and
AD. Tie stations T 1 and T2 are fixed on lines AB and AD. The distances AT 1, AT2 and T1T2 are
measured. Then the angle T1AT2 is said to be the chain angle. So, the chain angle is fixed by the
tie line T1T2.
(b) Second Method Sometimes the chain angle is fixed by chord. Suppose the angle between the
lines AB and AC is to be fixed. Taking A as the centre and a radius equal to one tape length (15
m), an arc intersecting the lines AB and AC at points P and Q, respectively, is drawn. The chord
PQ is measured and bisected at R.
The angle θ can be calculated from the above equation, and the chain angle BAC can be
determined accordingly.
2. Compass traversing In this method, the fore and back bearings of the traverse legs are
measured by prismatic compass and the sides of the traverse by chain or tape. Then the observed
bearings are verified and necessary corrections for local attraction are applied. In this method,
closing error may occur when the traverse is plotted. This error is adjusted graphically by using
‘Bowditch’s rule’ (which is described later on).
3. Theodolite traversing In such traversing, the horizontal angles between the traverse legs are
measured by theodolite. The lengths of the legs are measured by chain or by employing the
stadia method. The magnetic bearing of the starting leg is measured by theodolite. Then the
magnetic bearings of the other sides are calculated. The independent coordinates of all the
traverse stations are then found out. This method is very accurate.
4. Plane table traversing In this method, a plane table is set at every traverse station in the
clockwise or anticlockwise direction, and the circuit is finally closed. During traversing, the sides
of the traverse are plotted according to any suitable scale. At the end of the work, any closing
error which may occur is adjusted graphically.
(a) The sum of the measured interior angles should be equal to (2N – 4) x 900 where N is the
number of sides of the traverse.
(b) The sum of the measured exterior angles should be equal to (2N + 4) x 90 0.
(c) The algebraic sum of the deflection angles should be equal to 360 0.
(a) The lines should be measurement once each on two different days (along opposite directions).
Both measurements should tally.
(b) Linear measurements should also be taken by the stadia method. The measurements by
chaining and by the stadia method should tally.
In open traverse, the measurements cannot be checked directly. But some field measurements
can be taken to check the accuracy of the work. The methods are discussed below.
1. Taking cut-off lines Cut-off lines are taken between some intermediate stations of the open
traverse. Suppose ABCDEF represents an open traverse. Let AD and DG be the cut-off lines.
The lengths and magnetic bearings of the cut-off lines are measured accurately. After plotting the
traverse, the distances and bearings are noted from the map. These distances and bearings should
tally with the actual records from the field
(a) Compass Box The compass box is a circular metallic box (the metal should be non-
magnetic) of diameter 8 to 10 cm. A pivot with a sharp point is provided at the centre of the box.
(b) Magnetic Needle and Graduated Ring The magnetic needle is made of a broad, magnetised
iron bar. The bar is pointed at both ends. The magnetic needle is attached to a graduated
aluminium ring.
The ring is graduated from 00 to 3600 clockwise, and the graduations begin from the south end of
the needle. Thus 00 is marked at the south, 90 0 at the west, 1800 at north and 270 0 at the east. The
degrees are again subdivided into half-degrees. The figures are written upside down. The
arrangement of the needle and ring contains an agate cap pivoted on the central pivot point. A
rider of brass or silver coil is provided with the needle to counterbalance its dip.
(c) Sight Vane and Prism The sight vane and the reflecting prism are fixed diametrically
opposite to the box. The sight vane is hinged with the metal box and consists of a horsehair at the
centre. The prism consists of a sighting slit at the top and two small circular holes, one at bottom
of the prism and the other at the side of the observer’s eye.
(d) Dark Glasses Two dark glasses are provided with the prism. The red glass is meant for
sighting luminous objects at night and the blue glass for reducing the strain on the observer’s eye
in bright daylight.
(e) Adjustable Mirror A mirror is provided with the sight vane. The mirror can be lowered or
raised, and can also be inclined. If any object is too low or too high with respect to the line of
sight, the mirror can be adjusted to observe it through reflection.
(f) Brake Pin A brake pin is provided just at the base of the sight vane. If pressed gently, it stops
the oscillations of the ring.
(g) Lifting Pin A lifting pin is provided just below the sight vane. When the sight vane is folded,
it presses the lifting pin. The lifting pin then lifts the magnetic needle out of the pivot point to
prevent damage to the pivot head.
(h) Glass Cover A glass cover is provided on top of the box to protect the aluminium ring from
dust
2. The Surveyor’s compass The surveyor’s compass is similar to the prismatic compass except
for the following points.
(a) There is no prism on it. Readings are taken with naked eye.
(b) It consists of an eye-vane (in place of prism) with a fine sight slit.
(c) The graduated aluminium ring is attached to the circular box. It is not fixed to the magnetic
needle.
(d) The magnetic needle moves freely over the pivot. The needle shows the reading on the
graduated ring.
(e) The ring is graduated from 0 0 to 900 in four quadrants. 00 is marked at the north and south,
and 900 at the east and west. The letters E (east) and W (west) are interchanged from their true
positions. The figures are written the right way up.
The following procedure should be adopted while measuring the bearing by prismatic compass.
1. Fixing the compass with tripod stand The tripod stand is placed at the required
station with its legs well apart. Then the prismatic compass is held by the left hand
and placed over the threaded top of the stand. After this, the compass box is turned
clockwise by the right hand. Thus the threaded base of the compass box is fixed with
the threaded top of the stand.
2. Centering Normally, the compass is centred by dropping a piece of stone from the
bottom of the compass box. Centring may also be done with the aid of a plumb bob
held centrally below the compass box.
4. Adjustment of prism: the prism is moved up and down till the figures on the
graduated ring are seen sharp and clear.
5. Observation of bearing: After centering and leveling the compass box over the
station, the ranging rod at the required station is bisected perfectly by sighting
through the slit of the prism and horsehair at the sight vane.
At this time the graduated ring may rotate rapidly. The brake pin is pressed very gently to stop
this rotation. When the ring comes to rest, the box is struck very lightly to verify the
horizontality of the ring and the frictional effect on the pivot point. Then the reading is taken
from the graduated ring through the hole in the prism. This reading will be magnetic bearing of
the line.
Lesson 5. Errors In Chain Surveying
Chain survey is the simplest method of surveying. It is the exercise of physically measuring
horizontal distances. In this method the lengths of lines marked on the field are measured, while
the details are measured by offsets and ties from these lines. This field work will continue for 3
field hours. This is most suitable adapted to small plane areas with very few details.
In general, the distance measurement obtained in the field will be in error. Errors in the distance
measurement can arise from a number of sources:
1. Instrument errors:
2. Natural errors.
The actual horizontal distance between the ends of the tape can vary due to the effects of
temperature,
sagging.
3. Personal errors.
1. poor alignment
3. improper plumbing
Errors in Chaining: - The errors that occur in chaining are classified as (i) Compensating, (ii)
Cumulative. These errors may be due to natural causes such as say variation in temperature,
defects in construction and adjustment of the instrument, personal defects in vision etc.
Compensating Errors:- The compensating errors are those which are liable to occur in either
direction and hence tend to compensate i.e. they are not likely to make the apparent result too
large or too small.
Fractional parts of the chain or tape may not be correct if the total length of the chain is adjusted
by insertion or removal of a few connection rings from one portion of the chain, or tape is not
calibrated uniformly throughout its length.
During stepping operation crude method of plumbing (such as dropping of stone from the end of
chain) is adopted.
When chain angles are set out with a chain which is not uniformly adjusted or with a
combination of chain and tape.
Cumulative Errors: - The cumulative errors are those which occur in the same direction and
tend to add up or accumulate i.e. either to make the apparent measurement always too long or too
short.
Positive errors (making the measured lengths more than the actual) are caused by the following:-
The length of the chain or tape is shorter than the standard, because of bending of links, removal
of too many links in adjusting the length, ‘knots’ in the connecting links, cloggings of rings with
clay, temperature lower than that at which the tape was calibrated, shrinkage of tape when
becoming wet.
The slope correction is not applied to the length measured along the sloping ground.
