Method Statement For Road Marking
Method Statement For Road Marking
Subcontractor:
Contents
1. Introduction
2. Purpose
3. Scope of Work
4. Definitions
5. References
8. HSSE
9. Prior Activities
10. Procedure
11. Responsibilities
1- Introduction
Middle East Road Marking is one of the foremost road marking
contractors in UAE with years of experience in the industry. We
specialize in hot thermoplastic machine marking for roads and
highways, hot thermoplastic hand marking, cold road marking for
airport and parking lots, removing existing marking by sandblasting,
Road stud fixing & Kerb stone painting with spraying machines.
2- Purpose
To ensure that all Road Marking and Signs are executed safely and in
accordance with the contract requirements and that all quality
assurance/ control activities are conducted in a systematic manner,
works are inspected and conformance is verified and documented.
3- Scope of Work
a. This procedure is applicable to the following works associated with
the project.
4- Definitions
GM General Manager
PM Project Manager
SE Site Engineer
QS Quantity Surveyor
5- References
Contract – General &Special Conditions – BOQ – Approved Drawings –
Specifications - Shop drawings (Respectively).
Road marking Cold paint (Jotun Acrylic Based Road Marking Paint)
Warning tapes
Temporary signs
Safety Barriers
Traffic Cones
Grade Stakes
• Specification
Jotun Acrylic Based Road Marking Paint is a quick drying, solvent based
paint. Based on solvent based acrylic resin.Can be used for marking
roads and kerbs. Easy to apply. It has UV resistant colours. Ideal for use
on asphalt and concrete roads, primarily for kerbstones, speed humps
or other areas with light traffic.It can be use for both Roads and kerbs
painting.The temperature of the substrate should be minimum 10 °C
and at least 3 °C above the dew point of the air, measured in the vicinity
of the substrate. Good ventilation is usually required in confined areas
to ensure proper drying. The moisture content in the substrate should
not exceed 4 % (by weight). The coating should not be exposed to oil,
chemicals or mechanical stress until fully cured.Drying times are
generally related to air circulation, temperature, film thickness and
number of coats, and will be affected correspondingly.Recommended
data given is, for recoating with the same generic type of paint.In case
of multi-coat application, drying times will be influenced by the number
and sequence and by the total thickness of previous coats applied.The
surface should be dry and free from any contamination prior to
application of the subsequent coat.
Specification
SL. Current
Machinery Qty. Manufacturer Remarks
No. Location
Hofmann H33-3 type Hofmann Always
1 Thermoplastic spray 2 Roadmarking Available in
machine systems Dubai
Preheating twin boiler
Trucks for machine Always
2 marking and 4 Local Available in
Thermoplastic hand Dubai
marking
3 ton double cabin
Always
pickup for
3 4 Hino Available in
Sandblasting and
Dubai
Cold paint marking
Graco Line Lazer Always
4 machine for Cold 5 Graco Available in
paint marking Dubai
KAESER Always
300 CFT mobile type
5 2 KOMPRESSO Available in
Air Compressor
REN Dubai
3. Electronic scales / bead bucket and stop watch for glass bead
application rate
2. Retro reflectometers
3. Skid resistance testers.
4. Digital wheel meter
8- HSSE
a. Approved safety plan procedures shall be strictly followed.
b. Where possible hazards may arise from filling activities, the necessary
safety measures will be taken to prevent accident or injury at all
times. This may include barriers, warning tape/ net, signage,
watchman, and proper lighting.
g. Plant and Equipment will be provided with back-up alarms, lights, and
all other applicable safety devices.
h. Proper access to the work area shall be maintained throughout the
working period
9- Prior Activities
a. The Client Surveyor will locate and mark all Centerlines for all types .
b. Width and length for all types must be marked.
10- Procedure
The material shall be applied only on a surface which is clean and dry. It
shall not be laid over loose detritus, mud or similar extraneous matter,
or over an old paint marking, or over an old thermoplastic marking which
is faulty. New surfaces must be allowed to weather and compact for at
least 72 hours before applying the marking. In the case of smooth
polished surfaces, e.g. smooth concrete, old asphalt surfacings with
smooth polished surface stones, and/or where the method of application
requires or the Engineer directs, a tack coat shall be applied to the
surface prior to the application. The tack coat shall be as recommended
by the manufacturer of the thermoplastic material and to the approval of
the Engineer. Faulty thermoplastic markings shall be removed if required
by the Engineer.
The Contractor shall not proceed with the marking work until the
equipment, method of application, and rate of application, as established
by a test section, have been approved by the Engineer.
A) Manufacturer’s recommendation:
B) Materials
E) Applications:
Set marking machine in the correct position along the alignment of marking
Spray the Line with Line Lazer Machine at the rate of 300 microns – wet film
thickness, i.e. 120 microns – dry film thickness.
Spray Glass Beads at the rate of approximate 300g/m2 (Drop-on Method)
Remove the masking tape after 20 minutes
Mask the perimeter of the line with masking tape Apply Paint with roller or brush
after drying the first application. Repeat the same and apply glass beads.
11- Responsibilities
C) Quantity Surveyor along with our gang take the quantity done daily or
after the completion of project and verified by client site engineers.
D) Quality Control Engineer will ensure that the materials being used are
in accordance to the project specifications, the approved method
statement and the ITP.
E) The HSSE officer along with his team will ensure implementation of all
HSSE procedures related to the nature of the works being carried out
and in accordance with the HSSE Plan.