Extensions of Time and Concurrent Delay Case
Extensions of Time and Concurrent Delay Case
case
This guide was last updated in August 2011.
Construction contracts
TMT
Hotels
Energy
UK
repayment of damages.
The parties had used a standard form JCT contract which contained
a bespoke provision (clause 13.8) which City Inn argued barred
Shepherd from obtaining any EoT at all. Shepherd argued that City
Inn had waived its right to rely on this provision.
Lord Drummond Young's opinion
The case was first heard before Lord Drummond Young in 2007.
Clause 13.8 and waiver
The evidence showed that neither party, nor the architect, had made
any reference to clause 13.8 during the course of the contract, and
applications for EoT had been made and considered as if the
provision did not exist. In fact, it became clear that the first time
City Inn ever sought to rely on the provision was during the
adjustment of its written claim, sometime after the court action had
been raised and a number of years after the job was finished.
Lord Drummond Young agreed that it would make no sense to apply
the bespoke clause (clause 13.8) to the instructions and variations
which caused delay - not because of their content, but because the
instruction or variation had itself been given too late. He also found
that City Inn had effectively waived its right to rely on the clause by
its director's failure to mention the provision in face to face
discussions with the contractor and the fact that Shepherd had then
proceeded as if the clause did not exist. There was evidence, which
he accepted, to the effect that if City Inn and its architect had
refused the earlier EoT application on the basis that it didn't comply
with clause 13.8, Shepherd would have applied the clause to later
EoT applications.
Causation, concurrency and delay
With regard to delay it was clear that various events had occurred
concurrently with one another, particularly towards the end of the
project, which all potentially caused delays to completion. Some of
these were Relevant Events under the construction contract, and
some were events which were attributable to Shepherd.
Shepherd had been unable to locate the full version of its original
construction programme to use as evidence - all that was available
was a fairly basic programme showing activities and durations. An
as-built programme was agreed between the two parties' experts,
and City Inn's expert then worked backwards to establish the critical
path of how the job had to proceed and how much time had to be
given for each task from that information. However, the critical
path established by City Inn's expert managed to avoid many of the
matters on which Shepherd relied for its claims. This led him to the
conclusion that these had not affected the time for completion and
so the contractor was not entitled to a single day's EoT.
Shepherd's expert, on the other hand, gave evidence that he had also
tried to establish the critical path but felt it was impossible to do so
reliably from the information available. Instead, he compared the
original and as-built programmes to see where delays occurred and
then looked at what had caused those delays. He then used his
experience and judgement to offer an opinion as to the effect those
delays had on completion.
At the trial, numerous errors were identified in City Inn's critical
path analysis which were eventually conceded by its expert.
Lord Drummond Young concluded that the contract expected the
decision maker to come to a 'fair and reasonable' decision on
whether to approve an extension of time. Where a Relevant Event
and contractor risk event existed at the same time then, irrespective
of when the events began or ended, if neither of the events was
'dominant' then a fair and reasonable outcome may involve an
apportionment exercise. The judge then went on to consider the
evidence and the competing approaches of the two experts. Lord
Drummond Young rejected City Inn's critical path analysis and
preferred the evidence of Shepherd's expert. Applying this
approach, he found that Shepherd was entitled to the same nine-
week EoT that had been awarded by the adjudicator.
City Inn appealed.
The Appeal decision
The Scottish Inner House heard the appeal in 2009 and made their
decision in 2010. All three appeal judges rejected City Inn's appeal
on many of the same grounds as Lord Drummond Young. The
aspect of their decision which is most interesting, however, relates
to the proper application of an extension of time clause and how to
deal with issues of concurrency and causation. The majority
judgement, by two of the three judges, set out five propositions:
a Relevant Event must delay or be likely to delay the works;
the decision maker can decide whether the event has caused
delay by the use of whatever evidence he considers appropriate. This
may be a critical path analysis, but the absence of one is not fatal;