Bridges Failures in Extreme Flood Events
Bridges Failures in Extreme Flood Events
Sumaira Jan
Department of Civil Engineering, Bagwant University, Ajmer.
ABSTRACT
Transportation is an important requirement in people’s daily lives. Both urban and rural areas
are linked by highways and bridges. Road networks and critical road structures such as bridges,
culverts and floodways have vital role before, during and after extreme events to reduce the
vulnerability being served. The performance of the bridge is dependent on the strength and
durability of its components. Since bridges cannot resist indefinitely all the natural forces and
hazards including time-related degradation of materials, these structures have limited service life.
The bridges have to maintain in order to have better and longer service life and in order to prevent
premature failure. The service life expectancy of a bridge may generally be about 70 years for
superstructure and about 100 years for substructure. But many bridges fail before service 20 year
life term due to lack of maintenance.
This paper presents an analysis of the case study of 2014 floods in Kashmir valley region in
India to identify the failure mechanism of the road bridges exposed to flood events. In Jammu and
Kashmir state as many as 60 major and minor roads were cut-off and over 30 bridges were
damaged due to 2014 floods. Major failure mechanism of the bridges were identified as scouring of
the abutments and piers, damage to bridge decks due to urban debris, and in some areas due to
continuous striking of the heavy stones with the bridges. Some bridges were closely analyzed and
causes of the failure were studied also. The possible retrofit techniques were studied.
Key words: Bridge maintenance, inspection, waterway of bridges, failure of bridges.
Cite this Article: Azmat Hussain and Sumaira Jan, Bridges Failures in Extreme Flood Events by
Taking a Case Study. International Journal of Civil Engineering and Technology, 7(5), 2016,
pp.222–231.
http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=7&IType=5
1. INTRODUCTION
Thomas B. Macaulay once said, “Of all inventions, the alphabet and the printing press alone accepted,
those inventions which abridge distance have done the most for the civilization of our species.” According
to the New York state department of transportation the bridge can be defined “A structure, including
supports, erected over a depression or an obstruction such as water, highway, or railway and having a track
or passageway for carrying traffic or other moving loads, and having an opening measured along the centre
of the roadway of more than 20 ft between under copings of abutments or spring lines of arches, or
extreme ends of openings for multiple boxes. Multiple pipe configurations will qualify as bridges where
the clear distance between openings are less than half of the smaller, adjacent opening, and the total length
along the center of the roadway is greater than 20 ft”, A bridge is an important element in a transportation
system, as its capacity governs the capacity of the system, its failure or defective performance will result in
serious disruption of the traffic flow. It is well known that absolute safety is the criteria in building bridges
as there are risks of failure associated with the bridges. Its failure will result in loss of lives and will affect
the people. Bridges constructed over rivers, seas and waterways are vulnerable to disaster such as tsunami
and flooding. Bridges build over the rivers and seas are facing unexpected loadings due to floods and
tsunamis. Displacement of the bridges due to erosion and collapsing of the abutments, lateral pressure
generated by the water and floating debris are common. Since bridges cannot resist indefinitely all the
natural forces and hazards including time related degradation of materials, these structures have limited
service life. The bridges have to be maintained in order to prevent premature failure and to extend the
service life. Proper inspection and maintenance is necessary to maintain the life of the bridges.
3. RESEARCH OBJECTIVE
The objective of the research was to identify the strategies and technologies to restore the damaged
bridges. The damaged bridges are studied keenly and their cause of the failure is studied. Then the possible
retrofit solution is analyzed. As on September 2014, the valley of Kashmir suffered huge loss and about 60
major and minor roads were dammed and over 30 bridges were washed away. Some bridges were only 11
year old and yet they fail in the floods. The flood was worst since 109 years and it damaged the
infrastructure badly. The necessity of this research is to analyze one of the failed bridge and also to find the
cause of their failure. The possible methods to retrofit the bridge are also explained
4. A CASE STUDY
In September 2014, the Kashmir region suffered disastrous floods across many of its districts caused by
torrential rainfall. The Indian administrated Jammu and Kashmir, as well as Pakistan administered Azad
Kashmir, Gilgit-Baltistan and Punjab were affected by these floods. By September 24, 2014, nearly 277
people in India and about 280 people in Pakistan had died due to the floods. On 5 September, the Jhelum
River in Srinagar was reported to be flowing at 22.40 feet (6.83 m) which was 4.40 feet (1.34 m) above the
danger mark and at 33 feet (10 m) at Sangam in Anantnag district above the danger mark. The discharge
rate in the river was recorded as 70000 m3/s against the normal discharge of 25000 m3/s. The Chenab
River was also reported to flow above the danger mark by which hundreds of villages were affected
in Pakistan. These rivers flooded into the streets causing heavy casualties and loss of property.
