QCS Q&a
QCS Q&a
Anything which went violate the Project Specification, Standard, Procedure is Non Conformity
which need to record through NCR.
3. What is the maximum days from issue date to initiate corrective action as per Schedule Q?
It’s Seven days of issuance.
5. What is an RFI?
It’s an Inspection department document used in Saudi Aramco projects to request for Inspection
of any construction activity, material, equipment or services in the form of QMIS or hard copy.
8. What is Two Week Look ahead Inspection Schedule and how frequent you shall prepare it?
`Document showing the schedule Quality Inspection activity and Weekly shall prepare.
9. What is SATIP?
Inspection and Test Plans (ITPs) that are generated by Saudi Aramco Inspection Department
customized for use in Saudi Aramco managed construction projects.
10. What are the stages of SATIP?
1. Document Review
2. Material Inspection
3. Installation
4. Pre Commissioning
5. Commissioning
13. If any of the clauses in the SAIC do not comply or fail, what action you will do?
Issue INCR.
14. What are the International Standards you are familiar with?
1. API 598 - Valve Inspection and Test
2. API 600 - Steel Gate Valves
3. API 601 - Metallic Gaskets for Refinery Piping
4. API 609 - Butterfly Valves
5. API 1104 - Standard for Welding Pipelines and Facilities
6. ASME B31.1 - Power Piping
7. ASME B31.2 - Fuel Gas Piping
8. ASME B31.3 - Process Piping
9. ASME B31.9 - Building Services Piping
10. ASME B16.1 - Cast Iron Pipe Flanges and Flanged Fittings
16. What are the Saudi Aramco Standards you are familiar with?
1. SAES-A-004 - General Requirements for Pressure Testing
2. SAES-A-007 - Hydrostatic Testing Fluids and Lay-Up Requirements
3. SAES-A-114 - Excavation and Backfilling
4. SAES-D-001 - Design Criteria for Pressure Vessel
5. SAES-D-008 - Repairs, Alterations and Re-rating of Process Equipment
6. SAES-G-115 - Lubrication, Shaft Sealing and Oil Control Systems and Auxiliaries
7. SAES-H-001 - Coating Selection and Application Requirements for Industrial Plants and
Equipment
8. SAES-H-002 - Internal and External Coatings for Steel Pipelines and Piping
9. SAES-H-003 - Protective Coatings for Industrial Concrete Structures
10. SAES-J-902 - Electrical Systems for Instrumentation
11. SAES-K-402 - Centrifugal Compressors
12. SAES-L-150 - Pressure Testing of Plant Piping and Pipelines
13. SAES-L-350 - Construction of Plant Piping
14. SAES-P-113 - Motors and Generators
15. SAES-Q-001 - Criteria for Design and Construction of Concrete Structures
16. SAES-Q-005 - Concrete Foundations
17. SAES-Q-007 - Foundations and Supporting Structures for Heavy Machinery
18. SAES-S-060 - Saudi Aramco Plumbing Codes
19. SAES-S-070 - Installation of Utility Piping Systems
20. SAES-T-911 - Telecommunication Conduit System Design
21. SAES-W-011 - Welding Requirements for On-Plot Piping
22. SAES-W-012 - Welding Requirements for Pipelines
23. SAES-W-017 - Welding Requirements for API Tanks
18. What are the tests in your discipline you are familiar with?
1. Slump Test for Concrete as per Aramco standard 150 +/- 40mm
2. Surface Preparation and Moisture Test before coating and DFT test after coating
3. Hydrostatic Test for Pipelines
4. Continuity Test and Megger Test for Electric Cables
19. What is a Tie-In and what document is required for approval before actual Tie-In activity?
Tie-In is a welded Joints, which need to cut the existing pipe and to weld a new pipe to that line.
SAIC-L-2025 describes the required documents for approval before the activity.
20. What is a Hydrostatic Test and what document is required for approval before actual activity?
A pressure test conducted using water or other approved liquid as the test medium.
SAIC-A-2001 describes the required documents for approval before the activity.
22. What are the equipment you need to do your Job as QC Supervisor?
24. How many months is the required calibration cycle if no manufacturer recommendations?
It is 6 Months.
27. For QC Supervisors only, differentiate an orange to an apple and correlate it to QC Inspectors
in different disciplines under you?
28. What is a destructive test and identify what are the destructive tests?
The destructive testing is undertaken to understand a specimen’s performance or material
behavior.
Different types of Destructive Tests are Bend Test, Tensile Test, Impact Test and Hardness Test.
29. What is NDT and identify what are the types of NDT?
It is a testing and analysis technique used by industry to evaluate the properties of a material,
component or system without causing damage to the original part.
Different types of NDT are Dye Penetration Test, Magnetic Particle Testing, Radiographic Test
and Ultrasonic Test.
Procedure Qualification Record (PQR): It is another type of document that also refers to welding.
However, unlike WPS, the PQR documents purpose is to serve as a checklist or record of
compliance regarding the standard requirements of an appropriate welding procedure.