Daily Progress Report (DPR)

The daily progress report summarizes construction progress over 5 wings (A through E) for shuttering, steel, concrete, and blockwork. It also lists site issues, work done by various tradespeople, machinery on site, pending materials and requests. Construction is nearly complete in wings A through C, with shuttering, steel and concrete work over 70% done in wings D and E. Blockwork is over 90% complete across all wings. 280kg of steel was utilized.

Uploaded by

yash shah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views46 pages

Daily Progress Report (DPR)

The daily progress report summarizes construction progress over 5 wings (A through E) for shuttering, steel, concrete, and blockwork. It also lists site issues, work done by various tradespeople, machinery on site, pending materials and requests. Construction is nearly complete in wings A through C, with shuttering, steel and concrete work over 70% done in wings D and E. Blockwork is over 90% complete across all wings. 280kg of steel was utilized.

Uploaded by

yash shah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 46

Daily Progress Report (DPR

Progress
Wing Column Slab Shuttering Steel Concrete Blockwork

A COMPLETE COMPLETE COMPLETE COMPLETE


B COMPLETE COMPLETE COMPLETE 70%
C COMPLETE 100% 10% 20%
D 80% 20% 20% 10%
E 30% 0 20% 10%

Sr
Site Issues Reponsibility

2
3
Sr.No. Workdone Carpenter M/C F/C
1 C-Wing Shuttering Work 3 1
2 Deshuttering B-Work 1 2
3 Column Casting D-wing 4
4 Departmental Work (Safety & 3 3
Housekeeping)
5 Blockwork 3
Project : CENTENNIAL ENTE
Daily Progress Report (DPR) Date:13/03/2020

Material Labour
Item Last Qty Received Utilized Remaining

STEEL M/C
8mm 2980 kg 2920 kg 0 2920 kg Mason
10mm 190 kg 490 kg 0 490 kg Carpentor
12mm 620 kg 750 kg 0 750 kg Fitter
16mm 540 kg 480 kg 0 480 kg Electrician
20mm 500 kg 510 kg 0 510 kg Plumber
25mm 190 kg 280 kg 0 280 kg Welder
polisher
window fabricator
Breaker Man
Painter
F/C

Machinery & Pending Material Requisition Pending Request for Information (RFI)
No.
Equipment Form (MRF) Number Number

MATERIAL HOIST 1 Blocks Phase-2 Terrace Floor


Structural Drawing
4"-1700 Nos.
6"-500 Nos
Fixoblock-50 bags
Mason

3
CENTENNIAL ENTERPRISES

/03/2020

Labour
Total

13
3
4
0
0
0
0
0
0
0
0
3

Attendance

Avinash.K

Hussain.S

Gulshan

Mazhar

Hussain.R

Jayesh.P (Security)

C. Nalawde (Security)
Nawab (Cook)
Daily Progress Report (DPR)

Progress
Wing Column Slab Shuttering Steel Concrete Blockwork (3rd
floor)

A COMPLETE COMPLETE COMPLETE COMPLETE 90%


B COMPLETE COMPLETE COMPLETE 70% 70%
C COMPLETE 100% 20% 20% 90%
D 85% 30% 20% 10% 90%
E 30% 0 20% 10% 90%

Sr
Site Issues Reponsibility

2
3
Sr.No. Workdone Carpenter M/C F/C
1 C-Wing Shuttering Work 3 1
2 Deshuttering B-Work 1 2
3 Column Casting D-wing 4
4 Departmental Work (Slab 3 3
chipping,door frame paint &
Housekeeping)
5 Blockwork (B-wing 3rd floor) 3
6 column shuttering D-wing 1 1
Project : CENTENNIAL ENTERPR
Daily Progress Report (DPR) Date:14/03/2020

Material Labour
Item Last Qty Received Utilized Remaining

STEEL M/C
8mm 2980 kg 2920 kg 280 kg 2640 kg Mason
10mm 190 kg 490 kg 30 kg 460 kg Carpentor
12mm 620 kg 750 kg 53 kg 697 kg Fitter
16mm 540 kg 480 kg 0 480 kg Electrician
20mm 500 kg 510 kg 0 510 kg Plumber
25mm 190 kg 280 kg 0 280 kg Welder
polisher
window fabricator
Breaker Man
Painter
F/C

