Daily Progress Report (DPR)
Daily Progress Report (DPR)
Progress
Wing Column Slab Shuttering Steel Concrete Blockwork
Sr
Site Issues Reponsibility
2
3
Sr.No. Workdone Carpenter M/C F/C
1 C-Wing Shuttering Work 3 1
2 Deshuttering B-Work 1 2
3 Column Casting D-wing 4
4 Departmental Work (Safety & 3 3
Housekeeping)
5 Blockwork 3
Project : CENTENNIAL ENTE
Daily Progress Report (DPR) Date:13/03/2020
Material Labour
Item Last Qty Received Utilized Remaining
STEEL M/C
8mm 2980 kg 2920 kg 0 2920 kg Mason
10mm 190 kg 490 kg 0 490 kg Carpentor
12mm 620 kg 750 kg 0 750 kg Fitter
16mm 540 kg 480 kg 0 480 kg Electrician
20mm 500 kg 510 kg 0 510 kg Plumber
25mm 190 kg 280 kg 0 280 kg Welder
polisher
window fabricator
Breaker Man
Painter
F/C
Machinery & Pending Material Requisition Pending Request for Information (RFI)
No.
Equipment Form (MRF) Number Number
3
CENTENNIAL ENTERPRISES
/03/2020
Labour
Total
13
3
4
0
0
0
0
0
0
0
0
3
Attendance
Avinash.K
Hussain.S
Gulshan
Mazhar
Hussain.R
Jayesh.P (Security)
C. Nalawde (Security)
Nawab (Cook)
Daily Progress Report (DPR)
Progress
Wing Column Slab Shuttering Steel Concrete Blockwork (3rd
floor)
Sr
Site Issues Reponsibility
2
3
Sr.No. Workdone Carpenter M/C F/C
1 C-Wing Shuttering Work 3 1
2 Deshuttering B-Work 1 2
3 Column Casting D-wing 4
4 Departmental Work (Slab 3 3
chipping,door frame paint &
Housekeeping)
5 Blockwork (B-wing 3rd floor) 3
6 column shuttering D-wing 1 1
Project : CENTENNIAL ENTERPR
Daily Progress Report (DPR) Date:14/03/2020
Material Labour
Item Last Qty Received Utilized Remaining
STEEL M/C
8mm 2980 kg 2920 kg 280 kg 2640 kg Mason
10mm 190 kg 490 kg 30 kg 460 kg Carpentor
12mm 620 kg 750 kg 53 kg 697 kg Fitter
16mm 540 kg 480 kg 0 480 kg Electrician
20mm 500 kg 510 kg 0 510 kg Plumber
25mm 190 kg 280 kg 0 280 kg Welder
polisher
window fabricator
Breaker Man
Painter
F/C
Machinery & Pending Material Requisition Pending Request for Information (RFI)
No.
Equipment Form (MRF) Number Number
3
CENTENNIAL ENTERPRISES
/03/2020
Labour
Total
14
3
5
0
0
0
0
0
0
0
0
3
Attendance
Avinash.K
Hussain.S
Gulshan
Hussain.R
Jayesh.P (Security)
C. Nalawde (Security)
Nawab (Cook)
Daily Progress Report (DPR)
Progress
Wing Column Slab Shuttering Steel Concrete Blockwork (3rd
floor)
Sr
Site Issues Reponsibility
2
3
Sr.No. Workdone Carpenter M/C F/C
1 C-Wing Shuttering Work 3 1
2 Deshuttering B-Work 1 2
3 Column Casting D-wing 4
4 Departmental Work (Slab 3 3
chipping,door frame paint &
Housekeeping)
5 Blockwork 0
6 column shuttering D-wing 1 1
Project : CENTENNIAL ENTERP
Daily Progress Report (DPR) Date:15/03/2020
Material Labour
Item Last Qty Received Utilized Remaining
STEEL M/C
8mm 2980 kg 2920 kg 1030 kg 1890 kg Mason
10mm 190 kg 490 kg 80 kg 410 kg Carpentor
12mm 620 kg 750 kg 113 kg 637 kg Fitter
16mm 540 kg 480 kg 40 kg 440 kg Electrician
20mm 500 kg 510 kg 40 kg 470 kg Plumber
25mm 190 kg 280 kg 0 280 kg Welder
polisher
Blocks window fabricator
4" 1700 pcs 1700 pcs Breaker Man
6" 500 pcs 500 pcs Painter
Fixoblock 50 bags 50 bags F/C
Machinery & Pending Material Requisition Pending Request for Information (RFI)
No.
