Planning Tools and Techniques
Planning Tools and Techniques
1.2 Purpose
Planning integrates various tools and techniques that are used to make it effective for the
organization. The purpose of the research is to discuss the use and application of certain
techniques in detail. Moreover, the subject matter of the research is to provide a sound
analysis of the techniques for a deeper understanding for the corporate sector.
1.3 Scope
The findings of this paper will be taken into consideration and put forward some
recommendations that how certain planning tools and techniques can be utilized for the
betterment of an organization. Moreover, the paper also discusses that the strategic planning
is supportive for the corporate sector.
Explaining the use of budgeting and forecasting, PERT, Gannt Charts, Sensitivity Analysis
and Scenario Analysis.
Identifying and applying various planning tools and techniques. Understating their usage and
importance.
2.2.1 Definition
‘The devising and formulation of organisational level plans which set the broad and flexible
objectives, strategies and policies of a business, driving the organisation towards its vision of
the future’ (Stonehouse and Pemberton, 2002, p. 854).
Strategic planning takes into account the strategic thinking ability. The main purpose of such
planning is drive innovation and creativity into the business. In traditional planning
techniques the staff planners were involved in planning the budgets, future events, dealings
and other related matters of the organization (Al Ghamdi, 2005). However, staff planners are
never able to devise an optimal for the businesses. To etch out an optimal plan for the
business strategic planning was introduced in the year 1980’s. Strategic planning is
undertaken by top level managers, line managers and involvement of experienced employees,
which yields more sophisticated planning techniques (Abdul Moyeen, 1997).
2.3.2 PERT
PERT is acronym for Programme Evaluation Review Technique, it is defined as ‘a precise
knowledge of the sequencing of activities’ and ‘a careful time estimate for each activity,
ideally with a probability estimate of the times the activity might require’. It uses arrow
diagram technique (ADM) to schedule techniques and assume each activity finishes at a node
from which others start – there is no concept of overlapping activities. It is one of the most
common techniques used by the managers in achieving targets in an elapsed time.
2.3.3 Gannt Charts
A chart in which a series of horizontal lines shows the amount of work done or production
completed in certain periods of time in relation to the amount planned for those periods.
These are very helpful in determining when the required tasks are to be completed. The
charts allow comparison with the actual progress on each task and serve as a control tool of
for different activities. The progress of activities can be tracked easily using the Gannt Chart
approach.
3.1.1 Forecasting
Forecasting typically uses the actual performance data of the past years to project the future
period outcomes. Usually a future period of 12 to 18 months is predicted using different
forecasting techniques. These predictions help the managers to develop a strategical plan to
achieve the set goals and objectives. Forecasts focus on what is happening from a revenue
and income statement perspective. Three of the major forecasting techniques are stated as
under:
1. Top-Down Forecasting
The top-down forecasting approach is primarily focused on the current demand and the
current operational conditions of the business. The revenue related predictions are translated
here. Managers that have a passive nature often opt for the traditional top-down approach.
2. Bottom-up Forecasting
The bottom-up approach is often followed by the mangers who are willing to take risks. This
approach relies on business managers to enter current and specific line item details as per the
revenue budget.
3. Hybrid
The top-down approach when coupled with the bottom-up approach, makes it a Hybrid
Forecasting approach. Most of the managers apply the hybrid approach according to the
needs of the business and requirement of the competition in the market.
3.1.2 Budgeting
Budgeting provides the actual execution path for the plans with detailed, short-term and
operational view. Planning provides business the outcomes about “what is possible”, while,
the budgets provide an outline on “what is expected” from the business (Welsch et. Al,.
1988). The budgets play a significant role in monitoring the historical progress of the
business and adjusting activities to meet the budgeted profitability goals. It may also integrate
new ideas in the business to achieve the expected turnaround.
The above shows the sales budget and the operational budget of a Mobile Shoe Repair
business, for the year 2019. The data represent the sales forecast of the first three months of
the financial period staring from 1st of January. It also outlays the budgeted expenditures for
the same period.
Activity Cost
Bank Loan to start the business $ 100,000
License, for the mobile van $ 6,000
Advertisement cost $ 500 per month
Equipment and Material $ 9,000
Total Capital Expenditure $ 121,000
Exhibit 1.1
3.2 PERT
PERT is one of the oldest techniques / way to model the uncertainty associated with duration
estimate used in the schedule. The managers use PERT to estimate the number of days
required for the completion of a specific task or project.
