Design Standards For Cross Country Pipe Lines (Unloading Lines and Pre Cooling Lines)
Design Standards For Cross Country Pipe Lines (Unloading Lines and Pre Cooling Lines)
The pipeline originated from one place and terminated at another place with in the
country known as cross country pipeline. This terms is widely used in Oil and Gas Pipelines.
STATUTORY RULES /REGULATIONS:
LPG pipeline and its associated facilities are covered under various regulations and
require specific approval from concerned authorities. Various regulations applicable are as
follows:
i) Environmental Regulations :
Guidelines for Environmental clearance of new projects -1981.
The Environment (Protection) Act -1986
Water (Prevention & Control of Pollution) Act 1974.
Air (Prevention & Control of Pollution) Act 1981
Manufacture, storage & import of Hazardous chemical Rules-1989
ii) The Factories Act. 1948.
iii) Indian Electricity Rules.
iv) The Petroleum Pipelines (Acquisition of Right of Users in Land) Act’1962.
v) National Highways Act, 1956
vi) Railways Act, 1989
vii) All other statutory approvals required for laying of the pipelines across rail, road, River.
DESIGN TEMPERATURE:
0 0
(-) 30 C to (+) 55 C.
DESIGN OF COMPONENTS:
1) STRAIGHT PIPE:
The least nominal wall thickness (th ) for the steel pipe , shall be as per ASME B 31.4.
Wall thickness ‘t’ for straight steel pipe under internal pressure shall be calculated by the
following equation :
Pi D
t = ----------
2S
Where
D= outside diameter of pipe.
Pi= Internal Pressure
The allowable stress value S to be used for design calculations for new pipe of
known specifications shall be established as follows:
S = 0.72 x E x Specified minimum yield strength of pipe. Where
0.72 =Design factor based on nominal wall thickness. In setting design factor,
due consideration has been given to and allowance has been made for the under
thickness tolerance and maximum allowable depth of imperfection provided for in the
specification approved by code.
E = 1 for Seamless, ERW and SAW pipe.
2) CORROSION:
i) All underground and above ground pipes and its components shall be fully protected
against corrosion.
ii) Wall thickness allowance for corrosion is not required if pipe and component are
protected against corrosion.
ADDITIONAL REQUIREMENT:
With remote shut off provision from the control room shall be provided at the boundary of
station pipeline inlet and outlet locations to isolate the station facility.
2) CHECK VALVES:
Shall be installed to provide automatic blockage of reverse flow in the piping system,
within the station wherever required
i) Shall be provided with blow down connection to isolate the pipeline section and
evacuate the pipeline section in case of emergency and repair.
ii) All blow down piping shall have double valve segregation. Mainline
sectionalizing/block valves shall be installed at maximum spacing of 12 kms in industrial,
commercial and residential areas.
iii) Block valves shall also be installed on the upstream and downstream of river crossings
and public water supply reservoirs.
iv)The number of flanged or threaded joints for station piping shall be to the extent
minimum.
v) No free water in LPG being pump shall be allowed as per IS 4576. Online water
analyzer may be installed at the originating pump station to detect any free water in the LPG
being pumped.
5) VALVES:
Steel valves (preferably ball valves) conforming to API 6D shall be used. Cast iron
valves shall not be used.
CORROSION CONTROL:
i) All above ground and buried pipelines shall be adequately protected against corrosion.
ii) Above ground pipes should be protected from atmospheric corrosion by suitable
coating or paint.
iii) Above ground sections of pipelines should be electrically isolated from the buried
pipeline sections.
iii) Buried pipes likely to be affected by external corrosion should be protected by
combination of anti-corrosion coatings and Cathodic protection.
EXTERNAL CORROSION:
ELECTRIC INTERFERENCE:
i) The anode beds shall be located so that minimum adverse effect is caused to the
existing underground metallic structures.
ii)The pipeline shall be protected against stray DC or AC current induced corrosion by
providing metallic bonds, increased cathodic protection,
iii) Supplemental protective coatings, insulating flanges or galvanic anodes.
MATERIALS AND SPECIFICATIONS:
i) The flange joint shall be either spiral wound metallic gaskets or ring joints.
ii) Plain asbestos sheet / reinforced gaskets shall not be used.
iii) Gaskets used shall confirm to ANSI B 16.20 or equivalent.
iv) Flange connection ratings shall match with the design pressure of the pipeline (on
high pressure side) and in no case shall be less than 300 series rating (low pressure side)
confirming to ANSI 16.5 or equivalent.
v) All tapping or opening shall be minimum 20 mm dia. The materials used shall
conform to ASME B 31.4 or equivalent.
vii) Line pipe shall conform to API-5L.
