Rebar Delivery 2020

This document summarizes the delivery of reinforcing steel bars by Toyo Construction Co., Ltd. for a flood control project in the Philippines. It details the diameter, weight, length, quantity, and mill certificate information for bars delivered on January 5, 2020. A total of 127,821.72 kg of reinforcing steel bars across 7 diameters were delivered in 14 tension and bending test sample sets.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
44 views4 pages

Rebar Delivery 2020

This document summarizes the delivery of reinforcing steel bars by Toyo Construction Co., Ltd. for a flood control project in the Philippines. It details the diameter, weight, length, quantity, and mill certificate information for bars delivered on January 5, 2020. A total of 127,821.72 kg of reinforcing steel bars across 7 diameters were delivered in 14 tension and bending test sample sets.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

REPUBLIC OF THE PHILIPPINES

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


UNIFIED PROJECT MANAGEMENT OFFICE - FLOOD CONTROL MANAGEMENT CLUSTER
18Z00028 - FLOOD CONTROL PROJECT FOR CAGAYAN DE ORO RIVER (FRIMP-CDOR)
CONCTRACT PACKAGE NO. 2 (CONSOLACION)

TOYO CONSTRUCTION CO., LTD.

REINFORCED STEEL BAR DELIVERY - JANUARY 05, 2020


NO. OF SAMPLES
NO. DIAMETER LINEAR WEIGHT LENGTH QUANTITY WEIGHT WEIGHT PER DIA.
(Tension & Bending)
1 10 0.617 10.5 1000 6,478.50
16,473.90 2 sets
2 10 0.617 12 1350 9,995.40
3 12 0.888 10.5 550 5,128.20
23,776.20 3 sets
4 12 0.888 12 1750 18,648.00
5 16 1.578 10.5 1200 19,882.80
38,818.80 4 sets
6 16 1.578 12 1000 18,936.00
7 20 2.466 9 1750 38,839.50
48,752.82 5 sets
8 20 2.466 12 335 9,913.32
TOTAL WEIGHT 127,821.72
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
UNIFIED PROJECT MANAGEMENT OFFICE - FLOOD CONTROL MANAGEMENT CLUSTER
18Z00028 - FLOOD CONTROL PROJECT FOR CAGAYAN DE ORO RIVER (FRIMP-CDOR)
CONCTRACT PACKAGE NO. 2 (CONSOLACION)

TOYO CONSTRUCTION CO., LTD.

REINFORCING STEEL BAR DELIVERY - JANUARY 05, 2020


MILL CERTIFICATE NO. OF NO. OF NO. OF SAMPLES
NO. DIAMETER LINEAR WEIGHT LENGTH QUANTITY WEIGHT
FILE NO. BUNDLES PIECES/BUNDLE (Tension & Bending)
10.5 M51810-4578 4 250 1000 6,478.50
M51810-1831 1 85 85
1 10 0.617 2 sets
12 M51810-5087 4 251; 256; 257 1015 9,995.40
M51910-3179 1 250 250
M51912-3247 1 49 49
10.5 5,128.20
M51912-3324 2 249; 252 501
2 12 0.888 M51912-3314 3 250 750 3 sets
12 M51912-3318 3 250 750 18,648.00
M51912-3319 1 250 250
M51916-1683 4 150 600
10.5 M51916-8114 2 150 300 19,882.80
M51916-8115 2 150 300
3 16 1.578 4 sets
M51916-3657 2 100 200
12 M51916-3890 4 100 400 18,936.00
M51916-3897 4 100 400
M51920-2420 10 100 1000
9 M51920-2421 7 100 700 38,839.50
M51920-2268 1 50 50
4 20 2.466 5 sets
M51920-2321 1 80 80
12 M51920-2260 1 15 15 9,913.32
M51920-2417 3 80 240

TOTAL WEIGHT & SET 127,821.72 14 SETS


REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
UNIFIED PROJECT MANAGEMENT OFFICE - FLOOD CONTROL MANAGEMENT CLUSTER
18Z00028 - FLOOD CONTROL PROJECT FOR CAGAYAN DE ORO RIVER (FRIMP-CDOR)
CONCTRACT PACKAGE NO. 2 (CONSOLACION)

TOYO CONSTRUCTION CO., LTD.

REINFORCING STEEL BAR DELIVERY - JANUARY 05, 2020


DIAMETER LINEAR WEIGHT LENGTH MILL CERTIFICATE NO. OF NO. OF QUANTITY NO. OF SAMPLES
NO. WEIGHT (kg)
(mm) (kg/m) (m) FILE NO. BUNDLES PIECES/BUNDLE (pcs) (Tension & Bending)
10.5 M51810-4578 4 250 1000 6,478.50 *
M51810-1831 1 85 85 629.34
1 10 0.617 2 sets
12 M51810-5087 4 251; 256; 257 1015 7,515.06 *
M51910-3179 1 250 250 1,851.00
M51912-3247 1 49 49 456.88
10.5
M51912-3324 2 249; 252 501 4,671.32 *
2 12 0.888 M51912-3314 3 250 750 7,992.00 * 3 sets
12 M51912-3318 3 250 750 7,992.00 *
M51912-3319 1 250 250 2,664.00
M51916-1683 4 150 600 9,941.40 *
10.5 M51916-8114 2 150 300 4,970.70
M51916-8115 2 150 300 4,970.70 *
3 16 1.578 4 sets
M51916-3657 2 100 200 3,787.20
12 M51916-3890 4 100 400 7,574.40 *
M51916-3897 4 100 400 7,574.40 *
M51920-2420 10 100 1000 22,194.00 **
9 M51920-2421 7 100 700 15,535.80 **
M51920-2268 1 50 50 1,109.70
4 20 2.466 5 sets
M51920-2321 1 80 80 2,367.36
12 M51920-2260 1 15 15 443.88
M51920-2417 3 80 240 7,102.08 *

TOTAL WEIGHT & SET 127,821.72 14 SETS


REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
UNIFIED PROJECT MANAGEMENT OFFICE - FLOOD CONTROL MANAGEMENT CLUSTER
18Z00028 - FLOOD CONTROL PROJECT FOR CAGAYAN DE ORO RIVER (FRIMP-CDOR)
CONCTRACT PACKAGE NO. 2 (CONSOLACION)

TOYO CONSTRUCTION CO., LTD.

REINFORCING STEEL BAR DELIVERY - MARCH 07, 2020


DIAMETER LINEAR WEIGHT LENGTH MILL CERTIFICATE NO. OF NO. OF QUANTITY NO. OF SAMPLES
NO. GRADE WEIGHT (kg)
(mm) (kg/m) (m) FILE NO. BUNDLES PIECES/BUNDLE (pcs) (Tension & Bending)
M52012-0662 1 250 250 1,998.00 *
1 12 40 0.888 9 1 set
M52012-8019 1 50 50 399.60
M52016-0363 3 150 450 6,390.90 *
2 16 40 1.578 9 1 set
M52016-0474 1 50 50 710.10
M52020-0332 4 100 400 8,877.60 *
9
M52020-0334 1 100 100 2,219.40
M52020-0530 4 80 320 9,469.44
M52020-0531 6 80 480 14,204.16 *
12
M52020-0532 5 80 400 11,836.80 *
3 20 60 2.466 8 sets
M51820-1782 1 20 20 591.84
M52020-0539 5 80 400 13,316.40 *
M52020-0427 1 80 80 2,663.28
13.5
M52020-0538 10 80 800 26,632.80 ***
M52020-0539 2 80 160 5,326.56 *

TOTAL WEIGHT & SET 104,636.88 10 SETS