Final Soft Copy of Project
Final Soft Copy of Project
1.1 NECESSITY:
Electrical energy generated at generating stations is transported to remote load
centers. Between generating station and consumers we have transmission, sub transmission and
distribution levels of voltage. Since the long distance transmission at high voltage is cheap and
low voltages are required for utility purpose, the voltage levels goes on decreasing from the
transmission system to the distribution system. For this high voltages and low voltages
transformer is necessary in transmission and distribution system.
1.2 PRINCIPLE:
A transformer is a static piece of apparatus used for transferring power from one circuit to
another at a different voltage, but without change in frequency. It can raise or lower the voltage
with a corresponding decrease or increase of current.
A Current in the primary winding produces a magnetic field in the core. The magnetic field is
almost totally confined in the iron core and couples around through the secondary coil. The
induced voltage in the secondary winding is also given by Faraday’s law.
Constructionally, transformers are of two general types, distinguished from each other
merely by the manner in which the primary & secondary coils are placed around the laminated
core.
1
1. Core-type
2. Shell-type
In the core type transformers, the winding surrounded a considerable part of the core whereas in
shell type transformer, the core surrounds a considerable portion of the windings as shown in fig
(a) and (b) respectively.
In the small size core-type transformers, a simple rectangular core is used with
cylindrical coil which are either circular or rectangular in form. But for large size core-type
transformers, round or cylindrical coils are used which are so wound as to fit over a cruciform
core section. The circular cylindrical coils are used in most of the core-type transformers because
Of their mechanical strength. Such cylindrical coils are wound in helical layers with the different
layers insulated fromeach other by paper, cloth,micarta board or cooling ducts.
2
1.5 Shell-type transformers:
In these case also, the coils are form-would but are multi-layer disc type usually
wound in the form of pancakes. The different layer discs are insulated from each other by paper.
The complete winding consist of stacked discs with insulation space between the coils the spaces
form.
The very commonly used shell-type transformer is one known as berry transformer so
called after the name of its designer and is cylidrical in form. The transformer core consists of
laminations arranged in groups which radiate out from the centre.
The choice of core or shell –type construction is usually determined by cost, beacause
similar charecteristics can be obtained with both types. For very hiogh-voltage transformers or
for multi winding design,shell-type construction is preferred by many manufacturers. In this
type, usually the mean length of coil turn is longer than in a comparable core-type design. Both
core and shell forms are used and the selection is decided by many factors such as voltage rating,
kVA rating, weight, insulation stress, heat distribution etc.
1.6 Operation:
When a voltage is applied to the primary winding, a small current flows, driving flux
around the magnetic circuit of the core.
The changing magnetic field induces an electromotive force (EMF) across each
winding. So the voltages VP and VS measured at the terminals of the transformer are equal to the
corresponding EMFs.
3
1.7 No load operation:
If the secondary of a transformer is left open-circuited, primary current is very low. No-
load current produces the magnetic flux and supplies the hysteresis and eddy current losses in the
core.
The no-load current (IE) consists of two components magnetizing current (Im) and
core loss (IH). Magnetizing current lags applied voltage by 90°, while core loss is in phase with
the applied voltage. VP and VS are shown 180° out of phase. IH is very small in comparison
with Im and Im is nearly equal to IE. No-load current, IE, is also referred to as exciting current
The transformer under loaded condition differs in its characteristics of type of load
say resistive, inductive and capacitive loads.
When the secondary is loaded, the secondary current I2 is set up. The magnitude and phase of I2
with respect of V2 is determined by the characteristics of the load. Current I 2 is in phase with V2
if load is non-inductive, it lags if load is inductive and it leads if load is capacitive.
The secondary current sets up its own m.m.f. (=N 2I2) and hence its own flux Φ2 which is in
opposition to the main primary flux Φ which is due to I 0. The secondary ampere-turns N2 I2 are
known as demagnetizing amp-turns. The opposing secondary flux Φ2 weakens the primary flux
Φ momentarily, hence primary back e.m.f. E1 tends to be reduced. For a moment V1 gains the
upper hand over E1 and hence causes more current to flow in primary.
Let the additional primary current be I 21. It is known as load component of primary
current. This current is anti-phase with I21. The additional primary m.m.f N1 I21 sets up its own
flux Φ21 which is in opposition to Φ2 (but is in the same direction as Φ) and is equal to it in
magnitude. Hence, the two cancel each other out. So, we find that the magnetic effects of
secondary current I2 are immediately neutralized by the additional primary current I 21 which is
brought into existence exactly at the same instant as I2. The whole process is illustrated in figure,
4
Hence, whatever the load condition, the net flux passing through the core is approximately
the same as at no-load. An important deduction is that due to the constancy of core flux at all
loads, the core loss is also practically the same under all load conditions.
Hence, when transformer is on load, the primary winding has two currents in it; one is I0 and the
other is I21 which is anti-phase with I2 and K times in magnitude. The total primary current is
the vector sum of I0 and I21.
In figure are shown the vector diagrams for a load transformer when the load is non-inductive
and when it is inductive (a similar diagram could be drawn for capacitive load). Voltage
transformation ratio of unity is assumed so that the primary vectors are equal to the secondary
vectors. With reference to figure (a), I2 is secondary current in phase with E2 (strictly speaking it
should be V2). It causes primary current I21 which is anti-phase with it and equal to it in
magnitude (K=1). Total primary current I1 is the vector sum of I0 and I21 and lags behind V1 by
Φ1.
5
In figure (b) vectors are drawn for an inductive load. Here I2 lags E2 (actually V2) by Φ2. Current
I21 is again anti-phase with I2 and equal to it in magnitude. As before, I 1 is the vector sum of I21
and I0 and lags behind V1 by Φ1.
It will be observed that Φ1 is slightly greater than Φ2. But if we neglect I0 as compared to I21 as in
figure (c), then Φ1=Φ2. Moreover, under this assumption,
It shows that under full-load conditions, the ratio of primary and secondary current is constant.
This important relationship is made the basis of current transformer-a transformer which is used
with a low-range ammeter for measuring current in circuits where the direct connection of the
ammeter is impracticable.
