Distribution Transformer Main Handbook PDF
Distribution Transformer Main Handbook PDF
HANDBOOK
Copyright © 2009
International Copper Association Southeast Asia Ltd
According to our studies (“Global energy savings potential from high efficiency
distribution transformers”, ECI 2004) technical energy losses in all of the world’s
electrical distribution networks are at the level of one thousand TWh. About 30% of
these losses occur in distribution transformers which are one of the two largest loss
making components in electricity networks.
As already stated, distribution transformers can bring economic benefits to users but
also environmental benefits for the society. The economic benefits will not always
remain in the investors’ hands as energy regulators may try to interfere in the
balance of capital and operating cost of distribution companies in order to protect
customers against rapid price increases. The customers will pay the cost of losses
for the entire transformer life, but will not see any rapid change in their electricity
bill.
A good practice, in the purchase decision criteria, is to perform a lifetime cost
analysis based on the capitalization formula. The relative data for this formula is:
energy prices projections, interest rates, transformer lifetime, transformer loading
and anticipated change in future loading. The other side of the equation presents the
transformer price and its dependence on the level of rated losses.
The power distribution systems in the urban areas of these LMS countries, however,
do not have the same level of development. It is widely acknowledged that
harmonisation in the development of power distribution systems can benefit these
countries and accelerate their economic growth.
Building on the success of the first MOU, ICASEA and MEA inked a second MOU
to continue their strategic partnership in conducting further studies and facilitating
programmes as outlined in phase 2 of the road map and action plan. This impetus is
to enable the LMS countries to make further progress towards harmonisation and
the realisation of the objectives as set out in the MOU with all the power partners.
The study of power distribution systems in the LMS countries under the first MOU
had revealed that there are many differences in the power distribution systems in
this region. The objective of this second MOU was to narrow down the differences
in six key areas and enable the LMS countries to move towards greater
harmonization of their power distribution systems.
Preface|
Loss in the Power Distribution System is a common and
pressing concern expressed by Utilities in the LMS. Reducing
loss is the priority given the energy shortage arising from rapid
economic growth and high oil prices.
A Regional Loss Reduction Workshop for LMS Utilities was held in Phnom Penh,
Cambodia on 18 & 19 March 2008. It concluded with a consensus to, amongst
other areas of collaboration, reduce losses in the Power Distribution Systems of
EDC, EDL, HCMC PC and HNPC by harmonising technical specifications and
developing a best practices handbook for energy efficient equipment based on
international standards.
The views of and input from participating Utilities were crucial in the development
of technical specifications for the harmonisation of power equipment in the LMS.
Only with acceptance and implementation of the technical specifications can LMS
Utilities reduce losses associated with inefficient power equipment. Hence, a 6-
member Technical Working Group (TWG) comprising a senior technical
representative from each Utility and ICASEA was formed to participate and
contribute in discussions and meetings.
The objective of the TWG was to start with the development of technical
specifications to harmonise low loss power transformers in the LMS. This step-by-
step approach was to enable the participating Utilities to review and evaluate the
result of this Technical Working Group before collectively moving to the next step
of harmonising other equipment.
This handbook was developed to help LMS Utilities implement low loss
transformers. Reduction will only come when the minimum performance
guidelines are followed and implemented by all associated with the design of the
electricity grid, specifying the standards of equipment for procurement and
subsequently operating or maintaining them.
Chairman
Mr.Surapon Soponkanaporn
Director of Research and Development Department, MEA
Electricite Du Cambodge (EDC), Cambodia
Mr. Lim Sisophuon
Deputy Chief, Dispatching Control Centre
Chapter 2
Bidding Evaluation
1. Introduction
2. Objective
3. Formula Analysis
4. How to Evaluate The Best Choice
5. Excess Losses and Penalty
6. The Low Loss Limitation Table
7. Conclusion
8. Appendices
Chapter 3
Transformer Production Inspection
1. Introduction
2. Objective
3. Inspection committee management
4. Inspection Process
5. Conclusion
Chapter 4
Contract Acceptance
1. Introduction
2. Objective
3. Acceptance Committee Management
4. Acceptance Process
5. Conclusion
Chapter 5
Installation and Operation
1. Introduction
2. Objective
3. Construction Standard
4. Loading Guide
5. Conclusion
Chapter 6
Maintenance and Asset Management
1. Introduction
2. Transformer Load Monitoring (TLM)
3. Maintenance and Inspection
4. Conclusion
Figures
Figure 1: Expenses generated by transformer price and cost of electricity losses
Figure 2: Calculation of the present value of no-load loss
Figure 3: Calculation of the present value of no-load loss in actual costs
Figure 4: Calculation of the present value of load loss
Figure 5: Calculation of the present value of load loss in actual costs
Figure 6: Evaluation formula analysis
Figure 7: Production Process Flow
Figure 8: Silicon Steel Core Loss Curve
Figure 9: Test circuit & Apparatus Configuration for No-load Loss Measurement
Figure 10: Test Circuit & Apparatus Configuration for Load Loss Measurement
Figure 11: Punch List Form
Figure 12: List of approval drawings
Figure 13: Sample Drawing of Technical and Guaranteed Data
Figure 14: Supplier’s routine test report
Figure 15: Acceptance routine test report
Figure 16: Penalty Calculation without raising the Guarantee Value
Figure 17: Penalty Calculation with Raising the Guarantee Values
Figure 18: Construction drawing for transformer installation (single concrete pole)
Figure 19: Bill of material for transformer installation (single concrete pole)
Figure 20: Construction drawing for transformer installation (platform)
Figure 21: Bill of material for transformer installation (platform)
Figure 22: Transformer load monitoring (TLM) system configuration
Tables
Table 1: The low loss limitation of no-load & load loss for each transformer rating
Table 2: Table of power efficiency for low losses transformer
Table 3: Example of standard loss transformers
Table 4: Temperature condition of transformer
Table 5: Minimum permissible insulation resistance measurement
Chapter 1
Preparation of National Normative Technical
Specification of Distribution Transformer
1. Introduction
This is the first normative specification for distribution transformers. It is prepared
for the Lower Mekong Sub-region (LMS) utilities which are: Electricité du
Cambodge (EDC) Cambodia, Electricité du Laos (EDL), Lao People’s Democratic
Republic, Hanoi Power Company (HNPC), Ho Chi Minh City Power Company
(HCMCPC) Vietnam, and the Metropolitan Electricity Authority (MEA), Thailand.
The specifications refer to the latest edition of international and national standards.
Single-phase, three-phase and oil-immersed transformers are covered in the
discussion. The scope also includes transformers with maximum voltages of 36 kV,
off-circuit tap changing, frequency of 50 Hz and those of neutral solidly grounded at
the distribution substation and as well as outdoor application.
2. Objective
The Primary goal is to help to reduce losses caused by the ineffective use of
transformers, and minimize the need for new investment, through teaching the
utilities' about loss reduction programs and minimizing negative environmental
impact on our tomorrow.
The secondary goals are to: encourage greater energy efficiency in low loss energy
consuming transformers, create new national standards, start cost effective savings
programs in both utilities and customers, reduce losses from utility-owned
transformers and minimize life cycle costs. In addition, this will provide not only
more energy, but also decrease the investment cost of constructing new distribution
substations, while meeting the customers demand.
1
3. Principle Specification
Scope: This specification is created for power utility companies in LMS.
Transformers shall be connected to the system with neutral solidly grounded at the
distribution substations and fault level values in normal distribution status between
20kA and 25kA.
Site and Service Condition: LMS utilities operate in a tropical climate. The altitude
ranges from 0 meters to 1,800 meters above sea level, ambient temperature ranges
from 30°C to 45°C and relative humidity measures mostly 100%.
Test, Inspection and Test Report: There will be two main test reports, specifically
Type Test and Routine Test reports. Because the transformer is a very critical and
expensive piece of equipment, the type test report is a key source of information for
purchase assessment and decision.
Type Test contains data that validate factors such as design, raw material,
workmanship and quality control during the manufacturing process are well within
standard limits. The Routine Test certifies that all units pass limited values
according to the reference standards before installation for service. The Utility
reserves the right to send representatives to invigilate all required tests on the
manufacturer’s site. Thus, sampling of the first batch of the transformers lies in the
responsibility of the Utility’s representatives.
Drawings and Instructions: The supplier shall furnish six copies of all significant
details of the transformer to the Utility for response in approval within a stipulated
timeframe.
Ratings and Features: The major characteristic of the transformer must be properly
specified, such as suggested in the following:
Frequency 50 Hz
2
Cooling method ONAN
Insulation level
General Requirements
The transformer shall be self-cooled and/or designed with sealed-tank to ensure that
forced cooling is not required. The transformer installation methods such as single
concrete pole or platform concrete pole shall also be included. To protect the
transformer from damage caused by lightning, it will be the most efficient and
practical to install three lightning arresters on the transformer tank cover.
The lightning arrester shall be of the distribution class with a ground lead
disconnector, gapless or gapped with metal oxide as main elements.
The gaskets shall be specified to withstand hot oil of extremely high temperatures
and have a life span of more than 20 years.
One of the plans included to reduce system losses, is to up-rate the distribution
voltage; the dual voltage switch type shall be required such as 12/24 kV,
3
The kVA rating value should be visibly specified and easy to locate for field
workers. The information regarding the centre of gravity (CG) of the transformer is
essential for the installation and to improve safety for the field workers.
The concrete poles need to be designed to withstand the bending moment which is
calculated by accounting for the weight of the transformer, associated equipment,
cables, and wind speed. Hence, all transformers are recommended to have weight
limits. Transformers installed in close proximity to public facilities such as
hospitals, schools, etc shall also be designed to keep noise level within 58 to 68
decibels. Transformers installed near hospitals, schools and important places should
also be designed to generate audible noise within the limit of 58 to 68 decibels.
The material for fabricating the tank side walls and bottom shall be corrosion
resistant. Rust-preventive finishing shall be strongly recommended for units with
more than 20 years of service life. The paint coat shall depend on utilities’
requirement in preferred colours.
Core
It is necessary to mention the quality of the core material, such as high permeability
silicon steel, because no-load loss is mainly caused by the core material. The core
construction shall be firmly fixed in the tank and designed to avoid the occurrence
of loosened core strips due to vibration from road traffic. Adequate cooling
facilities shall also be provided at the oil ducts.
Windings
The winding or coil shall be made of copper for better performance based on
technical and economic comparisons. To cater to the physical characteristic, the
winding shall be designed to withstand thermal and mechanical effects caused by
external short circuits. The coil clamping arrangement and clamping rings shall be
designed to withstand force due to short circuit. To cater to the electrical
characteristic, the winding shall be designed and assembled to handle temperature
increase specified in the tender specification. The insulation of winding and
connections shall not be likely to soften, loose, shrink or collapse during service.
Insulating Oil
As mineral oil is used as the insulation and cooling mechanism; it should be well
filtered and tested to meet the dielectric strength (which is not less than 30kV)
before filling in the transformer tank. The insulating oil dielectric taken from a new
transformer shall not be less than 26 kV as tested by the method specified by ASTM
D877.
4
Bushings and Terminals
The requirements for bushings and terminals should be specified for different
applications such as platform transformer or pole mounted transformer to facilitate
installation, monitoring and maintenance. To maintain the current integrity
throughout the equipment’s useful lifecycle, the connectors shall be made with
solderless tin-plated copper; two belleville spring washer, coned-disk types shall be
supplied to provide adequate pressure on the conductor during thermal-cycling. The
size of the terminals or connectors, both high voltage and low voltage, shall be
subjected to the transformer capacity. The bushing cover shall be made of ultra-
violet radiation resistant and track resistant plastic or rubber to protect equipment
from impairments caused by animals such as birds, squirrels and snakes, etc.
Accessory Equipment
The transformers will be equipped with standard accessories, at least with lifting
lugs, tap changer, manual pressure relief fitting, nameplate, tank grounding pad or
stud, etc. Other accessories will be also specified depending on the size and
application.
Typically, the transformer price depends on core and winding loss i.e. high loss
transformers have a lower cost, and the low loss transformer a higher one.
Thus, Utilities work out an “evaluation formula” which takes into
consideration many factors such as: transformer service life, load factor,
operation and maintenance cost, interest rate and inflation rate, etc. Each
utility should compute the cost estimate based on updated data. This shall
eventually be used in the bid comparison for the evaluation of unit costs and
losses. The following is an example of cost evaluation.
A = B + XC + YD
Where
A = Evaluated cost of transformer in any currency
B = Unit cost of transformer converted into US Dollars according to the
evaluation clause specified in the bid condition
C = No-load loss at room temperature not more than 30°C in kW
D = Load loss in kW
X = Constant value for No-load condition
Y = Constant value for Loading condition
The excess loss and penalty will concentrate on transformer losses which are higher
than guaranteed no-load and load losses including allowable tolerances stated in the
reference standards. It will be divided into the following two cases:
5
a. The individual transformer loss is higher than tolerance: Individual transformer
with losses beyond the limits will be rejected unless the supplier agrees to
increase the guaranteed value of average losses of all transformers,
compensated at 1.5 times (arbitrary value) of the evaluation formula.
b. The total number of transformers: In the event that the supplier’s report shows
that the no-load and load loss values conform to the guaranteed values within
the tolerance limit, the utility shall conduct sampling on the transformers for
their individual loss measurement (i.e. the number of transformers depends on
utilities’ facility, but normally 5% of the contracted quantity or at least one unit
for small quantity order).
If the average values of no-load loss and load losses are higher than average
losses from the manufacturer test report by 2.5% (arbitrary value), the
manufacturer measured value will be adjusted by the ratio of difference
between both sets of measurements, and use the adjusted losses for the
calculation of loss compensation. Otherwise the losses from the manufacturer’s
report will be used.
Consideration shall be given to facilitate convenient clearing from the port customs.
The transformers shall be shipped oil-ed with the serial number properly indicated
in the invoice. All spare parts shall be delivered with the first shipment to ensure
that spares are available in the event of need. . Equipment or instruments packed in
the cartons shall be firmly attached on pallets for easy handling.
In the event of breakdown within the period of warranty, the manufacturer shall
promptly investigate, repair or replace the unit. All replacement shall be made with
60 days from the first notice, or risk forfeiting equipment performance and security.
This section discusses about the additional specifications specially collated for
Electricité du Cambodge of Cambodia (EDC).
6
b. The lightning arresters should be specified to be installed on the
transformer tank’s cover to effectively protect the transformer itself. The
lightning arrester ground lead isolator operation test is required to be
submitted with the quotation.
c. The transformers shall not produce audible noise exceeding the specified
limits due to environmental disturbance, especially when installed near
hospitals, temples and schools, etc.
It has been reported that the EDC’s total losses are approximately of 10% of
those in the year 2007. The utility has begun many activities to aid in reducing
losses, including hosting conferences which invited papers and research from
different experienced utilities. EDC plans to reduce the loss to 7% by the year
2012. One of the programs suggested in this Handbook is to acquire and/or
increase the use of low loss transformers in EDC’s system.
It is better to start by using an evaluation formula for a specific time period, for
example 5 years. After this period, the EDC will have learned about the
advanced transformer technology efficiency improvement by compiling
records of the best values of no-load loss and load loss for each rating and
applying it to the guaranteed low loss transformer table, included in the
transformer specification for implementation.
A = B +7,121C +2,939D
Where
A = Evaluated cost of transformer in US Dollars.
B = Unit cost of transformer converted into US Dollars according to the
evaluation clause specified in the bid condition.
C = No-load loss at room temperature not more than 30°C in kW.
b. No-load Loss: Typically, it is called core loss or iron loss. The no-load
loss is a constant value varying for each designed transformer rating and
is present no matter if the load is connected or not.
There are two types of core losses: hysteresis loss and eddy current loss.
The core material development progressed from hot-rolled steel to the
cold-rolled grain oriented silicon steels (CGO) to reduce the core losses. It
has since advanced to the new technology of high permeability grain
oriented steel (HiB) that controls the domains of the iron crystals by laser
etching.
7
number of manufacturers and sophisticated production lines which need
highly skilled workers and non-typical instruments. Nowadays, the low
loss transformers are more often used in large cities in order to reduce the
total system losses and to avoid construction of new substations in
expensive locations in attractive city centres. HiB grain oriented steels
together with experienced design, advanced core cutting and slitting
machine, high skilled fabrication and assembly, may exhibit transformer
efficiencies of up to 99.7%.
c. Load Loss: When the load is connected, the transformer will supply the
power to that load and produce resistive losses in windings as well as
eddy current losses in windings, structural steelwork and tank. These load
losses increase proportionally to the square of the load current. To reduce
the load losses, the designer may increase the cross section of the
windings. The designer must keep in mind, however, how it will affect
flux density and core losses.
Most of the transformer windings will be made of copper due to its high
conductivity and subsequent effect on energy efficiency, size reduction
and energy saving. The technology of the copper windings is remarkably
developed to withstand the short circuit strength, to prolong the service
life and safety by using copper foil instead of windings which can also
reduce eddy current loss from non-linear loads. There is another solution
to improve the load loss reduction by upgrading the copper windings to
super-conducting windings, but unfortunately, this new technology of
super-conducting transformers is not ready for market deployment due to
a number of technical obstacles and high construction cost.
Transformer losses are one of the main losses in the distribution system.
However, more research is necessary to predict and design a typical model that
takes into account items such as: the detailed loading patterns, types of
transformer, operation, and loading guides. When achieved, this will aid in
achieving: energy cost savings, greenhouse gas reduction, CO2 reduction and
increased ability for emissions trading. Nowadays, the trend of both the
8
manufacturers and the utilities is to try to meet high efficiency transformer
performance while maximizing production capability and minimizing
investment costs.
TCCloss = Eloss * C * (1 + r) ⁿ - 1/ r * (1 + r) ⁿ
Where:
TCCloss = Total Capitalized Cost of the losses
C = the estimated average electricity cost per kWh
r = the cost of capital
n = the life time of the transformer in years
ELoss = Total energy loss
These environmental and health costs originate from the various types of
emissions resulting from the combustion of fossil fuels. Apart from CO2,
the main offenders are SO2 and NOx which contribute to the acidification
of the environment. According to the Kyoto Protocol, the use of low loss
energy transformers can show a positive effect on carbon credits and can
balance the global warming effect. This will support the country’s policy
of the installation of more clean energy systems such as solar energy,
wind turbines, energy from waste energy, etc.
9
5. Electricité du Laos - Additional Specifications
This section discusses about the additional specifications specially collated for
Electricité du Laos of Lao PDR (EDL).
It has been reported that the EDL’s total losses are approximately 17.5% of
those in the year 2007. The utility has begun many activities to aid in reducing
losses, including hosting conferences which invited papers and research from
different experienced utilities. EDL plans to reduce the total system losses. One
of the programs suggested in this Handbook is to acquire and/or increase the
use of low loss transformers in EDL’s system.
It is better to start by using an evaluation formula for a specific time period, for
example 5 years. After this period, EDC will have learned about the advanced
transformer technology efficiency improvement by compiling records of the
best values of no-load loss and load loss for each rating and applying it to the
guaranteed low loss transformer table, included in the transformer specification
for implementation.
A = B +5,000C +3,500D
Where
A = Evaluated cost of transformer in US Dollars.
B = Unit cost of transformer converted to US Dollars according to the
evaluation clause specified in the bid condition.
C = No-load loss at room temperature not more than 30°C in kW.
10
b. No-load Loss: Typically, it is called core loss or iron loss. The no-load
loss is a constant value varying for each designed transformer rating and
is present no matter if the load is connected or not.
There are two types of core losses: hysteresis loss and eddy current loss.
The core material development progressed from hot-rolled steel to the
cold-rolled grain oriented silicon steels (CGO) to reduce the core losses. It
has advanced to the new technology of high permeability grain oriented
steel (HiB) that controls the domains of the iron crystals by laser etching.
c. Load Loss: When the load is connected, the transformer will supply the
power to that load and produce resistive losses in windings as well as
eddy current losses in windings, structural steelwork and tank. These load
losses increase proportionally to the square of the load current. To reduce
the load losses, the designer may increase the cross section of the
windings. He must keep in mind, however, how it will affect flux density
and core losses.
Most of the transformer windings will be made of copper due to its high
conductivity and subsequent effect on energy efficiency, size reduction
and energy savings. The technology of the copper windings is remarkably
developed to withstand the short circuit strength, to prolong the service
life and safety by using copper foil instead of windings which can also
reduce eddy current loss from non-linear loads. There is another solution
to improve the load loss reduction by upgrading the copper windings to
super-conducting windings, but unfortunately, this new technology of
super-conducting transformers is not ready for market deployment due to
a number of technical obstacles and high construction cost.
11
harmonic effect, the utility must set harmonic restrictions both voltage
and current generated to the industries which are the major contributors to
power distortion in the distribution system.
Transformer losses are one of the main losses in the distribution system.
However, more research is necessary to predict and design a typical model that
takes into account items such as: the detailed loading patterns, types of
transformer, operation, and loading guides. When obtained, this will aid in
achieving: energy cost savings, greenhouse gas reduction, CO2 reduction and
increased ability for emissions trading. Nowadays, the trend of both the
manufacturers and the utilities is to try to meet high efficiency transformer
performance while maximizing production capability and minimizing
investment costs.
TCCloss = Eloss * C * (1 + r) ⁿ - 1/ r * (1 + r) ⁿ
Where:
TCCloss = Total Capitalized Cost of the losses
C = the estimated average cost per kWh
r = the cost of capital
n = the life time of the transformer in years
ELoss = Total energy loss
These environmental and health costs originate from the various types of
emissions resulting from the combustion of fossil fuels. Apart from CO2,
12
the main offenders are SO2 and NOx which contribute to the acidification
of the environment. According to the Kyoto Protocol, the use of low loss
energy transformers can show positive effect on carbon credits and can
balance the global warming effect. This will support the country’s policy
of the installation of more clean energy systems such as solar energy,
wind turbines, energy from waste energy, etc.
This section discusses about the additional specifications specially collated for Ho
Chi Minh City Power Company (HCMCPC).
It has been reported that the HCMC PC’s total losses are approximately 7.07%
of those in 2007. The utility has begun many activities to aid in reducing
losses, including hosting conferences which invited papers and research from
different experienced utilities. HCMCPC plans to reduce the total system
losses. One of the programs suggested in this Handbook is to acquire and/or
increase the use of low loss transformers in HCMC PC’s system.
It is better to start by using an evaluation formula for a specific time period, for
example 5 years. After this period, EDC will have learned about the advanced
transformer technology efficiency improvement by compiling records of the
best values of no-load loss and load loss for each rating and applying it to the
guaranteed low loss transformer table, included in the transformer specification
for implementation.
13
purchase price, no-load loss and load loss. For the purpose of bid
comparison, the transformer unit cost and losses shall be evaluated to
obtain the evaluated transformer cost according to the formula below:
A = B +4,080C +2,220D
Where
A = Evaluated cost of transformer in US Dollars.
B = Unit cost of transformer converted in US Dollars according to
the evaluation clause specified in the bid condition.
C = No-load loss at room temperature not more than 30°C in kW.
b. No-load Loss: Typically, it is called core loss or iron loss. The no-load
loss is a constant value varying for each designed transformer rating and
is present no matter if the load is connected or not. There are two types of
core losses: hysteresis loss and eddy current loss.
c. Load Loss: When the load is connected, the transformer will supply the
power to that load and produce resistive losses in windings as well as
eddy current losses in windings, structural steelwork and tank. These load
losses increase proportionally to the square of the load current. To reduce
the load losses, the designer may increase the cross section of the
windings. He must keep in mind, however, how it will affect flux density
and core losses.
Most of the transformer windings will be made of copper due to its high
conductivity and subsequent effect on energy efficiency, size reduction
and energy saving. The technology of the copper windings is remarkably
developed to withstand the short circuit strength, to prolong the service
life and safety by using copper foil instead of windings which can also
reduce eddy current loss from non-linear loads. There is another solution
to improve the load loss reduction by upgrading the copper windings to
super-conducting windings, but unfortunately, this new technology of
super-conducting transformers is not ready for market deployment due to
14
a number of technical obstacles and high construction cost.
Transformer losses are one of the main losses in the distribution system.
However, more cases or research to predict and design a typical model taking
into account the detailed loading patterns, types of transformer, operation, and
loading guides are needed. This will result in energy cost savings, greenhouse
gas reduction, CO2 reduction and emission trading. Nowadays, the trend of
both the manufacturer and the utility is to try to meet high efficiency
transformer performance while maximizing production capability and the
minimizing the investment cost.
TCCloss = Eloss * C * (1 + r) ⁿ - 1/ r * (1 + r) ⁿ
Where:
15
TCCloss = Total Capitalized Cost of the losses
C = the estimated average cost per kWh
r = the cost of capital
n = the life time of the transformer in years
ELoss = Total energy loss
These environmental and health costs originate from the various types of
emissions resulting from the combustion of fossil fuels. Apart from CO2,
the main offenders are SO2 and NOx which contribute to the acidification
of the environment. According to the Kyoto Protocol, the use of low loss
energy transformers can show positive effect on carbon credits and can
balance the global warming effect. This will support the country’s policy
of the installation of more clean energy systems such as solar energy,
wind turbines, energy from waste energy, etc.
This section discusses the additional specifications specially collated for Hanoi
Power Company, Vietnam (HNPC).
It has been reported that the HNPC’s total losses are approximately of 8.85%
of those in the year 2007. The utility has begun many activities to aid in
reducing losses, including hosting conferences which invited papers and
research from different experienced utilities. HNPC plans to reduce the loss to
7% by the year 2012. One of the programs suggested in this Handbook is to
16
acquire and/or increase the use of low loss transformers in HNPC’s s system.
It is better to start by using an evaluation formula for a specific time period, for
example 5 years. After this period, the HNPC’s will have learned about the
advanced transformer technology efficiency improvement by compiling
records of the best values of no-load loss and load loss for each rating and
applying it to the guaranteed low loss transformer table, included in the
transformer specification for implementation
a. In the basic loss evaluation process, three transformer figures are purchase
price, no-load loss and load loss. For the purpose of bid comparison, the
transformer unit cost and losses shall be evaluated to get the transformer
evaluated cost according to the formula below:
A = B +6,300C +1,300D
Where
A = Evaluated cost of transformer in US Dollars.
B = Unit cost of transformer converted in US Dollars according to the
evaluation clause specified in the bid condition.
C = No-load loss at room temperature not more than 30°C in kW.
b. No-load Loss: Typically, it is called core loss or iron loss. The no-load
loss is a constant value varying for each designed transformer rating and
is present no matter if the load is connected or not. There are two types of
core losses: hysteresis loss and eddy current loss.
c. Load Loss: When the load is connected, the transformer will supply the
power to that load and produce resistive losses in windings as well as
eddy current losses in windings, structural steelwork and tank. These load
losses increase proportionally to the square of the load current. To reduce
the load losses, the designer may increase the cross section of the
windings. He must keep in mind, however, how it will affect flux density
and core losses.
17
Most of the transformer windings will be made of copper due to its high
conductivity and subsequent effect on energy efficiency, size reduction
and energy saving. The technology of the copper windings is remarkably
developed to withstand the short circuit strength, to prolong the service
life and safety by using copper foil instead of windings which can also
reduce eddy current loss from non-linear loads. There is another solution
to improve the load loss reduction by upgrading the copper windings to
super-conducting windings, but unfortunately, this new technology of
super-conducting transformers is not ready for market deployment due to
a number of technical obstacles and high construction cost.
Transformer losses are one of the main losses in the distribution system.
However, more cases or research to predict and design a typical model taking
into account the detailed loading patterns, types of transformer, operation, and
loading guides are needed. This will result in energy cost savings, greenhouse
gas reduction, CO2 reduction and emission trading. Nowadays, the trend of
both the manufacturer and the utility is to try to meet high efficiency
transformer performance while maximizing production capability and the
minimizing the investment cost.
18
The real power delivered to the load is: PL watts
The No-load core loss is: PC watts
The Load Loss is: PW watts
These environmental and health costs originate from the various types of
emissions resulting from the combustion of fossil fuels. Apart from CO2,
the main offenders are SO2 and NOx which contribute to the acidification
of the environment. According to the Kyoto Protocol, the use of low loss
energy transformers can show positive effect on carbon credits and can
balance the global warming effect. This will support the country’s policy
of the installation of more clean energy systems such as solar energy,
wind turbines, energy from waste energy, etc.
19
8. References
• Energy saving in industrial distribution transformers transformer
losses, May 2002, W.T.J. Hulshorst and J.F. Groeman (KEMA)
• The Potential for Global Energy Savings from High Efficiency
Distribution Transformers, February, 2005, (Roman Targosz, editor ;
Main authors and reviewers: Ronnie Belmans, Jan Declercq, Hans de
Keulenaer, Katsuaki Furuya, Mayur Karmarkar, Manuel Martinez,
Mike McDermott, Ivo Pinkiewicz)
• Technical Report, Distribution Transformers : Proposal to Increase
MEPS Levels, October 2007, T R Blackburn
20
Chapter 2
Bidding Evaluation
1. Introduction
This chapter is to guide and assist the utility to learn about the solution, and from
what criteria it is derived. Only distribution transformers will be discussed in this
handbook. Therefore, there will three factors: purchase price of the transformer,
load losses and no-load losses which shall be considered.
The lowest evaluated cost including losses will be the criteria utilized to choose the
initial proposal that the utility will study before making a contract. It will affect the
utility investment cost, paying a little more for low loss transformers, but in return it
can save more money than the cumulated value of losses during transformer
operation. The penalty values should be specified as well in the bid documents.
2. Objective
The trade off between the transformer’s price and the losses of the transformer is
simplified in the tender specification. It is accomplished by adding the evaluation
formula where the purchase cost minus the loss, which reflects the utilities’ true
investment cost.
The manufacturers should offer their best design capability and highest quality of
raw materials and workmanship in order to convince the utilities to invest in energy
efficient transformers.
3. Formula Analysis
There are many factors to be taken into account in the evaluation formula which are:
no-load loss, load loss, interest rate, inflation rate, electricity unit cost, operation &
maintenance cost and transformer service life. All these values differ due to
fluctuations in the economy and government policies which each utility operates in.
21
3.1. Interest Rate
Interest rates are an important part of a loan; they help determine its total cost.
Each utility has to apply for a loan in both local and foreign countries. It is
typical that the local loan will be less advantageous in terms of interest rate,
grace period and repayment terms than a foreign one. It is recommended that
one ask for all of this information, from the Finance Department or the
Department which responds to the loan application.
The purpose of this factor is to show the effect of the inflation rate on the real
value of the money. In fact, a substantial increase in the price of transformers
is related to an increase in the inflation rate which means a decrease in the
value of money. As inflation rate increases, the price of goods increases. As
with the interest rate analysis, the finance department will analyze and provide
the real figures. These figures will differ from country to country.
Some countries have divided the generation utility and distribution utility; in
this case it is common for distribution utility to get the average electricity unit
purchased from the generation utility. But some countries have an organization
who owns both power generation and distribution. In this case, the electricity
unit purchase will be calculated on the basis of the investment cost of
electricity unit production at the point of the terminal station where electricity
is sold to customers.
22
This is understood as the average service life of the transformer in number of
years. Some transformers may still be in service after 25 years, while others
may only reach the age of 15. After discussions with reputable transformer
manufacturers, all confirm that the recommend service life of the transformers
is typically to be 20 years for regular loading according to the international
standards.
The evaluation formula analysis starts from the no-load loss calculation. Once
the transformer is energized, the utility has to pay both the transformer cost and
the cost of electricity losses or energy losses consists of no-load loss (core loss)
and load loss (winding loss) throughout the life of the transformer as shown in
Figure 1.
Price of
Transformer
Cost of
Electricity Losses
The cost of no-load loss will be generated by the transformer core which
means that once the transformer is energized, this loss is present
throughout the transformers life and calculated back to present value as
shown in Figure 2.
23
Cost of
No-Load Losses
Computation of
Present Value
Year 0
Figure 2: Calculation of the present value of no-load loss
The result is calculated from the values of criteria as shown in clause a.,
using the formula of present value and is shown in Figure 3.
Computation of
Present Value
$7,109.29/kW
Year 0
Figure 3: Calculation of the present value of no-load loss in actual costs
24
• Interest rate = 6.26%
• Inflation rate = 1.56%
• Electricity unit purchased = 0.0597 $/kWh
• O&M expenses in distribution system = 29.29 $/kW/Year
• Loss factor 0.3803 (see more detailed below)
The cost of load loss will reflect resistive losses in the windings and leads,
and losses generated by eddy currents in the windings, the structural
steelwork, and the tank, throughout the transformer life and calculated
back to present value as shown in Figure 4.
Cost of
Load Losses
Computation of
Present Value
Year 0
Figure 4: Calculation of the present value of load loss
The result is calculated from the values of criteria as shown in clause b.,
using the formula of present value and is shown in Figure 5.
Present value of Load loss expense = 2,936.95 $/kW (20 years) (see
Figure 5)
25
$228.18/kW/year
Computation of
Present Value
$2,936.95/kW
Year 0
Figure 5: Calculation of the present value of load loss in actual costs
Price of
Transformer ($)
7,109C
2,936D
26
leads to loss issues as well. In this case that typically means total losses of the
transformer. Of course, its characteristics must conform to the reference standards.
The following example will show the Least Cost Analysis for the two transformers
having ratings of 24 kV 3-phase 500 kVA capacity and conform to the same
reference standards or specification, but the transformer price, no load loss and load
loss are different as shown below.
Transformer X Transformer Y
[Low Loss] [Standard Loss]
kVA 500 500
Price($) 24,533 15,758
No load(kW) 0.67 0.97
Load loss(kW) 3.030 5.500
Evaluated cost($) 38,192 38,801
Preferred Selection
After the supplier delivers the transformers to the utility together with the routine
test report, all units of the transformers technical information will be reported,
according to the contract. The testing values of no-load loss and load loss will be
calculated and declared for each unit with its separate serial number. The acceptance
process is explained as follows:
a. Limits of tolerance:-
No-load loss: not more than +10%
No-load loss + Load loss: not more than +6%
b. The individual transformer having losses beyond the limits of tolerance will be
rejected immediately
27
c. If average losses of all transformers of the same kVA rating exceeds the
guaranteed value but remains within the limits of tolerance, the penalty will
be:
No-load loss at USD 10,697 / kW x N.
Load loss at USD 4,424 / kW x N.
Where N = Number of transformers.
In the event of negotiation and/or dispute over loss tolerance, the maximum
value of the transformer shall be used to compute tolerance limits relating to
higher guaranteed values. In this case, the supplier shall bear all penalties
rightful of total purchase made.
Table 1: The low loss limitation of no-load & load loss for each transformer rating
• All transformer losses shall be within the limits without any tolerance.
For each transformer rating, and each lot of shipment, the utility will sample
the transformers for their own loss measurement purposes, at quantity specified
by the contract. The transformers will be accepted if the measured losses for
the sample are within the limits.
28
In the event that one of the samples has loss(es) higher than the limits in Table
1, the Utility will resample the transformers from the same lot in the same
quantity as the first sampling. All transformers in that lot will be rejected, if
one of the second sample of transformers has loss(es) higher than the limits. In
case the quantity of the sample is equal to the total number of the purchase, no
second test will be performed. The utility will reject only the transformer(s)
which loss(es) is (are) over the limit.
Based on the above conditions, the supplier shall repair and replace ALL failed
units. No penalty shall be negotiated. The supplier must design and assemble
transformers with care and accuracy without further provision of tolerances.
7. Conclusion
The evaluation formula in this chapter has been well proven to be the best practice
for distribution system of the capital city with lowest loss. Many factors such as
O&M expenses, electricity unit cost, interest rate, inflation rate, etc are part of the
evaluation process though some utilities may decide to use balance emphasis on
different factors, e.g. in USA, they will use the cost of installation for generation
and transmission system; while in some European countries, only electricity unit
cost is applied for loss evaluation.
Finally, the utilities are recommended to develop their own evaluation formula by
harnessing the information in the course of making a purchase decision. The
evaluation method also reinstates the need for manufacturers to design and deliver
the most economic transformer with ideal quality standards.
29
Chapter 3
Transformer Production Inspection
1. Introduction
After the procurement contract for transformers is signed, there are several
processes to verify that the equipment fulfils the specifications and conditions
specified in the agreement.
Representatives from the utilities, who are likely appointed based on experience in
various aspects such as specification handling, installation, testing, maintenance and
purchasing, shall inspect the manufacturing of the equipment on site.
In this chapter, only the manufacturing inspection will be discussed with reference
to a real-life example as illustration.
2. Objective
This production inspection is very important because if any process or raw material
is found non-conforming to the specification, the inspection committee shall reserve
the right to suspend the production line and resolve all issues before restarting the
production line.
This chapter details low loss verification which includes no-load loss and load loss.
A careful production inspection is fundamental to a transformer of satisfactory
quality that is operational for at least 20 years.
30
3. Inspection Committee Management
Each utility may have different practices and regulations depending on
governmental policies. This practice is used in the utility which distributes
electricity in the capital city and has a proven track record of success in the lowest
loss transformer selection and also suits this country’s economic background.
All engineers and technicians who are represented in the production inspection
committee will be given the approval drawings and related correspondence for their
references when witnessing the transformer production line and testing. The
supplier shall provide free access to the facilities where the transformers are being
manufactured and shall satisfy the representatives that the raw material and finished
transformers are in accordance with this specification and the purchase contract.
In the event of disagreement or dispute, either the contract’s details are not clear or
the supplier would like that an exception be made (for example, the value of the
guaranteed loss), these issues should be presented at a meeting with the top
management. The meeting should discuss the disadvantages and advantages to the
utility as the main focus. This convention should remain and be considered the
standard practice.
4. Inspection Process
There will be two main issues to discuss in this clause, the production process flow
of the transformer manufacturing which shows each step of production line and
inspection, and the second part which will explain some principal practical
inspection trips.
31
beginning from the incoming raw material, thru each step of production line and
inspection activities, testing facility, until packing and delivery to the customers.
32
Figure 7: Production Process Flow
For the purpose of low loss transformer verification, the production inspection
committee should scrutinize some main process concerns. Let’s start with the in-
coming material process which primarily is the silicon steel as most of the low loss
transformers shall be manufactured from high permeability grain oriented steel.
33
Figure 8: Silicon Steel Core Loss Curve
As can be seen from Figure 8: core loss can be reduced in two ways: firstly,
the standard technology of silicone steel can be upgraded to a silicone steel
core which is called the Laser –Irradiated Hi B silicone steel. Secondly, it can
be achieved via a thickness decrease, utilizing a less thick piece of silicon steel.
This will also have a lower no load loss. In the factory, the inspectors can
clearly identify Laser Hi-B silicone steel because its surface has a dotted line
where the Cold Grain Oriented silicone steel is plainly visible.
The load loss is generated from the copper windings in both high voltage and
low voltage sides. For low load loss transformers, the copper winding having a
‘high temperature class’ shall be selected in order to avoid the risk of
deformation of the enamel coat on the copper material.
Secondly, the core stacking process requires more skilled workers with many
years of experience. In this process there usually are two workers, one will
insert the silicon steel sheet while the other will compactly assemble. The fact
is that lower no loss is obtained by decreasing the gaps in each layer of the
steel sheet.
34
Thirdly, the welding of winding to make tapping and connections is also
important. Here, care must be taken in the welding quality and highest
working area cleanliness and orderliness is of utmost importance. The utility’s
report always shows the extra loss of the transformer and the failure records of
short circuit caused by the scrap in the welding process
Fourthly, there will be testing prior to the production of the core staking and
winding process. Samples of core staking with some designed turns of copper
winding assembly will be taken to be tested to verify the no load loss value. If
the value is over the guaranteed no load loss the core shall be investigated and
redesigned to meet the contract agreement. This will be done in order to
convince the inspection committees that the low loss transformers will be able
to meet the contract guarantee values.
Finally, the finished transformer is ready to undergo routine, and other special
tests required by the utility or customers. The inspection committee will
randomly test some transformers by themselves to run no-load loss and load
loss tests during routine testing. The testing circuit and apparatus configuration
for no-load loss and load loss measurement has shown in Figure 9 and 10
respectively.
Figure 9: Test circuit & Apparatus Configuration for No-load Loss Measurement
Figure 10: Test Circuit & Apparatus Configuration for Load Loss Measurement
35
a. Purpose and Test Method
No-load losses (also referred to as excitation losses, core losses and
iron losses) are a very small part of the power rating of the
transformer, usually less than 1%. Since these losses are essentially
constant over the lifetime of the transformer (do not vary with load),
they generally represent a sizable operating expense especially when
energy costs are high. Therefore, accurate measurements are
essential in order to evaluate individual transformer performance.
The no-load loss and current can be measured on one of the winding
at rated frequency and voltage on principle tapping. The remaining
winding shall be left open-circuited. Measuring no-load losses of a
transformer when subjected to a sinusoidal voltage wave form can be
achieved simply as per Figure 9. Transformers may be subjected to a
distorted sine-wave voltage. In order to achieve the required
measuring accuracy, the instrumentation used should accurately
respond to the power frequency harmonics encountered in these
measurements. Also, measured values need to be corrected to
account for the effect of the voltage harmonics on the magnetic flux
in the core and hence on both the hysteresis and eddy current loss
components of iron losses.
36
C57.12.91-1979 Standard. This is only correct for a reasonably
distorted voltage wave.
b. Reference standard
IEC publication 60076-1: Power transformer Part 1: General
ANSI C57.12.90-1999: Standard Test Code for Liquid-Immersed
Distribution, Power, and Regulating Transformers: Sub-Clause 8
d. Acceptance Criterion
The acceptance of transformer no-load loss and current shall be
lower than guarantee values or within tolerance of +15% of no-load
loss guarantee values and +30% of no-load current guarantee values.
Special precautions
i. Measurement at a lower than rated current: According to IEEE Std
C57.12.90-1993, load losses should be measured at a load current
equal to the rated current for the corresponding tapping position.
However, if it is not exactly equal to the rated current, the measured
load loss value will need to be corrected by the square of the ratio of
the rated current to the test current (average of the measured phase
current in three-phase transformers).
ii. Duration of the load loss measurement test:
37
During load loss measurement, the current in the winding increases
winding temperature and hence increases winding I2R losses. To
minimize the magnitude of this effect, it is the manufacturer’s
responsibility to keep the test time as short as possible.
iii. Optimizations of measuring range of instrumentation:
Transformer manufacturers are encouraged to use the instruments at
their optimum operating range to minimize the errors. Phase angle
corrections of voltage instrument transformers and current
instrument transformers that have magnetic core materials are
generally significantly higher when they are operated at lower than
about 70% of their rated operating voltage/current. Also, these
corrections can vary significantly with the turns-ratio setting of the
instrument transformer.
iv. Other precautions with the use of instrument transformers:
Using the proper burden, clean connections, and demagnetizing the
current transformer after every use are measures that would help
achieve a better measuring accuracy.
b. Reference standard
IEC publication 60076-1: Power transformer Part 1: General
ANSI C57.12.90-1999: Standard Test Code for Liquid-Immersed
Distribution, Power, and Regulating Transformers: Sub-Clause 9
d. Acceptance criteria
The acceptance of transformer load loss shall be lower than the guarantee
values or within tolerance of +15% of guarantee values and voltage
impedance shall be ±10% of guarantee values.
38
5. Conclusion
Some utilities may have their own inspection form or special document to process
the comments and some corrections during the inspection such as witness tests,
discussion, dimension and facilities, etc. One of the most practical forms used in the
production process inspection is called “Punch List” and shown in Figure 11. Punch
List. The inspection committee can give the notices and make pictures to compare
the status before and after modification or corrections are made on it.
39
Chapter 4
Contract Acceptance
1. Introduction
The commercial and technical conditions are all specified in the purchasing
contract. It is commonplace for utilities to make special requests in order to assure
the quality of the transformers fulfil the contract requirements. This step is also
important in that the utility must manage the delivery of the transformers as it can
delay the installation plans. This step is also important for the utility to manage
the delivery time of the transformers to avoid the delaying installation plans such
as to install the transformers before the contract can be completely settled to reach
both the utilities and supplier’ satisfaction.
The contract acceptance is difficult when the delivered transformers do not conform
to the contract specification which has many classifications such as: physical
characteristic, exceeding the guaranteed loss, etc. It is the intention of this chapter to
guide the utilities to learn and share experiences in solving these problems by
sample analysis and conclusion.
2. Objective
Experience shows that there are three main factors to discuss in the process of
transformer contract acceptance. One is a detailed specification with approval
drawings, the second is routine test reports with guaranteed loss verification and the
third is the final sampling test of the transformers before energizing and put in
service. Various scenarios are given and explained to be used as a problem solving
guide. It shows the process from top management’s policy viewpoint regarding
practical standards in the procurement system.
40
technical information will be selected from the related department which is
knowledgeable about transformer specification and testing at a minimum, as
follows:
All engineers and technicians who are represented as the contract acceptance
committee will be given the approval drawings as shown in Figure 12: List of
approval drawings and related accessories for their reference during sampling of the
delivered transformers for testing. Samples of technical and guaranteed data of the
transformer are shown in Figure 13. The supplier shall submit the routine test report
of all the transformers together with the transformers apart from the commercial
document.
In the event of disagreement or dispute, either the contract’s details are not clear or
the supplier would like that an exception be made (for example, the value of the
guaranteed loss) these issues should be presented at a meeting with the upper
management. The meeting should discuss the disadvantages and advantages to the
utility as the main focus. This convention should remain and be considered the
standard practice.
4. Acceptance Process
The acceptance committee will make a visual inspection for the quantity of the
delivered transformers according to the invoice of the supplier, after scrutinizing all
transformers and documents such as the instruction manual, spare parts, etc. The
acceptance committee will then randomly select a quantity of transformers per that
which is stated in the contract. This amount typically does not exceed 10 sets due to
the expense and time.
It is recommended that even though the supplier performs the entire routine test for
all transformers as shown in Figure 14: Supplier’s routine test report, the utility
should perform sampling for its own re-verification before installation on site. The
utility should implement a detailed step by step, pre-verification laboratory in order
to assure that the transformers conform to the specification, especially with respect
to guaranteed losses; otherwise, the supplier may try to deliver cheap transformers
with high losses.
In the event that the utility has budgetary constraints, it is strongly recommended
41
that a third party be employed to witness the tests and approve all contract
documents at the factory. This may require a monetary investment, but the value
outweighs the cost due to the high cost of equipment.
42
• Average supplier’s report value = 5,481.33 W
• New guarantee load loss is raised to = 5,481x1.0561 =
5,788.83 W
• The penalty is calculated to = (5,788.83 – 5,600)x penalty
values (normally is 2.0 times of the formula constant) x Total
number of transformers
This is illustrated in Figure 17 Penalty Calculation with Raising
the Guarantee Values
4.3.2. Case No. 2 - Utility does not have the requisite facility for making
acceptance tests and is dependent on the routine test report of all
transformers in computing excess losses. The process will be the same
as mentioned in case no. 1 above, by using tolerance limit instead of the
different values between the utility and supplier.
ii. In case of total loss exceeds the tolerance but with no-load loss
within the limit, the increase in load loss to the new guarantee
value is equal to (total loss)/( 1+%tolerance/100) – no-load as
shown below:
• Guarantee no-load loss = 5,000 kW
• Guarantee load loss = 10,000 kW
• Tolerance of no-load loss = 15 %
• Tolerance of total loss = 10 %
• Supplier report shows no-load loss = 4,500 kW < 5,000 kW
• Supplier report shows load loss = 13,000 kW
• Supplier report shows total loss = 13,000+5,000 = 18,000 >
(5,000+10,000)+10% kW
• Raised load loss guarantee = (18,000/1.10) – 5,000 =
11,363.64 kW
• The penalty is calculated to = (11,363.64 – 10,000) x penalty
values (normally is 2.0 times of the formula constant) x Total
number of transformers
• Check again if the average supplier’s load loss is lower than
the new guaranteed load loss value
43
LIST OF DRAWING
2 TRANSFORMER BASE 7
8 CONTROL BOX 13
LIST OF ACCESSORIES
44
Logo and Name of the manufacturer
TECHNICAL DATA
GUARANTEED DATA
TOLERANCE
45
Figure 13: Sample Drawing of Technical and Guaranteed Data
46
TEST REPORT
DISTRIBUTION TRANSFORMER
INSULATION RESISTANCE TEST at: 1000 V.DC Amb. Temp. 28.0 °C Humidity: 77 %
H.T.-L.T.: 69.00 G-Ohms H.T. Ground: 43.00 G-Ohms L.T. Ground: 27.60 G-Ohms
MEASUREMENT OF VOLTAGE RATIO AND VECTOR GROUP Amb. Temp. 28 °C Humidity: 76 % Complied
Tap position 1 2 3 4 5
Standard ratio 100.00 50.00 97.50 48.75 95.00 47.50 92.50 46.25 90.00 45.00
Ratio error 1-3 (% ) 0.05 N/A 0.06 N/A 0.07 N/A 0.10 N/A 0.12 N/A
Ratio error 2-4 (% ) 0.05 N/A 0.06 N/A 0.07 N/A 0.10 N/A 0.12 N/A
MEASUREMENT OF NOLOAD LOSS And EXCITING CURRENT Amb. Temp. 27.5 °C Humidity: 67 %
Voltage test: 240.0 V. Current: 8.7 A. No-load loss : 184.2 W. at reference temp. 20 °C
47
MA4-7552-AGA
12/24 kV 750 kVA THREE PHASE
GUARANTEE VALUE
NO LOAD LOSS 880.00 W
LOAD LOSS 4300.00 W
TOTAL LOSSES 5180.00 W
SUMMARY :
The above table shows that no load loss from MEA's report is not over the guarantee value but the load loss from MEA's report is
greater than that from supplier's report more than 2.5% and over the guarantee value. Therefore, results from MEA's report are
used in calculating compensation as follows:
penalty compensation of load loss = (load loss-guarantee load load) x (106.5 baht / W) x (total set)
= (43.83.3-4300) x (106.5) x 1
= 8871.45 Baht
48
MA4-7553-AGA
12/24 kV 750 kVA THREE PHASE
DISTRIBUTION TRANSFORMER CONVENTIONAL TYPE
GUARANTEE VALUE
NO LOAD LOSS 1060.00 W
LOAD LOSS 5600.00 W
TOTAL LOSSES 6660.00 W
SUMMARY :
The above table shows that load loss from MEA's report is greater than that from supplier's report more than 2.5% and over the
guarantee value. Therefore, load loss from supplier's report will be raised up 5.61% to used in calculating compensation as follows:
raised up = 5.61 %
= 5788.83 W.
penalty compensation of load loss = (adj. average load loss-guarantee load load) x (106.5 baht / W) x (total set)
= (5788.83-5600) x (106.5) x 3
= 60331.19 Baht
49
5. Conclusion
As mentioned earlier, the purpose of this chapter is to explain the practical
acceptance test process and exceeding transformer losses management which have
been utilized for more than 40 years and have been approved by the Asian
Development Bank (ADB) and World Bank (WB).
50
Chapter 5
Installation and Operation
1. Introduction
As the utility accepts the transformers delivered by the supplier, some transformers
shall be installed at the destination, but the balance will be kept in the warehouse as
stock. The suppliers’ transformer manual will be submitted with the transformer for
utility’s field workers to perform installation and operation. Therefore, all
instruction and caution will be completely utilized in order to assure quality for at
least twenty years.
The installation and operation in this chapter will be explained based on application
from well known utility having at least 50 years experience in the installation and
operation of the low losses transformers.
2. Objective
The transformers having low losses or standard transformers shall utilize the same
process of installation and operation. There are two main installation configurations
which are installed at the station: concrete or wooden pole type, and pad-mount
type. The construction standards will be shown to guide the utility to set up the
transformers and also other equipment in order to facilitate installation by the field
workers. The loading guide will be discussed to keep the high efficiency for the low
losses transformers.
51
3. Construction Standard
Firstly, the characteristics of the transformer have to be obtained from the
nameplate which shall be affixed to the transformer tank as per the requirement of
the relevant standards. The nameplate shall provide the necessary information for
transformer energizing, installation and operation. The nameplate shall include all
relevant information. Secondly, the transformers will be separated, and warehoused
for future extension power distribution planning. Various recommendations will be
briefly discussed, and an explanation of the other transformers will be clarified in
detail, according to the utility’s construction standards.
f. Type: This is the method of cooling system used to cool the system from
the heat generated during the transformer operation.
52
k. The total weight (kg): This is the total weight of the complete set of
transformer.
If the event that two or more transformers are stored together, there must be
sufficient space between the transformers to prevent collision on any projecting
attachments and also allow space for routine visual inspection.
a. Transportation
Note: Do not attempt to lift/jack the transformer other than the fitting
parts provided for this purpose.
53
The liquid immersed transformers, hermetically sealed type, are suitable
for indoor and outdoor installation. It can be moved to the designated
position utilizing wheels, roller, crowbar or pulley and must be levelled
when installed at the designated location.
b. Indoor Installation
For the air to circulate freely around the transformer and access
maintenance facilities there must be a distance of at least 0.5 meter
between the transformer and the wall of partition, the same precaution
must be taken should there be several transformers in a room.
c. Outdoor Installation
d. Cabling
54
1/3150 M48 70
• Torque Setting for various bolt sizes used in bus bar Connections -
Steel
Bolt Size Tightening Torque (Nm)
M6 6-9
M8 15-22
M10 35-44
M12 70-75
M16 120-150
4. Loading Guide
55
• Ambient temperature does not exceed 40°C; or average more than 30°C;
in one 24 hour period, the transformer may be used in over 40°C ambient
for very short intervals. Unless it is a specially designed unit with the
properly upgraded insulation level which can be operated at a higher
temperature rating.
• Installed elevation does not exceed 3,300 feet (1,000 meters) above sea
level, otherwise the transformer capacity will be de-rating due to the air
density and the cooling efficiency of the transformer is reduced, the
factors that can be calculated refer to ANSI standard C57.
• A schedule should be made for periodic checks of the load applied to the
transformer to verify that an excessive load is not being applied to the
unit.
The power efficiency of the transformer is the best method of specifying the
lowest losses during operation or loading the transformer as designed
approximately 40% of the transformer capacity. In fact the power efficiency of
56
transformers serviced in rural areas are s skewed by the continual presence of
no-load losses so that the transformer represents an energy drain on the system
when unloaded and when loaded at light loads (below about 15%), the
efficiency is very poor.
In contrast, in transformers which are serviced in the urban area or large cities,
it was found that the loading capacity is approximately 50%, which is still
defined as low loss energy.
Second stage, 10 years later MEA started to buy three phase and single phase
transformers with the same sizes and many ranges in capacity, to accommodate
the increase in customers. MEA made a decision to utilize the transformers as
efficiently as possible by considering the load curve of each type of customers,
load growth per annum and five year expansion consumption plan. The result
was that the need to replace transformers due to overcapacity was not reached
as frequently as had previously been the case.
Final stage. Currently, with the advanced power distribution designed software,
MEA is trying to reduce costs concerning the transformer management such as
inventory cost, warehouse’s facilities, low loss transformers, also, they decided
to minimize the sizes of transformers. They are only considering 8 ranges or
sizes which are 75 kVA, 150 kVA, 225 kVA, 500 kVA, 750 kVA, 1,000 kVA,
1,500 kVA and 2,000 kVA.
MEA had reduced costs considerably after the above mentioned changes.
They have also realized avoidance of heavy traffic, and lessened environmental
impact.
For other LMS utilities, the sizing of the transformers shall be considered by
using power distribution software and load forecasting, in some cases, it is
recommended to separate the urban and rural area’s sizing transformer
solutions due to different load characteristics, inventory cost, heavy traffic
impact, etc.
57
Figure 18: Construction drawing for transformer installation (single concrete pole)
58
Figure 19: Bill of material for transformer installation (single concrete pole)
59
Figure 20: Construction drawing for transformer installation (platform)
60
Figure 21: Bill of material for transformer installation (platform)
5. Conclusion
As stated, low cost - high losses transformers but high cost - low losses transformer
are both available. The recommendation is to reach and optimal financial decision
between the cost and the low losses of the transformer. Both the standard loss
transformers and the low loss transformers should be implemented for rural usage
61
and urban area respectively. The example of the standard loss transformer table has
shown in Table 3.
The loading guide of those types of transformers which are standard loss and
low loss applications should be carefully studied and practiced to reach the
most efficiency of transformer utilization.
62
Chapter 6
Maintenance and Asset Management
1. Introduction
The information provided in this chapter on maintenance and asset management of
oil filled transformers, is provided as a guide. This is a brief outline for the proper
procedures and requirements for the general and required practices that must be
followed.
This is an addition to the international standard ANSI and IEC requirements for the
maintenance and asset management for low losses transformers. Best practices
should be followed to lead to the best solution for the utility to prolong the
transformer‘s service life and maximize its operating efficiency.
Each district office or branch that has to manage the units individually, will send
field workers or technicians to inspect general characteristics and measure or update
the load capacity of each transformer periodically, this is time consuming and a
waste of manpower.
The Transformer Load Monitoring (TLM) system is designed to obtain basic data
from the transformer. It includes information such as: voltage, current, etc. It then
sends the data remotely to the control centre so that they may monitor the results
and send it to the operators for transformer management.
Thanks to the TLM system, the transformer management operator can make use of
this data for preventive maintenance, up-rated transformer replacement, and
electrical system planning and emergency mal-function management.
63
2.1 The TLM system consists of three main parts as follows:
a) Master station
This is a computer server which will be installed at each district office or
branch as the centre for collecting all transformer data from Remote
Terminal Unit (RTU) and convert to the data base having three main
functions which are:
64
• Acquire the transformer data, using the Protocol given in the
specification or TOR of the project
• Database capacity should be large enough to keep the electrical
data such as voltage, current , etc. of all transformers in each
district office at least one year having three values (maximum,
minimum and average) a day including the system event of fault
or mal-function.
• Searching criteria favour to the utility such as Transformer
manufacturer name, date-month-year of the malfunction.
NOTE: Special options for the advanced program which shows the
transformers in the form of a single line diagram of the distribution
system located in different district offices. The monitor displays an
alarm when any event occurs, and also displays the communication
between master station and each RTU.
65
• Calculating the power factor of the transformers
• Transferring the data in form of Protocol as specified in the
specification
• Warning message to alert users in case of sudden abnormal situation
• Withstanding to outdoor application such as Ultra violet (UV), direct
sunlight, pollution, etc.
c. Communication
The communication between Master Station and RTU should be via high
speed internet fiber optic communication wireless communication.
d. Protocol
Protocol for communication between the Master Station and RTU is
capable of:
• Sending important information such as RTU ID, electrical
characteristics and emergency case.
• Support for extension of installation of RTU more than 5,000 sets
• Verify the accuracy of information
• Support transmitting of data of “Polling” form
• Support transmitting of data in the form of Message (once an
emergency is found)
• While working adjacent to live parts: Be sure to check that the apparatus
is disconnected from the live circuit. The work should begin only after
ascertaining that the apparatus is not live.
• In case of regularly maintenance and inspection: Try to identify any
abnormal conditions or problems with the transformer as early as possible
by comparing such indication with the operation records carefully.
• Check the top oil temperature of the transformer: The top oil temperature
of transformer is specified to be not more than in Table 4. Make certain
that oil temperature rise is not more than Table 4. The Dial thermometer is
set to close the supervisory contacts at the temperature specified in Table
4. (See column Alarm) for alarm status and Table 4. (See column
Tripping) for tripping purpose.
66
Temperature of transformer (°C) Dial thermometer
At 40°C ambient temp. Contacts closed at (°C)
Oil Temperature Top Oil Alarm Tripping
Rise Temperature
50 90 85 95
55 95 90 100
60 100 95 105
Table 4: Temperature condition of transformer
• Oil leakage: Carefully check the parts to which gaskets are applied.
Note: While operating, transformer will generate heat and will effectively
remove condensation and moisture on the transformer.
Temperature °C 20 30 50 60
Insulation resistance MΩ 800 400 100 50
67
3.4. Recommended Maintenance Schedule
4. Conclusion
The asset management of the transformer begins with the specification preparation.
Reference standard design, raw materials and workmanship are used to manufacture
the transformer. The lifetime of transformers is determined by the lifetime of the
electrical insulation which is mainly organic in its chemical nature (being composed
of mineral oil, impregnated paper, cellulose materials, etc.) and the stability of such
materials is very susceptible to the operational temperature. Thus, the operating
temperature must be very closely specified and controlled in operation. If the
maximum temperature is exceeded for any length of time, the insulation lifetime
may be reduced from the nominal level.
The usual rule of thumb is that continuous operation above the rated temperature by
only 6°C will halve the effective life of the insulation: this is the life reduction
factor used in most international Standards such as the Australian Transformer
loading Standard AS2374.7 [11].
Finally, the main purpose of this Handbook is to encourage the utilities to begin
using the low loss transformer by implementing the evaluation formula. Then it will
lead to the specified values of low loss figures for each rating of transformers which
are suitable for their own system. It will result in the electrical reduction of losses
by improved transformer efficiency and will thus extend the life of transformers and
is an additional justification for the introduction of new high efficiency levels for
transformers.
68
Applying the new technology of the transformer load monitoring (TLM) will aid the
utility to keep the service transformer’s capacity to be in the limit of the loading
guide, and to reach the generated lowest loss energy. Another key is that the
insulation need be maintained within the appropriate temperature limits to reach and
surpass the service life at least twenty years as mentioned in the evaluation formula.
69
Notes
70
Notes
71
Notes
72
73
74