Finalconceptdesignreport
Finalconceptdesignreport
FINAL
City of Brockville WPCC Secondary Treatment Upgrade
Selection of Secondary Treatment and
Disinfection Technologies
Submitted to Submitted by
City of Brockville
WB092006004OTT 366480
Copyright © 2008 by CH2M HILL.
Reproduction and distribution in whole or in part beyond the intended scope of the report without the written consent of CH2M HILL is prohibited.
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
Contents
1. Introduction ......................................................................................................................................1
1.1 Background..............................................................................................................................1
1.2 Project Objectives....................................................................................................................2
1.3 Project Scope ...........................................................................................................................2
1.4 Value Engineering ...................................................................................................................4
2. Existing Plant....................................................................................................................................7
2.1 Problem Statement...................................................................................................................7
2.2 Treatment Processes ................................................................................................................7
2.3 Flow Rates ...............................................................................................................................7
2.4 Certificate of Approval............................................................................................................7
3. Design Basis.......................................................................................................................................8
3.1 Wastewater Flow and Characteristics......................................................................................8
3.2 Septage Receiving .................................................................................................................10
3.3 Effluent Criteria.....................................................................................................................10
3.4 Receiving Water ....................................................................................................................11
4. Secondary Treatment and Disinfection Technology Review ......................................................12
4.1 Approach to Evaluation .........................................................................................................12
4.2 Conceptual Design.................................................................................................................13
4.3 Secondary Treatment.............................................................................................................13
4.3.1 Design Basis .............................................................................................................13
4.3.2 Cost Analysis............................................................................................................17
4.3.3 Alternative Evaluation..............................................................................................18
4.3.4 Recommendation......................................................................................................18
4.4 Disinfection ...........................................................................................................................19
4.4.1 Design Basis .............................................................................................................19
4.4.2 Alternative Evaluation..............................................................................................19
4.4.3 Cost Analysis............................................................................................................20
4.4.4 Recommendation......................................................................................................21
5. Conceptual Design ..........................................................................................................................22
5.1 Treatment Processes and Process Sizing ...............................................................................22
5.2 Inlet Sewer.............................................................................................................................26
5.3 Septage Receiving .................................................................................................................26
5.4 Screening ...............................................................................................................................26
5.5 Grit Removal .........................................................................................................................26
5.6 Plant Hydraulics ....................................................................................................................26
5.7 Primary Treatment.................................................................................................................27
5.8 Biological Treatment .............................................................................................................27
5.8.1 Aeration System .......................................................................................................27
5.8.2 Secondary Clarification ............................................................................................27
5.8.3 RAS/WAS Pumping.................................................................................................28
5.8.4 Scum Removal .........................................................................................................28
5.9 Disinfection ...........................................................................................................................28
5.10 Outfall....................................................................................................................................29
5.11 Sludge Digestion ...................................................................................................................29
5.12 Dewatering of Biosolids ........................................................................................................30
5.13 Biosolids Management ..........................................................................................................30
6. Review of Existing Plant Upgrade/Rehabilitation Requirements ..............................................31
6.1 Screening ...............................................................................................................................31
6.2 Grit Removal .........................................................................................................................31
6.3 Primary Treatment.................................................................................................................31
6.4 Digestion and Dewatering .....................................................................................................31
7. Civil and Site Layout......................................................................................................................32
7.1 General ..................................................................................................................................32
7.2 Utilities ..................................................................................................................................32
WB092006 366480
COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL. i
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
List of Appendixes
Appendix A – Value Engineering Material
Appendix B – Site Layouts
Appendix C – Evaluation Criteria and Supporting Documentation
Appendix D – BAF Vendor Proposals
Appendix E – Example Process Flow Diagram
Appendix F – Detailed Cost Information
WB092006004OTT 366480
ii COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
1. Introduction
1.1 Background
The City of Brockville (City) currently operates a wastewater treatment plant with primary treatment and sodium
hypochlorite disinfection – the Brockville Water Pollution Control Centre (WPCC). Sludge is treated using
anaerobic digesters which generate methane used for in-plant heating. The MOE issued an order to the City to
complete an environmental assessment (EA) for the upgrade of the plant to secondary treatment, which provides the
current minimum level of treatment required in the Province of Ontario. In order to reach this goal, the City has been
awarded grant funding to assist in completing a secondary treatment expansion. This grant funding is part of larger
funding initiative by the Strategic Infrastructure Fund, administered by Industry Canada, to improve water quality in
the St. Lawrence River/Great Lakes area.
The City has previously completed a number of steps to move toward its upgrade goal including completion of the
Environmental Assessment (EA) in January 2005, as required by the MOE order, and by participating in a working
group of local municipalities to study the feasibility of including a local septage receiving and treatment facility as
part of the future Brockville WPCC upgrade. The City recently completed a cogeneration feasibility study to assess
the potential for inclusion of cogeneration in the plant expansion. The study concluded that cogeneration was not
financially viable at this time. Also, the septage receiving facility is currently not being included in the plan for the
secondary expansion.
The following provides a summary of work completed to date with respect to the upgrade of the plant, or that may
provide relevant background data:
Assimilative Capacity Report, May 2004
EA report, January 2005
The City was successful with its funding request to the Canada Strategic Infrastructure Fund in the amount of
$30.6M, representing two-thirds of the project funding, with the remaining funds to be provided by the City.
One of the Requirements of the funding assistance is that the project be completed by March 31, 2012.
Project Chartering Session November 26, 2007
Technical Memorandum #1 –Evaluation Criteria for Selection of Secondary and Disinfection Technologies,
December 2007
Technical Memorandum #2 – Preliminary Screening of Secondary Treatment Technologies, December 2007
Technical Memorandum #3 – Design Basis, December 2007
The EA report reviewed several areas, and included the following key items:
Secondary Treatment – further evaluate three final technologies including conventional activated sludge (CAS),
biological aerated filters (BAF), and moving bed bioreactors (MBBR). These technologies were chosen based
on preliminary evaluation from a longer list of available secondary treatment technologies. This study further
evaluates the three technologies and recommends one for implementation.
Disinfection – further evaluate ultraviolet (UV) disinfection and chlorination/de-chlorination (chlor/dechlor).