Transformer losses are divided into losses in the windings, termed copper loss,
and those in the magnetic circuit, termed iron loss.
Copper loss: Copper loss is the term often given to heat produced by electrical currents
in the conductors of transformer windings
Iron loss: Core losses or iron losses are caused by two factors: hysteresis and eddy
current losses.
1. Hysteresis loss: Hysteresis loss is that energy lost by reversing the magnetic field in the core
as the magnetizing AC rises and falls and reverses direction.
6
2. Eddy current loss: Eddy current loss is a result of induced currents circulating in the core.
VS/VP=NS/NP=k
7
1.13 Losses in Transformers:
The transformer shown below is an equivalent circuit in which the resistance and leakage
reactance of the transformer are imagined to be external to the winding whose only function is to
transform the voltage
Where
But there are certain types of transformers whose perfomance cannot be judged by this
efficiency. Transformers used for supplying lighting and general network i.e., Distribution
transformers have their primaries energized all the 24 Hrs although their secondary supplies little
or no-load much of the time during the day except during the house lighting period. It means that
whereas core loss occurs throughout the day, the copper loss occurs only when the transformers
are loaded. The performance of such is compared on basis of energy consumed during a certain
time period, usually a day of 24Hrs.
9
2.1 Introduction:
However here are the steps regarding the process of building up of a transformer.
Hence each of the sections are assigned a set of job to in order to attain
maximum profit and all these jobs are said to carry in parallel way in order to meet higher
production levels. The general block diagram for the process of manufacturing is as shown
below.
10
Fig: Manufacturing process sequence
2.2 Core section:
Here in this section the amorphous metal sheets are first transformed into core as
per the design which houses the windings of the transformer. Transformers operate 24 hours a
day during which time they undergo constant losses of 2 to 4% of the electricity that passes
through them. This loss is divided into two different categories mainly load losses caused by the
load on the transformer during the use of electricity and no-load losses caused regardless of
whether a load is present. Amorphous core transformers significantly reduce no-load losses by
using an amorphous alloy for the iron core, which the transformer windings that carry the
electricity are coiled.
Amorphous transformers use amorphous steel, instead of grain oriented steel. This
change allows a significant decrease of losses in Distribution Transformer, resulting in energy
savings. Metals have a crystalline structure with an orderly arrangement of atoms. Amorphous
metal is said to be as metallic glassy structures.
A metal in a liquid state at a high temperature can retain its liquid structure upon
solidifying if it is cooled rapidly. The resulting non-crystalline alloy has a random arrangement
of crystals and is called an amorphous alloy. Amorphous alloys have excellent strength and
electrical characteristics, but require advanced techniques for machining.
There are several other ways in which amorphous metals are produced which
include the physical vapour deposition, ion irradiation, extreme rapid cooling and mechanical
alloying.
11
The available ribbons of the amorphous core type material are varied in lengths as
5.6mm, 6.7mm and 8.4mm.
A proprietary molten alloy of iron, boron and silicon is cooled rapidly at a rate of
1 millionth degree per second such that crystals are not formed. The metal can be drawn very
thin (0.025mm-0.05mm) and so exhibit very low eddy current losses.
When the a.c magnetic field is applied the random atomic structure causes
less friction and hence less hysteresis loss. However it has less space factor than that of CRGO
type of core. Space factor is defined as the ratio of core cross section area to the area available
for the core. Here the weight and cost is more.
It can be seen that losses in amorphous metal core is less than 25% of that in
CRGO. This material gives high permeability and is available in very thin formations (like
ribbons) resulting in much less core losses than CRGO. The tradeoff between the both types is
interesting. The use of higher flux densities in CRGO (up to 1.5 T) results in higher core losses.
However, less amount of copper winding is required, as the volume of core is less. This reduces
the copper losses.
In amorphous core, the flux density is less and thinner laminations also help
in reducing core losses. However, there is relatively a larger volume to be dealt with, resulting in
longer turns of winding, i.e. higher resistance resulting in more copper losses. Thus iron losses
depend upon the material and flux densities selected, but affect also the copper losses.
4. Core annealing
12
2.4 Core pre spooling:
The core pre spooling process is that the thin ribbons of amorphous metal are
joined together to improve the mechanical strength. However the amorphous ribbons are
available at the thickness of 0.025mm.This thickness should not be exceed because the metal
forms a crystalline structure leading to increase in losses which is said to be undesirable.
Even though the thickness cannot be increased the net cross sectional area
can be increased. The widths available in the market are 142.23mm, 170.18mm and 213.35mm.
Since the design proposed in the report is single phase 15KVA the width chosen is
142.23mm.The width for higher ratings that is 200KVA to 3MVA is to be as 213.35mm.
In the process of manufacturing the thin ribbons of core are joined to form a
core of thickness 250 micro meters. This process of joining the ribbons of amorphous metal to
increase the thickness is called core pre-spooling.
Core cutting is a process in which the core sheets after pre-spooling are
cut to length as per the design of the transformer. The cutting is done in such a way that the first
layer has more length than last layer. This is because, when the core layers are bent to form the
rectangular shaped core, the outer layer must have more diameter than inner layer. This can be
obtained only when the first layer has more length than last layer.
Core stacking is the process in which the layers after cutting will be
arranged in such a way that the layer with long length is at the top and the layer with the short
length is at the bottom. This arrangement allows the manufacturer to make a rectangular core
with rounded edge.
Core lacing is the process in which the stacked core is bent in the shape of
rectangle with rounded edge. After the formation of rectangular core, one side of the core will
have more thickness than the other three sides .This is because the stacked core from the two legs
will be joined on this side .This joining of stacked core on one side of the rectangular core is
called core lacing.
13
2.6.2. Core forming:
After lacing, CRGO SHEETS are added to the inner and outer loops of
laced core to provide mechanical strength .Also plates of mild steel are added on four sides of the
core and are fixed by a package wire. After this process the core finally looks as a single piece.
This process is core forming.
It is the process in which the cooled core is painted with epoxy paint not
only serves as a insulation material but also used for joining the layers of core. Finally the mild
steel plates are removed and the core is sent to core coil assembly section.
