4. 1-A ____ is a set of activities which are networked in an order and aimed towards
achieving the goals of a project. *
Project
Process
Project management
Project cycle
https://docs.google.com/forms/d/14bintyazKUlw_hOIRTUVrthwGpfwp5RWE8xSPtfJrlI/edit 1/5
5/12/2020 Computer Science Department
5. 2-Resources refers to *
Manpower
Machinery
Materials
Option 5
Process
Project
Scope
https://docs.google.com/forms/d/14bintyazKUlw_hOIRTUVrthwGpfwp5RWE8xSPtfJrlI/edit 2/5
5/12/2020 Computer Science Department
Allocating resources
9. 6-Following are the phases of Project Management Life Cycle. Arrange them in
correct order Design, 2. Marketing, 3. Analysis and evaluation, 4. Inspection, testing
and delivery *
3-2-1-4
1-2-3-4
2-3-1-4
4-3-2-1
Input received
Output received
https://docs.google.com/forms/d/14bintyazKUlw_hOIRTUVrthwGpfwp5RWE8xSPtfJrlI/edit 3/5
5/12/2020 Computer Science Department
Time
Cost
Quality
https://docs.google.com/forms/d/14bintyazKUlw_hOIRTUVrthwGpfwp5RWE8xSPtfJrlI/edit 4/5
5/12/2020 Computer Science Department
Forms
https://docs.google.com/forms/d/14bintyazKUlw_hOIRTUVrthwGpfwp5RWE8xSPtfJrlI/edit 5/5