This study further evaluates the two options and recommends one for implementation.
Sludge Treatment Needs – an additional digester was not indicated as a firm requirement in the EA, however,
the EA indicated that this required further review, and that an additional digester is desirable based on
redundancy for maintenance/shutdown periods for the existing two digesters. A new solids handling process has
been proposed in this report involving thickening of waste activated sludge prior to the digesters, so that the
existing digester capacity is sufficient without the requirement to construct additional digestion facilities at this
time.
Septage Receiving – the EA considered various scenarios where a Regional septage receiving facility would be
constructed at the WPCC. This option has since been eliminated and will not be included in this study.
WB092006004OTT 366480
COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL 1
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
The team of CH2M HILL and JL Richards and Associates (JLR) was selected to complete a project to carry forward
the recommendations and outcomes of the EA report, and arrive at a final recommendation for the scope of work
and selection of treatment technologies, including estimated costs, for the upgraded Brockville WPCC.
WB092006004OTT 366480
2 COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
WB092006004OTT 366480
COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL 3
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
TABLE 1-1
List of Items Requiring Upgrade or Rehabilitation at the Brockville WPCC
Item No. – In
Order of
Description Category
Importance to
the City
1 Dewatering - Dewatered Centrate must flow away from Centrifuges quickly and to 1
an appropriate location within the WPCC
3 Dewatering - Feed Sludge must have proper blending in order to give consistent 2
feed sludge concentration to the Dewatering Centrifuge
4 Grit Removal - Must have better grit capture; grit is not fully being removed and/or 2
causing premature wear on equipment and Digesters
6 Primary Tanks – Concrete: Condition of existing tanks, dead spots and access 3
areas in the tanks
7 Boilers - Must have replacement of Boilers 501 and 502; 502 is soon to be red 3
tagged o/s (safety issue)
10 Primary Tanks - Effluent Gates installed to eliminate flow from weir boxes for 3
Maintenance work
WB092006004OTT 366480
4 COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
TABLE 1-2
Value Engineering Brainstorming Teams
Team Name Team Members
The outcome of the VE session included a number of proposals that were made by each team, as listed in Table 1-3.
The proposals were presented by each team to the entire VE group, and the recommended action as to whether or
not to include the proposal in the final design was determined based on the presented arguments for each proposal.
A detailed description of each proposal, including conceptual cost estimates (either increase or decrease to the
overall project cost) and included in the VE material, Appendix A.
The decided upon actions for each proposal are outlined in Table 1-3. Those actions that were recommended to be
carried forward have been incorporated into this final Conceptual Design Report. There are a number of proposals
that should be considered further during preliminary/detailed design, as noted in Table 1-3.
WB092006004OTT 366480
COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL 5
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
TABLE 1-3
Value Engineering Proposals and Recommended Action
Proposal
Description Team Action
Number
To be evaluated during
4 New Chemical facilities (coagulation) Site Optimization
preliminary/detailed design
Category #3 item – to be
considered as part of possible
plant rehabilitation/upgrade if
sufficient funds exist – not
11 Upgrade existing gas handling Existing Facilities
included in Conceptual design
for new secondary/disinfection
facilities – evaluate during
preliminary design
To be evaluated during
14 Program Delivery Program Delivery
preliminary/detailed design
To be evaluated during
15 Excavation optimization Site Optimization
preliminary/detailed design
WB092006004OTT 366480
6 COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
2. Existing Plant
2.1 Problem Statement
The existing Brockville WPCC plant does not meet the level of normal treatment, which is secondary treatment or
equivalent as stipulated in the Ministry of Environment (MOE) Guideline F-5 and Procedure F-5-1. Additionally,
the WPCC currently exceeds the existing Certificate of Approval (CofA) limits for biological oxygen demand from
time to time. The Ministry of Environment issued a Provincial Officer Order, which required the City to assess
alternative solutions to address this issue and to include a statement that the plant also does not meet the minimum
treatment standard of primary treatment. This order was addressed through completion of the EA.
WB092006004OTT 366480
COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL 7
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
3. Design Basis
3.1 Wastewater Flow and Characteristics
Table 3-1 presents flow data from 2003 to 2006 for the Brockville WPCC. Also included in this table are the
existing plant capacity, as well as future and projected flows, and population.
The flows noted in Table 3-3 are a summary of the design criteria that were used for this study. The design basis for
flows considered during process design of the secondary treatment process also included a maximum month flow
and a conservative approach to redundancy when considering average daily flow and average annual flow.
TABLE 3-1
Current and Projected Future Flows
Average Day Flow Maximum Daily Population
(m3/d) Peak Flow (m3/d)
Notes:
(1) Class Environmental Assessment Report (January 2005) – rated capacity of the existing plant
(2) 2004 Annual Summary Report (March 2005)
(3) WaterTrax Data for 2005 and 2006
WB092006004OTT 366480
8 COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
Table 3-2 presents the influent loadings from 2001 to 2006 as obtained from various data sources. There was no
septage receiving during this period.
TABLE 3-2
Historical Influent Loadings
BOD5 (mg/L) TSS (mg/L) TP (mg/L) TKN (mg/L)
Notes:
(1) Class Environmental Assessment Report (December 2004)
(2) 2004 Annual Summary Report (March 2005)
(3) WaterTrax Data for 2005 and 2006
(4) TKN Data currently not available through WaterTrax database in the raw influent
The City of Brockville receives wastewater from a number of industrial facilities, which contribute to the influent
wastewater characteristics.
One particular facility has in the past caused elevated pH as high as 11 at the wastewater plant for up to one hour.
The City has indicated that pH spikes in the wastewater influent will be controlled through sewer use by-law
enforcement. Such enforcement is recommended to preclude the discharge of any substances that can have a
deleterious affect on the WPCC. It is impractical to design systems for the plant to detect and pre-treat discharges
that could upset the plant. This includes discharges of alkaline materials to the extent that they could cause a
significant plant impact.
High pH discharges are not uncommon in municipalities with industrial dischargers, particularly food processing.