The sag correction is not applied when the tape or the chain is suspended in the air.
The tape bellys out during offsetting when working in the windy weather.
Negative errors (making the measured lengths less than the actual) may be caused because the
length of the tape or chain may be greater than the standard because of the wear or flattening of
the connecting rings, opening of ring joints, temperature higher than the one at which it was
calibrated.
compensating errors which are proportional to √L, where L is the length of the line.
Illustration: - Suppose a line 1280 m in length is measured with a 20 m chain which is 0.02 m
too long, and error in marking a chain length is say ±0.03 m.
Mistakes in Chaining: - The mistakes are generally avoidable and cannot be classed under any
law of probability. The following mistakes are commonly made by inexperienced chainmen.
Displacement of arrows: - When the arrow is displaced, it may not be replaced accurately. To
guard against this mistake, the end of each chain length should be marked both by the arrow and
by a cross (+) scratched on the ground.
Failure to observe the position of the zero point of the tape: - The chainmen should see
whether it is at the end of the ring or on the tape.
Adding or omitting a full chain or tape length (due to wrong counting or loss of arrows): -
This is the most serious mistake and should be guarded against. This is not likely to occur, if the
leader has the full number (ten) of arrows at the commencement of chaining and both the leader
and follower count them at each transfer. A whole tape length may be dropped, if the follower
fails to pick up the arrow at the point of beginning.
Reading from the wrong end of the chain: - e.g. reading 10 m for 20 m in a
30 m chain, or reading in the wrong direction from a tally, e.g. reading 9.6 m for 10.4 m. The
common mistake in reading a chain is to confuse 10 m tag with 20 m tag. It should be avoided
by noticing the 15 m tag.
Reading numbers incorrectly: - Transposing figures e.g.37.24 for 37.42 or reading tape upside
down, e.g. 6 for 9, or 36 for 98.
To guard against this mistake, the chainmen should call out the measurements loudly and
distinctly, and the surveyor should repeat them as he books them.
Correction for absolute length, (ii) Correction for temperature, (iii) Correction for tension or pull,
(iv) Correction for sag, and (v) Correction for slope or vertical alignment.
A correction is said to be plus or positive when the uncorrected length is to be increased, and
minus or negative when it is to be decreased in order to obtain true length.
Correction for Absolute Length: - It is the usual practice to express the absolute length of a
tape as its nominal or designated length plus or minus a correction. The correction for the
measured length is given by the formula,
Ca = Lc / l ------------------- (1)
The sign of the correction (Ca) will be the same as that of c. it may be noted that L and l must be
expressed in the same units and the unit of C a is the same as that of c.
Correction for Temperature: - It is necessary to apply this correction, since the length of a tape
is increased as its temperature is raised, and consequently, the measured distance is too small. It
is given by the formula,
Ct = a (T m – To)L-----------(2)
Correction for Pull (or Tension): - The correction is necessary when the pull used during
measurement is different from that at which the tape is standardized. It is given by the formula,
Cp = (P-Po)L / AE ----------(3)
Po= the pull under which the tape is standardized in newtons (N).
The value of E for steel may be taken as 19.3 to 20.7 x 1010 N/m2 and that for invar 13.8 to 15.2
x 1010 N/m2 . For every precise work its value must be ascertained. The sign of the correction is
plus, as the effect of the pull is to increase the length of the tape and consequently, to decrease
the measured length of the line.
Correction for Sag: - (Fig.1). When a tape is stretched over points of support, it takes the form
of a catenary. In actual practice, however, the catenary curve is
assumed to be a parabola. The correction for sag (or sag correction) is the difference in length
between the arc and the subtending chord (i.e., the difference between the horizontal distance
between supports and the length measured along the curve). It is required only when the tape is
suspended during measurement. Since the effect of the set on the tapes is to make the measured
length too great this correction is always subtractive. It is given by the formula,
If there are n equal spans per tape length, the sag corrections per tape length is given, by
Normal Tension: - The normal tension is a tension at which the effects of pull and sag are
neutralized, i.e. the elongation due to increase in tension is balanced by the shortening due to
sag. It may be obtained by equating the corrections for pull and sag. Thus we have,
Correction for Slope or Vertical Alignment: - (Fig 2) This correction is required when the
points of support are not exactly at the same level.
lt1, lt2 etc. = the differences in height between the extremities of each of these
slopes.
If l is the length of any one slope, and h the difference in height between the ends of the
slope,
the slope correction = l - √ l2 -h2
This correction is always subtractive from the measured length. If the slopes are given in terms
of vertical angles (plus or minus angles), the following formula may be used:
Examples 1: - A line was measured with a steel tape which was exactly
30m long at 18oC and found to be 452.343 m. The temperature during measurement
was 32oC. Find the true length of the line. Take coefficient of expansion of the
tape per oC=0.0000117.
= α (Tm - To) l
α = 0.0000117
~ Ct = 0.0000117 (32-18) 30
= 0.004914 m (+ ve)
= 30 + 0.004914 = 30.004914 m.
Temperature
= 0.00351 m (+ ve)
= 0.00357 m (+ve)
= 0.00708 m
= 459.350 m.
= 50 – 0.0206
= 49.9794 m.
Example 4: - The downhill end of the 30 m tape is held 80 cm too low. What is the horizontal
length?
Here h = 0.8 m; l = 30 m
= 29.9833 m
Example 5: - A 100 m tape is held 1.5 m out of line. What is the true length?
Chain survey is the simplest method of surveying. It is the exercise of physically measuring
horizontal distances. In this method the lengths of lines marked on the field are measured, while
the details are measured by offsets and ties from these lines. This field work will continue for 3
field hours. This is most suitable adapted to small plane areas with very few details.
Tape Corrections: - Precise measurements of distance is made by means of a steel tape 30 m or
50 m in length. Before use it is desirable to ascertain its actual length (absolute length) by
comparing it with the standard of known length, which can be done for a small fee by the Survey
and Standards department. It is well to note here the distinction between the nominal or
designated length and absolute length of a tape. By the former is meant it’s designated length,
e.g. 30 m, or 100 m, while by the latter is meant it’s actual length under specified
conditions. The tape may be standardized when supported horizontally throughout its full length
or in catenary. The expression that “a tape is standard at a certain temperature and under a
certain pull” means that under these conditions the actual length of the tape is exactly equal to its
nominal length. Since the tape is not used in the field under standard conditions it is necessary to
apply the following corrections to the measured length of a line in order to obtain its true length:
Correction for absolute length, (ii) Correction for temperature, (iii) Correction for tension or pull,
(iv) Correction for sag, and (v) Correction for slope or vertical alignment.
Correction for Absolute Length: - It is the usual practice to express the absolute length of a
tape as its nominal or designated length plus or minus a correction. The correction for the
measured length is given by the formula,
Ca = Lc / l ------------------- (1)
The sign of the correction (Ca) will be the same as that of c . it may be noted that L and l must be
expressed in the same units and the unit of C a is the same as that of c.
Correction for Temperature: - It is necessary to apply this correction, since the length of a tape
is increased as its temperature is raised, and consequently, the measured distance is too small. It
is given by the formula,
Ct = a (T m – To)L-----------(2)
in which Ct = the correction for temperature, in m.
Correction for Pull (or Tension): - The correction is necessary when the pull used during
measurement is different from that at which the tape is standardized. It is given by the formula,
Cp = (P-Po)L / AE ----------(3)
Po= the pull under which the tape is standardized in newtons (N).
The value of E for steel may be taken as 19.3 to 20.7 x 10 10 N/m2 and that for invar 13.8 to 15.2
x 1010 N/m2 . For every precise work its value must be ascertained. The sign of the correction is
plus, as the effect of the pull is to increase the length of the tape and consequently, to decrease
the measured length of the line.
Correction for Sag: - (Fig.1). When a tape is stretched over points of support, it takes the form
of a catenary. In actual practice, however, the catenary curve is assumed to be a parabola.