For core type transformer the windings are cylindrical and are arranged
concentrically. For shell type the coils are usually rectangular .The conductors used in
transformer windings may be Cu or Al. Small transformer with aluminum is cheaper when
compared to Cu winding .However with the increase of rating and voltage the transformer with
Cu winding is much cheaper in overall cost as compared to Al winding. Commonly the
following types of windings are mostly employed.
14
In this winding first the LV is wound on the mandrel and then the HV is
wound on LV winding with some of the layers of insulation between them, in such a way that
both the windings form a single coil. This type of winding is generally used in amorphous core
distribution transformers.
Dressing of mould i.e., assembly of insulation spacers and blocks on the mould
Preparation of leads
After removing the windings from the winding machine, each winding
is clamped between the top and bottom plates through tie rods a kept in an Owen for heating.
The windings are individually shrunk to require axial dimensions by heating in the steam heated
Owens and by applying the required pressure. Heating ensures removal of moisture from the
insulation items and this proceed is called stabilization of windings.
15
CCA consists of assembling the windings to the core .Core from the core
section is moved to CCA .Now the core is unlaced on one side and the LV/HV coil is placed on
the limb of the core .Bottom insulation items like press board rings ,petals ,perms wood rings are
placed on the bottom Yoke on each core limb.
Windings are lowered on the core limb in such a way that LV leads should come to the LV side
of the core channels and HV leads should come to the HV side of the core channels. After
placing the coils in the position the core which is unlaced is replaced and welded. Insulation
items like fiber tubes, empire sleeves and top insulation arrangement is completed. During
insulation assembly, various leads are properly positioned and fully insulated phase barrier
assembly is then completed. Top yoke laminations are assembled back in positions starting with
centre step top core channels are then clamped and tightened .Coils are kept under pressure by
tightening tie rods.
All the transformer tanks are made of high quality mild steel and can
withstand vacuum as specified by international standards and the customer. The tank is provided
with the pressure releasing devices so that the oil in the transformer tank should not burst in
extreme conditions.
The oil level is also found out through the help of oil level gauges. The provision for the circuit
breaker is also given depending on the customer specifications.
All the welds are tested in such a way that it assures 100 percent leak
proof. To provide mechanical strength these are provided with the cold rolled steel fins. The
height of the fin is according to the customer specifications. All the transformer tanks are given a
smooth finishing by using the shot blasting process.
16
2.12 Painting and finishing:
After cleaning a coat of hot oil resistance paint say varnish is applied on
the internal surface of the tank.
The external surface is coated with red oxide and subsequently by enamel
2.12.3 Finishing:
2.13 Tanking:
First the CCA jobs are loaded into preheating oven and kept for 8 to 10
hours at a temperature setting of 110°c for removal of moisture.
Then the jobs are tested for insulation check up using 2000 volts
megger and then tightened.
After this job o.c test is applied through 25% of the rated voltage on
LV side on each phase, to check the inter turns shorting if any.
17
Then fittings like HV & LV bushings drain valves, oil level indicator and
explosion vents are fitted to this tank.
Purely filtered transformer oil is then filled in the transformer tank and this
oil is maintained at the temperature of 60 degrees centigrade to avoid
further moisture check up.
This completes the tank up process and rest of the procedure is carried out
by the testing department.
Hence in this way the manufacturing process undergoes the above series
of steps and the transformer is made to dispatched to the required customer by the maintenance
department.
18
8. Available from Ribbon/foil Sheet / roll
Standard sizes
106mm,142.2mm
170.2mm,213.4mm
19
3.FAILURE OF DISTRIBUTION TRANSFORMERS
3.1 Introduction
DT (Distribution Transformer) is a static device without any rotating or moving parts and is
considered as most rugged device among all electrical equipment & should be least prone to
failure. Unfortunately for various reasons, the rate of failure of DT is high (20 to 30% annually)
in a number of Indian Power Utilities. This chapter examines the factors responsible for high
failures and steps to be taken to minimise it.
The factors responsible for failure of DT can be broadly classified into three categories namely
manufacturing defects, Utility defects and natural calamities.
3.3.1 Tank Size: Inadequate clearance to free circulation of oil in many Makes of Transformer,
have led to abnormal temperature rise, causing sufficient damage to the HV winding insulation
and consequently premature failure of transformers. Therefore Tank size and Quantum of oil
should be adequate.
The Percentage of impedance depends upon 2 factors namely Size of Wire used in HV Coils and
Radial Distance between HV & LV Coils.
3.3.3 Size of Wire used in HV Coils: Economical size of coil will yield lower size gauge wire,
but this will reduce mechanical capability of coils as a result the coils may not be able to
withstand higher current densities which occur during the short circuit conditions.
3.3.4 Radial Distance between HV & LV Coils: Increasing the radial distance between HV and
LV coils increases the percentage of impedance and this will lead to higher cost. But this will
20
lead to better mechanical strength of the coil to withstand higher short circuit stresses developed
during short circuit conditions.
3.3.5 Effect of Impedance on the Short Circuit Stresses: The short circuit stresses are
proportional to the square of the short circuit current. The impact of keeping the impedance at
4.5%, 5% & to 5.5%, on the short circuit stresses developed in the transformer is illustrated here.
3.3.6 Improper Use of Aluminium Wires: This leads to HV Coil failure. REC recommends use
of Aluminium conductors for windings upto 200 kVA transformers. Use of higher cross section
wires with paper cover insulation instead of enameled wire may be specified, the super enamel
covering aluminium wire tends to crack during asymmetrical condition that leads to coil failure
and this can be avoided with double paper covering conductor.
3.3.7 Improper Use of Inter Layer Papers: Major portion of coil failures are seen as electrical
failures. These electric failures occur once when interlayer insulation breaks down or at the end
of the turn and creeps to the next layer. This type of insulation failure can be avoided by using
folding papers and reinforcing the end turn insulation with proper sleeves Further HV coil, has to
be separated uniformly along with the inner coil spacers so as to avoid pressing of only end turns
as well as to avoid any further shrinkage during service.