These facilities employ both caustic and acidic type cleansers; however, their discharge tends to be predominantly
basic. For this reason, some facilities employ on-site pH adjustment systems which control the pH of the discharge
within by-law limits, typically between 6 and 9 or 10. Despite these controls, there are times when the effluent can
exceed the by-law, measured at the facilities point of discharge. Such incidents, in CH2M HILL’s experience, have
generally not been reported to impact plant operations.
Some level of excursions in pH can typically be tolerated by wastewater treatment plants owing to their inherent
buffering capacity. Systems that are installed that affect pH are related to maintaining sufficient alkalinity. In these
cases a basic substance such as soda ash is added to avoid pH depression which can adversely affect treatment
performance. However, total system hydraulic retention times in the range of 12 hours will tend to mitigate adverse
affects. Based on the hydraulic retention time and inherent buffering capacity, municipal treatment plants rarely, if at
all, pre-treat for pH control and it is not anticipated that this would be required at the Brockville WPCC.
Using a conservative design approach, the influent loadings from the EA and flow data as determined with the City
will be used as the basis for this project. These values are provided in Table 3-3 with rationale as to their selection as
a design basis.
WB092006004OTT 366480
COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL 9
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
TABLE 3-3
Design Basis Influent Loadings and Flows To Be Used for Secondary Treatment Conceptual Design
Parameter Raw Rationale for Use as Design Basis
Wastewater
Flow 21.8 MLD - The average day and peak flows are based on the existing plant rating and
Average Day the EA.
BOD ( mg/L) 120 From Tech Memo #4 in the EA. It represents a similar (low) strength waste
to the numbers provided in Table 1 based on recent plant data, in that the
average BOD (from 2001 to 2006) in that memo was 100 (if you average
the 2001-2003 Average, and the 2004-2006 Average).
TSS (mg/L) 160 From Tech Memo #4 in the EA. It represents a similar (low) strength waste
to the numbers provided in Table 1 based on recent plant data, in that the
average TSS (from 2001 to 2006) in that memo was 136 (if you average the
2001-2003 Average, and the 2004-2006 Average).
TP (mg/L) 4 From Tech Memo #4 in the EA. It represents a similar (low) strength waste
to the numbers provided in Table 1 based on recent plant data, in that the
average TP (from 2001 to 2006) in that memo was 2.85 (if you average the
2001-2003 Average, and the 2004-2006 Average).
TKN (mg/L) 25 From Tech Memo #4 in the EA. It represents a similar (low) strength waste
to the numbers provided in Table 1 based on recent plant data, in that the
average TKN (from 2001 to 2006) in that memo was 12.4 (if you average
the 2001-2003 Average, and the 2004-2006 Average).
TABLE 3-4
Septage Quantities
Number
Commercial None
WB092006004OTT 366480
10 COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
ensure conservatism at this preliminary stage of review, as agreed to by the City at a progress meeting of December
20, 2007. Further, it should be noted that many existing plants applying for amended or new Certificates of
Approval from the Ministry of Environment (MOE) are being required to have “non-lethal” effluent, which may
remove the numerical limits for ammonia, and require that the Brockville WPCC meet the non-lethality
requirements instead. This will be determined during the detailed design stage of the project through discussions
with the MOE at the onset of the approvals process.
TABLE 3-5
Recommended Effluent Criteria – Monthly Average1
Parameter Criteria (mg/L) Design Objective (mg/L)
cBOD5 25 15
TSS 25 15
Notes:
(1) From “Brockville Water Pollution Control Plant Assimilative Capacity Analysis” by XCG Consultants,
May 2004 and the Class Environmental Assessment Report by Simcoe Engineering and Hydromantis
Consulting Engineers, January 2005.
WB092006004OTT 366480
COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL 11
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
Secondary Treatment
Conventional activated sludge
Trickling filters/solids contactor
Rotating biological contactor
Sequencing batch reactor
Biological aerated filter
Biological nutrient removal
Membrane bioreactors
Moving bed biofilm reactors
Disinfection
Chlorination/dechlorination
Ozonation
Chlorine dioxide
Bromine chloride
Ultraviolet radiation
Environmental Assessment – a short list of technologies was recommended for further review during design.
The reader is referred to the EA report for further background information on the long list of technologies,
including the recommendation for short listing of the following:
Secondary Treatment
Conventional activated sludge
Biological aerated filter
Moving bed biofilm reactors
Disinfection
Chlorination/dechlorination
Ultraviolet radiation
Conceptual Design – a preliminary screening of the short listed alternatives for secondary treatment was
completed. Two final technologies were recommended to move forward to conceptual design for secondary
treatment – conventional activated sludge and biological aerated filters. The disinfection short list remained the
same as the EA recommendation. The moving bed biofilm reactor (MBBR) was removed from consideration
during conceptual design based on a preliminary screening with respect to implementation, operations and
technical considerations. The final scoring for the MBBR indicated that even with inclusion of life cycle
costing, this alternative would not reach the threshold for consideration as the recommended technology. The
evaluation criteria used throughout this study are outlined in Technical Memorandum #1, Appendix C. The
WB092006004OTT 366480
12 COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
preliminary screening and results are as outlined in Technical Memorandum #2, Appendix C, with backup
materials included in Appendix C including the preliminary evaluation scoring.
Conceptual Design – a final evaluation of the short listed technologies for both secondary treatment and
disinfection was completed. The evaluation was conducted using the criteria as outlined in Technical
Memorandum #1, to arrive at final scoring for each alternative, and a scored ranking. This ranking was the
ultimate basis upon which the recommended final treatment technologies were selected. Appendix C contains
the final supporting documentation including the evaluation criteria, and scoring. Section 4.3 provides further
information of the rankings and recommendations.
