Sample Construction Programme

This construction programme outlines the key tasks and timeline for a sample construction project from January 2013 through October 2013. It includes off-site works like structural steel preparation from February to May. On-site work begins in late February with site establishment and clearing. The major on-site activities include excavation and pouring of three building slabs from March to May, structural steel installation from April to May, framing of walls from April to May, and roof installation in May. The overall on-site construction period runs from late February to early October.

Uploaded by

Yang Rhia
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
55 views

Sample Construction Programme

This construction programme outlines the key tasks and timeline for a sample construction project from January 2013 through October 2013. It includes off-site works like structural steel preparation from February to May. On-site work begins in late February with site establishment and clearing. The major on-site activities include excavation and pouring of three building slabs from March to May, structural steel installation from April to May, framing of walls from April to May, and roof installation in May. The overall on-site construction period runs from late February to early October.

Uploaded by

Yang Rhia
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Sample Construction Programme Issue: A

Print date: 10/01/13 Project: sample


Construction Programme

ID Task Name Duration Start Finish Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Jul '13 Aug '13 Sep '13 Oct '13 Nov '13
7/1 4/1 1/1 7/01 4/0 1/0 8/0 4/02 1/0 8/0 5/0 4/03 1/0 8/0 5/0 1/04 8/04 5/0 2/0 9/0 6/05 3/0 0/0 7/0 3/06 0/0 7/0 4/0 1/07 8/07 5/0 2/0 9/0 5/08 2/0 9/0 6/0 2/09 9/09 6/0 3/0 0/0 7/10 4/1 1/1 8/1 4/11 1/1 8
1 Submit tender 1d 14/01/13 14/01/13 Submit tender
2 Design finalization & construction dwg issue 7d 14/01/13 23/01/13 Design finalization & construction dwg issue
3 Tender assessment 6d 15/01/13 22/01/13 Tender assessment
4 Building permit 10 d 16/01/13 31/01/13 Building permit
5 Tender award 1d 22/01/13 22/01/13 Tender award
6 Finalize key trades 17 d 23/01/13 19/02/13 Finalize key trades
7 PIC issued 1d 13/03/13 14/03/13 PIC issued
8 Off-site works 61 d 1/02/13 14/05/13 Off-site works
9 Structural steel - shop dwg preparation 21 d 1/02/13 5/03/13 Structural steel - shop dwg preparation
12 DB - shop dwg preparation 19 d 26/02/13 26/03/13 DB - shop dwg preparation
10 Structural steel - shop dwg approval 5d 6/03/13 14/03/13 Structural steel - shop dwg approval
11 Structural steel - manufacture 22 d 15/03/13 23/04/13 Structural steel - manufacture
13 DB - shop dwg approval 4d 27/03/13 9/04/13 DB - shop dwg approval
14 DB - manufacture 23 d 10/04/13 14/05/13 DB - manufacture
15 Site Activities 140 d 20/02/13 2/10/13 Site Activities
16 Establishment 5d 20/02/13 27/02/13 Establishment
17 Tree / site clearing 5d 21/02/13 28/02/13 Tree / site clearing
18 Site Survey & setout 2d 22/02/13 26/02/13 Site Survey & setout
19 Building construction 136 d 27/02/13 2/10/13 Building construction
20 Earthworks prep. to building footprint 9d 27/02/13 13/03/13 Earthworks prep. to building footprint
21 Services rough in - below slab 7d 14/03/13 22/03/13 Services rough in - below slab
22 Slab 1 (East slab) 14 d 19/03/13 15/04/13
