Hira Shakeel MGT 303 Homework 4 Zahra Azadi
Hira Shakeel MGT 303 Homework 4 Zahra Azadi
c) Duration is 39.50
d) Variance is 8.25
e) Probability is NORM.DIST (-1.21,0,1,TRUE) = 0.11313945
NETWORK DIAGRAM
B E
F H I
A
C
G J
Question 2
Varianc
Activity a m b Expected Time
e
A 9 10 11 10 0.33
B 4 10 16 10 2.00
C 9 10 11 10 0.33
D 5 8 11 8 1.00
Question 3
Using PERT, Adam Munson was able to determine that the expected project completion time for
the construction of a pleasure yacht is 21 months, and the project variance is 4.
The probability increases with increasing time. Hence delay is possible in the project.
Question 4
a) Average time in the line = Wq = A customer waits for 0.13 hours in the que
f. b) Lq = QTPMMS_Lq(10,15,2) = 0.083
f. c) Ws = 4.5
f. d) QTPMMS_L(10,15,2) = 0.75
Question 5
c) It’s almost the same, 33/10 = 3.3, adding up each individual seconds and then averaging
them gives the same result.