WB092006004OTT 366480
COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL 13
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
TABLE 4-1
Key Design Parameters for Process Sizing – Conventional Activated Sludge (CAS)
Treatment Unit Design Basis
− Existing process sizing sufficient for design flows, and possibly up to 40,000 –
Primary Clarification
45,000 m3/day based on an average SOR of 40 m/d
− SRT = 10 days
Aeration
− MLSS = 2,900 mg/ L
−
3 3
Total volume = 6,600 m (3 tanks @ 2,200 m )
−
3
Sized to treat up to 54,500 m /d hydraulically and up to a maximum month
3
flow of 25,000 m /d with a UV Transmittance (UVT) = 60% for secondary plant
effluent
Disinfection
− Peak flows will receive disinfection at a lower level, however, the system is
designed to meet the regulatory requirement of 200 E. coli/100 mL as a
monthly geometric mean
− Anaerobic digester volume sized to achieve SRT > 15 days at peak month
Digestion solids loading
4.3.1.2 BAF
Two vendors were consulted during conceptual design for the BAF process: John Meunier (Biostyr®) and
Degremont Technologies (Biofor®). These vendors are the two main suppliers of this technology, representing all of
the installations in Canada to date. The following provides a brief background on the BAF process from each of the
two vendors, as each process is slightly different due to the proprietary nature of the systems. The process
descriptions are taken directly from text provided by the vendors with minor modifications. The vendor proposals
and information are included in Appendix D.
Biofor
The Biofor® filter is a Submerged Biological Aerated Filter (SBAF) designed to treat primary effluent for removal
of carbonaceous and nitrification oxygen demand, and total suspended solids from the waste stream (Biofor® C and
N). Because of the modular design concept, the quantity of filters can be reduced or increased to accommodate the
treatment capacity today (flow and load) and in the future.
WB092006004OTT 366480
14 COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
Biofor – Principle
Treated
Water
Media Wash
Water Air Water
Outlet
Process Air
(Oxygenation)
Wash Water
Water to be
Scour Air treated
Aerated biological filtration combines in a single step both biological degradation of biodegradable soluble matter
and solids retention by mechanical filtration of suspended solids. Clarifiers downstream are not needed.
Biological filtration is achieved in up-flow filters loaded with a suitably sized granular support media, thus
providing an efficient filtration effect. The filter media provides adequate support for biomass attachment and a
mechanical filtration capability.
Process air provides the necessary oxygen for aerobic biological activity and is introduced in the media through a
network of diffusers (Oxazur) located at the base of the reactor. Oxygen transfer is achieved in the media due to the
up-flow pattern of air bubbles. The biological filtration process is of the submerged bed type.
Co-current up-flows of air and water allow for the finest particles to accumulate towards the upper reaches of the
support media thus avoiding system clogging; suspended matter becomes attached through the full height of the
media which allows for long filter runs. The influent must be screened to avoid clogging of the filter nozzles.
During treatment biomass accumulates in the support bed because of the bacterial growth due to the elimination of
dissolved pollution and the retention of suspended solids in the raw water, and of the biological flocs.
Periodic backwashing is necessary. The frequency varies from 24 hours to 48 hours depending on the loadings
applied and the treatment objectives. The filter wash is of the co-current type and the techniques are similar to those
applied to sand filters for potable water using simultaneous water and air. Treated water is used for running the
wash sequences. The wash sequence is designed so that it causes no damage to the support medium yet retains the
biomass required for rapid restart of the bio-filter after backwash. This ensures that the biofilter can immediately
return to service with the desired treatment efficiency.
Biostyr
The Biostyr® process belongs to the family of biological aerated filters and can be designed to remove BOD and
TSS, and provide nitrification, and/or denitrification. The filter media acts as a filter for the physical removal of
suspended solids, while providing ample surface area for the attachment of a biofilm. The purpose of the biofilm is
to achieve biological treatment of the soluble influent contaminants.
The influent wastewater is first brought to a common inlet feed channel above the Biostyr® cells where it flows
down to the individual cells by gravity. Upon entering the Biostyr® cells, the wastewater flows upwards through the
filter media. The media is composed of specially treated expanded polystyrene beads covered by active biomass.
Ceiling plates with regularly spaced nozzles are used to retain the filter media in the cell. The nozzles allow the
treated water to enter a common water reservoir above the filters, which in turn is used to provide water during
backwash sequences.
WB092006004OTT 366480
COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL 15
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
A process air grid is located below the filter media so that the entire filter bed is aerated. BOD is oxidized by the
biomass in the lower section of the filter. As the wastewater continues up the filter, additional BOD is consumed.
When the BOD:TKN ratio falls below a certain limiting level, nitrification occurs, thereby reducing the ammonia
level in the wastewater by converting it to nitrates.
Growth of biomass and the retention of suspended solids in the filter media make periodic backwashing necessary.
The Biostyr® process is designed for a backwash interval of 24-72 hours (typically), depending on the application.
The backwash phases are fully automatic and are triggered either when an operator adjustable time limit has expired
or when the head loss across the filter exceeds a pre-determined setpoint. Water from the common treated water
reservoir flows down through the filter by gravity, thereby fluidizing the media. The process air grid located below
the media is also used to supply scouring air during the backwash sequence. The grids are regularly spaced pipe
laterals with small orifices that produce a uniform, coarse-bubble pattern over the full cross-section of the filter.
Table 4-2 provides a summary of the BAF design basis, showing each item from the two vendors. The conceptual
design for these proposals, including quantity estimation and costing, was based on the Biofor proposal, which did
not include co-thickening, and which has a larger footprint, i.e. a more conservative design basis. Neither vendor
provided proposals with one cell off-line at all times to allow for redundancy and conservatism in the design at the
conceptual design stage. Therefore quantities and costs have been increased to allow for one additional cell (i.e. 9
cells as opposed to eight based on the Biofor design) to ensure direct comparison to the conventional activated
sludge process from the redundancy perspective. The two vendor proposal costs for their proprietary system and
equipment were very similar.
WB092006004OTT 366480
16 COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
TABLE 4-2
Key Design Parameters for Process Sizing – Biological Aerated Filter (BAF)
Biostyr Biofor
Filtration rate ADF (including co-thickening flow) @ N-11 m/h 4.5 8.6
Filtration rate PHF (including co-thickening flow) @ N-11 m/h 8.7 8.1
30 (energetic wash)
(1) Biostyr includes co-thickening, Biofor design based on separate WAS thickening.
(2) Note that the vendor proposals did not include an off-line redundant cell for allowance during maintenance
periods, etc. therefore one additional cell was considered during conceptual design to allow for redundancy as
described in the report text preceding this table.
A process flow diagram for the BAF process is included in Appendix E.