23 Detailed excavation 5d 19/03/13 25/03/13 Detailed excavation
25 Lift pit base - prep, tank & pour 4d 21/03/13 26/03/13 Lift pit base - prep, tank & pour
24 Blinding 1d 26/03/13 26/03/13 Blinding
26 Lift pit sides - prep & pour 4d 27/03/13 9/04/13 Lift pit sides - prep & pour
28 Prepare / form (not lift) 7d 27/03/13 12/04/13 Prepare / form (not lift)
27 Lift pit walls - tank & backfill 2d 10/04/13 11/04/13 Lift pit walls - tank & backfill
29 Concrete pour 1d 15/04/13 15/04/13 Concrete pour
30 Slab 2 (Central slab) 15 d 28/03/13 26/04/13
31 Detailed excavation 5d 28/03/13 12/04/13 Detailed excavation
32 Blinding 1d 12/04/13 15/04/13 Blinding
33 Prepare / form 7d 16/04/13 24/04/13 Prepare / form
34 Concrete pour 1d 26/04/13 26/04/13 Concrete pour
40 Structural steel - install east slab columns 4d 18/04/13 23/04/13 Structural steel - install east slab columns
35 Slab 3 (West slab) 9d 22/04/13 3/05/13
36 Detailed excavation 2d 22/04/13 24/04/13 Detailed excavation
37 Blinding 1d 24/04/13 26/04/13 Blinding
38 Prepare / form 4d 29/04/13 2/05/13 Prepare / form
39 Concrete pour 1d 3/05/13 3/05/13 Concrete pour
43 Framing - east slab walls 13 d 24/04/13 14/05/13 Framing - east slab walls
41 Structural steel - install Central slab zone 8d 29/04/13 9/05/13 Structural steel - install Central slab zone
42 Blockwork - structural blade wall 3d 7/05/13 9/05/13 Blockwork - structural blade wall
44 Roof purlins - upper level 4d 10/05/13 15/05/13 Roof purlins - upper level
46 Framing - west slab walls 7d 10/05/13 20/05/13 Framing - west slab walls
47 Timber roof trusses / LVL's (east slab) 5d 15/05/13 21/05/13 Timber roof trusses / LVL's (east slab)
48 Timber roof trusses / LVL's (west slab) 3d 21/05/13 23/05/13 Timber roof trusses / LVL's (west slab)
60 Roller shutter / doors - site measure agreed 1d 21/05/13 21/05/13 Roller shutter / doors - site measure agreed
45 Roofing - line / sheet roofs 11 d 22/05/13 6/06/13 Roofing - line / sheet roofs
52 Services rough in (walls / ceiling space) 17 d 22/05/13 18/06/13 Services rough in (walls / ceiling space)
49 Window / door frames install 9d 23/05/13 5/06/13 Window / door frames install
50 Wall linings - external (Brickwork) 9d 29/05/13 12/06/13 Wall linings - external (Brickwork)
77 Lift pit infill floor 4d 30/05/13 4/06/13 Lift pit infill floor
51 Wall linings - external (metal cladding) 13 d 6/06/13 27/06/13 Wall linings - external (metal cladding)
53 Services - mech duct / pipe rough-in 8d 17/06/13 27/06/13 Services - mech duct / pipe rough-in
55 Wall linings - internal (PB/villaboard) 16 d 19/06/13 12/07/13 Wall linings - internal (PB/villaboard)
61 Roller shutters - install 5d 28/06/13 4/07/13 Roller shutters - install
62 Roller doors - install 5d 28/06/13 4/07/13 Roller doors - install
78 Wall linings - external (render) 4d 28/06/13 3/07/13 Wall linings - external (render)
64 Services - elec DB install 6d 2/07/13 10/07/13 Services - elec DB install
56 Ceilings - frame & line 15 d 15/07/13 6/08/13 Ceilings - frame & line
57 2nd. Fix (doors / skirtings) 12 d 15/07/13 31/07/13 2nd. Fix (doors / skirtings)
59 Paint - interior 25 d 31/07/13 5/09/13 Paint - interior
67 Floor finishes - screeds & tanking 4d 2/08/13 8/08/13 Floor finishes - screeds & tanking
63 Services - mech fit off 9d 8/08/13 21/08/13 Services - mech fit off

Page 1 of 2
Sample Construction Programme Issue: A
Print date: 10/01/13 Project: sample
Construction Programme