Equipment Form (MRF) Number Number
0
CENTENNIAL ENTERPRISES
/03/2020
Labour
Total
11
0
5
0
0
0
0
0
0
0
0
3
Attendance
Avinash.K
Hussain.S
Gulshan
Mazhar
Hussain.R
C. Nalawde (Security)
Nawab (Cook)
Daily Progress Report (D
Progress
Wing Column Slab Shuttering Steel Concrete Blockwork (3rd Blockwork (4th
floor) floor)
Sr
Site Issues Reponsibility
2
3
Sr.No. Workdone Carpenter M/C F/C
1 C-Wing Shuttering Work 3 1
2 Deshuttering B-Work 1 2
3 Column Casting D-wing 4
4 Departmental Work (Slab 3 3
chipping,door frame paint &
Housekeeping)
5 Blockwork 2
6 column shuttering D-wing 1 1
Project : CENTENNIAL ENTERP
Progress Report (DPR) Date:16/03/2020
Material Labour
Item Last Qty Received Utilized Remaining
STEEL M/C
8mm 2980 kg 2920 kg 1550 kg 1370 kg Mason
10mm 190 kg 490 kg 105 kg 385 kg Carpentor
12mm 620 kg 750 kg 158 kg 592 kg Fitter
16mm 540 kg 480 kg 90 kg 390 kg Electrician
20mm 500 kg 510 kg 93 kg 417 kg Plumber
25mm 190 kg 280 kg 50 kg 230 kg Welder
polisher
Blocks window fabricator
4" 1700 pcs 1700 pcs 200 1500 Breaker Man
6" 500 pcs 500 pcs 100 400 Painter
Fixoblock 50 bags 50 bags 4 46 F/C
Machinery & Pending Material Requisition Pending Request for Information (RFI)
No.
Equipment Form (MRF) Number Number
2
CENTENNIAL ENTERPRISES
/03/2020
Labour
Total
13
2
5
0
0
0
0
0
0
0
0
3
Attendance
Avinash.K
Hussain.S
Gulshan
MAZHAR
Hussain.R
C. Nalawde (Security)
Nawab (Cook)
Daily Progress Report (D
Progress
Wing Column Slab Shuttering Steel Concrete Blockwork (3rd Blockwork (4th
floor) floor)
Sr
Site Issues Reponsibility
2
3
Sr.No. Workdone Carpenter M/C F/C
1 C-Wing Shuttering Work 3 1
2 Deshuttering B-Work 1 2
3 Column Casting D-wing 4
4 Departmental Work (debris 3 3
collection,door frame paint &
Housekeeping)
5 Blockwork 3
6 column shuttering D-wing 1 1
Project : CENTENNIAL ENTERP
Progress Report (DPR) Date:17/03/2020
Material Labour
Item Last Qty Received Utilized Remaining
STEEL M/C
8mm 2980 kg 2920 kg 1830 kg 1090 kg Mason
10mm 190 kg 490 kg 160 kg 333 kg Carpentor
12mm 620 kg 750 kg 200 kg 550 kg Fitter
16mm 540 kg 480 kg 150 kg 330 kg Electrician
20mm 500 kg 510 kg 180 kg 330 kg Plumber
25mm 190 kg 280 kg 50 kg 230 kg Welder
polisher
Blocks window fabricator
4" 1700 pcs 1700 pcs 400 1300 Breaker Man
6" 500 pcs 500 pcs 200 300 Painter
Fixoblock 50 bags 50 bags 8 42 F/C
Machinery & Pending Material Requisition Pending Request for Information (RFI)
No.