The correction for sag (or sag correction) is the difference in length between the arc and the
subtending chord (i.e., the difference between the horizontal distance between supports and the
length measured along the curve). It is required only when the tape is suspended during
measurement. Since the effect of the set on the tapes is to make the measured length too great
this correction is always subtractive. It is given by the formula,
If there are n equal spans per tape length, the sag corrections per tape length is given, by
Normal Tension: - The normal tension is a tension at which the effects of pull and sag are
neutralized, i.e. the elongation due to increase in tension is balanced by the shortening due to
sag. It may be obtained by equating the corrections for pull and sag. Thus we have,
lt1, lt2 etc. = the differences in height between the extremities of each of these
slopes.
If l is the length of any one slope, and h the difference in height between the ends of the
slope,
This correction is always subtractive from the measured length. If the slopes are given in terms
of vertical angles (plus or minus angles), the following formula may be used:
Examples 1: - A line was measured with a steel tape which was exactly 30m long at 18oC and
found to be 452.343 m. The temperature during measurement was 32oC. Find the true length of
the line. Take coefficient of expansion of the tape per oC=0.0000117.
Temperature correction per tape length = Ct
= α (Tm - To) l
α = 0.0000117
~ Ct = 0.0000117 (32-18) 30
= 0.004914 m (+ ve)
= 30 + 0.004914 = 30.004914 m.
Example 2: - A line was measured with a steel rape which was exactly 30 m at 18 oC and a pull
of 50 N and the measured length was 459.242 m. Temperature during measurement was 28oC
and the pull applied was 100 N. The tape was uniformly supported during the
measurement. Find the true length of the line if the cross-sectional area of the tape was 0.02
cm2, the coefficient of expansion
o 6
per C = 0.0000117 and the modulus of elasticity = 21 x 10 N per cm .2
Temperature
= 0.00351 m (+ ve)
= 0.00357 m (+ve)
= 0.00708 m
True length of tape = 30.00708 m
= 459.350 m.
Example 3: - A 50 m tape is suspended between the ends under a pull of 150 N. The mass of
the tape is 1.52 kilograms. Find the corrected length of the tape.
= 50 – 0.0206
= 49.9794 m.
Example 4: - The downhill end of the 30 m tape is held 80 cm too low. What is the horizontal
length?
Here h = 0.8 m; l = 30 m
= 29.9833 m
Example 5: - A 100 m tape is held 1.5 m out of line. What is the true length?
Plane table surveying is a graphical method of surveying in which the field works and the
plotting is done simultaneously. It is particularly adopting in small areas mapping. Plane
table surveying is used for locating the field computation of area of field.
Merits
It is most suitable for preparing small scale map or surveying small area.
It is particularly suitable for magnetic area where prismatic compass is not reliable.
It is less costly.
Demerits
There are several accessories to be carried out and therefore they are likely to be lost.
Plane Table essentially consists of a Drawing board mounted on tripod stand and Alidade.
A sheet of drawing paper, called plane table sheet is fastened to the board. Board is made up of
well seasoned wood such as teak of size 40x30 to 75x60cm. it had plane and smooth top. It is
mounted on a tripod in manner that it can be leveled. Leveling up of the table is done by shifting
the legs of tripod. Some tripod provided with leveling screw or by ball and socket head for
accurate leveling.
2. Alidade:
Alidade consists of two vertical sight vane fitted at end the end of straightedge. The straight edge
ruler usually made of brass or teak wood graduated beloved edge. One of the sight veins is
provided with narrow slit and the other with a central vertical wire or hair. Beveled working edge
alidade is called fiducial edge.
1. Trough compass
5. Drawing sheet
6. Pencil or eraser
U- frame or Plumbing fork: U frame with a plumb bob used for centering the table.
Water Proof Cover: Water Proof cover protects the sheet from rain.
Spirit level or level tube: A level tube is used to level the plane table.
Drawing sheet: The drawing sheet is fixed on the top of the drawing board.
Pencil and eraser: A pencil is used for constructing lines and eraser is used for erasing lines after
completion of the plan.
The setting up the plane table includes the following three operations.
The table should be set up at a convenient height for working say about 1m. The legs of tripod
should be spread well apart and firmly fixed in to the ground. The table should be approximately
leveled by tripod legs and judging by the eye. Then the operation of centering is carried out by
means of U-frame and plumb bob. The plane table is exactly placed over the ground station by
U-frame and plumb bob.
The process of leveling is carried out with the help of level tube. The bubble of level tube is
brought to center in two directions, which are right angles to each other. This is achieved by
moving legs.
The process of keeping the plane table always parallel to the position, which is occupied at the
first station, is known as orientation. When the plane table is oriented, the lines on the board are
parallel to the lines on the ground
Lesson 8. Radiation, Intersection and traversing
1.Radiation method
2. Intersection method
3. Traversing method
1.RADIATION METHOD
The plane table is set up over only one station from which the whole traverse can be
commanded. It is suitable for survey of small areas.
Procedure:
1) Select a point “O ” so that all points to be located are visible from it.
3) SELECT A POINT “O” on the sheet so that it is exactly over station “O” on
6) Measure the distances OA, OB, OC and OD and plotted to convenient scale to locate a, b, c
and d respectively
In this method the plane table is shifted to a known distance in a particular direction marked on
the ground and the line of sights are drawn to make intersection of the radial lines already drawn
from the first set up of the instrument.
PROCEDURE:
1) Select two points P and Q such that the points (building corners) to be plotted are visible from
their stations.
6) Pivot ‘P’ bisects the inaccessible objects A and B (building corners) and draw rays.
7) Shift the table to ‘A’ such that P is over Q and do temporary adjustments.
8) Place the alidade along QP and the rotate the table till P is bisected, clamp table.
10) The instruction of rays drawn from P and Q will give the points A and B.
11) To check the accuracy measured AB and compare with plotted distance AB.
12) The same procedure is applied for other features of the campus. each point is bisected from
two stations.
Fig. 7.2 Intersection method
3.TRAVERSE METHOD
We can traverse an area with the plane table along the boundry to prepare the map or plan of the
area.
PROCEDURE:
adjustments.
6) Measure the distance AB and locate ‘b’ on the sheet with a suitable scale.
7) Shift the table to next station B, set the table over B, and do temporary adjustments.
8) Place the alidade along ‘ba’ and bisect A for doing orientation of plane table.
10) Measure the distance BC and locate ‘c’ on the sheet with the suitable scale.
11) Report the same procedure at every successive station until the traverse is completed.
NOTE: By using radiation method, intersection and traversing methods we can locate the
points on the paper, which were already on the ground. By using algebraic formulae, we
can calculate the area of the given land.
FORMULAE:
4) Area of a trapezium = ½ * (a + b) * h
The art of determining relative altitudes of points on the surface of the earth of beneath the
surface of earth is called LEVELLING.
b) REDUCED LEVEL (RL) – Height or depth of a point above or below the assumed datum is
called Reduced level.
c) BENCH MARK – (BM) – B.M. is a fixed reference point of known elevation. It may be of
the following types.
ii) Permanent Bench Mark : They are fixed points of reference establish with reference to GTS
Bench mark (10 km. interval).
iii) Arbitrary Bench mark : These are reference points whose elevations are arbitrarily
assumed. In most of Engineering projects, the difference in elevation is more important than
their reduced levels with reference to MSL as given in a special catalogue known as GTS Maps (
100 Km. interval).
d) Mean Sea Level (M.S.L.) : M.S.L. is obtained by making hourly observations of the tides at
any place over a period of 19 years. MSL adopted by Survey of India is now Bombay which was
Karachi earlier.
e) Level Surface : The surface which is parallel to the mean sphereoidal surface of the earth is
known as level surface.
f) Line of Collimation : It is the line joining the intersection of the cross hair and the optical
center of the objective and its extensions, it is also called line of sight or collimation.
g) Height of Instrument (HI) : The elevation of the line of sight with respect to assumed datum
is known as height of Instrument(HI).
h) Back sight : (B.S.) - The first sight taken on a levelling staff held at a point of known
elevation. B.S. enables the surveyor to obtain HI +sight i.e. Height of Instrument or line of sight.
i) Fore Sight : (F.S.) – It is the last staff reading taken from a setting of the level. It is also
termed as minus sight.