6. GENERAL DETAILS
Some general details of the bridge are as under:
• Total length of the bridge is 108.3mtrs.
• 2No Dummy abutments.
• Solid wall type piers Rcc with circular ends having open foundation.
• 2NO Balanced Cantilever bridges each supported on two piers formed .by four longitudinal precast
prestressed girders.
• 7.5mtr carriage way.
7. BRIDGE SUBSTRUCTRURE
The bridge deck system is 108.3mtr in length and was supported by four NOs piers in river section as
2NOs Dummy abutment structures placed behind major deep drains/Nallahs located beyond both river
banks. The piers were solid wall type Reinforced cement concrete construction with circular ends having
open foundation. The Dummy abutment structures are located on the bank of the river.
8. BRIDGE SUPERSTRUCTURE
The bridge superstructure consists of 2NOs Balanced Cantilever type deck units each supported on two
piers, formed by four longitudinal precast prestressed girders in tandem with cast in situ RCC diaphragms
and deck slab forming the composite girder system. The cantilever arms of these units with articulation
provision support shore span on one end and central suspended span on the other end.POT bearings are
provided at seating of girders of shore span/central span. Strip seal movement joints are provided at ends of
the bridge deck and at one end of the central suspended span only and all other three joints were
hinged/rotation joints only for improved riding comfort.
characteristics of a bridge. Debris accumulation in the bridge may result in substantial block in bridge
opening, the waterway opening area is considerably reduced .As we can see here in this picture, the
opening under the bridge is reduced considerably thereby reducing the waterway of the bridge. With
reduced waterway, velocity would increase and greater scour depths would be involved, requiring deeper
foundations. But after constructing the bridge, these things became negligible and lead to the failure of the
bridges.
The above figure clearly shows how the construction of the shed, taxi stand etc reduced the waterway
of the bridge and thereby not giving free and full passage of the flood to pass which lead to scour failure of
the bridge.
6. The discharge of 9504 cusecs which should be pass through at least 91.5mtr width, only passed
through 36.6m, thereby causing the scour failure of the bridge. The below figure is the site plan
of the bridge clearly shows the damaged pier and linear waterway for the bridge. The detailed
site plan of the bridge was made after floods
• The bridge can be rehabilitated and put to use by the way of:
a) Abandoning/Dismantling the damaged pier only and raising a fresh one. The existing RCC
Girders can be restored back to position by supporting them on steel trestles and using
hydraulic jacks for lifting them to position
b) By the way of raising RCC protection wall for the left abutment.
c) The total waterway for which the bridge has been originally designed needs to .be restored
back in all cases so that further scouring does not take place in future.
The restoration of the bridge can be done by the above methods. But some more points will be put
forward to further explain the above procedure.
• Widening of the waterway and preparatory works for improvement and reconstruction. The waterway has to
be increased from the present 36.6m to about 91.5m(Bed level between the piers P1 to P4 should not be
more 91.9m).The right bank should be with 1:1.5(Hor) slope. This widening should be for about 150mtr
both U/S and D/S side. In case the land for widening is not available, then the minimum widening should be
for 65mtr (up to beyond pier P3).In case this reduced width is adopted, then stone pitching should be
provided with launching apron on right bank all along the length (say 50 to 150 metre both U/S and
D/S).Provide filter media behind stone pitching.
• Protect abutment A1 side soil with gabion wall
• The existing superstructure of span A1 P1 and P1 P2 have to be carefully dismantled. During dismantling
staging and crane facility would be needed to avoid free fall of the debris and for removal of debris. The pier
cap and pier shaft of pier P1 also have to be removed.
12.1.1. Introduction
Kashmir valley during September 2014 experienced one of the worst floods ever recorded in modern
Kashmir history. The flood has caused wide spread heavy damages to residential buildings ,commercial
complexes, bridges etc.In the same flood one bridge called chadoora bridge over Nallah Doodganga at
chadoora also got damaged. The J and K govt. has embarked upon massive restoration plan to rehabilitate
the damaged bridges. This chadoora bridge is one of them. In this study, methods to restore the bridge
were analyzed and some soil investigations were also done for the Pier P1 of the bridge.
