Prefabricated Structure
Prefabricated Structure
PREFABRICATED STRUCTURES
UNIT I INTRODUCTION 9
Need for prefabrication – Principles – Materials – Modular coordination – Standarization –
Systems – Production – Transportation – Erection.
TOTAL: 45 PERIODS
TEXT BOOKS
REFERENCES
1. Koncz T., Manual of precast concrete construction, Vols. I, II and III, Bauverlag,
GMBH, 1971.
2. Structural design manual, Precast concrete connection details, Society for the studies in
the use of precast concrete, Netherland Betor Verlag, 1978.
Sl.No: Contents Page
No.
Unit 1-INTRODUTION
1.1 Introduction 1
1.2 2
Principles:
1.3 Prefabricated Materials 4
1.4 ModularCoordination 7
UNIT-1
Conventional method of building a house is to transport bricks timber, cement, sand, Steel
and construction aggregate etc., to the site, and to construct the house on site from these
materials.
sections of (walls, floors, roof are Prefabricated with window & door frames included).-
transported to the site lifted into place by a crane and bolted together.
Uses of Prefabrication :
1. The most widely used from of prefabrication in building and civil engineering is the use
of Prefabricated Concrete & prefabricated steel sections in structures where a particulars
part on form is repeated many line.
2. Pouring Concrete section in a factory brings the advantages of being able to re-use
moulds and the concrete cab be mixed on the spot without having to be transported
to and pumped wet on a congested construction site.
3. Prefabricating Steel sections reduces on site cutting and welding costs as well as the
associated hazard’s.
4. Prefabrication techniques are wood in the construction of apartment slacks and
housing developments with repeated housing units.
5. The technique is also used in office blocks, warehouses and factory buildings.
6. Prefabricated Steel and glass sections are widely used for the exterior of large
buildings.
7. Prefabricated bridge elements and systems offer bridge designers & Contractors
significant advantages in terms of construction time, safety environmental impact
construct liability and cost.
8. Prefabrication can also help minimize the impact from bridge building.
9. Radio bowers for mobile phone and other service often consist of multiple
prefabricated sections.
10. Prefabricated has become widely used in the assembly of aircraft and space craft
with component such as wings and fuselage sections after being manufactured in
different countries or states from the final assembly site
Advantages of Prefabrication :
1.2 Principles:
The Main reasons to choose Precast Construction method over conventional in method.
1. Economy in large scale project with high degree of repetition in work construction.
2. Special requirement in finishing.
3. Consistency in structural quality control.
4. Fast speed of construction.
5. Constraints in availability of site resources(e.g. materials & Laborites )
6. Other space & environmental constraints.
7. Overall assessment of some or all of the above factors which points to the
superiority of adopting precast construction over convention method.
The following details gives. The cost implications of precast construction &
conventional in situ method.
8. Large groups of buildings from the same type of prefabricated elements tend to
look drab and monotonous.
1. Local Jobs are last.
The main reasons to choose. Precast Construction method over conventional in situ
method.
1. Economy in large scale project with high degree of repetition in work execution.
2. Special architectural requirement in finishing.
3. Colysistonay in structural quality control.
4. Fast speed of construction.
5. Constraints in availability of site resources ce.g.materials & labour etc..
6. Other space & environmental constraints.
7. Overall assessment of some or all of the above factors which points to the superiority of
adopting precast construction over conventional method
The following details gives the cost implications of precast construction &
conventional in situ method.
Prefabrication Elements :
1. Flooring / Roofing system.
2. Priciest Beams
3. Precast Columns
4. Precast walk panels.
5. recast Stabs.
Classification :
1. Small prefabrication
2. Medium Prefabrication
3. Large Prefabrication
4. Cast in Site Prefabrication
5. Off-Site (or) factory Prefabrication
6. Open system of prefabrication
7. Closed system of prefabrication
8. Partial prefabrication
9. Total prefabrication
Small Prefabrication :
The first 3 types are mainly classified according to their degree of precast
Elements using in that construction for eg.:brick is a small unit precast and used in
building.
This is called as small prefabrication. That the degree of precast element is very low.
Medium Prefabrication :
Suppose the roofing systems and horizontal members are provided with
pretested elements those construction are known as medium prefabricated
construction here th degree of precast elements are moderate.
Large Prefabrication :
In large prefabrication most of the members like wall panels, roofing /
flooring Systems, beams and columns are prefabricated. Here degree of precast
elements are high.
Cast – in – site prefabrication : OFF – site (factory) prefabrication :
One of the main factor which affect the factory prefabrication is transport.
The width of mad walls, mode of transport, vehicles are the factors which
prefabrication is to be done on site on factory.
Suppose the factory situated at a long distance from the construction site and
the vehicle have to cross a congested traffic with heavy weighed elements the cost
in side prefabrication is preferred even though the same condition are the cast in site
prefabrication is preferred only when number of houses and more for small elements
the conveyance is easier with normal type of lorry and trailers. Therefore we can
adopt factory (or) OFF site prefabrication for this type of construction.
Open system of prefabrication :
In the total prefabrication systems, the space framers are casted as a single
unit and erected at the site. The wall fitting and other fixing are done on site. This
type of construction is known as open system of prefabrication.
Closed system of prefabrication :
In this system the whole things are casted with fixings and erected on their
position.
Partial prefabrication :
In this method of construction the building element (mostly horizontal)
required are precast and then erected. Since the costing of horizontal elements (roof
/ floor) often take there time due to erection of from work the completion of the
building is delayed and hence this method is restored. In most of the building sites
this method is popular more. Son in industrial buildings where the elements have
longer spans. Use of double tees, channel units, cored stabs, slabs, hyperboloid shall
etc., are some of the horizontal elements.
This method is efficient when the elements are readily available when the
building reached the roof level. The delay caused due to erection of formwork, delay
due to removal eliminated completely in this method of construction Suitable for
any type of building provided lifting and erection equipments are available.
Total Prefabrication :
Very high speed can be achieved by using this method of construction. The
method can be employed for frame type of construction or for panel type of or the
total prefabrication can be on site or off-site. The choice of these two methods
depend on the situations when the factory produced elements are transported and
erected site we call if off-site prefabrication. If this method is to be adopted then we
have a very good transportation of the products to site. If the elements are cast near
the building site and erected, the transportation of elements can be eliminated, but
we have consider the space availability for establish such facilities though it is
temporary. The choice of the method of construction also depends on the following;
1. Type of equipment available for erection and transport.
2. Type of structural scheme ( linear elements or panel)
3. Type of connections between elements.
4. Special equipment devised for special method construction.
1.3 Prefabricated Materials :
Prefabricated building materials are used for buildings that are
manufactured off-site and shipped later to assemble at the final location same of the
commonly used prefabricated building materials are aluminum steel, wood, fiberglass
and concrete.
(Synthetic materials are used for the walls & roofs. To provide enhanced
security a combination of both metal and cloth materials are used. Plastic flooring
materials can be quickly assembled and are very durable)
Prefabricated, building materials used for small prefabricated buildings are
steel, wood, fiberglass. Plastic or aluminum materials. These materials are cheaper
than regular brick and concrete buildings. Materials like steel, fiberglass, wood and
aluminum are used as prefabricated building materials for sports buildings. These
materials provide flexibility and are preferred rfor making structures and accessories
like stands and seats for stadium and gyms.
For making low cost housed, prefabricated materials like straw bale, Ferro
cement calcium silicate. Products, campsites and other cheap wood based materials
are currently being used calcium silicate bricks are strong and durable. Ferro cement
consists of a cement matrix reinforced with a mesh of closely-spaced iron rods or
wires. In this type of construction, the techniques used are simple & quick.
Using Prefabricated materials one can make durable water and fire resistant
and cheap prefabricated buildings. Most of the prefabricated building materials are
eco-friendly & affordable.
Precast structure Installation (Erection)
The following steps to be followed to erect the precast structure :
5. Planning for precast installation
6. Installation process.
7. Installation using Big canopy
8. Installation construction Management.
9. Mishandling of precast panels.
10. Common defects in precast panels.
11. Precast failures.
Hoisting installation
1.Put temporary props to support slab or beam.
2.Lift and rig the elements to designated location
3.Align and check the level before placement
4.The beams shall prop atleast two locations
5. check level of precast elements
d. Preferred increments foa the still heights,doors,windows and other fenestration shall
be1M.
e. In case of internal coluums the grid lines shall coincide with the centre lines of columns.In
case of external columns,the grid lines shall coincide with the centre lines of the columns in the
storey or a line in the column from the internal face of the column in the topmost storey.
A basic module can be represented as module andfor larger project modules are represented
aMp.
For eg: For a project module in horizontal coordination,the component can be of 30cm and for
vertical component size be of 10cm.
The storey height is fixed between finished floor levels as 2.8m and if the thickness of slab
is<15cm storey height is fixed as 2.7m. The centre distance between the load bearing walls can
be chose from a set of modules. The use of other dimensions is not allowed.
In the design of a building,modular grid can be used consisting of parallel line spaced at a
value of module M or Mp and a grid line chosen as a base for setting out a part of a building
becomes a modular axis. In the fig (a),, a typical grid is chosen for load bearing walls without
duct. The interior walls are placed so that their centerlines coincide with the modular axis. In the
fig (b), a grid is shown for load bearing walls with hollw ducts in between. The centre line of the
grid is found by deducting the size of duct.
Advantage:
Disuniting at joints gives linear member. This means that a great advantage and facilitates
from the view point manufacture and assembly.
Disadvantage:
1. Joints are at corners i.e. at points of maximum moment values, so forming the joint is
difficult.
2. Joints must be over dimensioned to cope with insitu concreting. And one alternate
solution to replace moment resistant joints by hinged connection.
The stress distribution of staright members during hoisting is in general statistically determinate.
Advantage:
Advantage:
Disadvantage:
Arched structures are normally two hinged and three hinged arches. Arched structures are
normally used for bridging span more than 20-25m. Their production and placing is more
difficult than straight members. Arch can be two hinged and three hinged but they can also be
fixed at footings nd can be constructed with or without tie.
These members are generally precast and assembled in statistically determinant three hinged
variance and middle hinge is only eliminated after placing is finished. The reinforcing bars
protruding both sides are welded together and the joint between the members is filled in with
insitu concrete.
Arch structure can be precast in either vertical or horizontal positions. In the first case,
shuttering made of timber or concrete is required having the same curvature s the arch itself.