Fore sight is the sight taken on a levelling staff held at a point of unknown elevation to ascertain
the amount by which the point is above or below the line of sight. This is also called minus sight
as the foresight reading is always subtracted from height of Instrument.
j) Change Point (CP) : The point on which both the foresight and back sight are taken during the
operation of levelling is called change point.
It may be noted that for one setting of a level, there will be only one back sight and one foresight
but there can be any number of intermediate sights.
Dumpy level : It is simple compact and stable. The telescope is rigidly fixed to its support
therefore cannot be rotated about its longitudinal axis. A long bubble tube is attached to the top
of telescope. Dumpy literally means short and thick.
Tilting level : It consists of a telescope attached with a level tube which can be tilted within few
degrees in vertical plane by a tilting screw. The main peculiarity of this level is that the vertical
axis need not be truly vertical, since the line of collimation is not perpendicular to it. The line of
collimation, is, however, made horizontal for each pointing of telescope by means of tilting
screw. It is mainly designed for precise levelling work.
The Automatic level : Also termed as self aligning level. The fundamental difference between
automatic and the classic spirit level is that in the former the line of sight is no longer levelled
manually using a tubular spirit level, but is levelled automatically within a certain tilt
range. This is achieved by compensator in the telescope.
DUMPY LEVEL
It is simple compact and stable. The telescope is rigidly fixed to its support therefore cannot be
rotated about its longitudinal axis. A long bubble tube is attached to the top of
telescope. Dumpy literally means short and thick.
Fig 9.1 Dumpy level
(a)Telescope
(b) Eye-piece
(c) focussing knob
(h) diaphragm
TELESCOPE : Telescope is an optical instrument used for magnifying and viewing the images
of distant objects. It consists of two lenses. The lens fitted near the eye is called the eye piece
and the other fitted at the end near to the object is called the objective lens. The objective
provides a real inverted image infront of the eye piece at a distance lesser than its focal distance.
Two essential conditions are involved. :
i) The real image of the object, must be formed.
ii) the plane of image must coincide with that of cross hairs.
Focusing of Telescope : The operation of obtaining a clear image of the object in the plane of
cross hairs is known as focusing.
1. Diaphram : A frame carrying cross hairs usually made of either silk thread or platinum wire
and placed at the plane at which vertical image of the object is formed by the objective. Vertical
hair of the diaphram enables the surveyor to check the verticality of levelling staff whereas
horizontal hairs are used to read the staff graduations.
2. Level Tube : Also known as Bubble Tube consists of a glass tube placed in a brass tube
which is sealed with plaster of paris. The whole of the interior surface or the upper half is
accurately ground so that its longitudinal section, is an arc of a circle. Level tube is filled with
either or alcohol, the remaining space is occupied by an air bubble. The centre of air bubble
always rest at the highest point of the tube. Outer surface of the bubble tube is graduated in both
the directions from the centre. The line tangential to the circular are at its highest point i.e. the
middle of tube is called the axis of bubble tube. When the bubble is central the axis of bubble
becomes Horizontal. The level tube is attached on the top of Telescope by means of capstan
headed nuts.
3. Levelling head : Levelling head generally consists of two parallel plates with 3 foot
screws. Upper plate is known as Tribrach and lower plate is trivet which can be screwed on to
the tripod. Levelling head has to perform three distinct functions :
i) to support the telescope
ii) to attach the level to the tripod
iii) to provide a means for level (foot screws)
Adjustments of level :
(i) Temporarily Adjustments – adjustments which are made for every setting of a level.
(ii) Permanent adjustments- required if some error is there in instrument.
(i) Temporary Adjustments : includes
a) setting up the level
b) levelling up
c) elimination of parallax
a) Setting up the level : This operation includes fixing the instrument on the tripod and also
approximate levelling by leg adjustment.
b) Levelling up : Accurate levelling is done with the help of foot screws and by using plate
levels. The object of levelling up the instrument is to make its vertical axis truly vertical.
c) Elimination of parallax : If the image formed by the objective does not lie in the plane of the
cross hairs, there will be a shift in the image due to shift of the eye. Such displacement of image
is termed as parallax. Parallax is removed in two stages.
1) Focusing the eye for distinct vision of cross hairs.
2) Focusing the objective so that image is formed in the plane of cross hairs.
Levelling staff
It is an important accessory used with levelling instrument at the time of conducting levelling
survey. Reading is taken on the levelling staff held properly at the point concerned by viewing
through the telescope of the levelling instrument. Usually 4 m levelling staff may be used of
folding type or telescopic type. Aluminium levelling staff foldable at every metre length has also
came to the market. The levelling staff consists of three pieces. The topmost one slides into the
middle one and the middle portion slides into the bottom one. When the staff is fully pulled, it
will read exactly 40 decimeters (4m) from the bottom shoe.
The divisions are painted in black and white alternately of thickness 5 mm each.
The number indicating metre is in red and the decimeter number is in black.
The graduation are made continuously one above the other in the same line.
The division lines should be parallel to the base of the bottom shoe and perpendicular to
the length of the staff.
The graduation colour paints used should not crack or blister when exposed to adverse or
atmospheric conditions.
Lesson 10. Simple levelling and fly levelling methods
The art of determining relative altitudes of points on the surface of the earth of beneath the
surface of earth is called LEVELLING.
Adjustments of level :
(i) Temporarily Adjustments – adjustments which are made for every setting of a level.
(ii) Permanent adjustments- required if some error is there in instrument.
(i) Temporary Adjustments : includes
a) setting up the level
b) levelling up
c) elimination of parallax
a) Setting up the level : This operation includes fixing the instrument on the tripod and also
approximate levelling by leg adjustment.
b) Levelling up : Accurate levelling is done with the help of foot screws and by using plate
levels. The object of levelling up the instrument is to make its vertical axis truly vertical.
c) Elimination of parallax : If the image formed by the objective does not lie in the plane of the
cross hairs, there will be a shift in the image due to shift of the eye. Such displacement of image
is termed as parallax. Parallax is removed in two stages.
1) Focusing the eye for distinct vision of cross hairs.
2) Focusing the objective so that image is formed in the plane of cross hairs.
Principles of levelling :
a) Simple levelling : The operation of levelling for determining the difference in elevation, if
not too great between two points visible from single position of the level is known as simple
levelling.
Fig 10.1 Simple levelling
Procedure to be followed
3. Take the reading of Central, horizontal hair of the diaphram, where it appears to cut the
staff ensuring that the bubble is central.
6. Check up the bubble if central, if not bring it to the Central position by the foot screw
nearest to the telescope.
This method is used in order to find the difference in elevation between two points.
i) If they are too far apart
ii) if the difference in elevation between them is too great.
iii) If there are obstacles intervening. In such case it is necessary to set up the level in several
positions and to work in series of stages.
The difference of level of the points A&B is equal to the algebraic sum of these difference
between the sum of back sights and sum of the fore sights i.e. Σ BS - Σ FS.
= 100.00+1.60-1.10 = 100.50 m
= 100.50+1.25 = 101.75 m
foresight at Q
The staff readings of the points observed from the same setting of the instrument are
compared.
If the point is below the preceding point, the staff reading will be greater than that at the
preceding point. The difference between the staff readings is termed fall.
The difference between the staff readings at P and Q = 2.10 – 1.80 = 0.30 (rise)
1.245 100.00 BM
STATION
2.425 0.810 1.290 100.435
A
STATION
0.480 1.945 102.380
B
In this method, the height of the instrument is established for each setting of the instrument and
the reduced level of the new point is arrived by detecting the fore sight reading of that point.
Lesson 11. Contours- Introduction
The art of determining relative altitudes of points on the surface of the earth of beneath the
surface of earth is called LEVELLING.
A contour is defined as an imaginary line of constant elevation on the ground surface. It can also
be defined as the line of intersection of a level surface with the ground surface. For example, the
line of intersection of the water surface of a still lake or pond with the surrounding ground
represents a contour line.
Definition:
A line joining points of equal elevations is called a contour line. It facilitates depiction of the
relief of terrain in a two dimensional plan or map.
Characteristics of contour:
The principal characteristics of contour lines which help in plotting or reading a contour map are
as follows:
1. The variation of vertical distance between any two contour lines is assumed to be
uniform.
