06 MRP Tables (Excel)
06 MRP Tables (Excel)
LEVEL 1 ITEM A
Lot Sizing = LFL LT = 2 Weeks Safety Stock = 20
PERIOD 1 2 3 4 5 6 7
Gross Requirements 0 0 0 160 0 220 0
Scheduled Receipts 0 0 0 0 0 0 0
Planned Order Receipts 0 0 0 150 0 220 0
Available Balance 30 30 30 30 20 20 20 20
Planned Order Releases 150 220
LEVEL 1 ITEM B
Lot Sizing = >180 LT = 1 Safety Stock = 0
PERIOD 1 2 3 4 5 6 7
Gross Requirements 0 0 0 160 120 315 0
Scheduled Receipts
Planned Order Receipts 0 0 0 180 180 235
Available Balance 0 0 0 0 20 80 0
Planned Order Releases 180 180 235
LEVEL 1 ITEM C
Lot Sizing = 40multi. LT = 1 Safety Stock = 20
PERIOD 1 2 3 4 5 6 7 8 9 10
Gross Requirements 0 0 0 0 360 285 0
Scheduled Receipts 40 0 0 0 0 0 0
Planned Order Receipts 320 320
Available Balance 20 60 60 60 60 20 55
Planned Order Releases 320 320
LEVEL 2 ITEM D
Lot Sizing = 120multi. LT = 1 Safety Stock = 0
PERIOD 1 2 3 4 5 6 7 8 9 10
Gross Requirements 0 300 0 1400 960 0 0
Scheduled Receipts - - - - - - -
Planned Order Receipts 0 360 0 1320 960 0 0
Available Balance 50 110 30 30
Planned Order Releases 360 1320 960
LEVEL 2 ITEM
Lot Sizing = LT = Safety Stock =
PERIOD 1 2 3 4 5 6 7 8 9 10
Gross Requirements
Scheduled Receipts
Planned Order Receipts
Available Balance
Planned Order Releases
LEVEL ITEM
Lot Sizing = LT = Safety Stock =
PERIOD 1 2 3 4 5 6 7 8 9 10
Gross Requirements
Scheduled Receipts
Planned Order Receipts
Available Balance
Planned Order Releases
LEVEL ITEM
Lot Sizing = LT = Safety Stock =
PERIOD 1 2 3 4 5 6 7 8 9 10
Gross Requirements
Scheduled Receipts
Planned Order Receipts
Available Balance
Planned Order Releases
*2P1
*2P1 + 1P2
3*p2
*2A+3*C