WB092006004OTT 366480
COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL 17
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
The capital costs of the two technologies are quite close, with CAS being slightly less. With respect to present worth
on a life cycle basis, that is, the capital and O&M costs, CAS is lower than the BAF alternative. The O&M costs for
BAF are higher than CAS, this is due to the greater number of pumps/blowers, etc. that are be included in a BAF
process.
TABLE 4-3
Comparison of Secondary Treatment 20-Year Life Cycle Costs
Item CAS BAF
4.3.4 Recommendation
The CAS alternative is recommended as the secondary treatment process for the upgraded plant based on the
evaluation criteria and scoring developed with the City. The final score for CAS was a total of 8.2 out of a total
possible 10 points, whereas the BAF alternative scored a total of 7.2 points. The CAS alternative also scored higher
during the preliminary evaluation, and because the life cycle costs were not lower, the BAF technology did not
move ahead in scoring over the CAS process.
WB092006004OTT 366480
18 COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
4.4 Disinfection
The reader is referred to the EA report for further background information on the technologies, including the
recommendation to review these final technologies out of a long list of alternatives for disinfection at Brockville.
TABLE 4-4
Disinfection System Alternative Evaluation
Parameter Chlorination/Dechlorination Ultra-Violet Disinfection
Safety to operators − Involves strong chemical handling and − Minimal chemical handling involved,
storage, risk to operators chemicals are used only occasionally for
cleaning lamps
Environmental − Possible formation of disinfection by-products − UV bulbs are returned to a recycler after
Impacts replacement with new bulbs (service
− Risk of discharge of chlorinated effluent should
provided free of charge for by some
dechlorination system fail
vendors)
− Non-toxic effluent
Proven Technology − Most commonly used disinfection process for − Being operated in many small to medium-
wastewater treatment sized wastewater treatment plants with
proven success
Performance − Capable of meeting disinfection requirements − Capable of meeting disinfection
requirements
− More robust for disinfection of effluents with
varying quality, and for by-pass disinfection if
required
Complexity − Simple process − Simple process
− Chlorination is currently practiced at the plant, − More operator training required
therefore operators are familiar with system
WB092006004OTT 366480
COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL 19
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
TABLE 4-4
Disinfection System Alternative Evaluation
Parameter Chlorination/Dechlorination Ultra-Violet Disinfection
O&M − Regular maintenance to chemical equipment − Occasional manual cleaning of lamps may
be required
− Chemicals would need to be delivered
regularly − Lamp replacement
− Cleaning of equipment as necessary − Requires greater standby power capacity
Reliability − Highly reliable − Highly reliable
− Readily adaptable for use in disinfection of
primary by-passes if desired in future
The requirements for UV design could require up to a 20% increase in UV dose, as BAF often requires a larger UV
system to account for the larger possible particle size in the BAF effluent due to the sloughing of solids from the
fixed film process. UV vendors are currently beginning to look into new BAF installations to ascertain the possible
increase at this time. Chlorination/dechlorination systems are generally considered to be more robust in terms of
overall process operation in variable effluent situations. Should future treatment by-passing be incorporated into the
future plans for the Brockville WPCC, as opposed to the by-pass at the existing Main Pump Station, disinfecting
primary effluent (the minimum level of treatment required for emergency by-passes) using UV should also be
considered. The existing chlorine contact tank could be employed in this situation.
UV disinfection is often considered the more environmentally friendly disinfection technology from the perspective
of formation of disinfection by-products and “non-toxic” effluent.
From a performance and complexity perspective, both systems are comparable, although the UV system would
require some additional operations training and familiarization as chlorination is currently practiced at the plant and
UV would be a new type of system.
TABLE 4-5
Comparison of Disinfection System Costs
Item UV Chlorination/Dechlorination
WB092006004OTT 366480
20 COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
4.4.4 Recommendation
The recommended disinfection process for the Brockville WPCC is UV disinfection, based on the evaluation of the
technology as included in Appendix C and described in the previous sections. The weighted scores for both
alternatives were essentially equal, as they were 7.5 for both UV and chlorination/dechlorination. As the scores
showed advantages to either process, the UV process was selected by the City based on operations staff input. The
estimated overall life-cycle cost of the UV disinfection system is lower than that of chlorination/dechlorination. UV
disinfection is proven and reliable and requires a smaller footprint than chlorination/dechlorination, while having
minimal risk to the environment and operator health and safety.
WB092006004OTT 366480
COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL 21
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
5. Conceptual Design
The following sections outline the unit treatment processes that will comprise the final treatment train at the
Brockville WPCC. This section includes a review of each unit process, whether existing as part of the primary
treatment plant, or part of the new secondary and disinfection treatment processes. Each section describes the
evaluation of the unit process, and what the requirements are for the upgrade or expansion in order to implement the
selected secondary treatment process.
Section 6.0 discusses the possible items that could be upgraded that are either Category #2 or Category #3, i.e. not
required for secondary treatment or are maintenance items, based on the priority items identified by plant staff as
described in Section 1.3. Category #1 items are included in the following sections, as they would be required for the
secondary upgrade, such as the centrate equalization tank.
TABLE 5-1
Treatment Processes and Design Parameters
Treatment Unit New/Existing Design Basis
Screening Existing Existing process sized based on peak flow up to 54,500 m3/d
Grit Removal Existing Existing process sized based on peak flow up to 54,500 m3/d
Primary Existing Existing process sized based on 21,800 m3/d average day, peak flow up
Clarification to 54,500 m3/d
3 3
Aeration New Sized to treat flow of 21,800 m /d average day, and 54,500 m /d peak
instantaneous
Final Clarification New Sized to treat flow of 21,800 m3/d average day, and 54,500 m3/d peak
instantaneous
3
Disinfection New UV Disinfection sized to treat flows up to 54,500 m /d, duty/standby
channels
Digestion Existing Existing digesters checked based on sludge production from existing
primary process and new secondary process – new WAS thickening to
be added to economize on digester capacity and allow for secondary
sludge to be digested without additional digester construction
3
Dewatering Existing Existing process reviewed for flows up to 132 m /day or 2640 kg/d at 2%
dry solids (projected solids feed rate with secondary treatment)
WB092006004OTT 366480
22 COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
Table 5-2 provides the key design parameters used for process sizing at the conceptual design level. Process design
should be reviewed and refined at the preliminary design stage as required.