The prefabrication of larger arches in theh horizontal position is found to be more economical
The construction of arch trusses can be properly carried out in the horizontal position only.
Truck cranes
Gantry cranes
Mast cranes
Derrick cranes
Truck cranes:
Truck cranes consists of chasis includinig mortar and pivoting upper part. These cranes are
mobile and an travel on their own needs. Different features are:
Disadvantage:
Gantry Cranes:
These cranes are used mainly to serve the operation of manufacturing and storing areas in
prefabrication plants.
Mast Cranes:
These are wide spread hoisting devices,simple and cheap. Operation requires great skill and
practice. Useful in hoisting prefabricates in vertical direction. Suspension load can be slightly
moved forward by slackening the rear staying cable. Hoisting load is done by a winch.
It is used for hoisting member to great height. It consists of two steel column assembled from
sections and connected at top by bridging structure.
The crane can be transferred but takes 1-2 days and is suitable fr high lifting but difficult to
operate.
These are now a days replaced by 30T mast cranes hinged in 2 directions.
Derrick cranes:
It is stable or movable
Capacity 20-40T
Prefabricated structurers are erected in coonvinient sections which when fixed correctly
should be sufficiently rigid in all directions. Normal sequence of erection is
If the external walls are hand laid from small blocks or bricks, all necessary materials should
be hoisted by crane and stacked near the ultimate position. The mansonry work is begun after
the floor immediately above is laid.
The tolerances are comparatively strict and are normally coompliedwith the use of a skilled
rection gang. The distance between the wals are measured with the steel tape and the
thickness of joint with rule having mm scale.The accuracy is verified by means of surveying
instruments after all joints are connected or erected.
The hoisting machine for small column is less than five tones. First of all pick up gear must
be assembled on to the column and the column is then under pinned.
Thereafter the column is lowered temporarily on to a sheep shoe assembled at the foot and
the roller track is pushed under the shoe. When column is hoisted the pick up points moves
vertically and bottom resting on the roller tracks shifts towards the footing. When the column
is lifted to the required height, the retaining cable is used to decrease and finally stop the
swinging motion of the column.
Suspension:
For lifting up of trusse and large beams of length 25-30m. care is taken to lift the rocker in
uniform rate with two hoisting machines otherwise the beams would be subjected to
distortion during the lifting leading to cracks.
5. Methods of prefabrication:
Site prefabrication:
1. The RC members are produced t the site in the open air chiefly in the open air or in
the temporary sheds
2. The difficulties in construction in general are felt in this mechanization can case.
3. Mechanization can not be of such high degree as site PF is done for smaller duration
of time.
4. When the pre fabricates are of large size it is difficult to transport the pre fabricates to
the site.
5. In comparison with plant prefabrication transportation of the members are not needed.
As large members are not transported the design and weight of the prefabricates are
not limited.
CE2045 PREFABRICATEDSTRUCTURES
Plant prefabrication
1. The members produced are to be transported t the place of costruction this accounts
for about 10-15% of the cost of production and assembling.
2. Certain restriction is made in the dimension of prefabrication leading to restrainst in
the design and development of prefabrication.
3. Prefabrication is appropriate for mass production for manufacture of standaridized
members.
4. Needs costy materials for batching and production.
5. This method is most suited in the case of small prefabricates which are to be
prefabricated in very large number.
Plantt prefabrication is done under permanent plant or factories. It is done under the
covered roof so the effect of weather does not affect the work. So the quality and strength
of the members can be improved considerably. Plant prefabrication reduces the cost of
prefabrication if the number of prefabricate needed is more.
Dimensions of prefabricate:
1. The design of the errectio dimension governing the dimensional coordination of the
prefabricates.
2. Theoretical dimension
3. The actual dimension of the element when delivered the design dimension should be a
multiple of abasic module size m or of a module lmp.
Production of prefabricates:
1. Stand method
2. Conveyor method or line method
3. Aggregate method
Stand Method:
In this method, the prefabrication mature where they are moulded while the production
teams moves to successive stands. The bed on whih prefabricates are cast may be fixed or
movable. Tilting forms are often uused and in tthis method steam curing is generally done.
The whole production is split up in to series operations carried out at separate successive
and permanent points served by specialized teams. The movement of the mould or
prefabricate one point to other vary by means of conveyor belt trolleys.
CE2045 PREFABRICATEDSTRUCTURES
The rigid steel forms are assembled at station 1 where they are mould oil to reduce the
adhesion of concrete.The conveyor moves fron 1 to 2 where prestressing wires are fixed &
in the next station anchoring of the wires is carried out. The prepared mould is then
carried to the station 1ie casting station.After casting ,it is shifted to the vibrating
table & finally stacked @ station 5 for setting.
After that,it is passed through tunnel autoclave for curing.After steam curing move too
station 7 for demoulding & is finally stacked @ 8.
Aggregate method:
Aggregate method is used in the production of multi duct hollow floor pannel in
Poland.At production point the reinforcement is fixed in the form & remote controlled
aggregate(machine)inserts the duct formers,cast& vibrates the concrete,floats @ the top
of the floor.The prepared prefabricate then move to the autoclave chamber in which
hardening of concreteis accelerate.In many factories combined technology are employed
when complex prefabricate are required.
Advantages:
1.The stand technique is the most flexible one.It is used in varying degrees of
mechanization,in all kinds of prefabricate factories.
2.It is simple & less capital is required.It can be used for field prefabricate also.
3.Aggregate method is used for large scale productionin which case number of
machineries is required.
One of the most intricate and most difficult problems to be solved in both design &
construction of structures assembled of prefab members as the joining.
It is highly important that the construction of the joints should be easy that unavoidable
smaller in accuracies and deviations within dimensional tolerances should neither influence
the designed stresses in a detrimental manner nor cause in admissible changes in the stress
distribution of the structures.
The forming and construction of joints requires owing to their intricacy, greatly
increased consist joints which cannot be inspected should be omitted.
When solving the problem of joints the properties of reinforced concrete must be taken
into considerations. This means in other words, that the design & the construction of the joint
should harmonize with the materials to be used. The properties of steel of timber are quite
different from those of concrete and reinforced concrete. Therefore joints similar to those used
in timber and steel construction are generally not appropriate for the purpose.
Joints of reinforced concrete structures which should be omitted are shown.
The joint to be seen in fig. This is s solution resembling a butt jointed with splayed
table as used in timber construction. This does n’t comply with the nature of the material & So
is not good for this purpose. The limtating a joint used in steel construction, is not appropriate
either. The steel structure -like joint as seen in which the component structural parts are
coelded to the reinforcement is also not sufficiently adequate. The two halves of the steel
structure forming the main constituents of the joints have to be concrete is to
the placing of the pins.
The joints can be rigid hinge like or shed.
Rigid joints are adequate in addition to the bearing the tensile, compressive & shear
forces for resistances.
Design of c/s based an efficiency of the material used:-
The plastic concrete can be used for the subsequent concrete of joints & the fluid
cement mortar last or pressed into the gaps lase part of their water during the settling time &
shrisk, after setting the shrinkage of the insite concrete & mortar continue.
with respect to two phase of shrinkage same codes on reinforced concrete construction
permit only reduced stresses for a subsequent insite concrete of a mortar casting. These are
generally determined as a function of width of the joint on the gap to be concrete as cost.
Joints must be designed & executed so that compensation for the allowed dimensional
tolerances is ensured or relative displacement of the jointed members should be impossible
even as a result of a blow or of any other infavourable force effect. The length of the section
determined for the transmission of forces should be as short as possible, but should excluded
any excess of the permissible stress.
The joints can be regid hige like or shed. Regid joints are adequate in addition to the
bearing of tensile, compressive & shear forces recover displacement and
like joints can transmit forces passing through the hinge itself and also
allow a certain motion and rotation.
Rigid joints are generally used for the junction of column to footings, but they can also
be applied for joining of individual groups with one another. The joints generally used in the
construction with precast members are usually hinge like their execution is simpler and
requires less working -lime than rigid joints “shodjoints” are only exceptionally used in
industrial construction & are justified for a long span only. These joints are justified for chiefly
used in bridge construction for a long span bridges depending on the necessity of insite
concreting, two kinds of joinjts can be distinguished.
a. Dry joints - joint accomplished by simple placing of two members on each other &
fasting.
b. Wet joints - joints require not only casting with cement mortar but also subsequent
concreting.
2.4 Joints of different structural connections:-
a. jointing of column to footing
b. jointing of column to beams on top of column.
c. jointing of column to beam at an
intermediate. d.
e. jointing of beams
f. Forming of joints of arched structures
g. joining of joints of post tensioned structures.
h. joining of precast to monolithic reinforced concrete structures.
a. Joining column to footing:-
This joint is usually rigid but also can be hinge. A rigid joint can be made by placing
the column into a calyx of the footing or by using a welded joint the figure shows the three
variations of the this method.
a) Can be used for smaller b) for average and for large footings
The opening of the calyx is 6-10 cm greater in all directions than the c/s of the column. This is
enable the vibrator to be operated while concreting at the bottom of the calyx & checked by
leveling before concreting. A similar steel plate is also put on the lower end of the column
when positioning the column. These two steel plates must be on each other. The dimensions of
these steel plates are from 100 x 100 x 10 to 150 x 150 x 10mm an chored in to the concrete
after the column is put in placed properly plumbed tow advantages of the calyx joint should be
mentioned
1 The placing plumbing and fixing of the column as well as the subsequent filling of the
calyx with concrete is far simpler and requires less time then in the case of a welded
joint.
2 The method is least sensitive to inaccuracies occurring during the construction.
The disadvantages of the calyx Joint is more suitable for small columns. In the case of
large columns requiring a calyx depth of which is greater than 1.0m.
One members of joining a merge like joint consists either of placing to beams on to as
small cantilever protracting trans the column or of putting it on the bottom of an
adequately shaped opening deft out of the column shaft. The beam rests temporarily on a
tongue like extensist on a steel plate placed in this opening on the supporting surface the
tongue is also furnished with a steel plate anchored in to the concrete. The other parts of
the tongue are supported after the placing has been finished with concrete cast through an
opening left for this purpose.
d. Lengthing of columns:-
Columns are usually lengthened at floor levels. An intermediate lengthening should be
avoided it possible.
