George Massey Tunnel Replacement Project: Monthly Status Report September 2017
George Massey Tunnel Replacement Project: Monthly Status Report September 2017
QUARTERLY PROGRESS
REPORT
The Province’s work on the Project up to this point will be looked at closely as part of the independent review,
including technical information developed by the project team and from Metro Vancouver municipalities, as well
as new analysis that includes looking at how the removal of tolls will affect the crossing.
The review will focus on what level of improvement is needed in the context of regional and provincial planning,
growth and vision, as well as on which option would be best for the corridor, be it the proposed 10-lane bridge, a
smaller bridge or tunnel. Mayors from Metro Vancouver will be engaged, including Richmond & Delta, to gather
their perspectives on the Project, and to ensure that any plan for this crossing fits into the overall vison for the
region.
The review is expected to be finished in the spring of 2018 and will include recommendations to the Province on
the way forward.
Based on the recommendations received, the Province will determine next steps to address congestion along the
Highway 99 corridor.
The Project team’s collective experience includes an extensive breadth of knowledge and experience in delivering
major transportation projects to the Province and Project resources are available to support the independent
technical review as required. The Project team’s comprehensive expertise includes senior advisors, senior project
management and engineering professionals, and subject matter experts across all disciplines.
The application of the international standard ISO 9001 Quality Management Systems builds the foundation for
excellence, accountability and continual improvement on the Project. The Project Quality Management System is
an integral component of the Project delivery framework and requires that appropriate resources are available to
ensure conformance with internal project requirements, as well as contractual and legal requirements (statutory
and regulatory).
1
GEORGE MASSEY TUNNEL
REPLACEMENT PROJECT
Monthly Status Report – September 2017
The Project delivery framework is built on a systematic approach to all disciplines, combined with the application
of proven and recognized standards, principles and guidelines to these areas. The following provides a sampling of
how this is applied on the Project:
Safety planning and management of all Project activities are governed by the requirements of the
Workers Compensation Act and WorkSafeBC Occupational Health and Safety Regulation;
The Project’s commitment to developing sound partnerships with Project stakeholders, community
partners, and all project-related organizations is achieved by fostering and maintaining effective and
collaborative relationships, and employing best practices that draw upon international standards.
Environmental protection is managed within a framework provided by ISO 14001 Environmental
Management Systems, ensuring that all statutory and regulatory requirements are met;
Project Controls are governed by numerous Provincial policies such as the Ministry of Finance Capital
Asset Management Framework and the BC Government Core Policy and Procedures Manual;
Procurement processes are based on past transportation infrastructure projects, Ministry of Finance
Capital Asset Management Framework (CAMF), Core Policy and Procedures Manual (CPPM), and industry
best practices such as the “First Principles” method of estimating;
Engineering is governed by the APEGBC Act and Bylaws, quality management guidelines, industry best
practices, and the application of local and international standards including CSA-S6-14 Canadian Highway
Design Bridge Code (CHBDC), Supplement to CHBDC S6-14, Transportation Association of Canada (TAC)
Geometric Design Guide and BC Supplement to TAC; and
The direction for risk management practices on the Project is provided by the Risk Management Guideline
for the BC Public Sector issued by the Province of British Columbia Risk Management Branch and
Government Security Office, the companion CAN/CSA ISO 31000: Risk Management – Principles and
Guidelines, and the Core Policy and Procedures Manual, Chapter 14 (CPPM 14).
Stringent reviews during planning and development ensure a rigorous system is in place to ensure all Project
requirements are met. Ongoing internal reviews for each aspect of the Project are conducted to ensure
accountability, integrity, and continual improvement of the Project and the Quality Management System. Internal
reviews confirm compliance, documentation, progress and performance throughout the lifecycle of the Project.
2
GEORGE MASSEY TUNNEL
REPLACEMENT PROJECT
Monthly Status Report – September 2017
Scope Status*
The independent technical review will look closely at the Province’s work on the Project,
including technical information developed by the project team and from Metro Vancouver
municipalities, as well as new analysis that includes looking at how the removal of tolls will
affect the crossing.
Schedule Status*
Project activities through the coming months will primarily be focused on providing support to
the independent technical review team, generally aligned with the following tentative
timelines:
o September 2017 – Independent technical review announced
A summary of previous activities undertaken by the Project follows:
Consultation
o Phase 1 – Understanding the Need (2012)
o Phase 2 – Exploring the Options (2013)
o Phase 3 – Project Definition Report (2015/16)
o Environmental Assessment Consultation (2016)
Environment
o Environmental Assessment Certificate obtained on February 9, 2017.
o Approval from the Agricultural Land Commission (ALC) obtained on February 24, 2017.
Technical Studies
o Engineering, traffic, geotechnical and other technical studies.
