Unit 3 Estimation: Different Types of Estimates
Unit 3 Estimation: Different Types of Estimates
ESTIMATION
DEFINITION
➢ An estimate for any construction work may be defined as the process of calculating the
quantities and costs of the various items required in connection with the work.
➢ It is prepared by calculating the quantities from the dimensions of the drawings, the
various items required to complete the project and multiplied with the unit cost of item
concerned.
2. DETAILED ESTIMATE:
This includes the detailed particulars for the quantities, rates, and costs of all the items
involved for satisfactory completion of a project.
Quantities of all items of work are calculated from their respective dimensions on the
drawings on a measurement sheet.
Multiplying these quantities by their respective rates in a separate sheet, the cost of all
items of work are worked out individually and then summarized, i.e. abstracted (which
is the detailed actual estimated cost of work).
All other expenses required for satisfactory completion of the project are added to the
above cost to frame the total of a detailed estimate.
This is a complete estimate or list of quantities for all items of work required to
complete the concerned project.
The quantity of each individual item of work is worked out from respective dimensions
on the drawing of the structure.
To find the cost of an item its quantity is multiplied by the rate per unit for that item.
The purpose of the bill of quantities is to provide a complete list of quantities necessary
for the completion of any engineering project and when priced gives the estimated cost
of the project.
4. REVISED ESTIMATE
Revised Estimate is a detailed estimate for the revised quantities and rates for items of
works originally provided in the estimate without material deviations of a structural
nature from the design originally approved for a project.
Revised estimate is prepared when original sanctioned estimate is likely to exceed more
than 5%.
When expenditure on work is likely to exceed amount of administrative sanction by
more than 10%
When there are material deviation from original proposal even though cost may be met
from sanctioned cost.
It is accompanied by comparative statement showing variations in each item of works
and reason for the same.
5. SUPPLEMENTARY ESTIMATE
While a work is in progress, some changes or additional works due
to material deviation of a structural nature from the design originally approved may
be thought necessary for development of a project, an estimate is then prepared to
include all such works.
It is the fresh detailed estimate of the additional works in addition to the original
estimate.
It is required when further development is required during the progress of work.
Abstract should show the amount of original estimate and total amount including
supplementary amount.
PURPOSE OF ESTIMATING:
➢ Bill of quantities (BOQ) is the term which brings attention of every construction
professionals and stakeholders.
➢ It is one of the communication tool which connects the parties (client, consultant &
contractor) of construction project.
➢ BOQ is a schedule which categories, details and quantifies the materials and other cost
items to be used in construction project.
➢ It is important to know that, direct costs & indirect costs are to be considered for
complete cost of the project which are covered in different parts of the BOQ.
➢ Generally, BOQ is in tabular form which contents description, unit, quantity, rate &
amount in different columns.
OBJECTIVES OF BILLS OF QUANTITIES
The objects of bills of quantities are:
➢ To assist in the accurate preparation of tenders, by providing for measurement of
quantities on a uniform basis
➢ To provide a basis for the financial control of a project, in accordance with the
conditions of contract.
➢ Bills of quantities shall describe and represent the works to be carried out; work which
cannot be measured accurately shall be described as approximate or given in bills of
approximate quantities.
➢ Conditions of contract, drawings and specifications shall be provided with the bills of
quantities.
➢ The section headings and classifications do not impose restrictions upon the format and
presentation of bills of quantities.
FACTORS TO BE CONSIDERED
The Bills of Quantities which we provide to clients with can include the following main
sections:
➢ Form of Tender (including certificate of bona fide tender)
➢ Summary (or Main Summary)
➢ Preliminaries, comprising two main section as follows:
Information and requirements and Pricing schedule
➢ Measured works (incorporating the contractor designed works eg. pre-cast concrete
floors/stairs, windows etc.)
➢ Risks;
➢ Provisional sums;
➢ Credits (for materials arising from the works);
➢ Day works (Provisional); and
➢ Annexes
PRINCIPLES OF MEASUREMENT
➢ The Principles of Measurement provide a uniform basis for measuring bills of quantities
for works of construction.