The lengthening of columns can be executed similarly to the joining with fooling,
accordingly reinforcement are joined by overlapping looped steel bars a welding. Thereafter
the stirrups have to be placed & finally the joint must be concreted.
e) Joining of Beams:-
The functions of beams can be affected either by overlapping the protracting steel bars
or by welding them together.
Figure shows the tinge like joint of purlins. In this method the whole shear must be borm by
both cantilever (i.e) by two separate structures therefore it is expedient to form this joint atleast
for large girders.
The method illustrated in the fig presents a dry joint of beams which is called a bolted
form. The advantages of this joint is immediate bearing capacity.
f) Forming of functions of arched structures:-
Precast arches are usually produced and assembled in the form of three hinged
structures. When the constant load has already been applied the centre joint is frequently
eliminated. The omission of the centre joint increases the rigidity of the structure. Naturally
arched structures can also be precast in a piece i.e in the form of two hinged ones.
Hinges of arched structures can be made by using either steel shors are more
expensive, but the centre transmission of forces is enhanced by their use.
Figure shows the centre hinge of a three hinged arch with a span of 12.5 m for this kind
of each the joint can also be formed from the concrete itself. The latter method require exactly
executed and adequately reinforced concave & convex surfaces with hear against one another.
The joining of a smaller hinged structure is show in below mentioned.
The arrangements the centre junction of the end hige of an arched structure. This
method was used in the construction of the ball for the middle rolling train in D.O.Sayar. The
structure was precast & assembled in the form of a three-hinged arched transformed later in to
a two -hinged one.
g. Design of joints for post tensioned structures:-
Post tensioned structures can generally be joined for more simply then the usual
reinforced concrete structures, By using post tensioning it can be ensured that in the entire
structure. The joints included only compressive can develop consequently the problem of
joining can be solved in a very easy manner namely by placing plane surfaces side by side and
then filling the gaps with cement mortar.
precast member. Thus in post tensioned structures the forming of joints does not
cause difficults.
Sketches solutions of principles relating to the joining of post tensioned structure are
to be illustrated in the fig. All these joints are of course rigid and moment bearing. It is not
permissible for the mortar which is to be poured into the gaps to follow in to the ducts of the
stressing lables to arid this cable ducts are jointed by placing a shore piece of tube or rubber
ring into the duct itself.
A regid point of their kind established between a columned two girders supported by
the former after the casting of the gaps & hardening of the mortar, the short inserted cables are
stressed and so rigid joint is established.
h) Joining of precast to monolithic reinforced concrete structures:-
If frequently occurs that a monolithic beam has to be joined to a precast column in this
by placing the protruding from the column or into an opening formed in the column’s shaft.
When making the joint, first of all a 2.5 cm deep cavity is chielled out of the side of the
precast column. The bottom of this cavity should be roughened so as to attain a better bank
between the concrete of the monolithic beam and the precast column.
1. Explain about Roofing members in
as,
i. Reinforced planks.
members. iv.purlins
Reinforced planks made of hollow tiles.The reinforced planks with longitudinal circular
holes.Thickness of these tiles is 60mm,80mm & 100mm & the width is 200mm & length is vary
from 360mm to 400mm. On the upper side one longitudinal groove is provided.
Reinforcement is placed into these grooves which are subsequently filled with cement mortar.In
this way ,roofs of length 2 to 3m & thickness of 60 to 100mm & width 200mm can be constructed.
The end tiles resting on the support are provided with 3.11mm dia stirrups protruding from the
tile.There are kept together over mortar of 40mm thickness & in further concreting of joint.the joint
is completed.
Light weight concrete roofing members play a role in addition to space bordering &
load bearing in heat insulation.The thickness varies from 7.5 to 25cm for reinforcement of Light
weight concrete roofing members.weiding nets is used.steel reinforcement is given additional
coating to prevent any corrosion care is taken to give good bonding of reinforcement with concrete.
The unit weight of these members is 750kg/m3 & width of 50cm.Its varies from 1.75mm to
6m.precast members can be made either in usual way using light weight materials.sand as
aggregate
& combination of high strength concrete.The top & bottom layer of about 2 to 3cm thickness iss
provided with high strength concrete.Its consists of prestressed 2.5mm ddia embedded in
these layers.The middle portion is made with light weight concrete.
Purlin
s:
Purlins are precast concrete beams supported by the main girders serving the purpose of
bearing for the roof covering.The cross section of purlins iss generally rectangular but it can also
have trapezoidal,T,L and I shape.
Precast purlins can be simply supported or cantilever beams & for the bearing of
loads beyond these weight simply supported purlins can be transformed into continuous beams.It is
very simple & easy to place.For cantilever purlins placing of hinges should be determined in a
manner to develop positive & negative moments equal to each other.This can be arrived by placing
the hinges @
0.1451 from the support where I is the spacing between
Large reinforced concrete rest on the main girders.These are generally used for large hall
structures & these are most advanced type of precast structures.Members are manufactured
corresponding to spacing of the frame length of about 6 to 10m & width of 1.3 to 1.8m. As they are
most supported on main girder purlins are not required.
3. Members with
cornice.
2. Coupled shear
wall.
3. Framed shear
type.
When walls are to carry only compressive force,they can be designed as plain concrete,when
walls are subjected to tensile forces(due to wind force)due to eccentric loading& earthquake load the
walls are RC walls,shear walls are previously provided to resist the wind forces only.Hence became
popylar & to prvide shear walls to resist EQ forces.
These are simple type & these shea walls under forces & horizontal shear along its length
are subjected to bending & shear.To resist the forces the uniform distribution of steel along its length
is used in simple shear walls.In case of bar bell type 2 boundary elememts are provided on either
side.Minimum steel is provided over the 0.7 to 0.8L & the remaining steel is placed steel is placed
@
0.12 to 0.15L.These walls are designed in such a way that they never fail in shear but only by
yielding of steel in bending.Shear failures are sudden & brittle.One disadvantage of this type of wall
is that during EQ the shear walls attract all the earthquake forces & dissipates the forces in to the
wall.The loss of energy by crackingof the wall iss difficult to repair .This can be eliminating by
providing coupled shear wall.
Coupled shear wall:
If two straight walls are joined together by relatively short span beams they are called as
Coupled shear wall.The stiffness of resultantwall increases in addition to the structure cqn dissipate
most of the energy by yielding the coupling beams with no damage to the main walls.It is easy
to repair the coupling beams than repairing the walls.
The action of the couping beams of the shear walls.The beams are displaced vertically they
tend to bend in a double curvature.The consistent shear can reduce the axial force in the upwind wall
by a large amount & reduce pressure can lower tne shear capacity of the wall.To take up for this
force diagonal lateral steel is more effective.
The design should be taken care of to see that the system develop plastic hinges only in
the coupling beams before shear failure & coupling beams should be designed to have good enrgy
dissipation capacity.
These are load bearing structures having curved surface.The advantage of shells is that it
provides large column free area for the monolithic construction.The cost of shuttering & scaffolding
is very high but if manufactured in a precast factory in large scale.The production cosh can be
considerably reduced.
The shell structure can have ribs in the centre & provided with curved membranelikee
roof.The shells built of precast members used in the construction of industrial buildings are
many.The thickness of shell varies from 2 to 10cm.Some precast shell,,s are produced with
dimensions which are very difficult to transport.To avoid such difficulty large size shells are precast
near to the restting or construction place.
The transportable or small size shell members can be precast in factories & these are
transported to the site.Examples:Barrel shells,Saddle or hyperboloid shells.cupola or paraboloid
shells.
Types:
a.Single barrel:
The structure above is a single barrel with edge beams.The shell has been
allowed to project beyond the edge of the stiffener in order to show the shape of the
shell.Stiffeners are required at columns.They do not necessarily have to be complete
diaphragms but may be arches with a horizontal tie.The thickness is based on design of a
slab element,the thickness of the barrel shell is usually based on the minimum thickness
required for covering the steel for fireproofing,plus the space required for three layers
of bars,plus some space for tolerance.If these bars are all half inch rounds,a practical
minimum would be 3 ¼ inches.Near the supports the thickness may be greater for
containing the larger longitudinal bars.
If more than one barrel is placed side by side,the structure is a multiple barrel structure
& if more than one span,it is called as multiple
The maximum spans for this type shell are again limited by the geometry off the cros
section .Assuming the maximum width of barrel to be 50 feet & maximum end slope to be 45,the
rise would be about 14 feet,the maximum span would be in the order of 150 feet.
North light shells:
This type of shell structure is used to provide large areas of north light windows for
factories requiring excellent natural lighting.The windows may be slanting or may be
vertical.The member at the bottom forms a drainage trough with the curved shell & materially assists
in stiffening the structure. The effective depth of the shell is not the vertical distance between the
two ends but is morely represented b the depth if the shellis laid flat with the ends of the circle on the
same horizontal line.The spans for the north light shell must be rather small in comparison to the
vertical depth of
CE2045 PREFABRICATEDSTRUCTURES
construction.The edges of adjacent shalls should be tied together by concrete struts serving
as mullions between the window glazing.
Long barrel shell obtained hen the semicircle or a segment of same is translated along
the longitudinal axis.
Generally used for shed for industrially purpose & buildings for large column
free areas.Generally the prefabricated barrels off sizes 3.5 to 5m & 10m long with edge beams
having thickness of 60mm.The thickness of the shell should not be more than 40mm.The dimension
of these members were finally limited by the load carrying capacity of the available hoisting
machines using the girder system built of precast prestressed trusses with parallel chords,areas
having a span of even more than 15m can be covere with barrel shell
Folded plate:
A folded plate structure with 3 segments for each barrel.The forces from the reactions of the
sloping plates on these rigid frames will be quire large and at an outside column they will not be
balanced by thrusts from the adjacent plates.The size of the frames may be reduce by using a steel tie
between the tops of the columns.The dimensions of the plate are dependent on both the with of the
barrel & on the span.The depth of the shell should be about 0.10 timess the span & the
maximum slope of a plate should not be greater than 40.For example,assume that the span is 60feet
& the baywidth is 24 feet.The depth of the shell should be about 6 feet & the horizontal width of
each plate with a 3 segment plate should be about 8 feet.The lope of the plate is 6/8,which is about
Domes are construced with many planes so they ressemble the facets of a diamond.The
structural problem in designing these shells is to provide enough angle between the planes so that an
actual rib is formed which will be stiff enough to support the plane surface.Usually it is best to start
with a spherical translation surface.