Equipment Form (MRF) Number Number
3
CENTENNIAL ENTERPRISES
/03/2020
Labour
Total
14
3
5
0
0
0
0
0
0
0
0
3
Attendance
Avinash.K
Hussain.S
Gulshan
MAZHAR
Hussain.R
C. Nalawde (Security)
Nawab (Cook)
Daily Progress Report (DPR)
Progress Material
Wing Column Slab Steel Concrete Blockwor Blockwor Item Last Qty Received
Shuttering k (3rd k (4th
floor) floor)
A COMPLETECOMPLETECOMPLETECOMPLETE 90% 30% STEEL
B COMPLETECOMPLETE 100% 70% 70% 0% 8mm 2980 kg 2920 kg
C COMPLETE 100% 80% 20% 90% 0% 10mm 190 kg 490 kg
D 100% 50% 20% 10% 90% 0% 12mm 620 kg 750 kg
E 30% 0 20% 10% 90% 0% 16mm 540 kg 480 kg
20mm 500 kg 510 kg
25mm 190 kg 280 kg
Blocks
4" 1700 pcs 1700 pcs
6" 500 pcs 500 pcs
Fixoblock 50 bags 50 bags
Sr Machiner
Pending Material
Reponsibi y&
Site Issues lity Equipmen
No. Requisition Form
(MRF) Number
t
1 MATERIAL 1 BLOCKS
6"-1500 NOS
2 4"-700 NOS
3 FIXOBLOCK-50 BAGS
Sr.No. Workdone Carpenter M/C F/C Mason
1 C-Wing Shuttering Wo 3 1
2 Deshuttering B-Work 1 2
3 Column Casting D-wing 4
4 Departmental Work 3 3
(debris
collection,door
5 Blockwork 3 3
6 column shuttering D-wing 1 1
Project : CENTE
Date:18/03/2020
Material Labour
Utilized Remainin Total
g
M/C 14
1930 kg 990 kg Mason 3
210 kg 280 kg Carpentor 5
260 kg 490 kg Fitter 0
190 kg 290 kg Electrician 0
180 kg 330 kg Plumber 0
50 kg 230 kg Welder 0
polisher 0
window fab 0
550 1150 Breaker M 0
250 250 Painter 0
10 40 F/C 3
MAZHAR
Hussain.R
C. Nalawde (Security)
Nawab (Cook)
Daily Progress Report (DPR)
Progress Material
Wing Column Slab Steel Concrete Blockwor Blockwor Item Last Qty Received
Shuttering k (3rd k (4th
floor) floor)
A COMPLETECOMPLETECOMPLETECOMPLETE 90% 40% STEEL
B COMPLETECOMPLETE 100% 70% 70% 0% 8mm 2980 kg 2920 kg
C COMPLETE 100% 90% 20% 90% 0% 10mm 190 kg 490 kg
D 100% 50% 20% 10% 90% 0% 12mm 620 kg 750 kg
E 30% 0 20% 10% 90% 0% 16mm 540 kg 480 kg
20mm 500 kg 510 kg
25mm 190 kg 280 kg
Blocks
4" 1700 pcs 1700 pcs
6" 500 pcs 500 pcs
Fixoblock 50 bags 50 bags
Sr Machiner
Pending Material
Reponsibi y&
Site Issues lity Equipmen
No. Requisition Form
(MRF) Number
t
1 MATERIAL 1 BLOCKS
6"-1500 NOS
2 4"-700 NOS
3 FIXOBLOCK-50 BAGS
Sr.No. Workdone Carpenter M/C F/C Mason
1 C-Wing Shuttering Wo 3 1
2 Deshuttering B-Work 1 2
3 Column Casting D-wing 4
4 Departmental Work 3 3
(debris
collection,door
5 Blockwork 3 3
6 column shuttering D-wing 1 1
Project : CENTE
Date:19/03/2020
Material Labour
Utilized Remainin Total
g
M/C 14
2100 kg 820 kg Mason 3
280 kg 210 kg Carpentor 5
310 kg 440 kg Fitter 0
190 kg 290 kg Electrician 0
180 kg 330 kg Plumber 0
50 kg 230 kg Welder 0
polisher 0
window fab 0