Machinery & Pending Material Requisition Pending Request for Information (RFI)
No.
Equipment Form (MRF) Number Number

MATERIAL HOIST 1 Blocks Phase-2 Terrace Floor


Structural Drawing
4"-1700 Nos.
6"-500 Nos
Fixoblock-50 bags
Mason

3
CENTENNIAL ENTERPRISES

/03/2020

Labour
Total

14
3
5
0
0
0
0
0
0
0
0
3

Attendance

Avinash.K

Hussain.S

Gulshan

Hussain.R
Jayesh.P (Security)

C. Nalawde (Security)
Nawab (Cook)
Daily Progress Report (DPR)

Progress
Wing Column Slab Shuttering Steel Concrete Blockwork (3rd
floor)

A COMPLETE COMPLETE COMPLETE COMPLETE 90%


B COMPLETE COMPLETE COMPLETE 70% 70%
C COMPLETE 100% 40% 20% 90%
D 90% 40% 20% 10% 90%
E 30% 0 20% 10% 90%

Sr
Site Issues Reponsibility

2
3
Sr.No. Workdone Carpenter M/C F/C
1 C-Wing Shuttering Work 3 1
2 Deshuttering B-Work 1 2
3 Column Casting D-wing 4
4 Departmental Work (Slab 3 3
chipping,door frame paint &
Housekeeping)
5 Blockwork 0
6 column shuttering D-wing 1 1
Project : CENTENNIAL ENTERP
Daily Progress Report (DPR) Date:15/03/2020

Material Labour
Item Last Qty Received Utilized Remaining

STEEL M/C
8mm 2980 kg 2920 kg 1030 kg 1890 kg Mason
10mm 190 kg 490 kg 80 kg 410 kg Carpentor
12mm 620 kg 750 kg 113 kg 637 kg Fitter
16mm 540 kg 480 kg 40 kg 440 kg Electrician
20mm 500 kg 510 kg 40 kg 470 kg Plumber
25mm 190 kg 280 kg 0 280 kg Welder
polisher
Blocks window fabricator
4" 1700 pcs 1700 pcs Breaker Man
6" 500 pcs 500 pcs Painter
Fixoblock 50 bags 50 bags F/C

Machinery & Pending Material Requisition Pending Request for Information (RFI)
No.
Equipment Form (MRF) Number Number

MATERIAL HOIST 1 Phase-2 Terrace Floor


Structural Drawing
Mason

0
CENTENNIAL ENTERPRISES

/03/2020

Labour
Total

11
0
5
0
0
0
0
0
0
0
0
3

Attendance

Avinash.K

Hussain.S

Gulshan

Mazhar

Hussain.R
C. Nalawde (Security)
Nawab (Cook)
Daily Progress Report (D

Progress
Wing Column Slab Shuttering Steel Concrete Blockwork (3rd Blockwork (4th
floor) floor)

A COMPLETE COMPLETE COMPLETE COMPLETE 90% 10%


B COMPLETE COMPLETE COMPLETE 70% 70% 0%
C COMPLETE 100% 50% 20% 90% 0%
D 90% 40% 20% 10% 90% 0%
E 30% 0 20% 10% 90% 0%

Sr
Site Issues Reponsibility

2
3
Sr.No. Workdone Carpenter M/C F/C
1 C-Wing Shuttering Work 3 1
2 Deshuttering B-Work 1 2
3 Column Casting D-wing 4
4 Departmental Work (Slab 3 3
chipping,door frame paint &
Housekeeping)
5 Blockwork 2
6 column shuttering D-wing 1 1
Project : CENTENNIAL ENTERP
Progress Report (DPR) Date:16/03/2020

Material Labour
Item Last Qty Received Utilized Remaining

STEEL M/C
8mm 2980 kg 2920 kg 1550 kg 1370 kg Mason
10mm 190 kg 490 kg 105 kg 385 kg Carpentor
12mm 620 kg 750 kg 158 kg 592 kg Fitter
16mm 540 kg 480 kg 90 kg 390 kg Electrician
20mm 500 kg 510 kg 93 kg 417 kg Plumber
25mm 190 kg 280 kg 50 kg 230 kg Welder
polisher
Blocks window fabricator
4" 1700 pcs 1700 pcs 200 1500 Breaker Man
6" 500 pcs 500 pcs 100 400 Painter
Fixoblock 50 bags 50 bags 4 46 F/C

