Precast Structure
Precast Structure
1. INTRODUCTION
Precast concrete is made with concrete cast in a reusable mould or form and
cured in a controlled environment then transported to the construction site
and lifted into place.
Sr.
R.C.C Precast
no
30% to 40% of total Cross section 100% cross section area is
1
is utilized utilised
Section is uneconomical beyond
2 Economical upto span 25 to 30m
span of 10 to 12m
3 Self weight of section is higher. Self weight of section is lesser.
Cracking and Corrossion problems No cracking and corossion
4
are more. problems.
Reinforcement tendons can be
5 Reinforcement is striaght.
bent or have parabolic shapes.
Tension is developed below The whole cross section is in
6
neutral axis. compression.
Stresses are developed before
Stress are developed only after
7 loading due to pre-compressive
external load is allowed.
load.
Generally, in case of R.C.C structure the execution of the work is carried out
on site itself, but in case of precast first the products are manufactured in the
factory and then erection is done on site.
Parking structures are used to park the vehicles in densely populated areas.
Architect; engineer developer and owner have made precast and prestressed
material of choice for their commercial, municipal and institutional parking
needs.
They are subject to moving loads from automobile traffic and the roof level of
a parking structure is exposed to weather so requires consideration of
durability to weather so requires consideration of durability to ensure long
term performance. Precast structures overcome all the above limitation.
Durability chacarctertistics along with low cost, rapid erection in all weather
conditions, unlimited architectural expression long clear spans make precast
concrete the natural choice for parking structures.
The benefits of precast concrete are no longer limited to just a few aspects of
design and construction. New advances and product innovations have pushed
precast to the forefront of durable economic building systems. With clear
advantages in increased strength, and load bearing capacity, precast
concrete continues to perform impressively in structural components. Wall
systems and prestressed precast concrete planks and decking speed
construction, meet or exceed most building codes, while at the same time
reduce the load on escalating labour costs. Uniquely designed and intricate
architectural panels feature a wide range of colors textures and special
surface effects of acid-etching, sandblasting, water blasting and grooving
among other innovative techniques. Precast's greatest asset, however, may
be its ability to built faster and more efficiently with significant savings in
overall costs.
2.4 Warehouses
3.1 Advantages
1. Quick to install
2. Simple all weather construction.
3. Draught proof, rot proof and fire resistant.
4. Eliminates problems due to clay heave and shrinkage.
5. Better thermal insulation.
6. Immediate safe working platform.
4.1 Column
It is a vertical element which carries the load of structure and distributes the
load equally to the foundations. Column support girders and or spandrels at
all levels.
These are two types of columns.
Interior Columns
Exterior Columns.
4.3 Girder
4.4 Spandrels
4.5 Stairs
Formwork
Erection
1. Wall panels located along the outer boundary of the structure are
called Exterior wall panels.
2. Wall panels located inside the structure are called as Interior wall
panels.
3. Wall panels designed to resist lateral forces are called as “shear
walls”.
5.
Transportation Process
This is the process in which the units are transported from site through
trucks for erection process.
6. Erection Process
When these units are brought on site, the process of erection takes place by
assembling the units to connect them through welding process.
7. CONNECTIONS
8. AGENCIES INVOLVED
Owner
General Contractor
Architect
Structural Engineer of Record
Precaster
Specialist Precast Engineer
Detailers
Precaster Erection
Crew
8.2 Architect
The role of the architect is to develop the building design concept, establish
the overall geometry and select the appropriate building materials and
finishes. Drawing should clearly define the extend of the precast panels,
finishes, joints, corners, reveals and slab edge. Allowing the precaster to
suggest configurations and the opportunity to select which joints are 'false'
and which are 'real' will achieve greater economy and flexibility.
The Engineer of Record (EOR) is responsible for the overall structural design
of the completed facility. The EOR specifies the building framing systems,
loading criteria, applicable codes and any other special requirements the
precaster must consider in the design. This includes providing suggestion
connection concept, load points for bearing and tieback connections and any
special thermal or deflection limitations that need to be considered. While the
design of the connections is left to precaster,it is important that the bearing
locations and supplemental framing necessary to support the precast are
noted on the structural drawings. Supplemental support items such as
kickers, stiffners, out riggers and brackets are generally furnished and
installed by the steel supplier and designed by the EOR, so it is crucial they
are shown on the contract documents. This will allow them to be shop
installed for fireproofed before the precaster is on the site. The EOR also
defines and establishes interfacing details to other trades so that the extent
of the precast scope is clearly defined. When the precast shop drawings are
submitted, the EOR reviews them to ensure overall conformance with the
contract documents and to verify that the magnitude and location points
agree with the original design intent, It is always recommended that the EOR
involve the precaster early to help determine the most efficient connection
concepts.
8.4 Precaster
8.6 Detailer
This seminar gives us the brief information that precast structure can shorten
the project timetable six to eight weeks when compared with steel and even
more when compared with casting place concrete construction. These
savings can be critical in bringing a new building into a competitive
marketplace or in meeting a tenant's need for occupancy on a specific date. A
total precast system's speed helps keep projects on track. Precast concrete
building systems are becoming a popular choice for many construction
projects. Architectural and structural precast, prestressed concrete
components can be combined to create the entire building.
10. References
Google.com
Wikipedia.com
Advance Construction Technique & Equipments
Fundamental of Precast Structure.
http://www.hanson.com.au/
http://www.precaststructures.com/
http://www.hansonpc.biz/aboutus/aboutus.shtml
http://www.hansonpc.biz/casestudies/regency-case.shtml
http://www.freepatentsonline.com/4669240.html
Precast Concrete Structure (Multi-storey)- Kim. S. Elliott
Building Structure- James. E. Ambrose