3.2.1 Definition
‘A precise knowledge of the sequencing of activities’ and ‘a careful time estimate for each
activity, ideally with a probability estimate of the times the activity might require’.
(Fulkerson, 1962)
3.2.2 The basics of PERT
PERT originated from the Arrow Diagramming Method (ADM), scheduling technique and
assuming that each activity will finish at a node from which the other activity will start. There
is no concept of overlapping of activities (Fulkerson, 1962). The activities of business
structure are not mingled rather each activity starts with a different node. There are three
basic steps to apply a PERT schedule (Dodin, 1985).
Firstly, a logic network is developed with different activities. Each activity is subjected to 3
time estimates.
The critical path is then determined using the PERT critical path.
This longest path is then analysed using the PERT calculations. These calculations determine
the probable date for the completion of schedule.
Exhibit 1.3
Optimistic – the least time needed for the work (called either to or a)
Most Likely – the expected time needed for the work (called either tm or b)
Pessimistic – the maximum time needed for the work (called either tp or c)
From this data, we can see the longest path through the above network, the most likely
duration for this chain of activities is: 14 + 11 + 15 + 7 = 47. Pert is a weighted average Mean
of time calculated by following formula:
Mean = ¿)
Exhibit 1.4
Based on the PERT formula, the calculations, for the PERT Critical Path to determine the
likely duration for event 90 that has a 50% probability of being achieved is:
Exhibit 1.5
In this example the project has a 50% probability of completing during the 49th day and a
50% probability off finishing later.
3.3.1 Definition
A chart in which a series of horizontal lines shows the amount of work done or production
completed in certain periods of time in relation to the amount planned for those periods
(Maylor, 2001).
Exhibit 1.6
The above shows a series of activities of a Mobile Show Repair Business. It shoes a start date
and an end date for each task/activity. The weeks are shaded with different colours subject
their completion.
The sensitivity analysis is an important tool for the planning purpose. it is used to increase the
reliability of the given business model and its prediction by providing a detailed model of
variables that react to the input changes (Barkovic, 2002). Sensitivity analysis is used to
determine the following (Bonini et al., 1997):
The sensitivity analysis can be used in the model-based policy assessments. It is popular in
financial applications, neural networks and risk analysis.
It is defined as “the avalanche of data into a limited number of possible states. Each of these
states is then identified and outcomes are determined”. (Schnaars, 1989)
The scenario analysis can be used by the organizations to cast out different possibilities of the
expected events and then plan accordingly. The organizations facing the following conditions
might benefit from the scenario planning technique (Schnaars, 1989):
Businesses where the level of uncertainty is high relative to managers ability to adjust or
predict.
Too many costly unforeseen events have occurred for the business.
The quality of strategic thinking is quite low, and managers have a routinized business mind
set.
The following flow chart illustrates the basic process of scenario planning (Cerf & Navasky,
1974).
Develop
Identify Research
Define the Scope Quantitative
Needs
Models
Evolve Towards
Identify the Major Develop Learning Decision Scenario
Shareholder Scenarios
Check for
Identify Basic
Consistency and
trends
Plausibility
Exhibit 1.6
4- Conclusion
Thus, Strategic planning is an organization management activity that is used to determine
priorities, focus energy and resources, strengthen business, ensure that employees and other
stakeholders work toward common goals, establish agreements on expected outcomes /
results, and evaluate and adjust the organization's direction in response to a changed
environment. The research discusses various tools and techniques that are helpful for the
business organization around the globe.
References
Abdul Moyeen A. 1997. Strategic Planning and Strategic Awareness in Small Enterprises —
A Study
Al Ghamdi S. 2005. The use of strategic planning tools and techniques in Saudi Arabia: an
empirical
Bonini, Ch. P., Hausman, W.H., Bierman, H.: Quantitative Analysis for Management,
Irwin/McGraw-Hill, New York, 1997
C. Cerf and V. Navasky, The Experts Speak (New York’s Pantheon Books, 1974)
Dodin, B. (1985). Bounding the project completion time distribution in PERT networks.
Operations Research, 33(4), 862-881.
Maylor, H. (2001). Beyond the Gantt chart:: Project management moving on. European
Management Journal, 19(1), 92-100.
S.P. Schnaars, Mega mistakes: Forecasting and the Myth of rapid Technological Change
(1989)
Welsch, G. A., Hilton, R. W., & Gordon, P. N. (1988). Budgeting: profit planning and
control. London: Prentice-Hall.