This makes use of tapered folded plate slanting to the centre in the form of a tent.It can be
built so that each of the triangular elements is self supporting during construction except for
possibly a single shore at the crown.To obtain natural light the top may be cut off & a ring inserted
with a sky light.The arch thrusts are taken through this ring & the difficult forming of the narrow
plate at the crown is avoided.If the structure is large there would be very high bending stresses due
to the curvature & the ring would be very large.
There may be discontinuous in the layout of intersections which make or destroy the
visual effect & make the structure more difficult to design.This dome can be of much greater span
than the previous example because the span of the individual slab element is less.A dome hexagonal
in plain can be made continuous with adjacent units if it is necessary to cover a large area.
A half sphere for a dome of revolution does not require a thrust ring at the base so it can
be placed on vertical walls & made continuous with a walls.This design is used for tanks because
the roof becomes a part of the tank.The vertical portion of the sphere is not difficult to construct if
pneumatically applied shotcrete or a similar process is used.The structure with arched openings an a
plastic dome on the crown has a rather oriental feeling.The most serious problems in the
architecture of dome is acoustics.In a domed ceiling the sound may reverberate as many as 20
times unless there is acoustical treatment.
Domes-Square in plan:
This structure is a spherical dome with portions sliced off to form a square or
rectangle.Most areas to be covered are rectangular so a circular dome is not always a good solution
to the planning requirements.This dome is supported by four rigid frame & would only be suitable
for small span because the frame would get quire in large.For long spans it is necessary to place a tie
between the knees of the frame.These ties can be made a part of the windows.Stresses in the shell are
direct compression stresses except across the corner where there are direct tensile due to the outward
spread of the forces.The arches or rigid frames pic up the shell forces by shear parallel to the arches
which are zero at the top & maximum at the bottom.There is no component of force in the shell
perpendicular to the arches.
Multiple Domes:
CE2045 PREFABRICATEDSTRUCTURES
The domes is rectangular & is continuous with the adjacent domes.The edges of dome
are supported by tied arches or brousing trusses.If windows are needed in these arches,the
mullions may be made to serve as vertical hangers for the bottom chords of the arch.In
constructing the shell,each one of the dome elements is an independent structural unit so the
forms may be moved without shoring all or part of the dome already cast.The shell thickness of
this type of dome does not need to be greater than a circular dome except at the triangular
corners.Membrane action ceases to exists & the corner should be designed as a slab.
Translation domes:
This structure looks very much like the square dome.A translation shell is generated by a
vertical curve sliding along another vertical curve.The curvs can be circles,ellipses or
parabolas.Therefore the vertical sections are all identical as opposed to a circular dome in which all
vertical sections vary in height.This is a big advantage in construction of the formwork.This method
can provide a rectangular dome with the same height of arch on all sides,thus making a rectangular
dome feasible.
Most of the load is carried by the side arches with some coming directly to the corners.A
tie at the springing of the arches but usually this will be covered by the walls.Such shells are
suitable for quite long spans with some interior lighting furnished by skylights in the shell.
Warped surfaces have a great advantage for shell structure because they may be
formed from straight form boards eventhough they are surfaces of double curvature.There are two
typeswhich are most useful:the conoid which as its name suggests is a portion of a cone&
the hyperbolic paraboloid,a name for a particular mathematical surface.This type of shell
structure can be built to what appears to be the ultimate in lightness of construction,minimum
reinforcing & ease of moving forms.
Stresses in the hyperbolic paraboloid shell are almost entirely membrane(direct tension&
compression)& all forces are delivered as shear parallel to the stiffening ribs.The shell thickness in
structures is on &one half inches except for slight extra thickness at the intersection of the
surface.This dimension is based on a cover of one centimeter on each side of two layers of bars &
not an any structural requirement for strength.
Generally classified based on the function as load bearing & non load bearing
walls.Eg.partition wall.They taansfer self weight only & they are provided to create barriers that
can be visual,thermal on acoustic.
Stiffening walls:
Provides 3 dimentional stiffness .The load bearing walls which are referred to as supported
walls do not posses foundation o f their own but are either carried by beams or slabs or directly
attached to load bearing walls. The supported walls can form on integral part of structure or remain
as non structural depending on stiffness.
Depending on the orientation of the main beams or load bearing walls relative to long axis
of the building. Prefabricated wall system are classified as,
The main beams are load bearing walls are placed parallel to the long axis of building. It is
applied to the building with large prefabricates and is similar to traditional brick work technique .
The longitudinal external walls which carry the floor loads must posses not only thermal
properties but also sufficient load carrying capacity .
The long wall system construction is typical with large blocked structure and special pier
blocks between the windows which carry loads from lintel and the walls above. The horizontal still
blocks are not loaded . In some designs space between the piers is filled by prefabricated unit
consisting of RC window frame complete with window.
The internal wall blocks are normally of full storey height subject to limitations imposed by
lifting equipments available. Both internal and external walls are made of some materiel.
Load bearing walls and beams are placed at right angles to the longitudinal axis of
the building . In this system the floor units are provided with two way structural units which
distributes the to the cross walls and this system is more prominent. The internal walls are made of
ordinary concrete for load bearing walls and the external walls and the external walls are made of
light weight concrete to reduce the weight of the structure.
Load bearing walls and beams are placed in both ways longitudinally and transversely. In
the building with the ring system of support floor are normally supported on all four edges and
span in two directions. In skeleton construction these floors are placed directly on columns.
In this system, the floor slabs are designed to span in both direction and are loaded on to the
supporting walls. For large load panels cross beams are hidden within the thickness of the panel.
Where,
Mi = limit moment
Maco= arithmetic mean of the ultimate moment
mi = Value of the ultimate moments belonging to the individual planks, where (i=1............N)
N= Number of loading tests.
C=
Flooring members:-
In industrial buildings the us of prefab members, for floor consist of precast joints and
flooring member.
The flooring member is designed for a span of 9m and for the bearing of a live load of
1000 kg/m2. After the members are placed in final positions a longitudinal load bearing
reinforcement and stirrups are placed in the trough formed between the longitudinal ribs of
the adjacent member. A continuous mgh reinforcement is placed on the top of these
members, there after a 5cm thick insist concrete layer is cast on the top of the members and
the troughs between the longitudinal ribs are also filled u[p with concrete. In this way the slab
is transformed in to a span of 6.0m & live load of 500kg/m 2 & a wt of 1450kg are widely
used.
Flooring members to be used for smaller loads similarly to roofing members can also
be made of lightweight concrete. These members are used chiefly in houses and public
buildings.
The flooring members rest in general joists i.e. their cantilever like part.
The weight of flooring members should not exceed 5 tons otherwise the storage and
transportation as well as the placing of these members using the presents available equipment
would be difficult.
Shear walls:
Shear walls are the walls transmit then through the column of the frame work to the
foundations their main load bearing direction is therefore horizontal as contrasted with
vertically load-bearing wall panels for their reason these infilling wall panels or slabs are
usually disposed horizontally (i.e) extending from column to column.
They arise from the basic conception that the overall stability of the supporting from
work of a building can be ensured without additional bracing by means of components that
are necessary any way thus the large roof panels serve as bracing for the roof, & the wall
panels similarly provide the rigidity of the external walls. Industrial buildings not exceeding
about 6m in height will not require such bracing at all since the horizontal force is in the
longitudinal direction the more so as these forces may be distributed over a member of
columns wall panels also as wind bracing is that it is necessary to provide flexurally rigid
connections between the columns and these panels and such connections are difficult to
establish without giring rise to cold bridges in the thermal insulation.
a. ribbed slabs
b. hollow slabs
c. solid light weight concrete slabs.
are designed according to the same principles as are applied to [Load bearing wall]
units of similarity type. Depending on the roof beam spacing the slabs may be up to 12m
in length and may be as much as 4m wide transported in the upright position, however as
a rule they seldom exceed 3m in width.
may be constructed by
a) Purlins with covering of roofing slabs or corrugated asbestos cement sheets
b) Large roofing units.
One of the most intricate and most difficult problems to be solved in both design &
construction of structures assembled of prefab members as the joining.
It is highly important that the construction of the joints should be easy that
unavoidable smaller in accuracies and deviations within dimensional tolerances should
neither influence the designed stresses in a detrimental manner nor cause in admissible
changes in the stress distribution of the structures.
The forming and construction of joints requires owing to their intricacy, greatly
increased consist joints which cannot be inspected should be omitted.
When solving the problem of joints the properties of reinforced concrete must be
taken into considerations. This means in other words, that the design & the construction of
the joint should harmonize with the materials to be used. The properties of steel of timber are
quite different from those of concrete and reinforced concrete. Therefore joints similar to
those used in timber and steel construction are generally not appropriate for the purpose.
Joints of reinforced concrete structures which should be omitted are shown.
The joint to be seen in fig. This is s solution resembling a butt jointed with splayed
table as used in timber construction. This does n’t comply with the nature of the material &
So is not good for this purpose. The limtating a joint used in steel construction, is not
appropriate either. The steel structure -like joint as seen in which the component structural
parts are coelded to the reinforcement is also not sufficiently adequate. The two halves of the
steel structure forming the main constituents of the joints have to be concrete is to
the placing of the pins.
The joints can be rigid hinge like or shed.
Rigid joints are adequate in addition to the bearing the tensile, compressive & shear
forces for resistances.
Design of c/s based an efficiency of the material used:-
The plastic concrete can be used for the subsequent concrete of joints & the fluid
cement mortar last or pressed into the gaps lase part of their water during the settling time &
shrisk, after setting the shrinkage of the insite concrete & mortar continue.
with respect to two phase of shrinkage same codes on reinforced concrete
construction permit only reduced stresses for a subsequent insite concrete of a mortar casting.
These are generally determined as a function of width of the joint on the gap to be concrete as
cost.
Joints must be designed & executed so that compensation for the allowed dimensional
tolerances is ensured or relative displacement of the jointed members should be impossible
even as a result of a blow or of any other infavourable force effect. The length of the section
determined for the transmission of forces should be as short as possible, but should excluded
any excess of the permissible stress.
The joints can be regid hige like or shed. Regid joints are adequate in addition to the
bearing of tensile, compressive & shear forces recover displacement and
like joints can transmit forces passing through the hinge itself and also
allow a certain motion and rotation.