TABLE 5-2
Key Design Parameters for Process Sizing – Conventional Activated Sludge (CAS)
Treatment Unit Design Basis
− Existing process sizing sufficient for design flow, and possibly up to 40,000 –
Primary Clarification 45,000 m3/day based on an average SOR of 40 m/d without co-thickening (i.e.
separate WAS thickening to occur)
− SRT = 10 days
Aeration
− MLSS = 2,900 mg/ L
−
3 3
Total volume = 6,600 m (3 tanks @ 2,200 m )
Digestion − Anaerobic digester volume sized to achieve HRT > 15 days at peak month
solids loading, existing digesters considered sufficient with separate WAS
thickening to be added
WB092006004OTT 366480
COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL 23
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
Table 5-3 outlines proposed process equipment in terms of number of units, and basic unit sizing. Tank area and
volume are rounded in some cases, such as the area of the clarifiers. The proposed sizing is based on conceptual
level process modeling and calculations, and is approximately only. Final sizing for new processes and equipment
should be reviewed during preliminary design.
TABLE 5-3
Summary of Process Tankage and Equipment Sizing
Treatment Unit Number of Units and Basic Sizing
SCREENING1
PRIMARY CLARIFICATION1
Length (m) 29
Width (m) 8
AERATION
Length (m) 27
Width (m) 15
WB092006004OTT 366480
24 COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
TABLE 5-3
Summary of Process Tankage and Equipment Sizing
Treatment Unit Number of Units and Basic Sizing
FINAL CLARIFICATION
Length (m) 40
Width (m) 15
RAS Pumping Rate 100% of Average Day Flow returned to aeration tanks
BIOSOLIDS TREATMENT
SLUDGE DEWATERING
WB092006004OTT 366480
COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL 25
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
TABLE 5-3
Summary of Process Tankage and Equipment Sizing
Treatment Unit Number of Units and Basic Sizing
Capacity (m3/d) per centrifuge1 5,103 kg/d at feed solids concentration of 2.7% (operated
5 days/week, 7 hours/day)
The following sections briefly outline the design basis and assumptions for the unit processes in addition to the
information provided in the previous tables, which will be further refined during preliminary and detailed design.
5.4 Screening
The existing screening process has sufficient capacity to treat the peak flow of 54,500 m3/day which is the rated
flow for the existing plant. No changes to the screens are required in order to implement secondary treatment using
CAS.
WB092006004OTT 366480
26 COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
all excavation will be rock blasting. With respect to blasting versus hoe-ramming of rock, it was reported during
previous construction of the dewatering facility that hoe-ramming was a slow construction method, and thus, we
have assumed rock blasting will be necessary for the large amount of excavation required for secondary treatment
construction at Brockville.
With respect to groundwater, we have assumed no significant groundwater elevation in the tank excavations at this
stage of the study, again, based on previous knowledge during the screening/grit facility construction, where no
groundwater flow into the excavation was encountered.
Both the rock elevation and groundwater elevation assumptions will need to be confirmed during preliminary
design, upon completion of the geotechnical study.
A detailed hydraulic gradeline will be required during preliminary design, and confirmation of the decision with
respect to required pumping to the new secondary plant determined at that time.
The disinfected effluent will be discharged to the river via a connection to the existing outfall downstream of the exit
point from the existing chlorine contact chamber, which will be determined during the detailed hydraulic analysis.
WB092006004OTT 366480
COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL 27
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
tanks to be as short as possible to fit within site space, and maintain access to the tanks and allow for expansion in
the future. The Folded Gould design uses two passes in the clarifier.
The clarifier surface overflow rate at average day flow will be 12 m/d and 26 m/d at maximum day. This design
allows for the flexibility to provide adequate clarification and thickening even for sustained peak flows (i.e. in
excess of a day at the 54,500 m3/day peak) for sludge SVIs at or below 150 mL/g with all clarifiers and aeration
tanks in service.
Sludge collection in the clarifier will take place using three sludge collection mechanisms, two running
longitudinally in the tank, and one cross collector that runs across the width of the tank. The sludge collectors will
be chain and flight type. The sludge collectors will pull sludge to a sludge hopper at the opposite end of the tank
from the effluent launders, where piping will convey the sludge to the return and waste activated sludge pumps.
Rake speed for sludge collection in the clarifiers would normally be within the range of 0.3-0.6 m/min.
5.9 Disinfection
Disinfection of treated wastewater will be achieved using UV disinfection. The UV system will consist of two
channels which would be capable of providing full duty/standby UV treatment. Consideration should be given to
optimizing this design during preliminary design, which could include reducing the UV requirements such that both
channels would be required during peak flow from a UV treatment perspective, and only hydraulically size the
channels for peak flow. With this design, at lower plant flows, all the flow through the plant would be disinfected
through one UV channel. At higher flows, the inlet gate to the second channel would open and the flow would split
evenly between the two channels. This will reduce the power costs of the UV system, and should be considered
during preliminary design. However, in order to compare the UV and chlorination/dechlorination systems fairly and
equally, full duty/standby systems have been included in this conceptual design and this provides a more
conservative design approach at this stage.
WB092006004OTT 366480
28 COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
Each channel would be hydraulically designed to convey the full plant peak flow of 54,500 m3/d. The MOE’s
compliance limit and design objectives for disinfection are generally 200 E. coli/100 mL and 100 E. coli/100 mL
respectively based on a monthly geometric mean. The UV unit were sized to provide the required disinfection based
on UV transmittance of 60% and 15 mg/L suspended solids at the conceptual design level.
The proposed design involves one bank of UV lamps in each channel, each with nine modules containing eight
lamps. Therefore, each channel will have 144 lamps in total. The power consumption of this system would be 36
kW per hour with all lamps operational on full power, during maximum flow. The UV system information should be
confirmed during preliminary design. The information provided in this study is based on a preliminary quotation
from one UV system vendor.
The proposed system will have automated mechanical/chemical cleaning, reducing the frequency at which the lamps
would require removal for cleaning.
5.10 Outfall
The existing outfall pipe consists of a 900 mm (36”) diameter concrete pressure pipe that was installed with the
original WPCP. The outfall is a submerged discharge with eight 10” diameter diffuser outlets, and was originally
installed with four diffusers open, and four blanked closed.
