0% found this document useful (0 votes)
121 views2 pages

Fuid End PDF

This document provides inspection criteria for the intermediate inspection of a mud pump fluid end. It lists the make, type, serial number and year of manufacture. Key steps include visually inspecting thread connections and seals, installing and tensioning valves and springs, and function testing for leakage. The inspection must be conducted by an authorized third party and verified by representatives from the drilling contractor and oil company.

Uploaded by

Kaleem Ullah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
121 views2 pages

Fuid End PDF

This document provides inspection criteria for the intermediate inspection of a mud pump fluid end. It lists the make, type, serial number and year of manufacture. Key steps include visually inspecting thread connections and seals, installing and tensioning valves and springs, and function testing for leakage. The inspection must be conducted by an authorized third party and verified by representatives from the drilling contractor and oil company.

Uploaded by

Kaleem Ullah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Intermediate Inspection Criteria, Well Control Equipment

Equipment Group: Mud Pump fluid end

Drilling Contractor :
Rig Unit Number – Contractor :
Rig Unit Number – PDO :
Present Well Location :
Date :

Mud Pump fluid end ( 1-Yearly )


Make/Brand :
Type :
Serial Number :
Year of Manufacturing
When : Conducted by :
Last Major Maintenance
Last Intermediate Maintenance
Note :
1. No heating, welding, or cutting is allowed on any part of this equipment.
2. PTW is required for pressure tests in the field.
3. 3rd party is required for NDT, US and pressure testing.
MP 1-2-3 Visual Correct / Comments
Inspection Done?
YES NO
1 MPI inspect the thread connection of the top
plug and sealing area if required change the
seals.
2 Install valve and spring (check the spring
tension, change if required), install plug,
tight it properly. Remove all the tools.
3 Function test the fluid end and check for
leakage.

Well Control Equipment Intermediate Inspection: Mud Pump Fluid End Generated by: WCF
Page 1 of 2
All above Name : Company : Date : Signature :
Inspections &
Tests conducted
by :
(Authorized Third
Party Inspection
Company)
Agreed by :
(Contractor Rig
Manager)
Verified by :
(PDO Site
Representative)
Authorized by :
(Contractor DS)
Seen by :
(PDO SWE)

Well Control Equipment Intermediate Inspection: Mud Pump Fluid End Generated by: WCF
Page 2 of 2