Rigid joints are generally used for the junction of column to footings, but they can
also be applied for joining of individual groups with one another. The joints generally used in
the construction with precast members are usually hinge like their execution is simpler and
requires less working -lime than rigid joints “shodjoints” are only exceptionally used in
industrial construction & are justified for a long span only. These joints are justified for
chiefly used in bridge construction for a long span bridges depending on the necessity of
insite concreting, two kinds of joinjts can be distinguished.
a. Dry joints - joint accomplished by simple placing of two members on each other &
fasting.
b. Wet joints - joints require not only casting with cement mortar but also subsequent
concreting.
d. Lengthing of columns:-
Columns are usually lengthened at floor levels. An intermediate lengthening should
be avoided it possible.
The lengthening of columns can be executed similarly to the joining with fooling,
accordingly reinforcement are joined by overlapping looped steel bars a welding. Thereafter
the stirrups have to be placed & finally the joint must be concreted.
e) Joining of Beams:-
The functions of beams can be affected either by overlapping the protracting steel
bars or by welding them together.
Figure shows the tinge like joint of purlins. In this method the whole shear must be borm by
both cantilever (i.e) by two separate structures therefore it is expedient to form this joint
atleast for large girders.
The method illustrated in the fig presents a dry joint of beams which is called a bolted
form. The advantages of this joint is immediate bearing capacity.
f) Forming of functions of arched structures:-
Precast arches are usually produced and assembled in the form of three hinged
structures. When the constant load has already been applied the centre joint is frequently
eliminated. The omission of the centre joint increases the rigidity of the structure. Naturally
arched structures can also be precast in a piece i.e in the form of two hinged ones.
Hinges of arched structures can be made by using either steel shors are more
expensive, but the centre transmission of forces is enhanced by their use.
Figure shows the centre hinge of a three hinged arch with a span of 12.5 m for this
kind of each the joint can also be formed from the concrete itself. The latter method require
exactly executed and adequately reinforced concave & convex surfaces with hear against one
another.
The joining of a smaller hinged structure is show in below mentioned.
The arrangements the centre junction of the end hige of an arched structure. This
method was used in the construction of the ball for the middle rolling train in D.O.Sayar. The
structure was precast & assembled in the form of a three-hinged arched transformed later in
to a two -hinged one.
Unit –IV
JOINT IN STRUCTURAL MEMBERS
4.1 Expansion Joints
An expansion joint is an assembly designed to safely absorb the heat-induced
expansion and contraction of various construction materials. To absorb vibration, or to allow
movement due to ground settlement or earthquakes. They are commonly found between
sections of sidewalks, bridges, railway tracks, pipeing systems, and other structures.
Figure
Expansion joint design:
A design specification shall be prepared for each expansion joint application. Prior to
writing the expansion joint design specification it is imperative that the system designer
completely review the structural system layout, and other items which may affect the
performance of the expansion joint. Particular attention shall be given to the following items.
The system should be reviewed to determine the location and type of expansion joint
which is most suitable for the application. Both the EJMA Standards and most reliable
expansion joint manufacturers’’ catalogs provide numerous examples to assist the user in this
effort. The availability of supporting structures for anchoring and guiding of the system, and
the direction and magnitude of thermal movements to be absorbed must be considered when
selecting the type and location of the expansion joint.
Conventional rubber expansion joint
Expansion joints are designed to provide stress relief in piping systems that are loaded
by thermal movements and mechanical vibration. To deal with the various forces on the joint
they require fibre reinforcement which guarantees both flexibility and strength. Conventional
expansion joints are reinforced using prefabricated fibre plies. The use of these fabric plies
makes it impossible to control the orientation of the fibres on complex shapes such as the
bellow of an expansion joint. In both cases the inability to use the fibres in an optimal way
leads to the following disadvantages:
High Material Cost:
More fibres needed than necessary
More rubber needed than necessary
Additional parts such as metal reinforcement rings necessary with multiple
bellows Lower Performance
High rubber wall thickness and fibre pack make product less flexible
Undesired radial and axial expansion under pressure.
1) Introduction 2) Necessity 3) Advantages 4) Pre requisites 5) Types of prefabrications
Figure
Types of Fabrications
Filling Reinforcing
CE204 PREFABRICATED
5 STRUCTURES
Component
Compaction
Curing
Demoulding
Storage
Methods of Manufacture:-
On -SITE : Open yard casting or covered but purely temporary or semi-permanent type of
set-up with partly mechanized facilities.
Factors Influencing method of manufacture
The single and the total no of elements to be produced
1. The single of the element may decide the reinforcement of space for production as
well as the capacity of the handling equipment is decided by the heorist element.
2. Desired rate of output: This will have direct bearing on the nf of moulds required
degree of mechanization and need for accelerated method of curving.
Figure
Figure
Figure
Single Moulds:
These are employed for casting volumetric elements such as sanitary units, ventilates
shafts and refuse chuter. Battery moulds are employee for internal panel walls and floor
panels. The swing down moulds are used for simultaneous manufacture of two wall panels.
Flow Line Production :
This is a travelling horizontal mould system in which the moulds are moved and the element
from one position to the rest a series of stations, such as demoulding, mould cleaning and
oiling, placing of reinforcements concreting vibration, surface finishing and curiving a
stream chamber forms the part of the continuous travelling a chain and the chain can be in the
horizontal plane or in the vertical plane.
Figure
1. Placing of concrete by strips slips
2. Spreading of concrete is done manually or mechanically.
3. Compaction by vibrators or by vacuum process or pressing.
In the case of vibration it is effected by means of internal vibrations and external
vibrations. Internal vibrations in the form of immersion vibrators is used in places where
we have conjusted reinforcements. External vibrators ae generally used with steel moulds.
Vacuum process is suitable for components with large surface area or relatively thin
elements. In the case of compaction by pressing. The freshly poured concrete is subjected
to a pressure of about 70 ksc. It sequences out excessive water forming a cohesive slab
which can be immediately remoulded.
Curing :-
Accelerated curing -1 cycle - 1. Preheating period -3hrs-35ºC
(Steam curring) 2. Temp Rise Period -2hrs -35 to 8.
3. Period at max temp - 6hrs - 80ºC
4. Cooling period - 3hrs - 80ºC-45ºC
Accelerated curing techniques are adopted for quicker turnover. It may be in the form
of steam curing or heat treatment. Hot water or hot air. The duration of stream curing cycle is
influenced by the factors like type of cement, water cement ratio, size of the members, the
desired strength. With proper steam curing it is possible to achieve 60% of the moist curned
28 days strength of the concrete in 24 hours. In open casting yard for steam using specially
made hoods are used which are insulated and sealed to prevent excessive loss of heat and
moisture. In the case of flow line product.
The chamber is sufficiently long to ensure that the products remain wihin the chamber
for the desired time.
Demoulding and storage:
The units are first demoulded from the sides and then from the bases and the
earthwork required to separate the unit from the base is more than the weight of the unit to
account the adhesion of the unit to the base. Wall element are stored vertically. Floor and roof
elements are stacked horizontally with & wooden strips in between two elements.
The tolerance is the sum of acceptable positive and negative discrepancies of actual
dimensions from the theoretical one. The limits of tolerance are based on the manufacturing
and erection requirements.
Modular Co-ordination :
If the inter dependent arrangements based on the Pre Fabrication and System
Building
Definition
Pre-fabrication means that the structure is disunited in its members and these are
precast either in factories built and equipped particularly for this purpose or in temporary
plants established n the site. Then the precise reinforced concrete members are shifted to the
place where they are to be used, here they are hoisted, set into their final places, and
assembled to form a complete structure.
The limits of deviation in the dimensions the shape of the prefabricates. This
depends very much on the type of moduls, wooden, steel, concrete or plastic, the tolerance
also depends on the nominal dimension, nature of prefabricate and its position during
casting.
Erection tolerance
These are the limits of deviation of the positioning in the assembly of the
prefabricates. The position tolerance are normally defined by five components namely,
deviation in positioning of the prefabricates in x,y,z directions ( x, y, z) and deviation in
positioning with respect to another prefabricate ( p)and the deviation in the verticalioty of
the
4.5 Standardization
The following are the advantages of standardization.
1. Easier desing
Elimiation of unnecessary choices.
2.Easier manufacture
Limited number of variants.
3.Easier erection and completion
Repeated use of sepcialised equipment.
4.6.Factors infuenceing standardization:-
1. The most rational type of member for each element is selected from the point of production
from the assembly serviceability and economy.
2. The number of types of elements will be limited and they should be used in large
quantities.
3. To the extent possible the largest size to be used which results in less no of joints.
4. The size and no of the prefabricates is limited by the weight in overall dimension that can
be handled by the handling and erection equipment and by the limitation of transportation.
Hence it is preferable to have all the and transporting complete assemblies or sub-assemblies
to the construction site where the structure is to be located. The term is used to distinguish
this process from the more conventional construction practices of transporting the basic
materials to the construction site where all assembly is carried out.
The term prefabrication also applies to the manufacturing of things other than
structure at a fixed site. It is frequently unused when fabrication of a section of a machine or
any movable structure is shifted from the maid manufacturing site to another location, and the
section is supplied assembled and ready to fit. It is not generally used to refer to electrical or
electronic components of a machine, or mechanical parts such as pumps, gearboxes and
compressors which are usually supplied as separate items, but to sections of the body of the
machine which in the past were fabricated with the whole machine. Prefabricated parts of the
body of the machine may be called ‘sub-assemblies” to distinguish them from the other
components.
Contents
1. The process and theory of prefabrication
2. History
3. Current uses
4. Advantages of prefabrication
5. Disadvantages
6. Off-site fabrication
7. See also
8. External Links.
The process and theory of prefabrication
An example from house-building illustrates the process of prefabrication. The
conventional method of buildings a house is to transport bricks, timber, cement, sand, steel
and construction aggregate, etc, to the site, and to construct the house on site from these
materials. In prefabricated construction, only the foundations are constructed in this way,
while sections of walls, floors and roof and prefabricated (assembled) in a factory (possibly
with window and door frames included), transported to the site, lifted into place by a crane
and boiled together.
Prefabrication is used in the manufacture of ships, aircraft and all kinds of vehicles
and machines where sections previously assembled at the final point of manufacture are
assembled elsewhere instead, before being delivered for final assembly.