Procurement
o Business case (October 2015)
o Procurement Process - RFQ/RFP (June 2016- April 2017)
o Independent technical review announced – procurement process cancelled
(September 2017)
3
GEORGE MASSEY TUNNEL
REPLACEMENT PROJECT
Monthly Status Report – September 2017
Construction
o Site preparation works commenced in both Richmond and Delta in April 2017 and
continues in September. Monitoring settlement and performance of preload areas
continues.
Cost Status*
The forecast for the current fiscal year is $44M; to date, $ 22M has been spent (this includes
actuals plus incurred).
Total Project expenditures are forecast to approximate $66 million at the end of the current
fiscal year.
* Status Legend: Green = No issues to report; Yellow = Minor issues to report; Red = Significant issues to report.
4
GEORGE MASSEY TUNNEL
REPLACEMENT PROJECT
Monthly Status Report – September 2017
Report Structure
The table below provides a brief description of the contents of this report.
1. Introduction Project overview and goals, key milestones achieved and current
month highlights
4. Project Development Scope, monthly accomplishments and upcoming activities for the
each of the major disciplines: Stakeholders, Environment,
Agriculture, Aboriginal Groups, Procurement, Engineering,
Construction and Property
5. Cost Report Fiscal year cost summary
5
GEORGE MASSEY TUNNEL
REPLACEMENT PROJECT
Monthly Status Report – September 2017
1. INTRODUCTION
Project Overview
The George Massey Tunnel is an important link in the regional and provincial transportation system, carrying an
average of 80,000 vehicles each day. It connects to key gateways such as Vancouver International Airport (YVR),
the Peace Arch and Pacific Canada-U.S. border crossings, BC Ferries' Tsawwassen terminal, Deltaport and the
Boundary Bay Airport. It is a vital goods movement route that fuels our local, regional, provincial and national
economies, and a key access point for businesses in Delta, Surrey, Richmond, and Tsawwassen First Nation.
Since the Tunnel opened in 1959, Metro Vancouver’s population and economy have grown, and its population is
forecast to continue to grow by more than one million people over the next 30 years. Without improvements to
this crossing, economic growth and regional livability will be constrained by congestion and increasing travel times
for commuters, goods movers, commercial traffic and other traffic.
In 2012, the Ministry of Transportation and Infrastructure commenced a study of options to address the Highway
99 corridor and a new bridge to replace the Tunnel emerged as the proposed solution. Construction began in
spring 2017, placing preload in areas of soft soils in advance of the primary works.
In September 2017, Government announced the Project will undergo an independent technical review. The review
is expected to be finished in the spring of 2018, and based on the recommendations received, the Province will
determine next steps to address the congestion along the Highway 99 corridor.
Project Goals
Based on the Ministry’s mandate and results of consultation to date, six primary goals have been identified for the
Project:
1. Improve safety. This includes improving traffic and seismic safety, as well as emergency response
capabilities.
2. Reduce congestion. Improve travel times and reliability for all users.
3. Support increased transit on the Highway 99 corridor. Provide dedicated transit/HOV lanes on the new
bridge to improve travel time reliability and add capacity for long-term transit improvements.
4. Provide options for pedestrians and cyclists. Provide multi-use pathways on the new bridge to connect
cycling and pedestrian corridors in Richmond and Delta.
5. Enhance the environment. Enhance the environment under the new bridge and in the Project right-of-
way on Deas Island.
6. Support trade and commerce. Improve access to local businesses and gateway facilities, and improve
travel time reliability for goods movers and service providers.
6
GEORGE MASSEY TUNNEL
REPLACEMENT PROJECT
Monthly Status Report – September 2017
7
GEORGE MASSEY TUNNEL
REPLACEMENT PROJECT
Monthly Status Report – September 2017
8
GEORGE MASSEY TUNNEL
REPLACEMENT PROJECT
Monthly Status Report – September 2017
2. SCHEDULE
The following schedule depicts deliverables, milestones and associated dates and timelines for the planning and procurement phases of the Project as well as anticipated construction timelines.
9
GEORGE MASSEY TUNNEL
REPLACEMENT PROJECT
Monthly Status Report – September 2017
3. PROJECT MANAGEMENT
Objectives: Provide resources to support the independent technical review team in fulfilling its
mandate
Provide background information and technical work developed by the project
team for review
Update existing Project materials
Coordinate additional technical work or analysis requested by the independent
technical review team
Safety
10
GEORGE MASSEY TUNNEL
REPLACEMENT PROJECT
Monthly Status Report – September 2017
Quality
Objectives: Ensure design services and construction works delivered to the Province are
implemented within a quality standard consistent with Ministry standards and ISO
9001.
Ensure internal processes are conducted per Project quality requirements,
consistent with Ministry standards and ISO 9001.
Accomplished Quality Management input to site preparation works, including review of Quality
in month: Documentation.
Key activities Continue Quality Management input and related monitoring/audits of site
for next 3 preparation works.
months: Provide support to independent technical review team regarding the Project’s
quality program.