➢ More detailed information that is required by this document may be given to define the
precise nature of work or the circumstances under which it is to be carried out.
➢ These principles of measurement may be applied equally to the measurement of proposed
works and of completed works.
GENERAL ESTIMATING PRINCIPLES
1. Reality 4. Documentation
2. Level of Detail 5. Direct and Indirect Costs
3. Completeness 6. Variable and Fixed Costs
1. REALITY
➢ Anyone can come up with a set of numbers. A challenge to the estimator is to produce
an estimate that is an accurate reflection of reality.
➢ This is first a question of professional experience and judgment, and second a matter of
relevant historical data.
➢ To estimate at a detailed level one must mentally construct a project, selecting materials,
methods, equipment, and crews to fit the design.
➢ The estimator then uses the best information available to estimate the costs of
performing the required work using the selected resources.
➢ This information may be cost or crew time data from past work.
2. COMPLETENESS
➢ Another challenge is to include all items that will be in the facility yet to add nothing
extra.
➢ The estimator must have the vision to see beyond the obvious components and their
primary costs of construction, primarily in preparing cost estimates prior to completion
of design.
➢ In estimating industrial work, the major items of process equipment are obvious early
in the design period.
➢ Estimates must include not only costs of procuring equipment but also the cost of its
installation and the cost of piping, wiring, controls, and structure to support it.
3. DOCUMENTATION
➢ An estimate is a permanent document that serves as a basis for business decisions.
➢ It must be in a form that can be understood, checked, verified, and corrected.
➢ This requires that the source of each number be readily apparent not only to the person
who prepares the estimate but also to others who follow.
➢ Conditions that were assumed must be identified. Methods of construction equipment
spreads, and crews that were selected in the estimating process must be stated, if they
are not obvious.
➢ The estimate should be organized to be followed easily.
4. DIRECT AND INDIRECT COSTS
➢ A direct cost of an activity is physically traceable to the activity in an economic manner.
➢ A direct cost is one not counted if the activity is not performed. Indirect costs are
business costs other than direct costs of construction activities; they are not physically
traceable and are counted even if the activity is not performed.
➢ Indirect costs are also known as overhead
➢ Construction costs are classified as materials, labor, and equipment.
➢ Direct materials for concrete walls include ready-mix concrete delivered to the site and
placed in the forms, reinforcing steel fabricated off site and tied and placed in the forms,
and plywood and form ties from which the forms are constructed
CONTINGENCIES
➢ An estimate is a prediction—an approximation—that provides information for
decisions and is a surrogate or substitute for actual measurement that is not economical
or possible.
➢ It is considered accurate if it is sufficiently close to actual performance that decisions
based on the estimate are the same as decisions based on actual performance, were
actual performance available.
MEASUREMENT OF MASONRY WORKS:
➢ Masonry works are such as brick masonry, concrete block, stone or rubble masonry are
generally measured in volume, but are also measured in terms of area where the
thickness of masonry is limited to single brick or single block. Tiling is measured in
area.
➢ While measuring the quantities of masonry work, the wastage of materials such as
bricks, cement or sand is not taken into account.
➢ Also, the types and classes of bricks, blocks or tiles are not considering while
measuring the quantity of work. This is taken care in pricing of the different masonry
works.
➢ Each type of masonry works is measured separately into categories to calculate exact
cost of construction based on its price.
➢ Masonry work which requires cleaning of surface are measured in area such as square
meter or square feet.
➢ Any special treatment to masonry surfaces are measured in area such as square feet
or square meter, with the count of number of coats applied.
➢ Any joints in masonry structure such as expansion joints or control joints are
measured in length such as meter or feet with description of type of joint. Also the
type of joint filler material for the joint used is indicated in description.
➢ For different types of mortar, or mortar with different types of admixtures are
measured separately. These are measured in volume such as cubic meter or cubic feet.
➢ If any reinforcement is used in masonry, then it is measured separately.