NOTE:
i) The above mentioned minimum cover requirements shall be valid for all class locations.
ii) Minimum depth of cover shall be measured from the top of pipe coating to the top of
undisturbed surface of the soil, or top of graded working strip, whichever is lower. Fill material
in working strip shall not be considered to add to the depth of cover.
iii) Cover shall be measured from the top of road or top of rail, as the case may be.
iv)Incase of rivers/water bodies, which are prone to scour and erosion, adequate safe
cover (minimum 1.5metre) shall be provided below the predicted scour profile expected
during the life time of the pipeline.
v) Soft soil / sand padding of minimum 150 mm thickness to be provided around the
pipe in rocky areas.
vi) For river /water bodies which are prone to scour and erosion, adequate safe cover
shall be provided below the predicted scour profile expected during the life time of the
pipeline.
vii) Good pipeline practices shall be followed for public safety. In case the pipeline is
to be laid through populated area (which otherwise could not be avoided), additional
protective measures to be provided be by way of providing higher wall thickness pipe or
laying at a greater depth or by providing casing pipe.
DEFECTS IN PIPE:
i) All defects in pipe shall be removed in line with ASME B 31.4, API 5L or
equivalent.
ii) Notches or laminations on pipe ends shall not be repaired. The damaged portion
shall be removed as a cylinder and re-welled to the piped properly.
iii) Distorted or flattened lengths shall be discarded.
iv) A dent containing a stress concentrator, such as a scratch, gouge, groove, or arc
burn, shall be removed by cutting out the damaged portion of the pipeline as Cylinder.
v) All dents which affect the curvature of the pipe at the seam or at any girth weld
shall be removed as in ASME B 31.4.
vi) Buckled pipe shall be replaced as a cylinder.
BENDS, MITERS & ELBOWS:
i) To match the contours of the ditch in the event of change in direction, sagging, over
bending etc., the required fittings shall be made either by bending the pipe or factory made
bends or elbows shall be used.
ii) The pipe diameter shall not be reduced at any point by more than 2-½ % of the
nominal diameter, and the completed bend shall pass the specified sizing pig.
iii) Mitered bends are not permitted in mainline.
The minimum radius of field cold bends shall be as follows:
WELDING:
i) Standard of acceptability for welding process, filler materials, and weld quality shall
conform to be API-1104.
ii) Safe Practices in Cutting and Welding shall be ensured with safety work permits as per
OISD-STD-105.
WELDING QUALIFICATIONS:
i) Welding procedures or welders shall be qualified in line with under API 1104, or
section IX of the ASME Boiler and Pressure Vessel Code, whichever is appropriate for the type
of welding to be performed.
ii) Qualification Records: Records of the tests that establish the qualification of a
welding procedure shall be retained as long as that procedure is in use.
iii) A record of the welders’ qualification test, showing the date and results of the
tests, shall be retained during the construction involved and for 6 months thereafter.
i) The quality of all weld joints shall be checked by visual inspection and
supplemental non-destructive testing (NDT) methods or by removing completed welds as
selected for destructive testing (DT).
ii) A minimum of 10% of the girth welds (completely around pipe circumference)
completed each day shall be randomly selected and inspected by radiography or non-
destructive methods.
iii) 100% inspection by radiography of the weld joints shall be carried out at the
location of residential and industrial areas, river, lake, stream crossings(submerged or
bridge crossings), rail, road, overhead rail / road crossings, offshore and inland coastal
waters and tie-ins etc.
iv)The Non-destructive inspection method used shall produce indications of potential
defects, which can be accurately interpreted and evaluated. All NDT including Radiographic
examination and destructive method of examination shall be performed in accordance with the
requirements of API 1104.