Project Controls
Objectives: Effectively manage the Project’s contracts, scope, schedule and cost.
Minimize potential negative impacts of any changes to the Project.
Ensure an efficient system for document control and records management.
Ensure project controls are governed by provincial policies such as the Ministry of
Finance Capital Asset Management Framework and the Core Policy and
Procedures Manual.
Accomplished Held regular monthly project controls meetings with discipline leads.
in month: Updated the Project cost and schedule pursuant to announcement of independent
technical review.
Key activities Ongoing updates to project schedule in alignment with independent technical
for next 3 review team progress and activities.
months:
11
GEORGE MASSEY TUNNEL
REPLACEMENT PROJECT
Monthly Status Report – September 2017
4. PROJECT DEVELOPMENT
Stakeholders
12
GEORGE MASSEY TUNNEL
REPLACEMENT PROJECT
Monthly Status Report – September 2017
Environment
Key activities Continue environmental monitoring and auditing regarding completed site
for next 3 preparation works.
months: Provide support to independent technical review team regarding project’s
environmental assessment process and activities.
13
GEORGE MASSEY TUNNEL
REPLACEMENT PROJECT
Monthly Status Report – September 2017
Agriculture
Scope: Identify and work with farmers and other agricultural stakeholders potentially
affected by the Project.
Obtain official Project approval from the Agricultural Land Commission (ALC).
Prepare appropriate plans to mitigate potential agricultural effects and to enhance
agricultural land use.
Accomplished N/A
in month:
Key activities Provide support to independent technical review team regarding agricultural
for next 3 stakeholders interests, engagement, input and the ALC process.
months:
Aboriginal Groups
Accomplished N/A
in month:
Key activities Provide support to independent technical review team regarding Aboriginal Group
for next 3 interests, engagement, input and activities.
months:
14
GEORGE MASSEY TUNNEL
REPLACEMENT PROJECT
Monthly Status Report – September 2017
Procurement
Scope: Development of Request for Qualifications (RFQ), Request for Proposals (RFP) and
subsequent evaluation of submissions.
Key activities Provide support to independent technical review team regarding procurement
for next 3 processes and timelines.
months:
Engineering
Key milestones Draft reference concept for EA application, RFQ and RFP
achieved to Multiple traffic data and analysis reports
date: Multiple geotechnical studies
Pile Load Test
Reviewed technical compliance of proposals
Accomplished Assembled background materials and studies for independent technical review.
in month:
15
GEORGE MASSEY TUNNEL
REPLACEMENT PROJECT
Monthly Status Report – September 2017
Construction
Accomplished Completed preload placement at both Delta and Richmond preparation sites.
in month: Continued settlement gauge readings and environmental monitoring at both Delta
and Richmond preparation sites.
Key activities Continue settlement gauge readings and environmental monitoring of completed
for next 3 site preparation works.
months: Preload and drainage sites maintenance
Property
Key activities Provide support to independent technical review team regarding property
for next 3 requirements and planned land exchanges to increase local Agricultural Land Reserve
months: (ALR) inventory.
16
GEORGE MASSEY TUNNEL
REPLACEMENT PROJECT
Monthly Status Report – September 2017
5. COST
Objectives: Development of the Capital Cost and, Operation, Maintenance and Rehabilitation
Cost Estimates
Ensure costs for works performed are in accordance with scope and schedule
Control cost variance from budget
Regular review of the estimated Project Cost
Ensure cost control activities are governed by provincial policies such as:
Ministry of Finance Capital Asset Management Framework (CAMF)
(2002);
Ministry of Finance Core Policy and Procedures Manual (2015);
Auditor General Act;
Financial Administration Act;
Balanced Budget and Ministerial Accountability Act;
Supply Act;
Budget Transparency and Accountability Act; and
Transportation Investment Act.
Status: The forecast for the current fiscal year is $44M; to date, $22M has been spent (this
includes actuals plus incurred).
Total Project expenditures are forecast to approximate $66 million at the end of
the current fiscal year.
The Project will not be budgeted for in the government’s capital plan until a
solution has been identified.
17
GEORGE MASSEY TUNNEL
REPLACEMENT PROJECT
Monthly Status Report – September 2017
6. RISK MANAGEMENT
Objectives: Implementation of risk management at the operational level, while abiding by
enterprise-level protocols and other considerations
Development of a Risk Management Plan that details the standard risk
management processes and practices implemented on the Project
Ongoing development and management of a risk register for the Project, which
includes risk mitigation strategies
Ensuring that risk is managed using the following guiding framework, principles
and policies:
Core Policy and Procedure Manual, Chapter 14 (CPPM 14) (2015)
Risk Management Guideline for the BC Public Sector (2012)
CAN/CSA ISO 31000: Risk Management – Principles and Guidelines (2010)
18