WMS For Ground Slab Casting
WMS For Ground Slab Casting
Titl
: METHOD STATEMENT FOR GROUND SLAB CASTING
e
01 15/11/10 FI Mohammad
Status Code:
D : Draft FI : For Information FC : For Construction
FA : For Engineer Approval
This Work Method Statement describes the activities required for ground slab casting
2.0 REFERENCES
Revision : 00 Page 1 of 5
3.0 WORK LOCATION/ACCESS REQUIREMENTS
Building No1-A
4.0 METHODOLOGY/PROCEDURE
Base strata
a) Compacted excavation material (from site), selected to remove large boulders above 150mm
nominal diameters.
c) Plinth level – Top of ground slab (plinth level) for building 1A is 150mm (minimum) above the
surrounding finish level. Plinth level 1A = 33.85 ( 33.70 + .15 )
f) Finish to surface - Tamped with wooden dhoomas/bamboo stick or steel bar. Trowel finish
with IPS geru (brick colour) & 300mm x 300mm square with thread in plan markings.
g) Construction joints – 45 degree slope to be given & apply slab joint chemical next day to
continue pour.
h) Concrete pouring – Grade of concrete will be M-15 Mix proportion / cement content for M20
Masons: 16
Carpenters: 20
Steel Fixers: 40
Saw cutting masonry: 10
Labours: 120
Blocks
Nails
Wooden Patti
Planks (MS & wooden)
MS Plates
hessian cloth
Revision : 00 Page 2 of 5
7.0 EQUIPMENT REQUIREMENT
Wooden Float
6 nos of 150mmX 150 mmX 150mm cube moulds of MS
2Vibrator-electrical needles
Slump Cone
wheel barrows
Hand Trowels
Scrabbling tool,
Concrete mixer
Approved
11.0 DISTRIBUTION
Copies of this Work Method Statement have also been issued to the following personnel for
action: -
Project Manager/Senior Site Engineer
HSE Officer
Structural Consultant
Revision : 00 Page 3 of 5