Daily Progress Report of NGL: Faisal S. Al-Naimi Est

This daily progress report from Faisal S. Al-Naimi Est. documents work from April 13-May 1, 2020 on an NGL project. For several days in April, work was stopped due to flare gases being released at the working area. Template and mold preparation began on April 16. By April 21, molds were prepared and shed roof casting had started. Ceramic sleeve casting was completed on April 24. Muffle block casting was finished on April 27. Fireproof material application and dryout preparations continued through April 30.

Uploaded by

Saragadam Dilsri
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
34 views

Daily Progress Report of NGL: Faisal S. Al-Naimi Est

This daily progress report from Faisal S. Al-Naimi Est. documents work from April 13-May 1, 2020 on an NGL project. For several days in April, work was stopped due to flare gases being released at the working area. Template and mold preparation began on April 16. By April 21, molds were prepared and shed roof casting had started. Ceramic sleeve casting was completed on April 24. Muffle block casting was finished on April 27. Fireproof material application and dryout preparations continued through April 30.

Uploaded by

Saragadam Dilsri
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

FAISAL S. AL-NAIMI EST.

P.O. BOX 850 AL-JUBAIL K.S.A.


TEL # (013) 362 2919
FAX #: (013) 361 1518

DAILY PROGRESS REPORT OF NGL


Sr.No Date Description Activity Under Remarks
1 4/13/2020 No permit issued SA Work has stopped due to flare gases are releasing at working area
2 4/14/2020 No permit issued SA Work has stopped due to flare gases are releasing at working area continuously
3 4/15/2020 No permit issued SA Work has stopped due to flare gases are releasing at working area continuously
Work has stopped due to Mechanical peoples are doing alignment for burner
backside as per TPI(Rao) Instructions and we are waiting for SA(Hothaifa) call to
4 4/16/2020 Template preparation SA proceed refractory work

5 4/17/2020 Template preparation Alfran We prepared template for ceramic sleeve and muffle blocks as per site condition
6 4/18/2020 Mould marking Alfran Marking is going on for mould making of ceramic sleeve and muffle blocks
7 4/19/2020 Mould preparation Alfran Mould preparation is going on for muffle blocks

Mould preparation & Form Mould preparation is going on for muffle blocks in alfran store and prepared form
8 4/20/2020 work for Shed roof casting Alfran work for shed -roof casting at site

Mould preparation & Shed Prepared mould for muffle blocks in our alfran store and Shed roof casting started
9 4/21/2020 roof casting Alfran at site

Sleeve mould preparation Preparing ceramic sleeve mould in our alfran store and done casting on shed roof at
10 4/22/2020 & Shed roof casting Alfran site

Sleeve mould preparation


& Fireproof material Preparing ceramic sleeve mould in our alfran store and Started fireproof material
11 4/23/2020 application Alfran application at site
Ceramic sleeve mould preparation is completed and started casting for ceramic
12 4/24/2020 Sleeve casting Alfran sleeve

Sleeve casting & Fireproof Ceramic sleeve casting completed and preparing muffle block mould in our alfran
13 4/25/2020 material application Alfran store.Doing fireproof material application at site
Muffle block mould
preparation & Fireproof Preparing muffle block mould in our alfran store and Installing fireproof material at
14 4/26/2020 material application Alfran site
Muffle blocks casting and
fireproof material Done casting for muffle blocks in our alfran store and installing fireproof material at
15 4/27/2020 application Alfran site
Fireproof material
16 4/28/2020 application Alfran Installing fireproof material at site
Fireproof material
17 4/29/2020 application Alfran Installing fireproof material at site
Dryout preparation and
fireproof material Dryout preparation is going on for ceramic sleeve and muffle blocks in alfran store
18 4/30/2020 application Alfran and Fireproof material application at site
19 5/1/2020 Dryout Alfran Started dryout for ceramic sleeve and muffle blocks in alfran store