The theory behind the method is that time and cost is saved if similar construction
tasks can be grouped and assembly line techniques can be employed in prefabrication at a
location where skilled labour is available, while congestion at the assembly site, which
wastes time, can be reduced. The method finds application particularly where the structure is
composed of repeating units or forms, or where multiple copies of the same basic structure
are being constructed. Prefabrication avoids the need to transport so many skilled workers to
the construction site, and other restricting conditions such as a lack of power, lack of water,
exposure to harsh weather or a hazardous envioronment are avoided. Against these
advantages must be weighed the cost of transporting prefabricated sections and lifting them
into position as they will usually be larger, more fragile and more difficult to handle than the
materials and components of which they are made.
Disuniting of Structures:-
The solution of problems connected with the transportation and placing of structures
demands as a rule their disuniting into smaller members. One-by frames not exceeding 40
tons in weight, may represent an exception, because the problem of their hoisting and placing
can be solved with the aid of modern available hoisting machines and equipment.
In spite of this these frames are frequently disunited as their corners or points of
minimum moments into members, to make the hoisting of these smaller members possible,
using much simpler equipments.
In general there is trend towards the use of larger members. This is justified by more
then one reason. One is that the bearing of a certain moment can be solved more
economically by using one large girder instead of two or more smaller beams together having
the same bearing capacity indicates the moment bearing
capacity of the girder. While the enlargement of the cross section led to an 11-fold dead load,
the moment bearing capacity, increased 80-fold, However with regard to the load bearing
capacity, the moment-bearing capacity is not one unique Decisive factor because the shear
force that can be borne by a cross-section does not increase in the series ratio as does one
moment.
In addition the hoisting of one larges member is as a rule, less expensive than that of
two smaller members having the same combined weight. It is a direct consequence of the
following circumstances: the assembling of the lifting tackle, the transfer of the hoisting
machine, the hoisting, placing and plumbing must be done for each member separately,
Independently of its weight.
into larger members means, lower costs of hoisting and placing
as well as saving in joining costs.
In the first case the expenses of preparation and payments connected with the hire of
the equipment may be higher, but the work itself is much less.
Naturally, if plant prefabrication is practiced, the greatest size of precast members is
determined by the transportation and shipping cost.
But demands are not unlimited either so, members whose weight would exceed 60
tons cannot be found even in structures of the largest power stations.
Now a days, the hoisting capacity of derrick is 40 tons, while that of a pair of
twinned-mast cranes reaches 70 tons.
In this case the members should be as large as possible within the limits of the
available hoisting capacity.
Materials used:-
The materials used a prefabricated components are many. The modern trend is to use
concrete steel treated wood aluminum cellular concrete, light weight concrete ceramic
products etc.
Which choosing the materials for pre fabrication the following special characteristics
are to be considered and transported and to
economic an sections and sizes of foundations.
Thermal insulation property.
Easy workability
Durability in all weather conditions.
Non-Combustibility
Economy in cost
Sound insulation.
Modular Co-ordination :-
Only basic modules to be adopted. Basic module is the fundamental module used in
modular co-ordination. The size of basic module’s selected for general applications for
building and its components. The value of basic module chosening 100mm for maximum
flexibility and convenience. The symbol used for basis module is M. After adopting this,
further work is necessary to outline suitable range of multi module with greater increments,
often referred to as preferred increments are adequate for meeting the requirements of
conventional ad prefabricated construction. These rules relate to the following basic
elements, refer to figure (4.1).
Modular co-ordination :-
1) The planning grid in both directions of the horizontal plan shall be:
a. 3m for residential and institutional buildings.
b. For industrial buildings :
15 M for spans up to 12 M.
30 M for spans between 12 M and 18 M and 60 M for spans over 18 M.
The Centre lines of load bearing walls shall concede with the grid lines.
2) In case of external walls, the grid lines shall coincide with the centre line of the wall
of a line on the wall direction
shall be 1M up to ad including a height of 2.8 m; above the height of 2.8 M it shall be
2M.
3)
4. Preferred increments for rill lights doors, windows etc. shall be 1 M.
5. In the case of internal columns the gridlines coincide with the centre lines of columns.
In case of external columns ad columns near the lift and stairwells the grid lines shall
coincide with centre lines of the column in the top most storey or a line in the column
50mm from the internal face of the column in the top most storey.
Advantages of standardization :-
The following are the advantages of standardization.
1) Easier in design as it eliminates unnecessary choices.
2) Easier in manufacture as there are limited number of variants.
3) makes repeated use of specialized equipments in erection ad completion easier ad
quicker.
Systems:-
The word system is referred to a particular method of construction of buildings by using
prefabricated components which are inter-related in functions and are produced to a set of
instructions, with certain constraints, several plans are possible, using the same set of
components. The degree of flexibility varies from system to system.
a prefabrication system
The following characteristics among others, are to be considered in devising a system.
1. Intensified usage of spaces.
2. Straight and simple walling scheme.
3. Limited sizes and number of components.
4. Limited opening in bearing walls.
5. Regulated locations of partitions
6. Standardized service and stair units.
7. Limited sizes of doors and windows with regulated portions.
8. Structural clarity ad efficiencly.
9. Suitability for adoption in law rise ad high rise blocks.
10. Ease of manufacturing, storing ad transporting.
6.0 UNIT1.INTRODUCTION
PART- A
1.Define prefabrication.
The term prefab can apply to any construction method where the significant part
of the construction takes place off site in a factory . That produces relatively large complex
features that assembled at the site into the finished building .
Modular coordination is a concept for coordinating dimension and space for which
building and component are dimensionally it used and positioned in basic units (or)
modules. The standard specify that the module basic M = 100 mm . As the basic unit be
used in a square of M .
I) The basic module is small in terms of add size in order to provide design
flexibility
, yet large enough to promote simplification in the component variation in sizes .
II) Industry friendly features that not only for manufacturing but also
the transportation and assembly requirements .
I) Self supporting readymade components are used ,so the need for formwork ,
shuttering and scaffolding is greatly reduced .
Disadvantages :
The production of concrete blocks consists of four basic process They are,
II) Tempraray props may be required in some cases ,before the un-site concrete
joints achieve strength .
III) The cracks may develop at the joints between the precart in –site concrete due
to shrinkage and temperature stresses . To overcome them extra steel is required across
joint.
d. Preferred increments foa the still heights,doors,windows and other fenestration shall
be
1
M
.
e. In case of internal coluums the grid lines shall coincide with the centre lines of
columns.In case of external columns,the grid lines shall coincide with the centre lines of the
columns in the storey or a line in the column from the internal face of the column in the
topmost storey.
A basic module can be represented as module andfor larger project modules are represented
a
M
p.
For eg: For a project module in horizontal coordination,the component can be of 30cm
and for vertical component size be of 10cm.
The storey height is fixed between finished floor levels as 2.8m and if the thickness of slab
is
<15cm storey height is fixed as 2.7m. The centre distance between the load bearing walls
can be chose from a set of modules. The use of other dimensions is not allowed.
In the design of a building,modular grid can be used consisting of parallel line spaced at
a value of module M or Mp and a grid line chosen as a base for setting out a part of a
building becomes a modular axis. In the fig (a),, a typical grid is chosen for load bearing
walls without duct. The interior walls are placed so that their centerlines coincide with the
modular axis. In the fig (b), a grid is shown for load bearing walls with hollw ducts in
between. The centre line of the grid is found by deducting the size of duct.
2. Systems of
prefabrication:
System is referred to a particular method of construction of buildings using the
prefabricated
components which are inter related in functions and are produced to a set of
instructions. With certain constraints, several plans are possible, using the same set of
components, the degree of flexibility varies from system to system. However in all the
systems there is a certin order and discipline. The system of prefabricated construction
depends oon the extend of the use of prefab components, their characteristics to be
considered in devising a system:
joints: Advantage:
Disuniting at joints gives linear member. This means that a great advantage and
facilitates from the view point manufacture and assembly.
Disadvantage:
1. Joints are at corners i.e. at points of maximum moment values, so forming the joint
is difficult.
2. Joints must be over dimensioned to cope with insitu concreting. And one
alternate solution to replace moment resistant joints by hinged connection.
System for prefabricates of entire rigid frame:
In this system, to reduce the no of joints and to precast larger numbers I one piece leads to
the prefabrication of entire frame. Production of the frames does not cause any particular
trouble but the hoisting is more difficult and requires careful preparation.
Advanta
ge:
Advantag
e:
Disadvantag
e:
These members are generally precast and assembled in statistically determinant three
hinged variance and middle hinge is only eliminated after placing is finished. The
reinforcing bars protruding both sides are welded together and the joint between the
members is filled in with insitu concrete.
Arch structure can be precast in either vertical or horizontal positions. In the first case,
shuttering made of timber or concrete is required having the same curvature s the arch
itself. The prefabrication of larger arches in theh horizontal position is found to be more
economical The construction of arch trusses can be properly carried out in the horizontal
position only.
Truck
cranes
Gantry
cranes
Mast
cranes
Derrick
cranes
Twinned mast cranes
Truck cranes:
Truck cranes consists of chasis includinig mortar and pivoting upper part. These cranes
are mobile and an travel on their own needs. Different features are:
Gantry Cranes:
These cranes are used mainly to serve the operation of manufacturing and storing areas
in prefabrication plants.
Maximum height is up to
11m
Mast Cranes:
These are wide spread hoisting devices,simple and cheap. Operation requires great skill and
practice. Useful in hoisting prefabricates in vertical direction. Suspension load can be
slightly moved forward by slackening the rear staying cable. Hoisting load is done by a
winch.
It is used for hoisting member to great height. It consists of two steel column assembled
from sections and connected at top by bridging structure.
workers.
The crane can be transferred but takes 1-2 days and is suitable fr high lifting but difficult
to operate.
Derrick cranes:
Highly efficient lifting
machines
It is stable or
movable
Capacity 20-
40T
If the external walls are hand laid from small blocks or bricks, all necessary materials
should be hoisted by crane and stacked near the ultimate position. The mansonry work is
begun after the floor immediately above is laid.
The tolerances are comparatively strict and are normally coompliedwith the use of a skilled
rection gang. The distance between the wals are measured with the steel tape and
the thickness of joint with rule having mm scale.The accuracy is verified by means of
surveying instruments after all joints are connected or erected.
Hosting of Columns:
The hoisting machine for small column is less than five tones. First of all pick up gear
must be assembled on to the column and the column is then under pinned.