Machinery & Pending Material Requisition Pending Request for Information (RFI)
No.
Equipment Form (MRF) Number Number

MATERIAL HOIST 1 BLOCKS Phase-2 Terrace Floor


6"-1500 NOS Structural Drawing
4"-700 NOS
FIXOBLOCK-50 BAGS
Mason

2
CENTENNIAL ENTERPRISES

/03/2020

Labour
Total

13
2
5
0
0
0
0
0
0
0
0
3

Attendance

Avinash.K

Hussain.S

Gulshan

MAZHAR

Hussain.R
C. Nalawde (Security)
Nawab (Cook)
Daily Progress Report (D

Progress
Wing Column Slab Shuttering Steel Concrete Blockwork (3rd Blockwork (4th
floor) floor)

A COMPLETE COMPLETE COMPLETE COMPLETE 90% 20%


B COMPLETE COMPLETE 100% 70% 70% 0%
C COMPLETE 100% 70% 20% 90% 0%
D 100% 50% 20% 10% 90% 0%
E 30% 0 20% 10% 90% 0%

Sr
Site Issues Reponsibility

2
3
Sr.No. Workdone Carpenter M/C F/C
1 C-Wing Shuttering Work 3 1
2 Deshuttering B-Work 1 2
3 Column Casting D-wing 4
4 Departmental Work (debris 3 3
collection,door frame paint &
Housekeeping)
5 Blockwork 3
6 column shuttering D-wing 1 1
Project : CENTENNIAL ENTERP
Progress Report (DPR) Date:17/03/2020

Material Labour
Item Last Qty Received Utilized Remaining

STEEL M/C
8mm 2980 kg 2920 kg 1830 kg 1090 kg Mason
10mm 190 kg 490 kg 160 kg 333 kg Carpentor
12mm 620 kg 750 kg 200 kg 550 kg Fitter
16mm 540 kg 480 kg 150 kg 330 kg Electrician
20mm 500 kg 510 kg 180 kg 330 kg Plumber
25mm 190 kg 280 kg 50 kg 230 kg Welder
polisher
Blocks window fabricator
4" 1700 pcs 1700 pcs 400 1300 Breaker Man
6" 500 pcs 500 pcs 200 300 Painter
Fixoblock 50 bags 50 bags 8 42 F/C

Machinery & Pending Material Requisition Pending Request for Information (RFI)
No.
Equipment Form (MRF) Number Number

MATERIAL HOIST 1 BLOCKS Phase-2 Terrace Floor


6"-1500 NOS Structural Drawing
4"-700 NOS
FIXOBLOCK-50 BAGS
Mason

3
CENTENNIAL ENTERPRISES

/03/2020

Labour
Total

14
3
5
0
0
0
0
0
0
0
0
3

Attendance

Avinash.K

Hussain.S

Gulshan

MAZHAR

Hussain.R
C. Nalawde (Security)
Nawab (Cook)
Daily Progress Report (DPR)

Progress Material
Wing Column Slab Steel Concrete Blockwor Blockwor Item Last Qty Received
Shuttering k (3rd k (4th
floor) floor)
A COMPLETECOMPLETECOMPLETECOMPLETE 90% 30% STEEL
B COMPLETECOMPLETE 100% 70% 70% 0% 8mm 2980 kg 2920 kg
C COMPLETE 100% 80% 20% 90% 0% 10mm 190 kg 490 kg
D 100% 50% 20% 10% 90% 0% 12mm 620 kg 750 kg
E 30% 0 20% 10% 90% 0% 16mm 540 kg 480 kg
20mm 500 kg 510 kg
25mm 190 kg 280 kg