The exterior of the outfall has been inspected twice within the last 5 years, and showed that the current outfall
condition is good, with minor repairs required to the diffusers. Outfall hydraulics should be confirmed during
detailed design to determine if any additional diffusers require opening to account for increased flow over the years
since original construction. It is recommended than an interior inspection of the outfall is conducted during
preliminary design.
WB092006004OTT 366480
COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL 29
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
Using the more aggressive design basis with dilute sewage and thicker co-thickened solids from the primary
clarifiers, at a flow of 21,800 m3/day, there may be sufficient digester capacity, as there would be approximately 11
days HRT when one tank is out of service. It would be difficult to justify that the existing digesters can meet a
design flow basis with any average day flow greater than the existing rated plant capacity. Using the conservative
and more typical design approach with the raw wastewater influent values from the EA, the existing two digesters
would not be considered sufficient as 15 days HRT with both digesters in service would not be reached.
Co-thickening of the primary and secondary solids was not a desired process from the operations perspective at the
Brockville WPCC based on VE outcomes. To address concerns with capacity and operations of the digesters, the
following is recommended for implementation at the Brockville WPCC. This will address handling of biosolids
while making use of the existing two digesters without the requirement to construct a new digester and associated
facilities:
New separate WAS thickening (which may allow for an effective sludge feed concentration up to 5%, thereby
increasing the overall digestion capacity) consisting of a WAS holding tank of approximately 120 m3, and a
WAS thickening facility using drum thickeners and a polymer feed system. Thickened WAS would be pumped
to the digesters for further treatment.
Upgrade of the existing digesters to include external draft tube mixing to improve mixing.
New digested sludge holding tank of approximately 120 m3 to store digested sludge for feed to the dewatering
facility in winter, and directly to hauling for land application in summer. This tank could be included in a new
facility to be constructed east of the existing dewatering building that would house WAS thickening, digested
sludge holding, and centrate equalization facilities. This would combine all of these items into one common
facility that would facilitate any odour control requirements and is near existing sludge dewatering and truck
loading facilities.
New centrate holding tank/pumping station combined with the sludge holding tank as discussed further in
Section 5.12.
WB092006004OTT 366480
30 COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
6.1 Screening
Two existing mechanical screens with 3/8” opening size are located in the screening building. These screens were
installed during a retrofit improvement during 2004/2005. Operations staff report consistent problems with
maintenance of these screens, including misalignment of the bars/rake, causing rake tooth breakage, and difficulty in
accessing the screens for maintenance.
Odour control has also been reported to be an issue, although an existing carbon odour control system is in
operation.
A condition assessment and mechanical review of these screens is recommended to determine what improvement
could be made concerning the rake alignment and maintenance issues. Replacement of the screens would not be
recommended given their relatively recent replacement. Operation of the odour control system and regular
maintenance procedures should also be reviewed, including a capacity analysis, to determine what improvements
could be made.
WB092006004OTT 366480
COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL 31
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
The following sections provide suggested concepts for the new secondary plant and disinfection facilities. The
proposed concepts will require review at the preliminary design stage, when more detailed information is available
regarding the selected process, actual equipment, geotechnical information, and further consultation with Hydro
One. These sections are provided at the conceptual design stage in order to provide the City with the vision for the
future plant at the time of completion of this report, and it should be understood that items are subject to change as
the design process progresses.
7.2 Utilities
Extension of the existing natural gas feed to the plant may be required to service new heating as the HVAC design
progresses, and an allowance for this cost has been considered. Also, effluent service water and potable water
service allowances have been included to provide water to the new facilities as needed.
7.4 Landscaping
Landscaping will be determined during detailed design. An allowance for landscaping has been included in the
conceptual cost estimates.
WB092006004OTT 366480
32 COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
FIGURE 9-1
Existing Plant PLC & SCADA System Schematic
WB092006004OTT 366480
COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL 33
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
Some existing plant alarms and most remote facility telemetry uses a combination of a now obsolete Modudata
alarm annunciation system and a more modern Raco Verbatim Gateway alarm dialler. The various remote facilities
utilize smaller Modudata hardware at each site, relaying status and alarms signals over telephone lines to the main
Modudata system located at the plant. From this point, these signals are then hardwired to PLC4 in the
Administration building. Once the signals and alarms are within this PLC, they are displayed on the iFix computer
screens. Critical remote facility and plant alarms are then transmitted by the PLC to the Raco alarm dialler, typically
via DF-1 communications, for alarm callout. The existing Raco alarm dialler will be retained for use by the existing
systems and those new systems to be added to the plant for secondary treatment. Operations staff also indicated that
some remote facility control functionality was intended by use of the Modudata system, however it was never
implemented.
Replacement of any remote facility communication systems has not been included in the scope of this project, as the
existing Modudata system does not require replacement or modification for the implementation of secondary
treatment at the plant. Additionally it is anticipated that this system will not be expanded for use with the plant’s
new secondary treatment systems as neither the necessary new components or physical space are available to do so.
It is understood from discussions with the plant staff that the City is pursuing replacing the existing remote facility
communications systems with either fibre or wireless based communications. Once these upgrades are completed
and the various remote facilities can communicate directly with the plant control system (i.e. at the PLC or SCADA
levels), the Modudata system would become redundant and it recommended for removal at that time as part of that
project.
WB092006004OTT 366480
34 COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
Frequent, un-synchronized trends on one SCADA computer when compared to the second computer
Ongoing software support and maintenance needs
No automated data and system backup system
Minimal physical security of the SCADA computers in the present locations
8.4 Instrumentation
In consultation with operations staff, no specific issues or needs were identified regarding instrumentation within the
existing facility that requires addressing at this time. Our cursory inspection of the various plant instruments
indicated they are suitably maintained and operational. It was noted that some of the facilities electromagnetic flow
meters are quite dated and may present issues with obtaining spare parts, however a complete meter replacement can
normally be readily sourced from present day manufacturers and suppliers. It was also noted that the specific model
of MSA gas detection equipment, located in the electrical room, adjacent to the Screening room, is not longer being
manufactured. However spare parts such as the sensing cells and service of these systems remains available. If any
specific instrumentation is deemed in need of replacement as part of this project, these can be reviewed on an
individual basis with consideration for replacement given to those instruments of highest priority to continued plant
operations.
