Ramp 2 Rectification Micro Schedule

The document outlines a micro schedule for the rectification of beams in two cycles. It details the beam IDs, assigned teams, and timelines for hacking, formworks, rebar work, post-tensioning tendons, and casting for each beam. It notes that hacking has been reduced to 22 days and that three additional teams need to be prepared for the second cycle to work on beams 25, 27, and 29 concurrently. Six sets of beam formworks also need to be prepared.

Uploaded by

DharmaDwi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
49 views

Ramp 2 Rectification Micro Schedule

The document outlines a micro schedule for the rectification of beams in two cycles. It details the beam IDs, assigned teams, and timelines for hacking, formworks, rebar work, post-tensioning tendons, and casting for each beam. It notes that hacking has been reduced to 22 days and that three additional teams need to be prepared for the second cycle to work on beams 25, 27, and 29 concurrently. Six sets of beam formworks also need to be prepared.

Uploaded by

DharmaDwi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

RAMP 2 RECTIFICATION MICRO SCHEDULE

Hacking +Perimeter + Pot


Hydrojet
No. Beam ID Team Holes & Air Holes Formworks Rebar Work PT Tendon Casting
Start Finish Start Finish
1 Beam 24 1 Done 02-Mar 29-Feb 04-Mar 03-Mar 04-Mar
2 Beam 30 2 Done 07-Mar 01-Mar 09-Mar 08-Mar 09-Mar
3 Beam 34 3 Done 05-Mar 09-Mar 12-Mar 11-Mar 12-Mar
1st Cycle

4 Beam 40 4 29-Feb 02-Mar 07-Mar 11-Mar 14-Mar 13-Mar 14-Mar


5 Beam 36 1 02-Mar 04-Mar 09-Mar 13-Mar 16-Mar 15-Mar 16-Mar
6 Beam 32 2 04-Mar 06-Mar 11-Mar 15-Mar 18-Mar 17-Mar 18-Mar
7 Beam 28 3 06-Mar 08-Mar 02-Mar 24-Mar 28-Mar 31-Mar 30-Mar 31-Mar
8 Beam 22 5 08-Mar 10-Mar 02-Mar 24-Mar 28-Mar 31-Mar 30-Mar 31-Mar
9 Beam 26 6 10-Mar 12-Mar 02-Mar 24-Mar 28-Mar 31-Mar 30-Mar 31-Mar
10 Beam 38 7 12-Mar 14-Mar 02-Mar 24-Mar 28-Mar 31-Mar 30-Mar 31-Mar
11 Beam 35 1 14-Mar 20-Mar 19-Mar 10-Apr 14-Apr 17-Apr 16-Apr 17-Apr
12 Beam 31 2 20-Mar 16-Mar 21-Mar 12-Apr 16-Apr 19-Apr 18-Apr 19-Apr
13 Beam 33 4 16-Mar 18-Mar 21-Mar 12-Apr 16-Apr 19-Apr 18-Apr 19-Apr
2nd Cycle

14 Beam 37 3 18-Mar 22-Mar 01-Apr 23-Apr 27-Apr 30-Apr 29-Apr 30-Apr


15 Beam 39 5 22-Mar 24-Mar 01-Apr 23-Apr 27-Apr 30-Apr 29-Apr 30-Apr
16 Beam 21 6 24-Mar 26-Mar 01-Apr 23-Apr 27-Apr 30-Apr 29-Apr 30-Apr
17 Beam 23 7 26-Mar 28-Mar 01-Apr 23-Apr 27-Apr 30-Apr 29-Apr 30-Apr
18 Beam 25 8 28-Mar 30-Mar 01-Apr 23-Apr 27-Apr 30-Apr 29-Apr 30-Apr
19 Beam 27 9 30-Mar 01-Apr 01-Apr 23-Apr 27-Apr 30-Apr 29-Apr 30-Apr
20 Beam 29 10 01-Apr 03-Apr 01-Apr 23-Apr 27-Apr 30-Apr 29-Apr 30-Apr

Notes :
1. Hacking has been further reduce into 22 days
2. Cycle 2 need to prepare 3 more additonal team to start concurently for beam 25, 27 and 29
3. Need to prepare 6 sets of Beam Formworks