Construction Specification
Construction Specification
All construction and roads will be made according to the basis stated below.
Building and channel applications will be made on the construction area where general area
excavation is completed according to the coordinates basics.
Excavation works is made by a machine or worker with the approval of Project Manager.
Excavation codes are determined. Excavation will be delivered to the base construction with
the completed compacting. Materials taken from the excavation are preserved if its quality is
good in order to be used on filling later. Remaining materials are transported on a distant area
of the plant. The cost for base excavation and side filling is paid one time. Filling cost is
included to excavation cost. (Base, connection beam, places where made channel production,
roads area, all places which are made excavation)
2) Filling Works:
Materials which will be used on filling works are sand, clay, gravel materials. The proctor test
of the material which will be used on filling must give the %98 compactness. Project Manager
should be informed about the test results before the delivery of the materials on construction
site. Materials should be approved by the Project Manager.
Approved materials will be delivered on construction site. Under base, road and inside the
building, filling materials, will be put on a 30 cm width and compacted by a 20 tone roller.
Narrow places compacting will be done by hand made. Thickness of fillings layer will be 30
cm and will be spread layer by layer. During the irrigation of filling material, humidity level
should not pass 20%.
Single foundation which will be constructed on the scope of this project, single or two
continuous foundations or spread foundations are shown below.
All foundations will be placed on safe foundation.
Proctor 98%n compactness should be considered on foundation floor of the foundation
which placed on filling ground and settlement test must be done.
Under the foundation and on the final ground, polyethylene nylon of 8gr per square
meter should be spreaded. On single foundations and on foundations which are built
on the outside axes of the facility, nylon cover should be turned on foundation upper
level.
After the completion of the construction of foundation, back filling will be completed
as shown on filling specifications, degree of the back filling should be proctor 98%
compactness.
Under the foundation, working platform named lean concrete layer should be placed.
Protector Nylon polyethylene should be laid underneath.
Construction joints and expansion joints of the unfinished slab will be filled with
polyurethane based joint filter. On a finished covering surface no water accumulation
will appear. All water will be accumulated in channel and gully. Water accumulation
is not acceptable.
The soil should be stable, smooth (should have suitable leveling) and compacted. Especially
for base course, granular filling material should be used and silt / clay content should be low.
If silt/clay ratio is more than 5 %, this filling material doesn’t contain water more than
optimum water content.
During the economic life of building, water content should be stable by drainage system.
Filling:
2. JOINTS/BAYS
Insulation Joints:
Soil slab concrete and construction elements (walls, columns, beans, etc.) should be separated
by insulation joints. These joints should be constructed by flexible joint filler. Joint spacing
should be 5-20mm and determined according to the dimensions of bays.
Control Joints:
After casting slab concrete to prevent any cracks which come from contraction, control joints
should be formed.
The bays are formed by control joints should be square. If not, it can be formed as rectangular
but long side/ short side ratio can’t exceed 1,5.
- By Cutting
After casting concrete, between 24 and 48 hours, the concrete should be cut by jointer. Joint
spacing should be 3-4mm and depth should be 1/3-1/4 of concrete thickness. After 21 days,
these joints should be filled by appropriate joint filler.
Large area slab concrete should be separated by cont./exp. joints. If opposite thing is not
determined. For each 400-1200 m2 area, joints should be formed to prevent any cracks come
from temperature effect.
Cont./Exp. joints should be formed by steel base elements before casting concrete. Joint
elements can’t prevent concrete movement.
Construction Joints:
These joints are formed when casting concrete is stopped because of any cause. When
concrete casting is stopped, concrete should have determined height and vertical surface
should be smooth. For each 300mm, additional reinforcement which has 800 mm length and 14mm
diameter should be placed joint. The half of the reinforcement should be left in the first step
concrete; other half should be left in the second step concrete.
Min. 15 days before casting concrete, suitable bays should be determined for above joint
systems.
3. CONCRETE
-Concrete Contents
Cement : Normal Portland Cement,
Aggregates : Fine aggregate : Sand (Natural sand or Crushed rock sand)
Coarse aggregate: Crushed stone
Water : Water used for mixing concrete should be free of materials that significantly
affect the hydration reactions of Portland cement. Water that is fit to drink may
generally be regarded as acceptable for use in mixing concrete.
Admixtures : Plasticizer
Setting retarder or Setting Accelerator
Not: If need, admixtures will be used.
Cement Content : 300-380 kg/m3
Aggregate: Max. grain Size = 20mm
2-7mm : 40 %
7-20mm : 60%
Sand : 700-800 kg/m3
B : Steel Connections
D1- Welded Connections
D2- Bolted Connections DIN 267 (10.9 )
C : The following international specifications are in use for this steel structure specification :
DIN 1025 , DIN 1026 , DIN 1028 , DIN 1029 , DIN 1050 , DIN 1541 , DIN 1542 ,
DIN 1543 , DIN 6914 , DIN 6915 , DIN 6916 , DIN 6918 , DIN 4100 , DIN 4115 and
Related EUROCOD, BS; AISC Specifications for the Design,
Fabrication and Erection of Structural Steel for Buildings, AWS.
D : Control of welds.
F : Protective paintings.
I : All of the QC criteria to be obeyed in this contract, have to be concordant with ISO 9002
St33, St37-2, St44-2, St52-3 are the structural steel materials to be used in this steel
construction. All of this materials have to be satisfied DIN 17100 specification.
B : Steel Connections :
B1 – Welded Connections :
All of the welds defined in the related drawings have to be fit with DIN 1913 or AWS
specification. Weld Lengths and widths are defined in the application drawings.
Bar and plates connected with welds should be sand blasted, quality certified and approved
materials. Meanwhile, these materials have to be cleaned; removed from oil; rust, paint etc.
It is possible to construct load carrying members as well as built-up columns from St-37
an/or St-52 steel materials. In case of assembling load carrying structural members by means
of built-up sections, all of the welding should be full-penetration welds by forming edge
preparation. Application should be done according to DIN 1913 and/or AWS
Connections used in this steel specification, should be done with manual electrode welding
having 2-8mm electrode thickness. In built-up sections such as columns and beams,
submerged arc welding should be used.
B2 – Weld Defects :
After the welding process, some defects may occur in the secondary and main connection
elements. Some of these defects are metallurgical while the others are from thermal shrinkage.
- The following defects are due to insufficient weld preparation and they will never be
accepted.
Carving from bottom
Hydrogen crack
The abundance of pore
Insufficient melt
Slag entering
Concavity of root
Excess in full penetration
Excessive hardening
Failure in full penetration
Torn in the form of lamina
All of the above given defects should be checked with ultrasonic tests and should be given
periodically to the Project Manager.
Pre-tension in Bolts
Bolt Pre-tension
Diameter Force Ma : squezze moment
Pv Slightly lubricated
D : Weld Control
In this project all of the welding shall conform DIN 4100 and AWS.
These welds shall be checked with ultrasonic tests methods. The quantity of these tests will be
as much as required by the control engineer of Project Manager.
F : Protective Painting
Final painting should be done at side after steel erection have been completed. Slip critical
joints should never be painted.
The paintings that may be used in this construction are given below:
The corrosive level should be ISO 12944 C2 .
Assemblage and the erection of the steel structure should be done after quality control in all
aspect such as transportation, tolerances paintings etc. All the responsibility of the assemblage
and erection is on the Contractor.
Erections which do not satisfy the project (drawing) criteria will not be accepted.
Optical control shall be used in erection and assemblage. During erection, all type of
workman safety should be satisfied.
All of the steel structure shall conform the related structural drawings and technical
specifications. Structural Drawings used for the erection shall also be approved.