12.1.3. Methodology Adopted for Sub Surface Exploration and Tests Conducted
In accordance with IS;1892-1979 exploratory boreholes BH-1through BH-2 of Nx/Bx size have to drilled
to depth up to 15m using heavy duty diamond core drilling machine. Wherever gravel and cobbles and
sandy matrix are met with, it is not possible to collect undisturbed samples to find out the shear and
consolidation characteristics of the material. However in-situ tests are carried out for this purpose in such
materials. Standard penetration tests were conducted in the bore holes at various depths or wherever
possible in accordance with IS: 2131-1981.
Undisturbed samples are not possible in cobble, gravel and sandy matrix ( refer clauses 4.1 and 7.1 of
IS: 10042) met with at site..This is due to the fact that this material neither falls in the class of soils nor in
rocks but in the form of gravel cobble with sandy matrix. In such formations apart from borehole
investigation as per IS:10042,it becomes essential to conduct large scale in- situ density and grain size
measurements by excavating a pit of known dimensions at about 1m depth or at change of strata. Strength
parameters for such type of deposits are evaluated by conducting in-situ shear tests on blocks whose size
shall be 10 times the average size of boundaries/cobble or 120cm x 120cm x 30cm (refer clause 5.9 of IS
10042) whichever is more. These tests are beyond our scope.
Figure 6
In accordance with IS: 1888 for permissible settlement of 25 mm for shallow foundation of 6m x 6m
size , the allowable bearing capacity of gravel-boulder is evaluated from figure 2 corresponding to
settlement of plate as per equation Sp=Sf
[B(BP+0.3)/BP(B+0.3)]2 = 17.64 mm
For settlement of 17.64 mm , the allowable bearing capacity works out to be 4.4kg/cm2 or 44t/m2.On
the other hand, Teng’s modified allowable bearing capacity equation for gravelly soils in the case of
shallow foundation for 25mm settlement is given by
q25=3.35*Cb(N-3)[B+0.3/0.3/2B]2 dwdf (in which Cb =constant = 2 for gravelly soils and dw & df
are water table reduction factor and dw ,depth factor respectively) for widths greater than 4m reduces to
q25=2x(N-3)xdwxdf for with corrected N as 40,df as 1 and water table correction factor dw as 0.5,the
allowable bearing capacity for 25mm permissible settlement works out to be 37t/m2.The safe bearing
capacity in accordance with IS 6403,considering effective φ = 330 for 6m wide footing just below the scour
depth works out to be 39.85t/m2.Therefore for shallow foundations the allowable bearing capacity can be
considered as 35t/m2 in gravel-boulder material.
For open foundation, if the depth of the foundation is more than the width of foundation, the allowable
bearing capacity can be increased by a factor equal to (1+0.2D/B) but less than or equal o 1.33 i-e 46.55
t/m2.Therefore for open foundation we limit the allowable bearing capacity to 46.50t/m2
Open foundation shall not be allowed to rest on filled up material, this needs to be ensured that the bulk
density of foundation grade material is more than 2.2g/cc
14. CONCLUSION
By analyzing the recent failures in the bridges, the future planning can be better. In future, structures can
be saved from such disasters. Need of inspection is necessary for the bridges. Using advanced methods the
bridges can be monitored anywhere. Periodical inspection and regular maintenance is necessary to keep the
bridges functional. Otherwise disasters can come anytime as they are unpredictable and sometimes
uncontrollable.
REFRENCE
[1] Azmat Hussain, Saba Bashir, Saima Maqbool: Damage detection in bridges using image processing
[2] Prabhat Dahal, Dongming Peng, yaoqing (Lamar) yang, Hamid Sharif: RSS Based scour measurement
using underwater acoustic sensor networks.
[3] Yong Bai, M.ASCE, Willaim R.Burkett, P.E, and Phillip T.Nash, P.E: Rapid bridge replacement under
emergency situation.
[6] Azmat Hussain, Saba Bashir and Saima Maqbool, “Damage Detection in Bridges using Image
Processing”. International Journal of Civil Engineering and Technology (IJCIET), 7(2), 2016, pp.215–
225.
[7] Hudson, S., Comie, D., Tufton, E., Inglis, S.: Engineering resilient infrastructure. Civil Engineering
special issue.
[8] Blong, R (2003): A new damage index. Natural hazards 30, 1-23.
[10] Narayan, S.K.B, Ashok K: Foundation failure of bridges in Orissa: two case studies.
[11] Dr. K.V. Ramana Reddy, “Aerodynamic Stability of a Cable Stayed Bridge”. International Journal of
Civil Engineering and Technology (IJCIET), 5(5), 2014, pp.88–96.