WMS For Ground Slab Casting

This document provides a work method statement for ground slab casting at a construction site in Mazgaon. It outlines the steps which include preparing the base strata by compacting excavated material and applying anti-termite treatment. Concrete will be poured using a pump, dumper, or site mix, with a grade of M15 and curing will involve water and hessian covers for 72 hours. The document also specifies manpower, material, equipment, and safety requirements for the work.

Uploaded by

yash shah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
67% found this document useful (3 votes)
557 views3 pages

WMS For Ground Slab Casting

This document provides a work method statement for ground slab casting at a construction site in Mazgaon. It outlines the steps which include preparing the base strata by compacting excavated material and applying anti-termite treatment. Concrete will be poured using a pump, dumper, or site mix, with a grade of M15 and curing will involve water and hessian covers for 72 hours. The document also specifies manpower, material, equipment, and safety requirements for the work.

Uploaded by

yash shah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

WORK METHOD STATEMENT (WMS)

TRANSIT ACCOMMODATION AT MAZGAON FOR SBUP

METHOD STATEMENT NO. : WMS - 07 REV : 02

ORIGINATING DEPT : CONSTRUCTION DISCIPLINE : STRUCTURAL

Titl
: METHOD STATEMENT FOR GROUND SLAB CASTING
e

REV DATE STATUS REVISION DETAILS PREPARED BY APPROVED BY

01 15/11/10 FI Mohammad

02 27/11/10 FA Layer of backfilling, soling Mohammad

Status Code:
D : Draft FI : For Information FC : For Construction
FA : For Engineer Approval

Construction Department Health and Safety Representative


Distribution :
Design Department

1.0 SCOPE AND OBJECTIVES

This Work Method Statement describes the activities required for ground slab casting

2.0 REFERENCES

Project Technical Specification: Drawing no:-ST/02/RO

Revision : 00 Page 1 of 5
3.0 WORK LOCATION/ACCESS REQUIREMENTS

Building No1-A

4.0 METHODOLOGY/PROCEDURE

Base strata

a) Compacted excavation material (from site), selected to remove large boulders above 150mm
nominal diameters.

b) Level of sub strata – top of beam + 33.280

c) Plinth level – Top of ground slab (plinth level) for building 1A is 150mm (minimum) above the
surrounding finish level. Plinth level 1A = 33.85 ( 33.70 + .15 )

d) Anti-termite treatment to be applied prior to cast the ground slab casting.

e) Maximum area of slab – 22.5sqm

f) Finish to surface - Tamped with wooden dhoomas/bamboo stick or steel bar. Trowel finish
with IPS geru (brick colour) & 300mm x 300mm square with thread in plan markings.

g) Construction joints – 45 degree slope to be given & apply slab joint chemical next day to
continue pour.

h) Concrete pouring – Grade of concrete will be M-15 Mix proportion / cement content for M20

i) Placing of concrete by RMC using Pump or Dumping or Site Mix

j) 5cum per truck or Site Mix volumetric

k) 30 min cycle time ( complete in 3 hours )

l) Tamp off after maximum 30 minutes

m) Curing – water & hessian covers ( 72 hours curing )

5.0 MANPOWER RESOURCE REQUIREMENT/SUPERVISION

Masonry gang shall comprise of the following personnel:-

 Masons: 16
 Carpenters: 20
 Steel Fixers: 40
 Saw cutting masonry: 10
 Labours: 120

6.0 MATERIAL REQUIREMENTS

 Blocks
 Nails
 Wooden Patti
 Planks (MS & wooden)
 MS Plates
 hessian cloth

Revision : 00 Page 2 of 5
7.0 EQUIPMENT REQUIREMENT
 Wooden Float
 6 nos of 150mmX 150 mmX 150mm cube moulds of MS
 2Vibrator-electrical needles
 Slump Cone
 wheel barrows
 Hand Trowels
 Scrabbling tool,
 Concrete mixer

8.0 QC DOCUMENTATION REQUIRED/ATTACHED

 Approved Method Statement


 Checklist
 Pour Card

9.0 HEALTH AND SAFETY HAZARD ASSESSMENT

The safety hazards assessed for RAFT are as follows: -


 Provide Proper PPE
 Provide illumination

Safety Officer’s Approval

Approved

10.0 OTHER INFORMATION

11.0 DISTRIBUTION

Copies of this Work Method Statement have also been issued to the following personnel for
action: -
 Project Manager/Senior Site Engineer
 HSE Officer
 Structural Consultant

Signed: ____________ Date: _30-10-10

Revision : 00 Page 3 of 5