The document discusses decision making under uncertainty and risk using decision trees. It provides examples of decision trees involving:
1) A glass manufacturer considering sub-contracting, overtime, or a new facility based on future demand probabilities.
2) An engineer deciding whether to build a new processing facility or pilot plant based on success probabilities and costs.
3) A problem involving producing wooden and steel chairs to meet different quantity requirements for four locations, with the objective of maximizing total value.
Download as DOCX, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
144 views
Decision Tree Problems
The document discusses decision making under uncertainty and risk using decision trees. It provides examples of decision trees involving:
1) A glass manufacturer considering sub-contracting, overtime, or a new facility based on future demand probabilities.
2) An engineer deciding whether to build a new processing facility or pilot plant based on success probabilities and costs.
3) A problem involving producing wooden and steel chairs to meet different quantity requirements for four locations, with the objective of maximizing total value.
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 9
Decision Tree Problems
Decision Making Under Uncertainty
Decision under Uncertainty is made on the basis of Maximax, Maximin and Equally likely.
Decision Making Under Risk
Decision under Risk is made w.r.t the probabilities: Expected Value of Perfect Information (EVPI) b). Maximax Decision: Very Large Station c). Maximin Decision: Small Station d). Equally Likely: Very Large Station e). Decision Tree with each outcome equally likely. 1. A glass specializes in crystal is developing a substantial backlog and for this the firm’s management is considering the three courses of action. The correct choice depends largely upon the future demand – which may be low medium or high. Show this decision situation in the form of a decision tree and indicate the most preferred decision and its corresponding expected value. Deman Probabilit Course of Action d y S1 S2 S3 Low 0.1 10 -20 -150 Mediu m 0.5 50 60 20 High 0.4 50 100 200 S1: Sub-Contracting , S2: Being Overtime , S3: Construct New Facility
1. Ram, chief engineer at Southern Electronics, has to decide
whether to build a new state-of-the-art processing facility. If the new facility works, the company could realise a profit Rs.200000. If it fails, Southern Electronics could lose Rs.180000. At this time, Ram estimates a 60% chance that the new process will fail. The other option is to build a pilot plant and then decide whether to build a complete facility. The pilot plant would cost ₹10000 to build. Ram estimates a 50-50 chance that the pilot plant will work. If the pilot plant works, there is a 90% probability that the complete plant, if it is built, will also work. If the pilot plant does not work, there is only a 20% chance that the complete project (if it is constructed) will work. Ram faces a dilemma. Should he build the plant? Should he build the pilot project and then make a decision? Help Ram by analysing this problem using decision tree. Let X1 = Wooden Chair X2 = Steel Chair
Then Objective Function , Z = 5X1 + 3X2
Subject to X1 ≥ 150 Wooden chairs for Bhagirath Bhavan X2 ≥ 225 Steel chairs for Shankar Bhavan X1 + X2 ≥ 150 Mix Chairs for Krishna Bhavan X 1 - X2 ≥ 0 As many Steel Chairs as Wooden for Gandhi Bhavan