Blocks
4" 1700 pcs 1700 pcs
6" 500 pcs 500 pcs
Fixoblock 50 bags 50 bags

Sr Machiner
Pending Material
Reponsibi y&
Site Issues lity Equipmen
No. Requisition Form
(MRF) Number
t
1 MATERIAL 1 BLOCKS
6"-1500 NOS
2 4"-700 NOS
3 FIXOBLOCK-50 BAGS
Sr.No. Workdone Carpenter M/C F/C Mason
1 C-Wing Shuttering Wo 3 1
2 Deshuttering B-Work 1 2
3 Column Casting D-wing 4
4 Departmental Work 3 3
(debris
collection,door
5 Blockwork 3 3
6 column shuttering D-wing 1 1
Project : CENTE

Date:18/03/2020

Material Labour
Utilized Remainin Total
g

M/C 14
1930 kg 990 kg Mason 3
210 kg 280 kg Carpentor 5
260 kg 490 kg Fitter 0
190 kg 290 kg Electrician 0
180 kg 330 kg Plumber 0
50 kg 230 kg Welder 0
polisher 0
window fab 0
550 1150 Breaker M 0
250 250 Painter 0
10 40 F/C 3

Pending Material Pending Request for Attendan


Requisition Form Information (RFI) ce
(MRF) Number Number Avinash.K
BLOCKS Phase-2 Terrace Floor
6"-1500 NOS Structural Drawing
4"-700 NOS Hussain.S
FIXOBLOCK-50 BAGS
Gulshan

MAZHAR

Hussain.R
C. Nalawde (Security)
Nawab (Cook)
Daily Progress Report (DPR)

Progress Material
Wing Column Slab Steel Concrete Blockwor Blockwor Item Last Qty Received
Shuttering k (3rd k (4th
floor) floor)
A COMPLETECOMPLETECOMPLETECOMPLETE 90% 40% STEEL
B COMPLETECOMPLETE 100% 70% 70% 0% 8mm 2980 kg 2920 kg
C COMPLETE 100% 90% 20% 90% 0% 10mm 190 kg 490 kg
D 100% 50% 20% 10% 90% 0% 12mm 620 kg 750 kg
E 30% 0 20% 10% 90% 0% 16mm 540 kg 480 kg
20mm 500 kg 510 kg
25mm 190 kg 280 kg

Blocks
4" 1700 pcs 1700 pcs
6" 500 pcs 500 pcs
Fixoblock 50 bags 50 bags

Sr Machiner
Pending Material
Reponsibi y&
Site Issues lity Equipmen
No. Requisition Form
(MRF) Number
t
1 MATERIAL 1 BLOCKS
6"-1500 NOS
2 4"-700 NOS
3 FIXOBLOCK-50 BAGS
Sr.No. Workdone Carpenter M/C F/C Mason
1 C-Wing Shuttering Wo 3 1
2 Deshuttering B-Work 1 2
3 Column Casting D-wing 4
4 Departmental Work 3 3
(debris
collection,door
5 Blockwork 3 3
6 column shuttering D-wing 1 1
Project : CENTE

Date:19/03/2020

Material Labour
Utilized Remainin Total
g

M/C 14
2100 kg 820 kg Mason 3
280 kg 210 kg Carpentor 5
310 kg 440 kg Fitter 0
190 kg 290 kg Electrician 0
180 kg 330 kg Plumber 0
50 kg 230 kg Welder 0
polisher 0
window fab 0
680 1020 Breaker M 0
300 200 Painter 0
13 37 F/C 3

Pending Material Pending Request for Attendan


Requisition Form Information (RFI) ce
(MRF) Number Number Avinash.K
BLOCKS Phase-2 Terrace Floor
6"-1500 NOS Structural Drawing
4"-700 NOS Hussain.S
FIXOBLOCK-50 BAGS
Gulshan

MAZHAR

Hussain.R
C. Nalawde (Security)
Nawab (Cook)
Daily Progress Report (DPR)

Progress Material
Wing Column Slab Steel Concrete Blockwor Blockwor Item Last Qty Received
Shuttering k (3rd k (4th
floor) floor)
A COMPLETECOMPLETECOMPLETECOMPLETE 90% 50% STEEL
B COMPLETECOMPLETE 100% 70% 70% 0% 8mm 2980 kg 2920 kg
C COMPLETE 100% 100% 20% 90% 0% 10mm 190 kg 490 kg
D 100% 50% 20% 10% 90% 0% 12mm 620 kg 750 kg
E 30% 0 20% 10% 90% 0% 16mm 540 kg 480 kg
20mm 500 kg 510 kg
25mm 190 kg 280 kg