Thereafter the column is lowered temporarily on to a sheep shoe assembled at the foot
and the roller track is pushed under the shoe. When column is hoisted the pick up points
moves vertically and bottom resting on the roller tracks shifts towards the footing. When
the column is lifted to the required height, the retaining cable is used to decrease and
finally stop the swinging motion of the column.
Suspension:
For lifting up of trusse and large beams of length 25-30m. care is taken to lift the rocker
in uniform rate with two hoisting machines otherwise the beams would be
subjected to distortion during the lifting leading to cracks.
5. Methods of prefabrication:
prefabrication:
1. The RC members are produced t the site in the open air chiefly in the open air
or in the temporary sheds
2. The difficulties in construction in general are felt in this mechanization can case.
3. Mechanization can not be of such high degree as site PF is done for smaller
duration of time.
4. When the pre fabricates are of large size it is difficult to transport the pre fabricates
to
th
e
sit
e.
5. In comparison with plant prefabrication transportation of the members are not
needed.
As large members are not transported the design and weight of the
prefabricates are not limited.
Plant prefabrication
Plantt prefabrication is done under permanent plant or factories. It is done under the
covered roof so the effect of weather does not affect the work. So the quality and
strength of the members can be improved considerably. Plant prefabrication reduces the
cost of prefabrication if the number of prefabricate needed is more.
Dimensions of prefabricate:
Production of prefabricates:
1. Stand
method
2. Conveyor method or line
method
3. Aggregate
method
Stand Method:
In this method, the prefabrication mature where they are moulded while the
production teams moves to successive stands. The bed on whih prefabricates are cast may
be fixed or movable. Tilting forms are often uused and in tthis method steam curing is
generally done.
After that,it is passed through tunnel autoclave for curing.After steam curing move too
station 7 for demoulding & is finally stacked @ 8.
Aggregate method:
Aggregate method is used in the production of multi duct hollow floor pannel in
Poland.At production point the reinforcement is fixed in the form & remote controlled
aggregate(machine)inserts the duct formers,cast& vibrates the concrete,floats @ the top
of the floor.The prepared prefabricate then move to the autoclave chamber in which
hardening of concreteis accelerate.In many factories combined technology are employed
when complex prefabricate are required.
Advantages:
1.The stand technique is the most flexible one.It is used in varying degrees of
mechanization,in all kinds of prefabricate factories.
2.It is simple & less capital is required.It can be used for field prefabricate also.
3.Aggregate method is used for large scale productionin which case number of
machineries is required.
UNITII.PREFABRICATED COMPONENTS.
PART A
The main beam (or) load bearing wall are placed to the long axis of building . it is applied
to the building with large prefabricated and similar to traditional brickwork . The longitudinal
wall crosses the floor load must posses not only thermal .
function . d) Based on
the shape .
These members are used to give spaces like walls both load carrying and partition walls .
this may (or ) may not contain doors and windows the provision for the same is as per the
requirement . Another example for the space bordering member are floor slabs .
In the case of surface forming members, the load carrying and surface bordering are
united and a uniform load carrying surface is found loaded by complex forces and economic
shapes.
In the case the synclastic the curve of the shell in the same side (eg : hemispherical shell )
where as in the case of anticlastic the curvature of the shell is in opposite direction eg:
hyperbolic shell (saddle shell ).
A dome is a space structure covering a more (or ) less square (or ) irregular area . The best
known example is the dome of revolution , and it is one of the earliest of the shell structure.
Excellent examples are still is existence that were built in Roman times .
These are simple type and these shear walls under forces and horizontal shear along its
length are subjected to bending and shear walls.
To resist these forces , the uniform distribution of steel along its length is used in simple shear
5) Care type .
# Load bearing walls and beams are placed in both ways longitudinally and transversely .
In the building with ring system of support floors are normally supported on all four edges and
span is two direction .
classified as,
i. Reinforced planks.
members. iv.purlins
Reinforced planks made of hollow tiles.The reinforced planks with longitudinal circular
holes.Thickness of these tiles is 60mm,80mm & 100mm & the width is 200mm & length is vary
from
360mm to 400mm. On the upper side one longitudinal groove is
provided.
Reinforcement is placed into these grooves which are subsequently filled with cement
mortar.In this way ,roofs of length 2 to 3m & thickness of 60 to 100mm & width 200mm can be
constructed.
The end tiles resting on the support are provided with 3.11mm dia stirrups protruding from the
tile.There are kept together over mortar of 40mm thickness & in further concreting of joint.the joint
is completed.
Light weight concrete roofing members play a role in addition to space bordering &
load bearing in heat insulation.The thickness varies from 7.5 to 25cm for reinforcement of Light
weight concrete roofing members.weiding nets is used.steel reinforcement is given additional
coating to prevent any corrosion care is taken to give good bonding of reinforcement with concrete.
The unit weight of these members is 750kg/m3 & width of 50cm.Its varies from 1.75mm
to
6m.precast members can be made either in usual way using light weight materials.sand as
aggregate
& combination of high strength concrete.The top & bottom layer of about 2 to 3cm thickness iss
provided with high strength concrete.Its consists of prestressed 2.5mm ddia embedded in
these layers.The middle portion is made with light weight concrete.
Purli
ns:
Purlins are precast concrete beams supported by the main girders serving the purpose of
bearing for the roof covering.The cross section of purlins iss generally rectangular but it can also
have trapezoidal,T,L and I shape.
Precast purlins can be simply supported or cantilever beams & for the bearing of
loads beyond these weight simply supported purlins can be transformed into continuous beams.It is
very simple & easy to place.For cantilever purlins placing of hinges should be determined in a
manner to develop positive & negative moments equal to each other.This can be arrived by placing
the hinges @
0.1451 from the support where I is the spacing between
Large reinforced concrete rest on the main girders.These are generally used for large hall
structures & these are most advanced type of precast structures.Members are manufactured
corresponding to spacing of the frame length of about 6 to 10m & width of 1.3 to 1.8m. As they are
most supported on main girder purlins are not required.
2. Intermediate
members.
3. Members with
cornice.
2. Coupled shear
wall.
3. Framed shear
type.
When walls are to carry only compressive force,they can be designed as plain concrete,when
walls are subjected to tensile forces(due to wind force)due to eccentric loading& earthquake load
the walls are RC walls,shear walls are previously provided to resist the wind forces only.Hence
became popylar & to prvide shear walls to resist EQ forces.
SHEAR
WALLS:
These are simple type & these shea walls under forces & horizontal shear along its length
are subjected to bending & shear.To resist the forces the uniform distribution of steel along its
length is used in simple shear walls.In case of bar bell type 2 boundary elememts are provided on
either side.Minimum steel is provided over the 0.7 to 0.8L & the remaining steel is placed steel is
placed @
0.12 to 0.15L.These walls are designed in such a way that they never fail in shear but only by
yielding of steel in bending.Shear failures are sudden & brittle.One disadvantage of this type of wall
is that during EQ the shear walls attract all the earthquake forces & dissipates the forces in to the
wall.The loss of energy by crackingof the wall iss difficult to repair .This can be eliminating by
providing coupled shear wall.
The action of the couping beams of the shear walls.The beams are displaced vertically
they tend to bend in a double curvature.The consistent shear can reduce the axial force in the
upwind wall by a large amount & reduce pressure can lower tne shear capacity of the wall.To take
up for this force diagonal lateral steel is more effective.
The design should be taken care of to see that the system develop plastic hinges only in
the coupling beams before shear failure & coupling beams should be designed to have good enrgy
dissipation capacity.
These are load bearing structures having curved surface.The advantage of shells is that it
provides large column free area for the monolithic construction.The cost of shuttering & scaffolding
is very high but if manufactured in a precast factory in large scale.The production cosh can be
considerably reduced.
The shell structure can have ribs in the centre & provided with curved membranelikee
roof.The shells built of precast members used in the construction of industrial buildings are
many.The thickness of shell varies from 2 to 10cm.Some precast shell,,s are produced with
dimensions which are very difficult to transport.To avoid such difficulty large size shells are
precast near to the restting or construction place.
The transportable or small size shell members can be precast in factories & these are
transported to the site.Examples:Barrel shells,Saddle or hyperboloid shells.cupola or
paraboloid shells.
CE2045 PREFABRICATED STRUCTURES
Types:
a.Single barrel:
The structure above is a single barrel with edge beams.The shell has been
allowed to project beyond the edge of the stiffener in order to show the shape of the
shell.Stiffeners are required at columns.They do not necessarily have to be complete
diaphragms but may be arches with a horizontal tie.The thickness is based on design of a
slab element,the thickness of the barrel shell is usually based on the minimum
thickness required for covering the steel for fireproofing,plus the space required for
three layers of bars,plus some space for tolerance.If these bars are all half inch rounds,a
practical minimum would be 3 ¼ inches.Near the supports the thickness may be greater
for containing the larger longitudinal bars.
If more than one barrel is placed side by side,the structure is a multiple barrel
structure
& if more than one span,it is called as multiple
The maximum spans for this type shell are again limited by the geometry off the cros
section .Assuming the maximum width of barrel to be 50 feet & maximum end slope to be 45 ,the
rise would be about 14 feet,the maximum span would be in the order of 150 feet.
This type of shell structure is used to provide large areas of north light windows for
factories requiring excellent natural lighting.The windows may be slanting or may be
vertical.The member at the bottom forms a drainage trough with the curved shell & materially
assists in stiffening the structure. The effective depth of the shell is not the vertical distance
between the two ends but is morely represented b the depth if the shellis laid flat with the ends of
the circle on the same horizontal line.The spans for the north light shell must be rather small in
comparison to the vertical depth of
construction.The edges of adjacent shalls should be tied together by concrete struts serving
as mullions between the window glazing.
Long barrel shell obtained hen the semicircle or a segment of same is translated along
the longitudinal axis.