TESTING& COMMISSIONING:
1)HYDROTESTING OF PIPELINE:
i) Rail/ Road / River crossing sections shall be hydro tested before and after installation at
least for 4 hours at 1.25 times the design pressure.
ii) All sections including previously hydrostatically tested one Viz road / rail and river
crossings shall be retested along with completed mainline sections. A gauging pig shall be
passed through the pipeline to prove the internal diameter of the entire pipeline. The gauging
plate shall have minimum diameter of 95% of the internal diameter of the pipeline.
iii) Water used for the test medium shall be inhibited water i.e water to which suitable
doses of corrosion inhibitors are added depending upon quality of the water.
iv)API-1110 shall be used for guidance for the hydrostatic test.
v) Complete pipeline including previously tested section shall be subjected to a
hydrostatic proof test equivalent to not less than 1.25 times the internal design pressure at
that point for not less than 24 hours or as specified by respective code to which pipeline is
designed and accepted by statutory authority.
vi) Internal test pressure of high pressure station piping shall be done for a duration of
not less than 4 hrs in line with ASME B31.4’
vii) Internal test pressure of low pressure station piping shall be governed by pressure
ratings of fittings and valves fitted in the system. Duration of the test shall be not less than
4 hrs.
2) GEOMETRIC SURVEY:
The Caliper Survey shall be conducted after completion and acceptance of all the
following mainline activities
Gauge plate run
Hydrostatic Testing
Cleaning and swabbing of pipeline
Mainline Valve installation
Test section tie-ins
After tie-in of HDD crossings / other submerged crossings.
Installation of launching and receiving barrels.
3) PRESERVATION OF PIPELINE:
If the pipeline is to be preserved for a specified duration before it can be commissioned,
the pipeline shall be completely filled with water with sufficient quantities of corrosion
inhibitors depending upon the quality of water and the period of preservation at a suitable
pressure.
4)DOCUMENTATIONS:
5) COMMISSIOINING:
i) A proper commissioning procedure to be prepared for removal of air and nitrogen and
intermixing of air and hydro carbons
ii) Before starting commissioning these activities should be completed
Hydro testing is completed for entire pipeline and associated station
piping and records checked and documented.
Swabbing of the pipeline has been completed for removal of water from
the pipeline.
Ensure complete removal of ferrous materials / debris from the pipeline
All sectionalizing valves are installed as per requirement.
All golden joints are inspected and accepted.
Caliper pigging of the entire pipeline section completed and a base line
data has been obtained.
Temporary modifications required at the stations for commissioning have
been completed in all respect.
Commissioning check list
Pre pared and ensured availability of all materials tools, tackles and
consumable.
Fire-fighting facilities shall be kept ready.
Trained and experience personnel shall be placed to
Carry out commissioning operation.
Caution boards shall be displayed while venting in progress.
7) LPG CHARGING:
i) Liquid LPG shall not be directly used for displacement of air in pipeline / vessels.
ii) LPG shall be charged only after ensuring elimination of / absence of oxygen.
iii) While charging LPG, water /Nitrogen shall be drained simultaneously maintaining a
2
positive pressure of around 1-2 kg/ cm in the pipeline.
iv)Pressure in the pipeline system shall be monitored and creation of vacuum condition to
be prevented.
v) Where water draining is resorted to, by opening of end flanges of headers / pipelines,
such flanges shall be blinded at the end of draining operation.
vi)In-case of displacement of Nitrogen with LPG, constant reading of LPG –air mixture
should be taken with explosive meter to ascertain the displacement of Nitrogen with LPG.
vii) Provision should be made for proper drainage of water from vessel, pipelines and
equipment. In case of Nitrogen displacement, controlled venting shall be done.
ix) LPG can be introduced at a controlled rate after displacement of entire water /
Nitrogen.
x) The commissioning operation shall be controlled and supervised by authorized
personnel.
8) PIPELINE REPAIR:
9) PATROLLING:
Periodic inspections and maintenance shall be carried out for controls and protective
equipment, including pressure limiting devices, regulators, controllers, relief valves, and other
safety devices in accordance with OEM and following OISD Standards
DOCUMENTATIONS:
The following records shall be maintained for operation and maintenance purposes:
All records as per clause 11.4 of this document.
Necessary operation data
Pipeline patrolling records
Records and maps showing the location of CP facilities and piping.
CP monitoring report, test and survey reports.
Leak and burst records
Records pertaining to routine or unusual inspections, such as external or
internal line conditions
Pipeline repair records
History cards of equipment.
Near miss, minor and major incidents.
For section replacement, all weld repairs and inspection shall be carried out in accordance
with API 1104, ANSI B.31.4 and ANSI B.31.8. API 2200, API 2201 and API 1107 shall be
referred for guidance. All repaired welds shall be 100% radiographed.
SAFETY INSTRUMENTATION:
VALVE:
Valves shall be partially operated and serviced once in six months to ensure operability.
ELECTRICAL EQUIPMENT: