Geothermal Energy Development in The Philippines: Country Update
Geothermal Energy Development in The Philippines: Country Update
net/publication/228575099
CITATIONS READS
4 3,179
3 authors:
James Stimac
Stimac Geothermal Consulting
71 PUBLICATIONS 1,472 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Manuel Ogena on 28 May 2014.
[email protected]; [email protected]
Keywords: The Philippines, installed generating capacity, and dampened investors’ interest in the country. Thus, only
topping cycle plant, bottoming cycle plant, Mak-Ban, Tiwi, 22 MWe was added to the total installed capacity from
Bacman, Tongonan, Palinpinon, Mt. Apo. geothermal power plants since 1998 and a total of 28 wells
with total depth of 63.1 kms. drilled between 2000-2003
ABSTRACT (Table 2).
The Philippines is the world’s second largest producer of To date, since production began in 1977, the cumulative
geothermal energy for power generation. As of end 2003, electricity generation from geothermal energy totals 152,336
the total installed generating capacity from geothermal gigawatt-hour (GWh) from 100,602 GWh in 1998 or an
power plants was 1,931 MW, accounting for about 19% of increase of 51.4% (Table 1). The electricity generated is
the country’s power generation mix. about 262.65 million barrels of fuel oil equivalent
(MMBFOE), which translates to about US$5.57 Billion in
The Government has set a renewable energy target, dubbed
terms of foreign exchange (forex) savings (Department of
“100 in 10”, that aims to double the current installed
Energy, 2003).
generating capacity from renewable energy sources in the
next ten years. Geothermal energy will be a major
contributor to the attainment of this target, as the country 2. GEOTHERMAL RESOURCES AND POTENTIAL
also aims to become the world’s largest geothermal energy The geologic setting of the Philippine archipelago and
producer, having proven geothermal as a reliable and clean individual Philippine geothermal systems was described and
source of energy for the past 30 years. extensively discussed in Sussman et al. (1993). The service
contract areas that are either currently producing, or likely to
1. INTRODUCTION be developed in the next decade are discussed below which
is essentially an update of the country paper presented by
As of December 2003, the Philippine Government through
Karunungan et al. (2000) in the last World Geothermal
the Department of Energy (DOE) continue to administer the
Congress held in Japan in 2000.
operations of nine (9) geothermal service contract areas. Of
these contract areas, six (6) are producing fields and three
(3) are in advanced exploration stage (Figure 1). Two of the 2.1 Tiwi, Albay
contracts are operated by Philippine Geothermal, The Tiwi field is located about 300 km southeast of Manila
Incorporated (PGI), a subsidiary of the Union Oil of in the Albay Province of Luzon Island and operated by PGI
California (UNOCAL), while the rest are managed by the (Figure 1). Throughout much of the past five years,
government-owned and -controlled Philippine National Oil production in the Tiwi field has been limited by the
Company-Energy Development Corporation (PNOC-EDC). availability of aging power plant stations. The capacity of
the field was also derated from 330 MW to 275 MW with
The Philippines’ total installed generating capacity from the shutdown of Unit 4 as of December 2001 (Table 3).
geothermal power plants stood at 1,931 MWe and is about
12.7% of the country’s total capacity of 15,132 MWe (Table Rehabilitation of Plants A (Units 1 and 2) and C (Units 5
1). The country has likewise maintained its position as the and 6) commenced in 2003, and should be completed in
world's second largest producer of geothermal energy for 2005. As part of this rehabilitation, the rated capacities of
power generation. The largest geothermal installation is the units will be increased to 59 MW for Units 1 and 2 and
located in Tongonan, Leyte with an aggregate capacity of 57 MW for Units 5 and 6. By late 2005, it is therefore
722.68 MWe or 37% of the total installed geothermal expected that Tiwi will be operating at 232 MW capacity.
capacity. In terms of actual production, the contribution of Unit 3 will continue operation without rehabilitation, in a
geothermal energy to the country’s total power generation standby mode. During the period of relatively low plant
mix has decreased from 21.52% in 1998 to 19.1% in 2003 availability that has occurred from 1996 to 2005, reservoir
(Figure 2) due to the commissioning between 2000-2001 of pressures and fluid levels have recovered significantly,
about 2,760 MWe natural gas power plants. especially in the Naglagbong and Kapipihan areas (Protacio
et al., 2001), and this also helped to stabilize the overall
The onset of the 1997 Asian financial crisis slowed down steam production capability of the field. However, since no
the growth of the country’s economy, thereby reducing new wells have been drilled in Tiwi since 1997, some steam
electricity demand because the projected industrial activities, development projects were required to meet the anticipated
with its corresponding electricity requirement did not steam needs of the rehabilitated units (estimated at 4,400
materialize (Perez, 2004). This economic slow down was kph at the wellhead).
aggravated further by the 9/11 incident in the U.S. in 2001
1
Benito et al.
2
Benito et al.
3
Benito et al.
• 112.5 MWe Tongonan I power plants are operated by MWe in the Palayang Bayan sector (Bacman I) was
NAPOCOR; commissioned in 1993. In 1994, a 20-MWe extension in the
• 219.48 MWe Tongonan II BOT power plants are Cawayan sector (Bacman II) was commissioned followed by
composed of the 141.98-MWe Upper Mahiao Binary the additional 20-MWe in the Botong sector, which was
and the 77.5-MWe Malitbog power plants; and commissioned in May 1998. To date, a total of 24
• 390.70-MWe Tongonan III BOT power plants which production and 12 reinjection wells have been drilled in
come from the 3 x 6.5-MWe Tongonan I Topping Bacman. As of December 2003, the power plants have
Cycle, 2 x 6.50-MWe Mahanagdong A Topping Cycle, delivered a cumulative total of 5,939.2 GWh of electricity
1 x 6.50-MWe Mahanagdong B Topping Cycle, 1 x (Table 4). A number of mechanical and other problems
16.70-MWe Malitbog Bottoming Cycle, 3 x 60-MWe related to the power-generating turbines have plagued the
Mahanagdong A&B and the 2 x 77.5-MWe Malitbog Bacman-I power plant for several years now. Most of the
power plants. time, Bacman-I was run with only one (1) unit operating,
Topping cycle plants are installed in Tongonan I, thus the low electricity output of the power plant. On the
Mahanagdong A and Mahanagdong B Sectors, while other hand, power plant operations in both Cawayan and
bottoming cycle in the Malitbog Sector. Tongonan II power Botong sectors have been relatively smooth, and steadily
plants commissioned in 1996 export electricity from Leyte supply power to the Luzon grid.
to Cebu via an AC submarine cable, while Tongonan III
commissioned in 1997 transports power from Leyte to Operation of the Manito Livelihood Geothermal Project
Luzon via DC submarine cable. inaugurated in 1998, has been suspended by PNOC-EDC.
The Project is a joint undertaking by the DOE, National
The power plants in Leyte have been in full operation since Power Corporation (NPC), National Electrification
May 1998. Consequently, Tongonan's electricity gross Administration (NEA), PNOC-EDC and the Local
generation of 3,111.98 GWh in 1998 escalated by as much Government of Manito. It is located at Pawa, Manito, Albay
as 200% as against the previous year’s 998.36 GWh. As of within the Bacon-Manito Geothermal Power Project. The
December 2003, Tongonan power plants have generated a drop in market demand as well as major turbine problems
cumulative total of 35,223.3 GWh of electricity. Gross have caused the shelving of the livelihood project.
generation for 2003 of 4,745.6 GWh was slightly lower (by
300 GWh) than the year previous because of minor fluid and 2.6 Mindanao, North Cotabato/Davao
operational problems encountered, but these have been dealt The country's sixth geothermal production field, the
with accordingly (Table 4). All ongoing activities in Leyte Mindanao field, is also operated by PNOC-EDC. It is
are geared towards sustaining the steam supply for the located on the northwest slopes of Mt. Apo in the northern
power plant requirements. These activities include drilling part of Cotabato and Davao provinces (Figure 1). It is made
of make-up and replacement wells, working-over old wells up of two power plants – Mindanao-I commissioned in
with reduced outputs and injection capacities, and dealing 1996 with an installed capacity of 54.24 MWe, and
with corrosion, erosion and mineral scaling problems. Mindanao-II put on line in 1999 with the same installed
capacity of 54.24-MWe. As of December 2003, total
2.4 Palinpinon, Southern Negros accumulated generation of both plants was 4,493.7 GWh of
The Palinpinon geothermal field, which is also operated by electricity (Table 4).
