Installation of uPVC Drainage System
Installation of uPVC Drainage System
PREPARED BY:
Riyadh
KINGDOM OF SAUDI ARABIA
2018
United Code Cc METHOD STATEMENT FOR Installation of uPVC Drainage System Below Ground Pipes;
Page 1
THIS DOCUMENT IS UNCONTROLLED WHEN PRINTED
United Code Contracting Company
Method Statement For Installation of uPVC Drainage
System Below Ground Pipes
Document No: UCCC-FRUP-MST-0007-00 Revision: 0
Date Issued: April. 2018
Contents
1 Purpose..................................................................................................................................................................... 4
2 Scope......................................................................................................................................................................... 4
3 Responsibilities........................................................................................................................................................4
4 Document & Drawings.............................................................................................................................................4
5 Equipment/ Tools/ Material Requirements...........................................................................................................4
6 Pre-Preparation Work.............................................................................................................................................5
7 Safety Precautions...................................................................................................................................................5
8 Work Procedure.......................................................................................................................................................5
Leak test procedure:........................................................................................................................................................6
United Code Cc METHOD STATEMENT FOR Installation of uPVC Drainage System Below Ground Pipes;
Page 2
THIS DOCUMENT IS UNCONTROLLED WHEN PRINTED
United Code Contracting Company
Method Statement For Installation of uPVC Drainage
System Below Ground Pipes
Document No: UCCC-FRUP-MST-0007-00 Revision: 0
Date Issued: April. 2018
United Code Cc METHOD STATEMENT FOR Installation of uPVC Drainage System Below Ground Pipes;
Page 3
THIS DOCUMENT IS UNCONTROLLED WHEN PRINTED
United Code Contracting Company
Method Statement For Installation of uPVC Drainage
System Below Ground Pipes
Document No: UCCC-FRUP-MST-0007-00 Revision: 0
Date Issued: April. 2018
1 Purpose
United Code Cc METHOD STATEMENT FOR Installation of uPVC Drainage System Below Ground Pipes;
Page 4
THIS DOCUMENT IS UNCONTROLLED WHEN PRINTED
United Code Contracting Company
Method Statement For Installation of uPVC Drainage
System Below Ground Pipes
Document No: UCCC-FRUP-MST-0007-00 Revision: 0
Date Issued: April. 2018
6 Pre-Preparation Work
a) Check the wall/floor sleeves, opening sizes, positions, etc. according to approved Shop
drawings.
b) Confirm availability of storage space, storage and delivery method for piping materials.
c) Check all pipes and fittings for damage before any installation.
7 Safety Precautions
b) Always wear PPE for personal safety and protection within project site.
c) Always wear proper eye goggles and dust mask while undertaking concrete drilling
works.
8 Work Procedure
For below ground pipes:
a) Check routing of pipes as per approved shop drawing
b) Mark the alignments of the pipes and fittings
c) Excavation for pipe trench shall be by manual method.
United Code Cc METHOD STATEMENT FOR Installation of uPVC Drainage System Below Ground Pipes;
Page 5
THIS DOCUMENT IS UNCONTROLLED WHEN PRINTED
United Code Contracting Company
Method Statement For Installation of uPVC Drainage
System Below Ground Pipes
Document No: UCCC-FRUP-MST-0007-00 Revision: 0
Date Issued: April. 2018
d) Level the trenches as per required levels and must be free from stone and other
foreign materials.
e) Lay the pipes as per the invert levels and slope shown in the approved shop drawing
f) Clean all inside portion of all fittings and pipes to be connected by PVC cleaner before
joining and apply enough amount of PVC cement to each joint.
g) Back fill the trench with approved materials leaving open the pipe joints and prepare
for leak test.
a) All horizontal pipes shall be tested after installation by filling up the pipes with water
up to 2.0 meters head after plugging all openings. The whole piping will be observed
for 2 hours for leakage. If any leakage is found in pipes or fittings, the same will be
removed and repaired immediately.
b) If no visible reduction in water level as can be seen in the test header pipe, it shall be
immediately submitted to Consultant for final inspection and approval.
e) Once approval from KM is achieved, then, backfilling work shall commence.
United Code Cc METHOD STATEMENT FOR Installation of uPVC Drainage System Below Ground Pipes;
Page 6
THIS DOCUMENT IS UNCONTROLLED WHEN PRINTED