WB092006004OTT 366480
COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL 35
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
FIGURE 9-2
Conceptual Plant PLC & SCADA System Schematic
WB092006004OTT 366480
36 COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
9. Architectural Design
9.1 General
The proposed expansion of the Brockville WPCC would generally include the addition of new secondary treatment
facilities with ancillary facilities such as access tunnels, and electrical service/communications service buildings,
and possible miscellaneous upgrades to the existing plant. The majority of the expansion work would consist of
open tanks that are semi recessed into the terrain with modest control building or buildings between the tanks.
The exterior cladding of the new buildings would be in keeping with an expression similar to the existing facility.
The intent would be to use exterior cladding finishes and colours that will compliment, and visually integrate the
new structures into the existing facility.
WB092006004OTT 366480
COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL 37
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
10.3 Materials
Concrete will conform to CAN/CSA A23.1 “Concrete Materials and Methods of Concrete Construction.” Typical
compressive strength for tank structures would be 32 MPa with a maximum water/cementing material ration of 0.45,
nominal maximum size of coarse aggregate of 20 mm and an air content of 5 to 8%. Steel reinforcement should
conform to CSA G30.18, Grade 400 deformed billet steel.
Structural steel will conform to CAN/CSA G40.21 “Structural Quality Steels.” Hot rolled structural sections and
plates will be to Grade 350W. Stainless steel sections and plates will generally conform to Type 316 and aluminum
sections and plates will conform to Aluminum Alloy 6061-T6.
WB092006004OTT 366480
38 COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
WB092006004OTT 366480
COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL 39
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
11.2.1 Distribution
Typical distribution conductors will be armored Teck cable in tray. Conductors in hazardous areas will be conductor
in rigid conduit with appropriate seals as it enters these areas.
Distribution panels and step down transformers will be located in the main electrical room or non hazardous areas to
avoid hazardous environment conflicts.
11.2.2 Lighting
Lighting will be manually switched fluorescent. Fixtures will be sealed as required for the hazardous or damp areas.
WB092006004OTT 366480
40 COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
12.2 Ventilation
Ventilation would be provided to meet expected occupational loads and be designed to meet the latest Ontario
Building Code (OBC) and American Society of Heating, Refrigeration and Air Conditioning (ASHRAE) 62
standards for administration/non-process areas. Process areas/pipe galleries would be ventilated in accordance with
National Fire Protection Association (NFPA) 820 Standard for Fire Protection in Wastewater Treatment and
Collection Facilities. Ventilation of process areas not having defined minimum code ventilation rates but potentially
posing health risks to personal would be considered as required (ex. enclosed/covered tanks).
12.4 Plumbing
Separated storm and sanitary drainage would be provided for new facilities per OBC standards. The existing treated
effluent water system would be used to meet process requirements (wash down, etc.) for new areas and tanks.
Potable water would be distributed to new facilities as required and be designed per OBC standards.
WB092006004OTT 366480
COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL 41
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
TABLE 13-1
Typical Project Implementation Schedule for Planning Purposes
Duration
Activity Projected Date (months)
Select Design Consultant and Project Kick-Off Mid February to Mid April, 2008 2
WB092006004OTT 366480
42 COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
Class A Estimate
This is a detailed estimate based on quantity take-off from final drawings and specifications. It is used to evaluate
tenders or as a basis of cost control during day-labour construction.
Class B Estimate
This estimate is prepared after site investigations and studies have been completed and the major systems defined. It
is based on project brief and preliminary design. It is used for obtaining approvals, budgetary control and design cost
control.
Class C Estimate
This estimate, which is prepared with limited site information, is based on probable conditions affecting the project.
It represents the summation of all identifiable project component costs. It is used for program planning, to establish
a more specific definition of client needs and to obtain approval-in-principle.
Class D Estimate
This is a preliminary estimate, which due to little or no site information indicates the approximate magnitude of cost
of the proposed project, based on the client’s broad requirements. This overall cost estimate may be derived from
lump sum or unit costs as identified in the construction cost manual for a similar project. It may be used to obtain
approval-in-principle and for discussion purposes.
Appendix F contains the cost estimating work sheets completed for this study. The total cost estimate was prepared
using the following bases and assumptions:
Costs are 2008 dollars
Building estimates are approximated from their size and type of construction using per square meter costs
Equipment estimates are based on historical data or vender quotations from recently tendered wastewater
projects with allowances for installation based on percentage of the equipment cost
Detailed equipment, electrical, heating and ventilating, process piping, etc. layouts will be completed during
detailed design, therefore, costing for these items has been done at a conceptual level, with an allowance for
conservative quantities with unit prices based on recent tender information from similar projects
Contractors Markup: 15% (10% overhead, 5%) based on recent projects in construction in the Ottawa area
WB092006004OTT 366480
COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL 43
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
TABLE 14-1
Contingency Allowance Carried in Cost Estimate
Total Contingency Allowance Carried
Cost Estimate Level in Cost Estimate
Pre-Design 20%
Pre-Tender 10%
WB092006004OTT 366480
44 COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL
BROCKVILLE WPCC SECONDARY TREATMENT UPGRADE SELECTION OF SECONDARY TREATMENT AND DISINFECTION TECHNOLOGIES
CONCEPTUAL DESIGN REPORT – FINAL
WB092006004OTT 366480
COPYRIGHT 2008 BY CH2M HILL CANADA LIMITED • COMPANY CONFIDENTIAL 45
CONVENTIONAL ACTIVATED SLUDGE
Example Process Flow Diagram
Outfall to
River
Disinfection
Screens Grit
Tanks Aeration Tanks Final
Clarifiers
Return/Waste
Primary Return
Sludge Pumps
Clarifiers Blowers
Waste Sludge
Thickened Waste Sludge Holding
Tank/Thickening
Digested Sludge
Sludge Holding Tank
Pump
Dewatering
Truck to
Centrate Pumping Reuse
LEGEND Station
Wastewater
Anaerobic
Sludge
Digesters
Air
Return to Primary
Treatment
Truck to Land
Application