2. The horizontal distance between any two contour lines indicates the amount of slope and
varies inversely on the amount of slope. Thus, contours are spaced equally for uniform
slope
3. The steepest slope of terrain at any point on a contour is represented along the normal of
the contour at that point. They are perpendicular to ridge and valley lines where they
cross such lines.
5. Contours of different elevations cannot cross each other (caves and overhanging cliffs are
the exceptions).
6. Contours of different elevations cannot unite to form one contour (vertical cliff is an
exception).
8. A contour line must close itself but need not be necessarily within the limits of the map.
9. A closed contour line on a map represents either depression or hill . A set of ring contours
with higher values inside, depicts a hill whereas the lower value inside, depicts a
depression (without an outlet).
10. Contours deflect uphill at valley lines and downhill at ridge lines. Contour lines in U-
shape cross a ridge and in V-shape cross a valley at right angles. The concavity in
contour lines is towards higher ground in the case of ridge and towards lower ground in
the case of valley .
Contour Interval:
The vertical distance between any two consecutive contours is known as a contour interval.
For example, if the various consecutive contours are 100m, 98m,96 m etc., then the contour
interval is 2m. This interval depends upon,
Contour intervals for flat country are generally small, eg. 0.25m, 0.5m, 0.75 m etc. For a steep
slope in hilly area is greater, eg. 5m, 10m, 15 m etc.
Again ,for a small-scale map, the interval may be of 1m,2m,3m etc. and for large scale map,it
may be of 0.25m,0.50m,0.75m etc.
It should be remembered that the contour interval for a particular map is constant.
Contouring:
The process of locating these contour lines on the surface of the earth is known as contouring.
Methods of contouring:
1. Direct methods
2. Indirect methods
Direct Method:
In the direct method, the contour to be plotted is actually traced on the ground. Points which
happen to fall on a desired contour are only surveyed, plotted and finally joined to obtain the
particular contour. This method is slow and tedious and thus used for large scale maps, small
contour interval and at high degree of precision.
Vertical control :
In this method, a benchmark is required in the project area. The level is set up on any
commanding position and back sight is taken on the bench mark. Let the back sight reading on
the bench mark be 1.485 m. If the reduced level of the bench mark is 100 m, the height of
instrument would be 100 + 1.485 = 101.485 m.
To locate the contour of 100.5 m value, the staff man is directed to occupy the position on the
ground where the staff reading is 101.485 -100.500 = 0.985 m. Mark all such positions on the
ground where the staff reading would be 0.985 m by inserting pegs. Similarly locate the points
where the staff reading would be 101.485 -101 = 0.485 m for 101m contour.
The contour of 101.5 m cannot be set from this setting of the instrument because the height of
instrument for this setting of the instrument is only 101.485 m. Therefore, locating contours of
higher value, the instrument has to be shifted to some other suitable position.
Establish a forward station on a firm ground and take fore sight on it. This point acts as a point of
known elevation, for shifting the position of the instrument to another position, from where the
work proceeds in the similar manner till the entire area is contoured.
Horizontal control :
The horizontal control is generally provided by method of plane table surveying or locating the
positions of points.
In this method, the spot levels of selected guide points are taken with a level and their levels are
computed. The horizontal positions of these points are measured or computed and the points are
plotted on the plan. The contours are then drawn by a process called interpolation of contours
from the levels of the guide points. The following are the indirect methods are commonly used
for locating contours.
In this method, the area to be surveyed is divided into a grid or series of squares. The grid size
may vary from 5 m x 5 m to 25 m x 25 m depending upon the nature of the terrain, the contour
interval required and the scale of the map desired. Also, the grids may not be of the same size
throughout but may vary depending upon the requirement and field conditions. The grid corners
are marked on the ground and spot levels of these comers are determined by leveling. The grid is
plotted to the scale of the map and the spot levels of the grid corners are entered. The contours of
desired values are then located by interpolation. Special care should be taken to give the spot
levels to the salient features of the ground such as hilltops, deepest points of the depressions, and
their measurements from respective corners of the grids, for correct depiction of the features. The
method is used for large scale mapping and at average precision.
In these sections, a base line, centre line or profile line is considered. Cross sections are taken
perpendicular to this line at regular intervals. After this points are marked along the cross
sections at regular intervals. A temporary bench mark is set up near the site. Staff readings are
taken along the base line and the cross sections. The readings are entered in the level book the
base line and the cross sections should also be mentioned. The RL of each of the points
calculated. Then the base line and cross sections are plotted to a suitable scale. Subsequently
the RLs of the respective points are noted on the map, after which the required contour line is
drawn by interpolation
This method is suitable for route survey, when cross sections are taken transverse to the
longitudinal section.
The process of locating the contours proportionately between the plotted points is termed
interpolation. Interpolation may be done by:
1. Arithmetical calculation
By arithmetical calculation
Let A and B be two corners of the squares. The RL of A is 98.75 m, and that of B 100.75 m. the
horizontal distance between A and B is 10m.
This calculated distance is plotted to the same scale in which the skeleton was plotted to obtain a
point of RL of 99.00 m.
By graphical method
On a sheet of tracing paper, a line AB is drawn and divided into equal parts. AB is bisected at C
and a perpendicular is drawn at this point. A point O is selected on this perpendicular line and
then radial lines are drawn from O to the divisions on AB. After this lines 1-1, 2-2, 3-3….are
drawn parallel to AB. These lines serve as guide lines. Boundary line and every fifth the line is
marked with a thick or red line.
Suppose we have to interpolate a 2m contour between two points a and b of RLs 92.5 and
100.75m.
Let us consider the lowest radial line OB to represent an RL of 90.00. So, every fifth line will
represent 95,100,105, etc. The tracing paper is moved over the plan until ‘a’ lies at 92.5 and ‘b’
at 100.25. Line ‘ab’ should be parallel to AB. Now the points 94, 96, 98,100 are picked through
to obtain the positions of the required contours.
The process of locating the contours proportionately between the plotted points is termed
interpolation. Interpolation may be done by:
1. Arithmetical calculation
By arithmetical calculation
Let A and B be two corners of the squares. The RL of A is 98.75 m, and that of B 100.75 m. the
horizontal distance between A and B is 10m.
This calculated distance is plotted to the same scale in which the skeleton was plotted to obtain a
point of RL of 99.00 m.
By graphical method
On a sheet of tracing paper, a line AB is drawn and divided into equal parts. AB is bisected at C
and a perpendicular is drawn at this point. A point O is selected on this perpendicular line and
then radial lines are drawn from O to the divisions on AB. After this lines 1-1, 2-2, 3-3….are
drawn parallel to AB. These lines serve as guide lines. Boundary line and every fifth the line is
marked with a thick or red line.
Suppose we have to interpolate a 2m contour between two points a and b of RLs 92.5 and
100.75m.
Let us consider the lowest radial line OB to represent an RL of 90.00. So, every fifth line will
represent 95,100,105, etc. The tracing paper is moved over the plan until ‘a’ lies at 92.5 and ‘b’
at 100.25. Line ‘ab’ should be parallel to AB. Now the points 94, 96, 98,100 are picked through
to obtain the positions of the required contours.
Lesson 12. Methods of grid levelling
The art of determining relative altitudes of points on the surface of the earth of beneath the
surface of earth is called LEVELLING.
A contour is defined as an imaginary line of constant elevation on the ground surface. It can also
be defined as the line of intersection of a level surface with the ground surface. For example, the
line of intersection of the water surface of a still lake or pond with the surrounding ground
represents a contour line.
To determine the positions of the contours on a plan the leveling methods are used to find the
relative positions of points on the surface of the ground with reference to certain benchmarks at
regular intervals. This technique of making observations and plotting on a plan is called as grid
leveling.
Contour Interval:
The vertical distance between any two consecutive contours is known as a contour interval. For
example, if the various consecutive contours are 100m, 98m, 96 m etc., then the contour
interval is 2m. This interval depends upon,
Contour intervals for flat country are generally small, eg. 0.25m, 0.5m, 0.75 m etc. For a steep
slope in hilly area is greater, eg. 5m, 10m, 15 m etc.