PNOC-EDC, is located in Southern Negros on the southern
flanks of a young volcanic complex. A total of 43 Existing idle production wells are planned to be used for an
production and 26 reinjection wells have been drilled in the expansion project beyond the existing Mindanao-I and -II
field. Power plants with a combined capacity of 192.5 MWe power plants. In the event that this project is realized,
are installed in Palinpinon. In Palinpinon-I (Puhagan), the Mindanao will have more than enough steam to supply
installed capacity is 112.5MWe, and the plants have been in another 20-MWe plant.
operation since 1983. Palinpinon-II is divided into three (3)
modular power plants (Table 3): Balas-balas (20 MWe), 2.7 Other Areas
Nasuji (20 MWe) and Sogongon (40 MWe). As of 2.7.1 Northern Negros, Negros Occidental (PNOC-EDC)
December 2003, all the above plants have generated a
cumulative total 16,244.8 GWh of electricity (Table 4). The Northern Negros Geothermal Project covers an area of
4,310.84 hectares situated in Mambucal, Negros Occidental
Power plant related problems have been encountered in the Island in the Visayas Region. A projected 40 MWe of
Palinpinon-I units, causing prolonged shutdowns and geothermal capacity is expected to be commissioned in
reduced loads. To date, however, all units are fully 2006. To date, a total of ten (10) exploratory wells have
operational. been drilled in Northern Negros by PNOC-EDC. Current
activities in this field are fluid collection and reinjection
Plans are underway to expand the capacity of Palinpinon-II system (FCRS) and power plant construction.
by adding another 20-MWe power plant. Idle and throttled
production wells from the Nasuji sector will be utilized and 2.7.2 Palinpinon-II Optimization (PNOC-EDC)
optimized for the additional plant. PNOC-EDC is in the As mentioned earlier, construction activities for the 20-MWe
process of discharging stand-by wells and constructing new Palinpinon-II optimization project will be underway by late
production and injection pads for the expansion project. 2004. The new plant will utilize excess steam from existing
Target commissioning year of this planned 20-MWe power Nasuji wells, and separated brine will be piped to the current
plant is 2006. Nasuji RI sink. No new well drilling is programmed for the
expansion. Like in Northern Negros, commissioning date is
2.5 Bacon-Manito (Bacman), Albay/ Sorsogon early 2006.
The Bacon-Manito Geothermal Production Field (BGPF) is
also operated by PNOC-EDC and is located in the provinces
of Sorsogon and Albay in the Bicol Peninsula (Figure 1). A
first stage geothermal power plant development of 110-
4
Benito et al.
3. EXPLORATION AND DEVELOPMENT (Figure 3). The technical details of the prospective areas
The country’s geothermal resource potential from 35 and the contracting round activity are described in the
identified areas is estimated at 4,335 MW. Given this vast Geothermal Contracting Round-1 Brochure published by the
amount of potential reserves and the anticipated increase in Department of Energy (2004). Short description of these
energy demand, the Philippines has embarked on aggressive prospective areas are as follows:
exploration activities to bring the total geothermal capacity
to at least 3,131 MW and become the largest geothermal 3.1 Manito-Kayabon, Albay/Sorsogon
energy producer in the world in 2013. The Manito-Kayabon is a sector of BGPF located in the
Bicol Peninsula. BGPF is currently producing 110 MWe
As part of its Renewable Energy Policy Framework (REPF), from its Palayang Bayan sector (Bacman-1) and 20 MWe
the Philippine Department of Energy has undertaken in each from its Cawayan and Botong sectors. The Manito-
March to July 2004, the so-called Philippine Kayabon sector is the northernmost cluster of resource
"GEOTHERMAL-1", a contracting round aimed at blocks in BGPF. Stored heat calculations of this sector point
attracting investments in 10 prospective geothermal areas to a total power potential of 51.2 MWe.
5
Benito et al.
6
Benito et al.
8
Benito et al.
geothermal field, Philippines. Proceedings of the World Sussman, D., Javellana, S.P., and Benavidez, P.J., 1993,
Geothermal Congress. Pisa, Italy 1803-1805. Geothermal energy development in the Philippines: an
overview. Geothermics, 22, 353-367
Sugiaman, F., Sunio, E., Molling, P., and Stimac, J., 2004,
Chemical response to production of the Tiwi
Geothermal Field, Philippines. Geothermics, 33, 57-86.