Improper Alignment of HV Windings: When the transformer is loaded, the primary and
secondary ampere turns acts in magnetic opposition with respect to the core and coils and the
space between these are magnetically excited. In case of a small error in the alignment of either
of the coils, an asymmetrical ampere turn balancing, leads to production of cross fluxes resulting
in mechanical failure of the coils.
3.4.2 Improper Connections: In many cases the connecting delta leads to the bushing are not
properly supported on the frame work, resulting in breaking during transhipment or at the first
21
charge. Improper soldering of leads will result in open circuit due to even normal full load
conditions also such transformer may fail during encountering the first fault or a few faults.
3.4.3 Inadequate Tightening of Core: Even with proper fuse protection on the HV side,
inadequate tightening will result in failure of transformer due to collapse of the windings. Even
under minor fault condition in the LT distribution, due to mechanical vibration in the core and
windings due to the above fault, the transformer will fail.
3.4.4 Continuous Over Heating and Higher No Load Losses: In addition to normal full load,
continuous over heating and higher no load losses may reduce the life of the transformer, due to
reduction in life of insulating papers, oil etc.
The quantity and grade of input materials of core and windings furnished in the tender may be
verified with the design calculation of the bidder and this will ensure that the losses and
impedance furnished in the tender would be achieved in the transformers.
3.5.1 Over Loading of Distribution Transformer: Inadvertent connecting of extra load more
than capacity of DT, unauthorized load can be identified by periodical testing of current in
distribution transformer using Tong Tester at peak hours and other times of the day. Transferring
the load to the near by transformer or enhancement of the existing transformer capacity or
proposing a new transformer will avoid transformer failure even though total load may be within
limits of DT capacity. Unequal loading in three phases may also cause over loading in one phase.
This also can be detected by Tong tester readings. Redistribution of the loads will avoid
transformer failure.
3.5.2 Usage of Improper Size of HG Fuse: HG fuse is the only main reliable protection for the
DT other than CSP type under condition of fault in LT distribution. The importance of HG fuse
protection can be appreciated considering the following facts
22
The most reliable protection for the transformer is the HG fuses only as the LT fuses
being of a heavy size for dealing high currents on the LT side, the chance of LT fuses
blowing in short time is less.
Higher size HG fuses will sustain the faults for longer period causing damage leading to
failure.
Usage of proper size HG fuse will minimise damage in case of fault within the
transformer.
3.6 Improper Maintenance
3.6.1 Tree Branches Touching LT Lines: Tree branches touching LT Lines will reflect as high
impedance earth fault, resulting in sustained over loading off resulting in failure. It may result in
conductor snapping or cracked LT pin insulators. This in turn causes heavy earth fault current
which may lead failure, if protective devices do not act promptly.
3.6.2 Tree Fouling on HT Lines: This may cause failure of transformers due to flow of earth
fault current since the primary of all the transformers are delta - connected and all the 3 windings
from cluster of transformers connected to this HT distribution line will feed the fault apart from
the source of substation.
3.6.3 Non Maintenance of Breather: Non provision of fly-nuts for the breather container will
create a gap through which moisturized air wilt enter into the transformer tank. To arrest this
gap, neophrine gaskets are to be provided instead of rubber gaskets. Rubber will damage, if it
comes in contact with transformer oil. If oil is not filed in the breather, then the dust particles
will not be absorbed from the air entering the transformer tank causing transformer failure.
3.6.4 Oil Leak in Bushings or any Other Weak Part of the Transformer: Oil leak may be
due to excessive heating or pressure developed in the bushing. This will bring down the oil level
in the tank and also moisture will find access into the tank through the aperture from which oil is
oozing. Because of this oil in tank will be contaminated resulting in deterioration of HV/LV
insulation and ultimately to transformer failure. To avoid these bimetallic clamps with proper
size of bolt and nuts connected to the LT bushing will reduce excessive heating and damage to
bushing rods.
23
3.6.5 Low Oil Level: The non-visibility of the oil level in the gauge glass level due to
accumulated dust may not show the exact level in the tank. The oil is likely to go below the core
level, the jumper wire from core winding assembly to the bushing rod will not be covered with
oil, this leads to excessive temperature rise and the failure of inter turn insulation and flash over
the windings.
3.6.6 High Oil Level: The Oil should be filled upto the marking in the conservator tank. There
should be space in the conservator tank for expansion of oil when the transformer's loaded, if the
conservator tank is filled with oil, then the transformer may fail due to high pressure by
explosion of vent pipe.
3.6.7 Low BDV of the Oil: Oil contamination may cause the BDV of the transformer oil to be
very low. This results in the increase of the carbon content and decrease of resistance in the oil.
The temperature of the oil will not be reduced and hence aridity of the oil increases resulting in
deterioration of insulation of the windings and transformer failure.
To avoid this oil has to be filtered to remove the dust and processed through the reclamation
plant to reduce the acidity and improve the BDV value of the oil.
3.6.8 Low IR Value: This may be due to moisture content in the oil and in the winding
insulation. This may cause transformer failure. To avoid this, the transformer core with windings
should be placed in Hot air chamber till the moisture content is removed from the core and
windings insulation.
3.7.1 Heavy Lightning: If HT LA'S fails to divert the direct stroke or surges due to discontinuity
in earthing system, this will result in either failure of HV winding due to surge voltage or
bursting of HT lightning Arrestor itself.
3.7.2 Bushing Flash Over: Dust and chemicals carried away with air and deposited on the
bushings will reduce the electric leakage distance causing flashover. To avoid this, clean the
bushings (both HT & LT) periodically with banian waste. If cotton waste is used for cleaning
this may cause scratches in the bushing & subsequently leading to flashover to bushing.
24
3.7.3 Failure due to Bird Fault: To avoid failure of DT due to squirrel crossing the DT or due
to the birds sitting on the transformer, the HT/LT bushing and HT/LT jumper leads from the
bushing may be covered with yellow tape insulation. This yellow tape insulation will also
indicate the overloading phase of the transformer by the colour of the tape changing from Yellow
to Black.
The determination of cause of failure of DT is important to plan strategy for reduction of failure.