Generally used for shed for industrially purpose & buildings for large column
free areas.Generally the prefabricated barrels off sizes 3.5 to 5m & 10m long with edge beams
having thickness of 60mm.The thickness of the shell should not be more than 40mm.The dimension
of these members were finally limited by the load carrying capacity of the available hoisting
machines using the girder system built of precast prestressed trusses with parallel chords,areas
having a span of even more than 15m can be covere with barrel shell
Folded plate:
A folded plate structure with 3 segments for each barrel.The forces from the reactions of the
sloping plates on these rigid frames will be quire large and at an outside column they will not be
balanced by thrusts from the adjacent plates.The size of the frames may be reduce by using a steel
tie between the tops of the columns.The dimensions of the plate are dependent on both the with of
the barrel & on the span.The depth of the shell should be about 0.10 timess the span & the
maximum slope of a plate should not be greater than 40.For example,assume that the span is 60feet
& the baywidth is 24 feet.The depth of the shell should be about 6 feet & the horizontal width of
each plate with a 3 segment plate should be about 8 feet.The lope of the plate is 6/8,which is about
37 & is satisfactory.The thickness of plate could be about 3 ½ inches.The principle components
in a folded
plate consist of 1.inclined plate 2.edge plate which must be used to wide plate.3.Stiffeners to carry
the loads to the supports & to hold the plate.4.Column to support the structure in the air.
Domes are construced with many planes so they ressemble the facets of a diamond.The
structural problem in designing these shells is to provide enough angle between the planes so that an
actual rib is formed which will be stiff enough to support the plane surface.Usually it is best to start
with a spherical translation surface.
This makes use of tapered folded plate slanting to the centre in the form of a tent.It can
be built so that each of the triangular elements is self supporting during construction except for
possibly a single shore at the crown.To obtain natural light the top may be cut off & a ring inserted
with a sky light.The arch thrusts are taken through this ring & the difficult forming of the narrow
plate at the crown is avoided.If the structure is large there would be very high bending stresses
due to the curvature & the ring would be very large.
There may be discontinuous in the layout of intersections which make or destroy the
visual effect & make the structure more difficult to design.This dome can be of much greater span
than the previous example because the span of the individual slab element is less.A dome
hexagonal in plain can be made continuous with adjacent units if it is necessary to cover a large
area.
A half sphere for a dome of revolution does not require a thrust ring at the base so it can
be placed on vertical walls & made continuous with a walls.This design is used for tanks
because the roof becomes a part of the tank.The vertical portion of the sphere is not difficult to
construct if pneumatically applied shotcrete or a similar process is used.The structure with arched
openings an a plastic dome on the crown has a rather oriental feeling.The most serious problems in
the architecture of dome is acoustics.In a domed ceiling the sound may reverberate as many as 20
times unless there is acoustical treatment.
Domes-Square in plan:
This structure is a spherical dome with portions sliced off to form a square or
rectangle.Most areas to be covered are rectangular so a circular dome is not always a good solution
to the planning requirements.This dome is supported by four rigid frame & would only be suitable
for small span because the frame would get quire in large.For long spans it is necessary to place a
tie between the knees of the frame.These ties can be made a part of the windows.Stresses in the shell
are direct compression stresses except across the corner where there are direct tensile due to the
outward spread of the forces.The arches or rigid frames pic up the shell forces by shear parallel to
the arches which are zero at the top & maximum at the bottom.There is no component of force in
the shell perpendicular to the arches.
Multiple Domes:
The domes is rectangular & is continuous with the adjacent domes.The edges of dome
are supported by tied arches or brousing trusses.If windows are needed in these arches,the
mullions may be made to serve as vertical hangers for the bottom chords of the arch.In
constructing the shell,each one of the dome elements is an independent structural unit so the
forms may be moved without shoring all or part of the dome already cast.The shell thickness of
this type of dome does not need to be greater than a circular dome except at the triangular
corners.Membrane action ceases to exists & the corner should be designed as a slab.
Translation domes:
This structure looks very much like the square dome.A translation shell is generated by a
vertical curve sliding along another vertical curve.The curvs can be circles,ellipses or
parabolas.Therefore the vertical sections are all identical as opposed to a circular dome in which all
vertical sections vary in height.This is a big advantage in construction of the formwork.This method
can provide a rectangular dome with the same height of arch on all sides,thus making a rectangular
dome feasible.
Most of the load is carried by the side arches with some coming directly to the corners.A
tie at the springing of the arches but usually this will be covered by the walls.Such shells are
suitable for quite long spans with some interior lighting furnished by skylights in the shell.
Warped surfaces have a great advantage for shell structure because they may be
formed from straight form boards eventhough they are surfaces of double curvature.There are two
typeswhich are most useful:the conoid which as its name suggests is a portion of a cone&
the hyperbolic paraboloid,a name for a particular mathematical surface.This type of shell
structure can be built to what appears to be the ultimate in lightness of construction,minimum
reinforcing & ease of moving forms.
Stresses in the hyperbolic paraboloid shell are almost entirely membrane(direct tension&
compression)& all forces are delivered as shear parallel to the stiffening ribs.The shell thickness in
structures is on &one half inches except for slight extra thickness at the intersection of the
surface.This dimension is based on a cover of one centimeter on each side of two layers of bars &
not an any structural requirement for strength.
Generally classified based on the function as load bearing & non load bearing
walls.Eg.partition wall.They taansfer self weight only & they are provided to create barriers that
can be visual,thermal on acoustic.
Stiffening walls:
Provides 3 dimentional stiffness .The load bearing walls which are referred to as supported
walls do not posses foundation o f their own but are either carried by beams or slabs or directly
attached to load bearing walls. The supported walls can form on integral part of structure or remain
as non structural depending on stiffness.
Depending on the orientation of the main beams or load bearing walls relative to long axis
of the building. Prefabricated wall system are classified as,
The main beams are load bearing walls are placed parallel to the long axis of building. It is
applied to the building with large prefabricates and is similar to traditional brick work technique .
The longitudinal external walls which carry the floor loads must posses not only thermal
properties but also sufficient load carrying capacity .
The long wall system construction is typical with large blocked structure and special pier
blocks between the windows which carry loads from lintel and the walls above. The horizontal still
blocks are not loaded . In some designs space between the piers is filled by prefabricated unit
consisting of RC window frame complete with window.
The internal wall blocks are normally of full storey height subject to limitations imposed by
lifting equipments available. Both internal and external walls are made of some materiel.
Load bearing walls and beams are placed at right angles to the longitudinal axis of
the building . In this system the floor units are provided with two way structural units which
distributes the to the cross walls and this system is more prominent. The internal walls are made of
ordinary concrete for load bearing walls and the external walls and the external walls are made of
light weight concrete to reduce the weight of the structure.
Load bearing walls and beams are placed in both ways longitudinally and transversely. In
the building with the ring system of support floor are normally supported on all four edges and
span in two directions. In skeleton construction these floors are placed directly on columns.
In this system, the floor slabs are designed to span in both direction and are loaded on to the
supporting walls. For large load panels cross beams are hidden within the thickness of the panel.
CE2045 PREFABRICATED STRUCTURES
QUESTION BANK
UNIT I - INTRODUCTION
PART – A
1. Define prefabrication
2. What are the types of prefabricates based on i. Plan area ii Based on weight(MAY /JUNE
2012)&MAY/JUNE 2013
3. What are the types are of prefabricates based on shape? (MAY/JUNE 2012)
4. What is the need for pre fabricates structures
5. What are the Advantages of PFS? (MAY/JUNE 2012) &(MAY/JUNE
2009)& MAY/JUNE 2013
6. What are the disadvantages of PFS? (MAY/JUNE 2012)
7. What are the Production techniques?(NOV/DEC2012)
8. Explain the stand system Production technique
9. Explain the conveyor belt or production line system Production technique?
10. Explain the aggregate system production technique?
11. Explain the Erection procedure of PFS building?
12. What are the aims of prefabrication?
13. What are the characteristics of Materials used for construction of PFS?
14. What is meant by modular co-ordination? (NOV/DEC 2012)& NOV/DEC 2013
15. What are the Advantages of standardization?
16. What are the Factors influencing the standardization?
17. What are the Prefabrication systems?
18. What the Types of system are of prefabricate d construction systems? (MAY/JUNE2012)
19. What are the methods for Manufacture of precast concrete elements (or) types of
pre fabrication? (MAY/JUNE 2013)
20. Write short note on Production process
21. Define the term Off-site fabrication
22. List out the limitations of pre-fabrication?
PART – B
PART – B
1. Classify the structure of building based on the load distribution and briefly explain
the different types of such prefabricated building MAY/JUNE 2012) &MAY/JUNE
2013
2. Explain the methods of construction of roof and floor slab. Also explain the
precautions taken during the manufacturing process. (MAY/JUNE 2012)&
(NOV/DEC2013)
3. What is the necessity of providing shear walls in the precast structures? Also discuss
the different types of shear walls (MAY/JUNE 2009)
4. Write briefly about types of wall panels
5. Write briefly about precast concrete columns
6. Write about the structural behavior of precast structure
7. Write briefly large panel construction with neat sketches?
8. Explain the merits and demerits of large panel constructions.
9. Explain the behavior of prefabricated roofs and floor slabs.
10. Differentiate the behavior of frame and large panel construction in precast structures.
11. Discuss about behavior of columns in prefabricated structures.
PART-A
PART-B
PART-B
PART-A
1. What is progressive collapse? (NOV/DEC 2012)& NOV/DEC 2013
2. Define Degree of Progressivity?
3. What are the approaches to avoid progressive collapse?
4. What are the special requirements for building in High Seismic Zones?
5. What are provisions made in a Prefabricated R C floors in a cyclone prone zone?
6. What is strong column weak beam concept?
7. List the possible abnormal effects for prefabricated buildings.
8. Give the formula for design temperature change.
9. How are cyclones formed?
10. What are the different types of seismic waves?
11. Explain equivalent design loads.
12. Explain the importance factor and response reduction factor used in static analysis for
the calculation of design seismic force.
PART-B
1. Mention in detail the codal provision for considering the effect of earthquake and
cyclones. (MAY/JUNE 2012)
2. Explain strong column and weak beam(MAY/JUNE 2012) (MAY/JUNE 2013)
3. When a progressive collapse does occur? Why is it very critical to avoid progressive
collapse of structures? (MAY/JUNE 2009)
4. Explain the procedure for calculating equivalent design loads when the structure is
subjected to earthquake loading MAY/JUNE 2009)& (NOV/DEC2013) (MAY/JUNE
2013
5. What are the methods to avoid the progressive collapse? Explain each briefly?
(MAY/JUNE 2009)& (NOV/DEC2013)
6. Discuss the codal provisions for the design of prefabricated elements subjected
to abnormal effects.
7. How are explosive loads different from loads typically used in building design?
www.Technical4u.com
www.Technical4u.com