➢ Extra items in masonry construction such as anchor bolts, sleeves, brackets, and
similar items that are built into masonry are described in the measurement and
measured separately.
➢ Enumerate weep holes where they are required to be formed using plastic inserts and
such like.
➢ Measure rigid insulation to masonry work in square feet or square meters, describing
the type and thickness of material.
1. Brick masonry is measured in volume for thickness more than single bricks. For
masonry with single bricks, it is measured in square meters.
2. Facing bricks are measured separately.
3. Different types or class of brick masonry are measured separately.
1. Different types of concrete block masonry such as type and size of concrete blocks are
measured separately.
2. Special units required at corners, jambs, heads, sills, and other similar locations are
measured separately.
3. Measure concrete to core fills and bond beams in cubic feet or cubic meters, stating the
strength and type of concrete to be used. These are measured separately for different
types of concrete block based on strength.
4. Measure in linear feet or meters reinforcing steel to core fills and bond beams, stating
the size and type of rebar to be used.
➢ Reinforced concrete and reinforced brickwork may be in roof or floor slab, in beam
lintel, column, foundation etc and the quantities are calculated in cubic meter.
➢ Length, breadth and thickness are taken correctly from the plan, elevation and
section or from other detailed drawings.
➢ The quantities are calculated in cubic meter exclusive of steel reinforcement and its
bending but inclusive of centering and shuttering and fixing and binding
reinforcement in position.
➢ The reinforcement including its bending is taken up separately under steel work in
as per weight.
➢ For this purpose, 0.6% to 1% (usually 1%) of R.C.C. or reinforced brickwork by
volume may be taken for steel if other details are not available.
➢ The volume of steel is not required to deducted from R.C.C. or reinforced brick
work.
➢ Reinforced concrete and reinforced brickwork may also be estimated inclusive of
steel and centering and shuttering for the complete work, if specified.
➢ Centering and shuttering are usually included in the R.C.C or R.B. work but may
also be taken separately as per square meter of surface in contact with concrete.
The length and breadth are measured as inside dimensions from wall to wall of
superstructure. both the work of base concrete and floor finishing are paid under one
item.
Measurement of Plastering:
Plastering usually 12mm thick is calculated in square meter. for wall the measurement
is taken for whole face of the wall for both side as solid, and deducting for opening are
made in following manner.
(1) No deduction is made for the end of beams, posts, rafters etc.
(2) For small opening up to 0.5 square meter no deduction is made, and at the time no
additions are made for jambs, soffits and sills of these opening.
(3) For opening exceeding 0.5 square meter but not exceeding 3 square meter deduction
is made for one side and other face is allowed for jambs soffits and sills which are not
taken into account separately
(4) For opening above 3 square meter deduction is made for both faces of the opening
and the jambs, soffits and sills are into account and added.
Wooden beams, posts, wooden roof trusses, doorpost etc. come under this items and the
quantities are computed in cubic meter. The dimension of finished work shall be taken.
This computed weight in kg or quintal and the quantities are calculated correctly by
multiplying the weights per running meters by length. the weight per running meter can
be obtained from the steel section book. For steel joint the length is equal to the clear
span plus two bearing the bearing may take third forth thickness of wall or 20 to30 cm.
The quantities are computed in square meter and are usually same as for plastering. The
inside is usually white washed or distempered and this item will be same as for outside
plaster. These items need not be calculated separately but simply written as same as for
outside plaster and inside plaster.
The preparations of detailed estimate consist of working out quantities of various items
of work and then determine the cost of each item. This is prepared in two stages.
ii) Location of site: The site of work is selected, such that it should reduce damage or in
transit during loading, unloading, stocking of materials.
iii) Local labour charges: The skill, suitability and wages of local laboures are
considered while preparing the detailed estimate.
ii) Cost of labour: The exact number of labourers required for unit of work and the
multiplied by the wages/ day to get of labour for unit item work.
iii) Cost of equipment (T&P): Some works need special type of equipment, tools and
plant. In such case, an amount of 1 to 2% of estimated cost is provided.