Sequence of Operations
Sequence of Operations
Paralleling Switchgear:
DOCUMENTING THE SEQUENCE OF
OPERATION WITH CHARTS LOADS
INTRODUCTION
This article describes the sequence chart approach, how a chart is custom-
created for an individual system and its benefits in the design, testing and
training processes.
DESIGNING A PARALLELING
SWITCHGEAR PROJECT
There are four distinct stages of designing a
paralleling switchgear system.
1.1.1 Loss of utility 1.1.2 Return of utility Utility B Failure timer starts. B
The loss of starts engine start delay timer in the The return to utility is controlled by the return to
PLC. If this timer expires, than the following utility control switch 2 Both utility failure timers expire or Utility breaker UA opens. C
sequence occurs: one timer expired while the other
Utility breaker UB opens. D
is still timing.
1. The closed utility breaker opens. Return to utility control switch All available generators start.
Required GOL Bypass timer starts.
2. The generators start.
3 Utility breaker UA is open. Bus A Open Transfer timer starts.
3. The first generator to reach 90% of rated Manual The system remains on generator
voltage and frequency closes onto the bus. power until the operator depresses the
Startup Shed Option:
First-on logic prevents both generators from Return or Auto pushbutton. The Utility Based on the Load-Management settings,
closing onto the bus simultaneously. stable timer does not time. loads on bus A are shed.
4. The other generator synchronizes to the 4 Utility breaker UB is open. Bus B Open Transfer timer starts.
bus. When synchronized, its circuit breaker Auto When utility returns, the utility stable
closes. timer in the PLC starts. When the utility Startup Shed Option:
stable timer expires the system Based on the Load-Management settings,
5. With both generators on-line, the tie breaker automatically starts the return to utility loads on bus B are shed.
closes. sequence.
5 The first generator reaches rated The first generator breaker closes.
voltage and frequency.
NOTE: Using the HMI, the operator can If the system is on generator
preset the system to automatically signal a Return
power and utility power is available,
load shed and then close the tie breaker if depressing the Return pushbutton 6 The remaining generators independently The remaining generators independently synchronize to E, F
the second generator fails to go on-line. initiates the return to utility sequence. reach rated voltage and frequency. the bus and close their respective circuit breakers.
2 / Paralleling Switchgear
POWER SYSTEMS TOPICS 111
Single-Line Diagram
M2
F6
GM2 F5
F4
M1 GM1 G2
G1
F3
F2
F1
Each stage builds on the previous one; following • They eliminate the ambiguity of knowing how the
them in order is key to a successful project. system responds to both normal operations and
While progressing through each design stage, it system failure.
is important to review decisions made in the
prior stages to be sure they remain valid and • They are easier to read than a typical flowchart.
make any necessary adjustments if changes are
made. For example, if the drawing is revised to • They clearly show system response, timing
add a bus tie breaker to the single line, it is of response, and what the system and operator can
important that the sequence is updated to do if the system fails to respond properly.
indicate the purpose of the tie breaker and its
role in the sequence of operation. • They provide a checklist for testing and
commissioning the paralleling switchgear.
Each of the four stages used to design
paralleling switchgear is vital to the creation Each sequence has two charts—the sequence itself
of a cohesive system. However, the most and the response to abnormal conditions.
challenging—and often the most important for
proper operation—is establishing the sequence • The sequence lists the steps the system
of operation. This is especially important for will take from the initial state to the final state as
complex projects with multiple utilities, where a well as the expected system response to each step.
detailed and precise sequence of operation
provides the foundation upon which the project • The response to abnormal conditions
is built. Critical to the sequence of operation is describes the system response and the
an understanding of how the system works action an operator can take if the system
normally and how it responds if there is a failure does not respond as expected to an event.
in the normal sequence, such as a breaker
failing to open or close. The chart-based method describes the operation
that a typical paralleling switchgear sequence
takes in a series of steps that transition from an
NEW APPROACH-SEQUENCE CHARTS initial state, such as “on utility power,” to a final
The unique charts developed by KOHLER state, such as “on generator power.” The number
Power Systems are a distinctive approach of charts for an individual project will vary
to documenting the sequence of operation. depending on the number of normal states and
These intuitive charts offer benefits for everyone the different types of transitions, such as open or
involved in the design and operation of closed, between the states.
the project.