Again ,for a small-scale map, the interval may be of 1m,2m,3m etc. and for large scale map,it
may be of 0.25m,0.50m,0.75m etc.
It should be remembered that the contour interval for a particular map is constant.
Contouring:
The process of locating these contour lines on the surface of the earth is known as contouring.
Methods of contouring:
1. Direct methods
2. Indirect methods
Direct Method:
In the direct method, the contour to be plotted is actually traced on the ground. Points which
happen to fall on a desired contour are only surveyed, plotted and finally joined to obtain the
particular contour. This method is slow and tedious and thus used for large scale maps, small
contour interval and at high degree of precision.
Vertical control :
In this method, a benchmark is required in the project area. The level is set up on any
commanding position and back sight is taken on the bench mark. Let the back sight reading on
the bench mark be 1.485 m. If the reduced level of the bench mark is 100 m, the height of
instrument would be 100 + 1.485 = 101.485 m.
To locate the contour of 100.5 m value, the staff man is directed to occupy the position on the
ground where the staff reading is 101.485 -100.500 = 0.985 m. Mark all such positions on the
ground where the staff reading would be 0.985 m by inserting pegs. Similarly locate the points
where the staff reading would be 101.485 -101 = 0.485 m for 101m contour.
The contour of 101.5 m cannot be set from this setting of the instrument because the height of
instrument for this setting of the instrument is only 101.485 m. Therefore, locating contours of
higher value, the instrument has to be shifted to some other suitable position.
Establish a forward station on a firm ground and take fore sight on it. This point acts as a point of
known elevation, for shifting the position of the instrument to another position, from where the
work proceeds in the similar manner till the entire area is contoured.
Horizontal control :
The horizontal control is generally provided by method of plane table surveying or locating the
positions of points.
In this method, the spot levels of selected guide points are taken with a level and their levels are
computed. The horizontal positions of these points are measured or computed and the points are
plotted on the plan. The contours are then drawn by a process called interpolation of contours
from the levels of the guide points. The following are the indirect methods are commonly used
for locating contours.
In these sections, a base line, centre line or profile line is considered. Cross sections are taken
perpendicular to this line at regular intervals. After this points are marked along the cross
sections at regular intervals. A temporary bench mark is set up near the site. Staff readings are
taken along the base line and the cross sections. The readings are entered in the level book the
base line and the cross sections should also be mentioned. The RL of each of the points
calculated. Then the base line and cross sections are plotted to a suitable scale. Subsequently
the RLs of the respective points are noted on the map, after which the required contour line is
drawn by interpolation
This method is suitable for route survey, when cross sections are taken transverse to the
longitudinal section.
Lesson 13. Contours- Map preparation
The art of determining relative altitudes of points on the surface of the earth of beneath the
surface of earth is called LEVELLING.
A contour is defined as an imaginary line of constant elevation on the ground surface. It can also
be defined as the line of intersection of a level surface with the ground surface. For example, the
line of intersection of the water surface of a still lake or pond with the surrounding ground
represents a contour line.
In this method, the spot levels of selected guide points are taken with a level and their levels are
computed. The horizontal positions of these points are measured or computed and the points are
plotted on the plan. The contours are then drawn by a process called interpolation of contours
from the levels of the guide points. The following are the indirect methods are commonly used
for locating contours.
In this method, the area to be surveyed is divided into a grid or series of squares. The grid size
may vary from 5 m x 5 m to 25 m x 25 m depending upon the nature of the terrain, the contour
interval required and the scale of the map desired. Also, the grids may not be of the same size
throughout but may vary depending upon the requirement and field conditions. The grid corners
are marked on the ground and spot levels of these comers are determined by leveling. The grid is
plotted to the scale of the map and the spot levels of the grid corners are entered. The contours of
desired values are then located by interpolation. Special care should be taken to give the spot
levels to the salient features of the ground such as hilltops, deepest points of the depressions, and
their measurements from respective corners of the grids, for correct depiction of the features. The
method is used for large scale mapping and at average precision.
In these sections, a base line, centre line or profile line is considered. Cross sections are taken
perpendicular to this line at regular intervals. After this points are marked along the cross
sections at regular intervals. A temporary bench mark is set up near the site. Staff readings are
taken along the base line and the cross sections. The readings are entered in the level book the
base line and the cross sections should also be mentioned. The RL of each of the points
calculated. Then the base line and cross sections are plotted to a suitable scale. Subsequently
the RLs of the respective points are noted on the map, after which the required contour line is
drawn by interpolation
This method is suitable for route survey, when cross sections are taken transverse to the
longitudinal section.
Method of interpolation of contours:
The process of locating the contours proportionately between the plotted points is termed
interpolation. Interpolation may be done by:
1. Arithmetical calculation
By arithmetical calculation
Let A and B be two corners of the squares. The RL of A is 98.75 m, and that of B 100.75 m. the
horizontal distance between A and B is 10m.
This calculated distance is plotted to the same scale in which the skeleton was plotted to obtain a
point of RL of 99.00 m.
By graphical method
On a sheet of tracing paper, a line AB is drawn and divided into equal parts. AB is bisected at C
and a perpendicular is drawn at this point. A point O is selected on this perpendicular line and
then radial lines are drawn from O to the divisions on AB. After this lines 1-1, 2-2, 3-3….are
drawn parallel to AB. These lines serve as guide lines. Boundary line and every fifth the line is
marked with a thick or red line.
Suppose we have to interpolate a 2m contour between two points a and b of RLs 92.5 and
100.75m.
Let us consider the lowest radial line OB to represent an RL of 90.00. So, every fifth line will
represent 95,100,105, etc. The tracing paper is moved over the plan until ‘a’ lies at 92.5 and ‘b’
at 100.25. Line ‘ab’ should be parallel to AB. Now the points 94, 96, 98,100 are picked through
to obtain the positions of the required contours.
The process of locating the contours proportionately between the plotted points is termed
interpolation. Interpolation may be done by:
1. Arithmetical calculation
By arithmetical calculation
Let A and B be two corners of the squares. The RL of A is 98.75 m, and that of B 100.75 m. the
horizontal distance between A and B is 10m.
This calculated distance is plotted to the same scale in which the skeleton was plotted to obtain a
point of RL of 99.00 m.
By graphical method
On a sheet of tracing paper, a line AB is drawn and divided into equal parts. AB is bisected at C
and a perpendicular is drawn at this point. A point O is selected on this perpendicular line and
then radial lines are drawn from O to the divisions on AB. After this lines 1-1, 2-2, 3-3….are
drawn parallel to AB. These lines serve as guide lines. Boundary line and every fifth the line is
marked with a thick or red line.
Suppose we have to interpolate a 2m contour between two points a and b of RLs 92.5 and
100.75m.
Let us consider the lowest radial line OB to represent an RL of 90.00. So, every fifth line will
represent 95,100,105, etc. The tracing paper is moved over the plan until ‘a’ lies at 92.5 and ‘b’
at 100.25. Line ‘ab’ should be parallel to AB. Now the points 94, 96, 98,100 are picked through
to obtain the positions of the required contours.
LESSON 14. Computation of area and volume
The main objective of the surveying is to compute the areas and volumes.
There are formulae readily available for regular polygons like, triangle, rectangle, square and
other polygons.
But for determining the areas of irregular polygons, different methods are used.
Earthwork computation is involved in the excavation of channels, digging of trenches for laying
underground pipelines, formation of bunds, earthen embankments, digging farm ponds, land
levelling and smoothening. In most of the computation the cross sectional areas at different
interval along the length of the channels and embankments are first calculated and the volume of
the prismoids are obtained between successive cross section either by trapezoidal or prismoidal
formula.
a) Mid-ordinate method
c) Trapezoidal rule
d) Simpson’s rule
Consider figure.
h1,h2,……..hn=mid-ordinates
Area = common distance* sum of mid-ordinates
n= number of divisions
While applying the trapezoidal rule, boundaries between the ends of ordinates are assumed to be
straight. Thus the areas enclosed between the base line and the irregular boundary line are
considered as trapezoids.
Let O1, O2, …..On=ordinate at equal intervals, and d= common distance between two ordinates
Total area=d/2{ O1+2O2+2O3+…….+2O n-1+On}
To the sum of the first and last ordinate, twice the sum of intermediate ordinates is added. This
total sum is multiplied by the common distance. Half of this product is the required area.