But concluding cause of failure from preliminary reports and maintenance record of field is
difficult for various reasons. The best method to arrive at causes in by examination of damages
caused in failed units. The Table gives the probable cause of failure based on damages observed
on failed unit.
1. Top coils in all 3 phases got charred and all Lev.- oil level
coils below them are 6,K
3. End coils got damaged Severe external short circuit not cleared
4. Insulation on all coils in all phases turned Obvious case of continuous overloading
brittle
- Ageing
- Bad Oil
- Moisture
6 Puncturing of Coils
7. Strips forming L.V star point got sheared Unbalance in loading coupled with bad
25
earthing
10. High magnetizing current and flash to core Core bolt insulation failure
26
The high rate of failure of secondary distribution transformers in power systems may
perhaps be described as one of the tragedies of distribution system management of present times,
especially in developing countries like India.
The advent of CSP technology has encouraged progressive manufactures to go in for high
performance distribution transformers which mitigate the operation and maintenance problems
associated with conventional transformers.
Every year distribution transformers worth nearly 200crore rupees fail in power
distribution companies in India. The average period before a new distribution transformer comes
back to repair shop is estimated to be a mere 3-4 years. Even a conservative estimate puts the
failure rate at over 20% compared to less than 1-2% in many utilities in advanced countries.
Why should these simple, static, silent and efficient pieces of electric equipment fail in
such large numbers causing enormous loss to electric utilities?
Distribution transformers in rural areas form the bulk of the transformers in service. They
are very much exposed to changing weather conditions and more dangerously to lightning.
Distribution transformers in low load density rural areas feed lengthy low voltage lines
which are themselves prone to faults, not merely because they are with, bare conductors and in
exposed environment but ate also carelessly constructed.
27
assuming unrealistic diversity factors. Unauthorized loads result in unforeseen overloading.
Periodical checks are not made for overloading and corrective measures are not taken.
Wide variation in load levels and ambient temperature makes undesirable breathing and
ingress of moisture even more intense in the case of rural distribution transformers. The
interchange of air brings oxygen from the atmosphere into contact with oil it is well known that
moisture weakens the dielectric strength of oil to form sludge and finally causes a deposit to
form on the windings. The deposit may in time be sufficient to obstruct the ducts placed in the
windings for the purpose of oil circulation resulting in temperatures higher than those for which
the transformers are designed. Ultimately the insulation of the winding may become carbonized
to such an extent as to cause failure. The dehydrating breather is more often than not in a
deteriorated condition to be of any use for want of timely check and reconditioning/replacement
which is not practicable because of the ever increasing number of these transformers in the
distribution network.
Power utilities in India provide horn gap fuse (HG Fuse) on primary side and a
rewirable fuse with fuse holders set on LV side of a distribution transformer for system
protection.
Both the HV and LV fuse sets provided externally are exposed to all weather conditions like
wind and rain. They become mechanically weak very soon and blow frequently.
28
They are vulnerable for tampering by eager consumers especially in rural areas who would
replace the blown fuses with the available fuse wires mostly with higher size wires which
cannot protect the transformer from over loads.
CSP Technology shows the way out of this distressing situation. Unfortunately, the
advantages of CSP Technology are yet to be fully appreciated by a majority of power utilities in
developing countries.
Primary Fuse: Internal expulsion fuse (other than oil filled) for system protection.
Secondary Circuit Breaker: for overload and secondary fault protection. Signal Light,
The Emergency Control, Magnetic trip.
Surge Arrester: for lightning protection.
29
4.6.1 Primary (High Voltage Fuse)
Power Utilities in India provide a HG Fuse on primary side of a distribution transformer
for system protection, it has the following demerits.
It is exposed to wind and rain and becomes mechanically weak very soon and blows
frequently.
It is vulnerable to tampering by eager consumers especially in rural areas who would
replace a blown fuse, with the available fuse wire.
It is not ensured that it does not blow for secondary faults and inrush current
surges.
Ideally the primary side fuses for an outdoor for distribution transformer should be
internally mounted (tamper proof) and the rating is determined on the basis that it should not
blow for secondary faults and exciting current surges. British Electricity Authority have found
from experience that when the fuse is rated to stand 12 times the full load current for 10ms it
meets the requirement.
30
In a CSP transformer, the primary fuse which fulfills the above requirement is placed in
series with the primary winding. This fuse is normally mounted inside of the primary bushing
and is connected via a terminal block to the high voltage winding.
The purpose of this expulsion fuse is to protect the part of the electrical distribution
system, which is ahead of the transformer from faults which occur inside of the distribution
transformer. If a fault occurs in the windings or some other part of the transformer, it will cause
abnormally large currents to flow and the flow of these currents will cause the fuse to melt open
and clear the circuit. In this way, the fault is limited only to those customers who are served by
this particular transformer and service is maintained on the rest of the system. When this type of
fault exists, the transformer is no longer usable and must be removed from service for repair.
Any fault ahead of the transformer will not be seen by any of the transformer's internal protective
devices and will have to be cleared by some other protective device upstream from the
transformer.
31
The average temperature of the transformer winding at any time, is given by the average
oil temperature plus the average winding temperature rise due to the instantaneous load current.
In general, these will be or maximum value of average winding temperature which should not be
exceeded if the transformer is to function satisfactorily over its normal product life. One of the
functions of the circuit breaker is to make sure that this predetermined value of average winding
temperature is not exceeded.
Maximum oil temperature could also be the limiting constraint. In many cases oil
temperature limits are established recognizing the inflammability of insulating oil and these can
be the limiting thermal parameters (instead of average winding temperature) in certain
transformer designs.
The CSP circuit breaker in order to be universally applicable to all transformers and all
thermal constraints, has protective characteristics which are sensitive to the same thermal inputs
as the transformers.
4.8 Secondary Fault Protection: The Other Important Function of the CSP Circuit Breaker
The CSP circuit breaker will respond to secondary faults external to the transformer by
tripping open, and in most cases, this action will prevent any thermal damage occurring to the
transformer. This feature is particularly important for the installations where un-insulated
Secondary distribution and service lines are used. The use of bare conductors increases the risk
of faults especially in areas where there is large growth of trees and vegetation.
