Activity Duration (Weeks) Dependency

The document provides information about the activities, durations, dependencies, and resources for a project. It asks to: 1. Draw an activity-on-node (AoN) network diagram showing the activities and their dependencies. 2. Determine the overall project duration based on the diagram. 3. Identify the critical path of the original project network. 4. Determine the new critical path if the dependency of activity G is changed from F to F,H.

Uploaded by

suthur27
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
42 views

Activity Duration (Weeks) Dependency

The document provides information about the activities, durations, dependencies, and resources for a project. It asks to: 1. Draw an activity-on-node (AoN) network diagram showing the activities and their dependencies. 2. Determine the overall project duration based on the diagram. 3. Identify the critical path of the original project network. 4. Determine the new critical path if the dependency of activity G is changed from F to F,H.

Uploaded by

suthur27
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Question 1 – Critical Path Method / 10 Marks

The activities of a project have the following durations (in weeks), dependencies and
resources.

Activity Duration Dependency


(Weeks)
A 2 -
B 4 A
C 6 B
D 3 A
E 7 B, D
F 5 C
G 2 F
H 1 C, E
J 4 E
K 6 H
L 3 J
M 2 K, L
N 4 G, K
O 2 N, M
P 2 O

Part 1: Draw a AoN Network Diagram (7 Marks)


Part 2: Determine the overall project duration (1 Marks)
Part 3: Determine the overall project critical path (1 marks)
Part 4: What is the project critical path if the Dependency on Activity G is changed
from F to F, H (1 Marks)