ID Task Name Duration Start Finish Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Jul '13 Aug '13 Sep '13 Oct '13 Nov '13
7/1 4/1 1/1 7/01 4/0 1/0 8/0 4/02 1/0 8/0 5/0 4/03 1/0 8/0 5/0 1/04 8/04 5/0 2/0 9/0 6/05 3/0 0/0 7/0 3/06 0/0 7/0 4/0 1/07 8/07 5/0 2/0 9/0 5/08 2/0 9/0 6/0 2/09 9/09 6/0 3/0 0/0 7/10 4/1 1/1 8/1 4/11 1/1 8
65 Services - elec / comms fit off 15 d 8/08/13 29/08/13 Services - elec / comms fit off
72 Joinery install - wet areas 5d 9/08/13 15/08/13 Joinery install - wet areas
54 Wall linings - internal (feature) 9d 14/08/13 28/08/13 Wall linings - internal (feature)
58 Paint - exterior elements 19 d 16/08/13 13/09/13 Paint - exterior elements
68 Floor finishes - vinyl 8d 16/08/13 28/08/13 Floor finishes - vinyl
70 Floor finishes - epoxy 8d 28/08/13 6/09/13 Floor finishes - epoxy
71 Wall vinyl 12 d 29/08/13 16/09/13 Wall vinyl
69 Floor finishes - carpet 6d 11/09/13 18/09/13 Floor finishes - carpet
66 Services - hyd fit off 8d 12/09/13 23/09/13 Services - hyd fit off
73 Joinery install - balance areas 7d 19/09/13 27/09/13 Joinery install - balance areas
74 Toilet / shower partitions 3d 20/09/13 24/09/13 Toilet / shower partitions
75 Services - commission 6d 24/09/13 2/10/13 Services - commission
76 Accessories 5d 25/09/13 2/10/13 Accessories
79 Clean & hand over 3d 27/09/13 2/10/13 Clean & hand over
80 External civil works 119 d 25/03/13 1/10/13 External civil works
83 Sewer - site reticulation works 6d 25/03/13 9/04/13 Sewer - site reticulation works
84 Sewer - rising main works 13 d 10/04/13 29/04/13 Sewer - rising main works
85 Sewer - pump station installation 6d 30/04/13 8/05/13 Sewer - pump station installation
87 Water / fire service - street tapping 9d 1/05/13 15/05/13 Water / fire service - street tapping
82 Stormwater - site reticulation works 19 d 7/05/13 3/06/13 Stormwater - site reticulation works
86 Water / fire service - site reticulation works 9d 15/05/13 28/05/13 Water / fire service - site reticulation works
89 Elec / comms - site reticulation works 14 d 22/05/13 13/06/13 Elec / comms - site reticulation works
88 Non-potable water service - site reticulation works 6 d 29/05/13 5/06/13 Non-potable water service - site reticulation works
81 Civil earthworks 8d 14/06/13 26/06/13 Civil earthworks
97 Retaining walls 9d 19/06/13 2/07/13 Retaining walls
90 Concrete pavement - prep subgrade 13 d 27/06/13 16/07/13 Concrete pavement - prep subgrade
96 Shed slab - prep & install 18 d 27/06/13 24/07/13 Shed slab - prep & install
91 Concrete pavement - kerb & channel 7d 16/07/13 25/07/13 Concrete pavement - kerb & channel
92 Concrete pavement - prep & place concrete 12 d 25/07/13 12/08/13 Concrete pavement - prep & place concrete
93 Cross-over works 6d 13/08/13 21/08/13 Cross-over works
95 Perimeter fencing & gates 20 d 13/08/13 11/09/13 Perimeter fencing & gates
98 Water tanks - install & commission 6d 13/08/13 21/08/13 Water tanks - install & commission
100 Landscape - soft landscaping works 19 d 28/08/13 24/09/13 Landscape - soft landscaping works
99 Landscape accessories 7d 18/09/13 26/09/13 Landscape accessories
94 Carpark - line marking 4d 25/09/13 1/10/13 Carpark - line marking
101 De-establish site 5d 25/09/13 2/10/13 De-establish site
102 Project Hand Over 1d 2/10/13 2/10/13 Project Hand Over