1. Scope of Works
2. References
3. Material
4. Responsibility
5. Flow of Work
6. Procedure
7. Quality Control
8. Records
-1-
1. Scope of Work
This Work Procedure covers all activities required to procedure acceptable wall mortar
finish.
2. References
3. Material
3.1 Cement
3.2 Sand
Sand for first coat, second coat and finishing coat is river sand from Tonle quarry. Sand
shall be good quality and free from salt, mud, dust and hazardous levels of organic matter.
4. Responsibility
Engineers, under the supervision of the Construction Manager shall be responsible for all
inspection.
-2-
5. Flow of Work
Select Materials
Inspection
-3-
6. Procedure
This procedure has been applied for two types: Plastering on the concrete surface and
plastering on the concrete block surface.
6.1.1 Preparation (Marking and Plaster Peg)
1500
1500
1500 1500
1.0 m
1.0 m
-4-
6.1.2 Concrete Surface:
The block wall surface shall be cleaned from dirty, and watering. The guide level shall be
installed before plastering (the same to the concrete wall).
Spray water in order to avoid dry-up
- 1st coat: 1:3.5 mortar is used and its thickness is around 10mm.
Before applying the 2nd , it must be cured 7 days, the 1st coat should be confirmed no
loose bond.
- 2nd Coat: 1:4.0mm mortar is used and its thickness is around 10mm and keep it about 2
hours (depending on the moisture of mortar which is subjected to weather and area
temperature) till the mortar get a bit dry before applying the finishing coat.
- Finishing Coat: mortar with fine sand thickness is around 3 mm the surface.
-5-
Notes: Before plastering, the wire mesh shall be installed in the following cases below:
- Between the joint of block walls and Concrete beam, Column, Wall.
-6-
9. Quality Control
-7-
8. Records
Appendix-1: Inspection record sheet for plastering work
Site Engineer shall be complete the attached Inspection Record Sheet.
-8-