Quantity Estimation OHSR
Quantity Estimation OHSR
PCC
Concrete (M-25)
PCC
S.N Item CSR Item no. CSr(2010) Current Rate of Estimated Units Cost of
o base rate, sanctioned activity quantities Activities, Rs
Rs premium at
as per quoted
11/12/201 premium,
3,% Rs
1 RCC Work 10.22, providing cement concrete M-25 hand 3980.97 28 5095.51 3.773 cum 19225.36
mixed excluding rebar centring and
shuttering
10.46, extra for mechanical mixer used by 48 18 56.64 3.773 cum 213.71
contractor at his own cost
10.47, extra for vibrator used by contractor at 160 18 188.80 3.773 cum 712.35
his own cost
2 Reinforcin 18.18, CTD/TMT bars of FE 500D grade as 5166.94 16 5993.65 2.72 Qty. 16302.7
g Steel per Is 1786 Latest for RCC work where not
include in complete rate of RCC including
bending, placing in position complete
3 PCC 10.12, 150 mm soffit of beams, footing 330.21 26 416.06 1.416 cum 589.14
edges
Total of all activities 34043.26
Adding unforeseen/ mislanious item @ 5% 1852.16
Grand Total 35895.42 =
35900 say
Total amount difference = Rs. 35900-/- (Thirty five thousand nine hundred only)