If the circuit breaker does trip in response to even a temporary secondary fault,
service can be restored easily by clearing the fault and reclosing the circuit breaker.
When the simple action of reclosing the CSP circuit breaker is compared to the action
required in the case of a non CSP transformer where either a primary fuse or secondary fuse
must be replaced, the benefit of CSP technology is apparent.
32
For all that it does the circuit breaker is of relatively simple construction. It is an electro
mechanical device with three major elements. These elements are:
Temperature sensing,
Latching and tripping,
Current interrupter.
The temperature sensing function is accomplished through the use of bimetallic strips
which are built into the breaker such that the load current flows through them.
The circuit breaker is mounted inside the transformer, so that these bimetallic strips are within
the top layer of the transformer in this way, the critical thermal modeling of the transformer by
the circuit breaker is accomplished because the bimetallic strips are responding thermally to the
temperature of the transformer oil and also to the temperature changes created by the flow of the
load current through them.
The latching and tripping functions of the circuit breaker are carried out with an assembly
of parts quite similar to those used in industrial type air circuit breakers. Other features that are
built into the latching and tripping functions are
A signal light is mounted on the wall of the transformer tank. It gives a visual external
indication that the transformer has reached a specified level of overload and overload duration at
least once, and thus alerts the power utility about the need to change out transformer for a longer
size in time.
33
SIGNAL LIGHT
The signal circuit is mechanically connected to the circuit breaker latching and bimetal
systems through an auxiliary contact. The signal light circuit consists of an auxiliary transformer
winding (one turn) which generates about 3 volts and signal light contacts set within the circuit
breaker. Signal light is mounted on the wall of this transformer tank.
The signal light contacts will close at a preset thermal condition. This occurs before the
main latching system opens the main contacts.
The signal light mechanism does not reset itself when the load drops off. The signal light
remains lighted once the signal light contacts close and can only be turned off by manually
operating the external handle of the circuit breaker. However if the overload has persisted the
signal light will relight as soon as the operating handle is restored to its normal position
indicating the need for a larger size transformer.
This device is provided when the power utility wants the facility of immediate restoration
of service in an emergency by closing the circuit breaker even when the preset overloading limit
is reached.
Once the emergency control is activated the circuit breaker is no longer thermally
protecting the transformer and significant insulation deterioration can occur if these high loads
reoccur.
Once it becomes necessary to activate the emergency control, the power utility should
plan to change out the transformer for a larger size as soon as possible.
34
The emergency control linkages can be externally activated to increase the amount of
engagement of the main and signal light latches within the circuit breaker which has the effect of
requiring more bimetal strip movement to trip the circuit breaker open and more bimetal
movement requires higher temperature.
Certain circuit breakers are furnished with an instantaneous magnetic trip element in addition to
the standard bimetallic thermal trip element. The magnetic trip element increases the opening
speed of the circuit breaker under high fault current conditions. This increased opening speed
permits the circuit breaker to interrupt larger values of fault current than would normally be
possible. The response of the circuit breaker to thermal activity is unchanged by the addition of
the magnetic trip element.
One of the most important design tasks which are done by the CSP transformer design
engineer is the coordination between the primary fuse and the secondary circuit breaker as
mentioned earlier, in performing this coordination task, the design engineer must use the
minimum melt time current, characteristic curves of the primary expulsion fuse and the average
clearing time current characteristic curves for the CSP Circuit breaker. Coordination should be
such that the circuit breaker clears the circuit for any fault on the load side of the transformer
before the primary fuse melts. In order to achieve this coordination, the calculations are made for
the worst case.
35
The maximum secondary current that can flow under any fault condition is that current
created by a bolted fault on the secondary terminals of the transformer. Usually, when this
calculation is made, an infinite bus is assumed on the primary side of the transformer and the
transformer's own impedance is taken as the only current limiting impedance. Coordination is
achieved by selecting the expulsion fuse's minimum melt curve and the circuit breaker's average
clearing curve so that under this worst case situation, the circuit breaker will clear the circuit
without the expulsion fuse melting.
If the coordination is not properly done, the expulsion fuse can melt when the fault is on
the secondary side of the transformer thus bypassing the protective function of the circuit
breaker. When coordination is properly done, the melting open of the primary fuse, generally,
can only occur when a fault is inside the transformer. When this type of fault occurs, the
transformer is no longer usable and must be removed from service and taken to a repair shop. If
the fault had been on the load side of the transformer, the circuit breaker would have interrupted
the circuit.
Of course, any fault ahead of the transformer will not be seen by any of the transformer's
internal protective devices and will have to be cleared by some other protective device upstream
from the transformer.
The closer the surge arrester can be mounted to the transformer, the shorter will be the
ground lead connection between the arrester and the transformer. The shorter this connection, the
less will be the lightning surge induced voltage stress on the transformer winding. When the
36
surge arrester is mounted directly to the transformer tank (as in the case of CSP transformer) the
ground lead length is effectively zero and maximum transformer protection is obtained.
4.15 How CSP Technology Facilitates Optimum use of the Transformer's Capability?
In the case of cyclic loads (containing peaks and valleys) where peak load is of relatively
short duration, transformers considerably smaller than the peak loads can be safely installed
without any concern for rapid loss of transformer life due to overload. The CSP Circuit Breaker
will permit the transformer to function within cyclic loads up to the point where the amount and
duration of the peak load begins to cause significant loss of transformer life. When this point is
approached, the signal light will light with the first indication that the loads on this particular
transformer have grown to the point when significant insulation deterioration can occur.
With the signal light indication mentioned, several options are open to the power utility.
They are
A change out of the transformer for a larger size can be planned for at a future convenient
date.
The signal light may be reset to determine if it will light again indicating that the
overload condition has become a normal load condition at this site and then a change out
can be planned-
Nothing can be done except to wait and see if the breaker itself will trip open at some
future date.
If nothing is done, and the load continues to grow at the location, eventually a condition
of peak load and load duration will be reached which will cause the circuit breaker to open. At
this point the lineman from the power utility must be sent to the transformer location in order to
restore electric service to these customers.
37
3. Not plan a change out and see if the load reaches these levels again and causes the circuit
breaker to trip open.