Blocks
4" 1700 pcs 1700 pcs
6" 500 pcs 500 pcs
Fixoblock 50 bags 50 bags

Sr Machiner
Pending Material
Reponsibi y&
Site Issues lity Equipmen
No. Requisition Form
(MRF) Number
t
1 MATERIAL 1 BLOCKS
6"-1500 NOS
2 4"-700 NOS
3 FIXOBLOCK-50 BAGS
Sr.No. Workdone Carpenter M/C F/C Mason
1 C-Wing Shuttering Wo 3 1
2 Deshuttering B-Work 1 2
3 Column Casting D-wing 4
4 Departmental Work 3 3
(debris
collection,door
5 Blockwork 3 3
6 column shuttering D-wing 1 1
Project : CENTE

Date:20/03/2020

Material Labour
Utilized Remainin Total
g

M/C 14
2190 kg 730 kg Mason 3
330 kg 160 kg Carpentor 5
380 kg 370 kg Fitter 0
190 kg 290 kg Electrician 0
180 kg 330 kg Plumber 0
100 kg 180 kg Welder 0
polisher 0
window fab 0
780 920 Breaker M 0
350 150 Painter 0
13 37 F/C 3

Pending Material Pending Request for Attendan


Requisition Form Information (RFI) ce
(MRF) Number Number Avinash.K
BLOCKS Phase-2 Terrace Floor
6"-1500 NOS Structural Drawing
4"-700 NOS Hussain.S
FIXOBLOCK-50 BAGS
Gulshan

MAZHAR

Hussain.R
C. Nalawde (Security)
Nawab (Cook)
Daily Progress Report (DPR)

Progress Material
Wing Column Slab Steel Concrete Blockwor Blockwor Item Last Qty Received
Shuttering k (3rd k (4th
floor) floor)
A COMPLETECOMPLETECOMPLETECOMPLETE 90% 60% STEEL
B COMPLETECOMPLETE 100% 70% 70% 0% 8mm 2980 kg 2920 kg
C COMPLETE 100% 100% 20% 90% 0% 10mm 190 kg 490 kg
D 100% 50% 20% 10% 90% 0% 12mm 620 kg 750 kg
E 30% 0 20% 10% 90% 0% 16mm 540 kg 480 kg
20mm 500 kg 510 kg
25mm 190 kg 280 kg

Blocks
4" 1700 pcs 1700 pcs
6" 500 pcs 500 pcs
Fixoblock 50 bags 50 bags

Sr Machiner
Pending Material
Reponsibi y&
Site Issues lity Equipmen
No. Requisition Form
(MRF) Number
t
1 MATERIAL 1 BLOCKS
6"-1500 NOS
2 4"-700 NOS
3 FIXOBLOCK-50 BAGS
Sr.No. Workdone Carpenter M/C F/C Mason
1 C-Wing Shuttering Wo 3 1
2 Deshuttering B-Work 1 2
3 Column Casting D-wing 4
4 Departmental Work 3 3
(debris
collection,door
5 Blockwork 3 3
6 column shuttering D-wing 1 1
Project : CENTE

Date:21/03/2020

Material Labour
Utilized Remainin Total
g

M/C 14
2190 kg 730 kg Mason 3
330 kg 160 kg Carpentor 5
380 kg 370 kg Fitter 0
190 kg 290 kg Electrician 0
180 kg 330 kg Plumber 0
100 kg 180 kg Welder 0
polisher 0
window fab 0
830 870 Breaker M 0
400 100 Painter 0
16 34 F/C 3

Pending Material Pending Request for Attendan


Requisition Form Information (RFI) ce
(MRF) Number Number Avinash.K
BLOCKS Phase-2 Terrace Floor
6"-1500 NOS Structural Drawing
4"-700 NOS Hussain.S
FIXOBLOCK-50 BAGS
Gulshan

MAZHAR

Hussain.R
C. Nalawde (Security)
Nawab (Cook)