Paralleling Switchgear / 3
THE FIVE STEPS IN CREATING A SEQUENCE CHART
Let’s look at the five steps we take in creating the chart, and how they illustrate–in sequence—the
system’s loss of both utilities. The sequence to transfer from utility power is described in a series of
steps. Within each step are an event and a corresponding system response to the event.
Simultaneous responses to the same event are shown as separate response lines.
THE FIVE STEPS IN CREATING A The power of the chart becomes evident in the next step of
the sequence. When both utility failure timers expire or one
SEQUENCE CHART timer expires while the other is still timing, the following
things happen simultaneously:
DETERMINE THE INITIAL STATE
• Utility breaker UA opens
The initial state shows the status of each breaker
in the power transfer sequence and the power
• Utility breaker UB opens
status of each bus in the system.
In the initial state, the system is on utility power, Utility • All available generators start
Breaker A (UA) and Utility Breaker B (UB) are closed, and
main breakers Generator Main A (GMA) and Generator • Required GOL (Generator Online) Bypass timer starts
Main B (GMB) are open. The chart shows the status of each
breaker that is part of the power transfer sequence and the The chart not only shows how a system
power status of each of the three buses in the system. responds to an event but also when each
response occurs. By showing each response
on a separate line, the operator can refer to the
DEFINE THE TRIGGERING EVENT corresponding step on the “response to
abnormal conditions” chart to determine how
The triggering event starts the sequence.
to correct an “if fail” scenario.
Examples might be the receipt of a remote start
signal, the utility being out of tolerance or an
operator pushing a button. For example, in Step LIST THE FINAL STATE OF THE SYSTEM
1, when UA and UB are out of tolerance, both the
The final state of the system is described for
UA Failure timer and the UB Failure timer start.
each breaker within the power transfer sequence
The “if fail” column directs the operator to the correspond- and the power status of each bus in the system.
ing letter on the “response to abnormal conditions” chart,
explaining how the system reacts if it does not respond as
expected. In this example, the “if fail” describes the
DETERMINE “IF FAIL” SCENARIOS
response that occurs if utility power returns before the Each system response is reviewed to determine
failure timers expire. if an “if fail” scenario is needed. In general, an
“if fail” scenario is required for any response that
involves a breaker opening or closing or a timer
LIST EACH EVENT (STEP) AND starting. This step preplans how the system
CORRESPONDING RESPONSE should respond if a breaker fails to open or close
or if something happens and a fail-safe timer
Each step required to transition from initial state
expires. Responses that require an “if fail”
to desired final state is described. Each row in
scenario include a generator failing to start, a
the sequence lists the required change in system
generator failing while running or generators
state and the corresponding system response.
becoming overloaded. In an “if fail” scenario, the
For example, if a system is performing an open
“if fail” column in the sequence chart references
transfer back to the utility after a power outage,
the corresponding step in the “response to
one of the events might be the opening of the
abnormal conditions” chart, describing the
generator main breaker and the startup of the
system’s automatic response to that failure and
open transfer timer (event/corresponding system
the actions an operator should take to correct
response). See chart on Page 5.
the system.
4 / Paralleling Switchgear
POWER SYSTEMS TOPICS 111
8 Generator main breaker GMA is closed. Required GOL Bypass timer stops.
Paralleling Switchgear / 5
Response to Abnormal Conditions Chart
Utility A returns, Utility B remains Operator may manually transfer bus B from generator power to utility A
failed: Bus A remains on utility A. power.
Bus B remains on generator power.
6 / Paralleling Switchgear
POWER SYSTEMS TOPICS 111
Paralleling Switchgear / 7
POWER SYSTEMS TOPICS 111
KOHLERPOWER.COM
Printed in U.S.A. G26-22 KPS 111 1/18 © 2018 by Kohler Co.