Limitation: There is no limitation for this rule. This rule can be applied for any number of
ordinates
SIMPSON’S RULE
In this rule, the boundaries between the ends of ordinates are assumed to form an arc of parabola.
Hence simpson’s rule is some times called as parabolic rule. Refer to figure:
Let
Here,
= 2/3* eE*2d
= d/3(O1+4O2+O3)
∆2 = d/3(O1+4O2+O3) and so on
To the sum of the first and the last ordinate, four times the sum of even ordinates and twice the
sum of the remaining odd ordinates are added. This total sum is multiplied by the common
distance. One third of this product is the required area.
Limitation: This rule is applicable only when the number divisions is even i.e. the number of
ordinates is odd.
The trapezoidal rule may be compared in the following manner:
Note: sometimes one or both the end of the ordinates may be zero. However they must be taken
into account while applying these rules.
Problem 1: The following offsets were taken from a chain line to an irregular boundary line at
an interval of 10 m:
Compute the area between the chain line, the irregular boundary line and the end of offsets by:
d) Simpson’s rule
= 10*18.80=188 m2
By average-ordinate rule:
Number of ordinates= 7
Required area=10((1.25+3.00+5.00+4.60+3.20+0)/7)
By trapezoidal rule:
Here d=10m
Required area=10/2{0+0+2(2.50+3.50+5.00+4.60+3.20+)}
= 5*37.60=188 m2
By Simpson’s rule:
d=10m
required area=10/3{0+0+4(2.50+5.00+3.20)+2(3.50+4.60)}
= 10/3{ 42.80+16.20}=10/3*59.00
10/3*59= 196.66m2
Problem 2: The following offsets were taken at 15 m intervals from a survey line to an irregular
boundary line
Calculate the area enclosed between the survey line, the irregular boundary line, and the offsets,
by:
b) simpson’s rule
solution:
a) the trapezoidal rule
required area=15/2{3.50+3.25+2(4.30+6.75+5.25+7.50+8.80+7.90+6.40+4.40)}
= 15/2{6.75+102.60} = 820.125 m2
c) simpson’s rule
if this rule is to be applied, the number of ordinates must be odd. But here the number of
ordinates must be odd. But here the number of ordinate is even(ten).
So, simpson’s rule is applied from O 1 to O9 and the area between O9 and O10 is found out by the
trapezoidal rule.
Problem 3: the following offsets are taken from a survey line to a curves boundary line, and the
first and the last offsets by:
b) simpson’s rule
solution:
here the intervals between the offsets are not reglar through out the length.
Let
Here
d1= 5 m
d2=10 m
d3=20 m
a) by trapezoidal rule
b) by simpson’s rule
A. trapezoidal rule
i.e. V=common distance {area of 1st section+ area of last section+ 4(sum of areas of even
sections)
Note: the prismoidal formula is applicable whrn there is an odd number of sections. If the
number of sections is even, the end strip is treated separately and the area is calculated according
to the trapezoidal rule. The volume of the remaining strips is calculated in the usual manner by
the prismoidal formula. Then both the results are added to obtain the total volume.
i) Trapezoidal formula
∆= (b+sh)*h
∆7=(10+1.5*0.85)*0.85= 9.58 m2
V= 40/2{10.22+ 9.58+2(14.84+28.43+34.38+23.63+16.23)}
= 20{19.80+235.02} = 5096.4 m2
V = 40/3 {10.22+9.58+4(14.84+34.38+16.23)+2(28.43+23.63)}
Problem the areas enclosed by the contours in the lake are as follows:
Area (m2)
2050 8400 16300 24600 31500
Calculate the volume of water between the contours 270 m and 290 m by:
i) Trapezoidal formula
=5/2{2050+31500+2(8400+16300+24600)}
=330,250 m3
LESSON 15. Theodolite –description of the instrument & Traversing
THEODOLITE
Uses of Theodolite
i) Measurement of Horizontal and vertical angles.
ii) Setting out lines and angles
iii) Optical distance measurement
iv) Plumbing tall building
v) Setting out of Railway curves
vi) Locating the position of piers for Bridge etc.
vii) Geographical position fixing from observation of sun and stars.
viii) Alignment control in tunnel construction.
CLASSIFICATION
Theodolite may be classified into transit and non-transit theodolites.
1. Transit theodolite
A theodolite is said to be transit one when its telescope can be revolved through
180° in a vertical plane about its horizontal axis, thus directing the telescope in
exactly opposite direction.
2. Non-transit theodolite
A theodolite is said to be a non-transit one when its telescope cannot be revolved
through 180° in a vertical plane about its horizontal axis.
TYPE OF THEODOLITE
In general, theodolite is divided into three types based on angles, which are vernier, optical and
electronic.
1. Vernier Theodolite
Uses vernier scale
2. Optical Theodolite
Uses optical with horizontal and vertical circles made from transparent glasses
and graduated scale
3. Electronic Theodolite
Has a screen with digits for angles on front and back of the instrument.
The face of the current observation (telescope position) is the side on which the
vertical circle is, when viewed from the eyepiece, which is either face left or face
right
The telescope has its own clamp and tangent screws. (The clamp screws require
only finger tip pressure)
4. Basically Transit Theodolite are those in which the telescope can revolve through a
complete revolution about its Horizontal axis in vertical plane.
5. Components of Transit theodolite
Transit theodolite consists of the following parts :
1. Levelling Head
2. Lower Plate or Scale Plate
3. Upper Plate or Vernier Plate
4. The standard or A Frame
5. T-Frame or Index Bar.
6. Plate Levels
7. Telescope
1. Levelling Head - Levelling Head consists of upper tribrach and lower Tribrach. Upper
tribrach has three arms, each arm carries a levelling screw for levelling the equipment. Lower
tribrach has got a circular hole through which a plumb bob may be suspended for centering.
Three distinct functions of levelling head are:
i) to support the main part of the instrument
ii) to attach the Theodolite to the Tripod
iii) to provide a means for levelling the theodolite
2. Lower Plate (Scale Plate) : Lower Plate which is attached to outer spindle, carries a horizonta
graduated circle, it is graduated from 0-360. Each degree is further divided into 10 minutes or 20
minutes. Scale plate can be clamped to any position by a clamping screw and a corresponding
slow motion screw.
When the lower plate is tightened, the lower plate is fixed to the upper tribrach of the levelling
head. The size of the Theodolite is determined by the size of the diameter of this lower plate.
3. Upper plate or Vernier Plate : Upper plate is attached to Inner spindle axis. Two verniers are
screwed to the upper plats. It carries an upper clamp screw and tangent screw. On clamping the
upper clamp and unclamping the lower clamp, the instrument may be rotated on its outer spindle
without any relative motion between the two plates.
On the other hand if lower clamp screw is tightened and upper clamp screw is
unclamped, the instrument may be rotated about its inner spindle with a relative motion between
the vernier and graduated scale of the lower plate. This property is utilised for measuring angles.
4. Plate Levels - Upper plates carries two plate levels placed at right angles to each other. One
of the plate bubble is kept parallel to the trunion axis. Plate levels can be centred with the help
of foot screws.
5. Telescope – Telescope is supported on the pivots of the trunion axis which affords its
movement in the vertical plane.
IMPORTANT DEFINITIONS –
i) Line of Collimation - the line which passes through the Intersection of the cross hairs of the
eye piece and optical centre of the objective and its continuation is called as line of
collimation. This is also known as line of sight.
ii) Transiting - The process of turning the telescope in vertical plane through 180 deg. about its
horizontal axis is known as transiting.
iii) Swing - A continuous motion of telescope about the vertical axis in horizontal plane is called
swing. The swing may be in either direction i.e. Right swing or left swing.
iv) Face left observation – When vertical circle is on the left of the telescope at the time of
observation, the observations are called face left observation.
v) Face right observation – When vertical circle is on the right of the telescope at the time of
observation.