4. Finally, it may not be possible to close the circuit breaker at all because the connected
load has not dropped off and the circuit breaker will trip open as soon as it is closed.
The CSP circuit breaker thus provides several types of warning to the power utility of the
existence of overload conditions long before it becomes mandatory to change out the
transformer.
To overcome the problem indicated at (4) and to permit the power utility to rapidly restore
services without having to perform an immediate transformer change out, most CSP transformers
contain the emergency control element.
It is these early warning features which permit the power utility to effectively plan its
transformer loading so that maximum use of the transformer's capability is obtained without
sacrificing significantly the life expectancy of the transformer.
Lower Installed Cost: Less external mounting arrangement and connections there is no
need for separate mounting arrangement for primary fuse, surge arrester, low voltage
circuit breaker and connecting leads.
Less time for Installation: A non CSP installation takes twice as long as a CSP
installation.
Easier and Simpler Installation: Less external connections and spacing for electrical
clearances. Transformer, surge arrester, H.V.Primary Fuse and secondary circuit breakers
are one compact unit.
4.17 SAFER OPERATION
38
be restored quickly, and safely. One procedure commonly used is to send the lineman to the
location. The lineman inspects the installation for any obvious secondary faults and finding none
places a new fuse in the cut out to restore service. If the fuse operates again, he replaces it and
tries again. In some cases there were failures causing harm to person (s) and property. The
chances of this kind of failure occurring can be reduced significantly in the CSP transformer
because the circuit breaker provides the type of protection which will prevent excessive oil
temperatures and/or severe damage to the transformer insulation system, When severe failure
does occur within the CSP transformer, the internal primary fuse operates - operation of this fuse
is a signal to the lineman that a severe fault has taken place and the transformer must be
replaced. There is no provision in the CSP transformer installation for the replacement of any
primary side fuse because the fuse operates only when the transformer itself has been damaged.
In the case of the non CSP transformer installation, there is no early warning of
increasing load on a particular transformer. The load will Increase until either the transformer
completely fails or the cut-out fuse operates. When this happens, the consumer is suddenly
without electric service, generally during peak load time, and a lineman must be sent out to try
and restore service and alert the power utility to the potential overload problem at the
installation. As stated before, once the potential load problem is identified, it can be corrected on
a planned basis through planned transformer change out. A planned transformer change out
creates much less of a problem for the consumer because the consumer can be informed of the
time of change out, the consumer will be without electric service for a very much shorter period
of time and the change out can be scheduled for a time of day when the demand for electric
power is minimal.
If the transformer has been severely damaged, the serviceman must call out
repair over to replace the transformer which will create a service outage of several hours
duration.
39
The CSP transformer, as load builds up, will light, the signal light and alert the power
utility to the potential overload problem at the installation. As stated before, once the potential
load problem is identified, it can be corrected on a planned basis through planned transformer
change out. A planned transformer change out creates much less of a problem for the consumer
because the consumer can be informed of the time of change out, the consumer will be without
electric service for a very much shorter period of time and the change out can be scheduled for a
time of day when the demand for electric power is minimal.
Checking for any oil leaks and Replacement of oil seals does
rectification (including not arise as there is no breather.
replacement of oil seals if The transformer is hermetically
required) sealed and ingress of air &
moisture affecting oil is ruled
out.
40
light is calibrated to operate
when the temperatures effect of
the instantaneous toad current
plus the steady state oil
temperatures as above 80 percent
of the value which will trip open
the circuit breaker.
Automatic Load Management: The CSP Signal light at each transformer provides
information about loading conditions. This can be used by the power distribution
company to manage the loading on the transformers to insure the best economic use of
each size transformer. This concept is further explored under Benefit - 6.
4.19 Lower Cost of Operation
There are some very sophisticated analytical techniques available which compare the cost
of operating two different sizes of transformers with a given load profile. As the load
increases, a point is reached where the best economic decision is to replace the smaller
size transformer with the larger size-Use of this type of analysis requires continuous
knowledge of the loading on individual transformers and a thorough knowledge of the
system economics involved.
The CSP technology method of optimizing loading on individual transformer relies upon
the information provided by the signal light. Normally, the signal light is calibrated to
41
operate when the temperature effect of the instantaneous load current plus the steady state
oil temperature is about 80% of the value which will trip the breaker.
Lower Maintenance Cost and Time From the comparative statement of schedules of
maintenance for conventional secondary distribution transformers and CSP secondary
distribution transformers, it will be seen that CSP transformers offer great, advantage to
power utility in reducing the time and cost of maintenance of the ever increasing
population of distribution transformers in Power utilities.
Neater Appearance
CSP transformer installation presents a much cleaner and uncluttered appearance. Unlike
the non-CSP transformer installation with mounting arrangements for externally fixed
protective equipment like primary fuse, surge arrester and secondary circuit breaker and
electrical connections between them.
D J Ristuccia, the Westing House Engineer aptly describes the CSP transformers as
"beautiful in concept and in physical appearance".
42
The existing rural distribution system in India consists of largely 3 phase 11 KV
main distribution feeders with 3 phase and 11/0.4 KV three phase distribution transformers. The
distribution system on low voltage side is done by 3 phase 4 wire, 3 phase 5 wire, single phase 3
wire, and single phase 2 wire LT lines. This system involves nearly 2:1 ratio of LV and HV line
lengths. Large LT network results in high occurrence of LT faults leading to frequent
interruptions in supply and high incidence of distribution transformer failures due to LT fault
currents.
This system is unsuitable to cater certain areas like villages, desert, tribal and forests
where the load density is very low and the development of load in these areas is slow. Heavy
capital investment on 3 phase 11 KV lines with higher rating 3 phase transformers is not
economically justified.
To improve the quality of supply, one of the recommendations is the implementation
of "Single phase HT distribution system with small capacity single phase transformers”. Under
this system HT line is extended up to or as near the load as possible and to erect small capacity
distribution transformers i.e. 10 KVA, 16 KVA and to extend supply to the consumer through a
short length of LT lines, preferably insulated overhead cable (Aerial Bunched Cables) system.