680 1020 Breaker M 0
300 200 Painter 0
13 37 F/C 3
MAZHAR
Hussain.R
C. Nalawde (Security)
Nawab (Cook)
Daily Progress Report (DPR)
Progress Material
Wing Column Slab Steel Concrete Blockwor Blockwor Item Last Qty Received
Shuttering k (3rd k (4th
floor) floor)
A COMPLETECOMPLETECOMPLETECOMPLETE 90% 50% STEEL
B COMPLETECOMPLETE 100% 70% 70% 0% 8mm 2980 kg 2920 kg
C COMPLETE 100% 100% 20% 90% 0% 10mm 190 kg 490 kg
D 100% 50% 20% 10% 90% 0% 12mm 620 kg 750 kg
E 30% 0 20% 10% 90% 0% 16mm 540 kg 480 kg
20mm 500 kg 510 kg
25mm 190 kg 280 kg
Blocks
4" 1700 pcs 1700 pcs
6" 500 pcs 500 pcs
Fixoblock 50 bags 50 bags
Sr Machiner
Pending Material
Reponsibi y&
Site Issues lity Equipmen
No. Requisition Form
(MRF) Number
t
1 MATERIAL 1 BLOCKS
6"-1500 NOS
2 4"-700 NOS
3 FIXOBLOCK-50 BAGS
Sr.No. Workdone Carpenter M/C F/C Mason
1 C-Wing Shuttering Wo 3 1
2 Deshuttering B-Work 1 2
3 Column Casting D-wing 4
4 Departmental Work 3 3
(debris
collection,door
5 Blockwork 3 3
6 column shuttering D-wing 1 1
Project : CENTE
Date:20/03/2020
Material Labour
Utilized Remainin Total
g
M/C 14
2190 kg 730 kg Mason 3
330 kg 160 kg Carpentor 5
380 kg 370 kg Fitter 0
190 kg 290 kg Electrician 0
180 kg 330 kg Plumber 0
100 kg 180 kg Welder 0
polisher 0
window fab 0
780 920 Breaker M 0
350 150 Painter 0
13 37 F/C 3
MAZHAR
Hussain.R
C. Nalawde (Security)
Nawab (Cook)
Daily Progress Report (DPR)
Progress Material
Wing Column Slab Steel Concrete Blockwor Blockwor Item Last Qty Received
Shuttering k (3rd k (4th
floor) floor)
A COMPLETECOMPLETECOMPLETECOMPLETE 90% 60% STEEL
B COMPLETECOMPLETE 100% 70% 70% 0% 8mm 2980 kg 2920 kg
C COMPLETE 100% 100% 20% 90% 0% 10mm 190 kg 490 kg
D 100% 50% 20% 10% 90% 0% 12mm 620 kg 750 kg
E 30% 0 20% 10% 90% 0% 16mm 540 kg 480 kg
20mm 500 kg 510 kg
25mm 190 kg 280 kg
Blocks
4" 1700 pcs 1700 pcs
6" 500 pcs 500 pcs
Fixoblock 50 bags 50 bags
Sr Machiner
Pending Material
Reponsibi y&
Site Issues lity Equipmen
No. Requisition Form
(MRF) Number
t
1 MATERIAL 1 BLOCKS
6"-1500 NOS
2 4"-700 NOS
3 FIXOBLOCK-50 BAGS
Sr.No. Workdone Carpenter M/C F/C Mason
1 C-Wing Shuttering Wo 3 1
2 Deshuttering B-Work 1 2
3 Column Casting D-wing 4
4 Departmental Work 3 3
(debris
collection,door
5 Blockwork 3 3
6 column shuttering D-wing 1 1
Project : CENTE
Date:21/03/2020
Material Labour
Utilized Remainin Total
g
M/C 14
2190 kg 730 kg Mason 3
330 kg 160 kg Carpentor 5
380 kg 370 kg Fitter 0
190 kg 290 kg Electrician 0
180 kg 330 kg Plumber 0
100 kg 180 kg Welder 0
polisher 0
window fab 0
830 870 Breaker M 0
400 100 Painter 0
16 34 F/C 3
MAZHAR
Hussain.R
C. Nalawde (Security)
Nawab (Cook)