ADJUSTMENT OF A THEODOLITE
The adjustments of a theodolite are of two kinds:
1. Permanent adjustment
2. Temporary adjustment
PERMANENT ADJUSTMENT
The permanent adjustment are made to establish the fixed relationships between the
fundamental lines of the instrument, and once made, they last for long time.
They are essential for the accuracy of observations. The permanent adjustment in case of
transit theodolite are:
1. Adjustment of the Horizontal Plate Levels.
2. Collimation Adjustment
The temporary adjustments are made at each set up of the instrument before starting taking
observations with the instrument.
ii) Bring the bubble to the centre of its run by turning both foot screws simultaneously in
opposite directions either inwards or outwards. The movement of the left thumb indicates the
direction of movement of bubble.
iv) Note the position of the bubble. If it occupies a different position, move it by means of the
same two foot screws to the approx. mean of the two positions.v) Turn the theodolite through 90
in azimuth so that the plate level becomes perpendicular to the previous position.
vi) With the help of third floor screw, move the bubble to the approx. mean position already
indicated.
vii) Repeat the process until the bubble, retains the same position for every setting of the
instrument.
3. Elimination of Parallax : Elimination of parallax may be done by focusing the eye piece for
distinct vision of cross hairs and focusing the objective to bring the image of the object in the
plane of cross hairs.
1. Set up, Centre and level the theodolite over the ground point B.
2. Loosen the upper plate, set the vernier to read zero and clamp the upper clamp.
3. Loosen the lower plate and swing the telescope until the left point A is sighted. Tighten
the lower clamp. Accurate bisection of the arrow held on the Point A is done by using
the lower tangent screw. Read both the vernier and take the mean of the reading.
4. Unclamp the upper plate and swing the telescope in clockwise direction until point C is
brought in the field of view. Tighten the upper clamp and bisect the mark of C
accurately, using the upper clamp tangent screw.
5. Read both the verniers and take the mean of readings. The difference of the means of the
reading to C to A is the required angle ABC.
6. Change the face of the instrument and repeat the show procedure, the measure of the
angle is again obtained by taking the difference of the means of the readings to C&A on
face right.
7. The mean of the two measures of the angle ABC on two faces is the required value of the
angle ABC.
Fig 9.1 Parts of theodolite
Fig 9.2 Measurement with thodolite
Fig 9.3 Reading a theodolite
—Turn the telescope clockwise set vernier A to 0° and vernier B to approximately 180°.
—Upper clamp is tightened and using the upper tangent screw the vernier A and B are
exactly set to 0° and 180°.
—Upper clamp is tightly fixed, lower one is loosened and telescope is directed towards A
and bisect the ranging rod at A.
—Tightened the lower clamp and turn the lower tangent screw to perfectly bisect ranging
rod at A.
—Loose the upper clamp and turn the telescope clockwise to bisect the ranging rod at C
tightened the upper clamp and do the fine adjustment with upper tangent screw.
—The reading on vernier A and B are noted. Vernier A gives the angle directly and
vernier B gives the reading by subtracting the initial reading (180°) from final reading
1. The theodolite is set up at O. It is centred and levelled properly. The zeros of the vernires
(generally C and D) are set at the 0° - 0° mark of the vertical circle (which is fixed to the
telescope). The telescope is then clamped.
2. The plate bubble is brought to the centre with the help of food screws (in the usual
manner). Then the altitude bubble is brought to the centre by means of a clip screw. At
this position the line of collimation is exactly horizontal.
3. To measure the angle of elevation, the telescope is raised slowly to bisect the point A
accurately. The readings on both the verniers are noted, and the angle of elevation
recorded.
4. The face of the instrument is changed and the point A is again bisected.The readings on
the verniers are noted. The mean of the angles of the observed is assumed to be the
correct angle of elevation.
5. To measure the angle of depression, the telescope is lowered slowly and the point B is
bisected. The readings on the verniers are noted for the two observations (face left and
face right). The mean angle of the observation is taken to be the correct angle of
depression.The result is tabulated as shown in Table 9.4.
Method of traversing
Errors in theodolite
Instrumental errors
Personal errors
Natural errors
—High winds cause vibration in the instrument, and this may lead to wrong readings on
verniers
Closing Error
Lesson 16. Introduction to setting of curves
Curves are regular bends provided in the lines of communication like roads, railways and canals
etc. to bring about gradual change of direction.
They enable the vehicle to pass from one path on to another when the two paths meet at an angle.
They are also used in the vertical plane at all changes of grade to avoid the abrupt change of
grade at the apex.
HORIZONTAL CURVES
Curves provided in the horizontal plane to have the gradual change in direction are known as
horizontal curves.
VERTICAL CURVES
Curves provided in the vertical plane to obtain the gradual change in grade are called as vertical
curves.
Curves are laid out on the ground along the centre line of the work.
Curves are needed on Highways, railways and canals for bringing about gradual change of
direction of motion. They are provided for following reasons:-
ii) To bring about gradual change in grade and for good visibility.
CLASSIFICATION OF CURVES
Most types of transportation routes, such as highways, railroads, and pipelines, are connected by
curves in both horizontal and vertical planes.
Horizontal Curves: Curves used in horizontal planes to connect two straight tangent sections.
Compound Curve: Two or more circular arcs of different radii tangent to each other.
Broken-back Curve: Combination of a short length of tangent connecting two circular arcs that
have centers on the same side.
Reverse Curve: Two circular arcs tangent to each other, with their centers on opposite side of
the alignment.
1. Simple Curves.
2. Compound Curves.
3. Serpentine Curves.
4. Deviation Curves.
1. Simple Curve:
A simple curve Consists of a single arc of circle connecting two straights. It has radius of the
same magnitude throughout.
2. Compound Curves.
A compound Curve consists of two or more simple curves having different radii bending in the
same direction and lying on the same side of the common tangent. Their centres lie on the same
side of the curve.
A reverse or serpentine curve is made up of two arcs having equal or different radii bending in
opposite direction with a common tangent at their junction . Their centres lie on opposite sides of
the curve. Reverse curves are used when the straights are parallel or intersect at a very small
angle.
4. Deviation curve
A deviation curve is simply a combination of two reverse curves. it is used when it becomes
necessary to deviate from a given straight path in order to avoid intervening obstructions such as
bend of river, a building , etc.
They should be avoided as far as possible on main lines and highways where speeds are
necessarily high.
Degree of Circular Curve
The rate of curvature of circular curves can be designated either by their radius (100-m
curve), or by their degree of curve.
Arc definition: The central angle subtended by a circular arc of 30m (100-ft).
Chord definition: The angle at the center of a circular arc subtended by a chord of 30m
(100 ft).
R: Curve radius
Stationing
Stationing: In route surveying, stationing is used to specify the relative horizontal positioning of
any point along the reference line. The starting point is usually designated with some arbitrary
value.
The beginning point of any project is assign a station value, and all other points along the
reference line are then related to it.
After the tangents have been staked and stationed, the I angle is observed at each PI, and curves
computed and staked.
Assume that the instrument is set up over the PC and each full station is to be marked
along the curve.
To mark that point form the PC, a backsight is taken on the PI with zero set on the
instrument’s horizontal circle.
Deflection angle δa to station 63 + 00 is then turned and two tape persons measure chord
ca from the PC and set 63 + 00 at the end of the chord on the instrument’s line of sight.
With station 63 + 00 set, the tape persons next measure the chord length c from it and
stake station 64 + 00, where the line of sight of the instrument , now set to δ64, intersects
the end of that chord.
The total station instrument is set up over the PC and each full station is to be marked
along the curve.
To mark that point form the PC, a backsight is taken on the PI with zero set on the total
station’s horizontal circle.
Deflection angle δa to station 63 + 00 is then turned and the reflector placed on line and
adjusted until its distance from the instrument is ca from the PC and the stake set at 63 +
00.
To set station 64 + 00, the deflection angle δ64 is turned, reflector placed on this line of
sight, and adjusted in position until the total chord from the PC to station 64 + 00 is
obtained, and the stake set.
For deflection angle method, deflection angles and chords are important values that must
be calculated.
distance from the PC (shorter than a full-station increment), subdeflection angle δa and subchord
ca are needed.
Theorem: The angle at a point between a tangent and any chord is equal to half the central angle
subtended by the chord.