43
1. Current (Amps) 11.0 100
2. Losses (KW) 8.5 100
3. Voltage drop (KV) 12.7 100
The LT lines have to be laid using aerial bunched cables (ABC) of size 16 Sq. mm
with a bearer wire. The length of LT lines has to be kept minimum level to reduce LT losses. It
is seen that the cost of line is cheaper compared to conventional LT 3 phase line used in LT
distribution system.
The major advantage of ABC is that the fault on the LT lines are totally eliminated thereby
improving the quality of supply, besides elimination of theft of energy/ conductors reduced
height of supports and elimination of isolators/ associated hardware, etc.
1) In single phase system only few numbers of consumers are connected to a particular
transformer, as a result of which chances of unauthorized connections and energy
thefts are reduced.
2) Reduction of system faults because of low length of LV lines.
3) Distribution losses are reduced by 75% or more depending on the load factor
4) The HVDS is cost effective to electrify remote villages where bringing of long 3
phase lines is costly due to low demand.
5) The single phase line can be upgraded to 2 phase or 3 phase circuits in future, if the
load growth warrants it. The power utilities can keep the investment low and cut
down the expenses during the initial period of low demand and electrifying remote
rural areas.
6) In the event of failure of transformers, it will affect only a small number of
consumers, whereas failure of large sized distribution transformers will affect large
number of consumers.
7) In view of less LT system and usage of ABC, which has tough insulating cover, direct
tapping by unscrupulous consumers is avoided.
8) Since losses are reduced considerably, power can be supplied to additional loads
without any further investment on infrastructure.
9) No additional generation capacity is needed for giving power to new loads as there is
a reduction in power drawn.
10) Single phase motor up to 5 HP can operate efficiently on single phase lines. The
power factor of these motors is nearly unity. And thus the system efficiency also gets
improved.
44
5.5 Merits and Demerits in comparison to 3 phase LV systems:
1. Line Losses: The losses in H.V.D.S for distribution of same power are much less when
compared to that of L.V.D.S. Thus, the losses in LV network are negligible bringing down
the total energy losses considerably.
2. Voltage Drop: The voltage drop for distribution of same power is less than that of L.V.D.S
and thus ensures proper voltage profile at consumer points.
3. System Power Factor: The single phase motors have built in capacitors and PF is more than
0.95. This high PF causes low energy losses and better voltage profile.
5. Theft of Energy: The LT lines are virtually eliminated and even short LT lines required will
be with AB Cables. This makes direct tapping very difficult.
6. End Use Equipment: Due to better voltage profile, the efficiency of end use equipment is
high, bringing in considerable benefit by way of energy conservation.
7. Reliability of Supply: The failure of transformer will affect only a small number of
consumers served by it, thus the reliability of supply is high.
8. Voltage Fluctuations: The voltage drop on LV lines is negligible and voltage profile is very
stable. Any voltage fluctuations occurring can be remedied by installations of Automatic
Voltage Regulators on H.V line.
From the figure (1) it can be seen that power is directly tapped from the parallel
lines by the 3-phase transformers and then is supplied to the various loads. Also we can observe
the presence of many L.T lines which accounts for very high losses.
45
Fig (1) Connection Diagram of L.V.D.S
The figure(2) below is that of a typical high voltage distribution system where the
loads are fed by small capacity individual transformers. A noticeable difference is the reduction
in the L.V lines and corresponding increase in the number of H.V lines which eventually reduce
the losses.
To implement H.V.D.S, the present system i.e. L.V.D.S need not be completely
removed. But the same system could be restructured to H.V.D.S with minimal changes and used
with good results.
46
Existing L.V lines are restricted to H.V lines by
1) Replacing large 3-phase distribution transformer with small capacity 1-phase or 3-phase
transformers (5, 10, 15, 25 kVA).
2) Same conductors could be used because H.V lines carry less current than L.V lines.
3) L.V 3-phase cross arms are replaced by 11KV cross arm.
4) Replacement of 3 numbers LT pin insulators with 3 number 11KV pin insulator.
5) Replacement of 3 numbers LT shackles with 3 number 11KV strain insulator.
6) Erection of additional support where ever clearances are inadequate.
In case 1, the existing 3-phase, 4-wire L.V lines is restricted to 1-phase and neutral. Here
the 1-phase are connected through small D.T.R to the 3-phase H.V lines. The D.T.R is tapped
between any phase and neutral.
In case 2, the restructuring is done in the same way as case 1, except for the D.T.R which
is connected between the phases. In this case the neutral wire is not needed but the D.T.R turns
ratio would be more, hence even the cost would be more.
In the case 3, the L.V.D.S is directly given to smaller capacity 3-phase D.T.R and thus
power is tapped.
Let us consider the case of Kotturu, where 15KVA transformers were erected and
operated for 15 days. The results are tabulated below.
47
3 Input 5310 units
4 Output 5019.2 units
5 Losses 290.8 units
6 % of line loss on H.V.D.S 5.47%
7 % of line loss on earlier LT distribution system 18.63%
8 % net reduction in line losses 13.16%
6.Conclusion:
The scope of our project includes the manufacturing of a single phase amorphous core
transformer and we also added an introduction to high voltage distribution system.
48
The amorphous core is the latest technological advancement in the development of
distribution transformers with which decreases no load and core losses when compared to
that of the conventional transformer.
The CSP transformer is hermetically sealed (top covered welded to the tank).
There is no scope for ingress of moisture during breathing due to variations in ambient
conditions and loading pattern. Pilferage of oil from the transformers can be eliminated
which is very common by the unscrupulous persons.
Built in protection is available for external and internal faults. The space above the oil
level is filled with nitrogen. Thus expansion of oil is taken so that chances of failure of
transformer is very remote.
Hence CSP technology provides protection against internal faults, lightning and
external faults (over loads).
The H.V.D.S is technically superior to that of the LV distribution system with regard to
the quality of supply, better voltage profile, reduced losses and reliability. However this
system is costlier, but it is more economical when compared with the other.
49
7. BIBLIOGRAPHY:
1. Study material of M/s Vijai electrical Ltd .
-Mr.T.Sugunakara Rao
Advisor,VEL
50