Assignment For Chapter 8: Scheduling Assignment 1:: B15 E15 H35 End

The document contains 6 assignments related to project scheduling and critical path analysis. It includes network diagrams, identifying critical paths and activities, calculating slack times, and determining probabilities of project completion. The critical paths identified are: A-C-E-G for Assignment 1; A-B-F-G-H for Assignment 2; A-C-F-H for Assignment 3; A-D-G-I for Assignment 4; AC-CB-BE-EF for Assignment 5; and c-f-h for Assignment 6. The probability of completing Assignment 6 in 25 weeks is 0.969.

Uploaded by

Phuong
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
136 views

Assignment For Chapter 8: Scheduling Assignment 1:: B15 E15 H35 End

The document contains 6 assignments related to project scheduling and critical path analysis. It includes network diagrams, identifying critical paths and activities, calculating slack times, and determining probabilities of project completion. The critical paths identified are: A-C-E-G for Assignment 1; A-B-F-G-H for Assignment 2; A-C-F-H for Assignment 3; A-D-G-I for Assignment 4; AC-CB-BE-EF for Assignment 5; and c-f-h for Assignment 6. The probability of completing Assignment 6 in 25 weeks is 0.969.

Uploaded by

Phuong
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 10

Name: Lê Lâm Trúc Phương

ID: BABAIU17021
Class: BABA174WE21 (Tuesday Class)
Subject: Project Management

Assignment for Chapter 8: Scheduling

Assignment 1:
a) Path:
A-D-G: 8 + 7 + 5 = 20
A-C-E-G: 8 + 3 +6 +5 = 22
A-C-F-H: 8 + 3 + 7 + 3 = 21
B-F-H: 10 + 7 + 3 = 20
B-E-G: 10 + 6 + 5 = 21
So, critical path is A-C-E-G.
b) It takes 22 days to complete the project.
c) B is not on critical path, so B can be delayed without delaying completion of the
project. B-E-G path needs 21 days to complete, and it takes 22 days to complete
project. So, B can be delayed 1 day.
Assignment 2:
1. Network diagram:

B15 E15

H35 End

Start A5 C10

G170
F10
D5
2. Paths:
A-B-E-H: 5 + 15 + 15 + 35 = 70
A-B-F-G-H: 5 + 15 + 10 + 170 + 35 = 235
A-C-E-H: 5 + 10 + 15 + 35 = 65
A-C-F-G-H: 5 + 10 + 10 + 170 + 35 = 230
A-D-F-G: 5 + 5 + 10 + 170 + 35 = 225
So, the critical path is A-B-F-G-H.
3. Slack:

Activity LS ES Slack

A 0 0 0

B 5 5 0
C 5 10 5

D 5 15 10

E 20 185 165
F 20 20 0

G 30 30 0

H 200 200 0

Assignment 3:
1. Network diagram

D6 G6
B4
End
E4
Start A3
H8

C6 F4
2. Paths:
A-B-D-G: 3 + 4 + 6 + 6 = 19
A-B-E-H: 3 + 4 + 4 + 8 = 19
A-C-F-H: 3 + 6 + 4 + 8 = 21
So, the critical path is A-C-F-H.
3. Slack:

Activity LS ES Slack

A 0 0 0
B 5 3 2

C 3 3 0

D 9 7 2
E 9 7 2

F 9 9 0
G 15 13 2

H 12 12 0

Assignment 4:
1. Network diagram

C4

A5

D4
Start I4 End
G3
E3

B2
F7 H2
2. Paths:
A-C-I: 5 + 4 + 4 = 13
A-D-G-I: 5 + 4 + 3 + 4 = 16
B-E-G-I: 2 + 3 + 3 + 4 = 12
B-F-H-I: 2 + 7 + 2 + 4 = 15
So, the critical path is A-D-G-I.
3. Slack:

Activity LS ES Slack

A 0 0 0
B 1 0 1

C 8 5 3

D 5 5 0
E 6 2 4

F 3 2 1
G 9 9 0

H 10 9 1

I 12 12 0

Assignment 5:
a) AOA network and critical path:

B BD
D
DF
BE
AB
A F
DE
CB

AC
EF
CD

C CE E
Activity a m b Expected Variance Standard
Time deviation

AB 3 6 9 6 1 1

AC 1 4 7 4 1 1

CB 0 3 6 3 1 1
CD 3 3 3 3 0 0

CE 2 2 8 3 1 1

BD 0 0 6 1 1 1

BE 2 5 8 5 1 1
DF 4 4 10 5 1 1

DE 1 1 1 1 0 0

EF 1 4 7 4 1 1

Paths:
AB-BD-DF: 6 + 1 + 5 = 12
AB-BD-DE-EF: 6 + 1 + 1 + 4 = 12
AB-BE-EF: 6 + 5 + 4 = 15
AC-CB- BD-DF: 4 + 3 + 1 + 5 = 13
AC-CB- BD-DE-EF: 4 + 3 + 1 + 1 + 4 = 13
AC-CB-BE-EF: 4 + 3 + 5 + 4 = 16
AC-CD-DF: 4 + 3 + 5 = 12
AC-CD-DE-EF: 4 + 3 + 1 + 4 = 12
AC-CE-EF: 4 + 3 + 4 = 11
Therefore, critical path is AC-CB-BE-EF.
b) Slack:
Event LS ES Slack

A 0 0 0

B 7 7 0

C 4 4 0
D 11 8 3

E 12 12 0

F 16 16 0

c) Critical path to event D.


Paths to event D:
AB-BD: 6 + 1 = 7
AC-CD: 4 + 3 = 7
AC-CB-DB: 4 + 3 + 1 = 8
So, critical path to event D is AC-CB-DB.
d) Critical path probability of completion in 14 days.
!" $ '("')
Z= = = -1
√&! √(

P (X ≤ 14) = P (Z ≤ -1) = 1- 0.8413 = 0.1587


So, the critical path probability of completion in 14 days is 0.1587.
e) The effects if CD slips to 6 days; to 7 days; to 8 days.
• If CD slips to 6 days, then AC-CD-DF: 4 + 6 + 5 = 15; AC-CD-DE-EF:
4 + 6 + 1 + 4 = 15. So, there is no change.
• If CD slips to 7 days, then AC-CD-DF: 4 + 7 + 5 = 16; AC-CD-DE-EF:
4 + 7 + 1 + 4 = 16. So, there will be two more critical paths besides AC-CB-
BE-EF, they are AC-CD-DF and AC-CD-DE-EF.
• If CD slips to 8 days, then AC-CD-DF: 4 + 8 + 5 = 17; AC-CD-DE-EF:
4 + 8 + 1 + 4 = 17. So, there will be only two critical paths, they are AC-CD-
DF and AC-CD-DE-EF.
Assignment 6:
a) Network diagram:

2 d7
5

h5
a3

e5
f10
b6
1 3 7
c8

i6
g4
4 6

b) Paths:
a-d-h: 3 + 7 + 5 = 15
b-e-h: 6 + 5 + 5 = 16
c-f-h: 8 + 10 + 5 = 23
c-g-i: 8 + 4 + 6 = 18
So, critical path is c-f-h.
c) Slack:

Activity LS ES Slack

a 8 0 8
b 7 0 7
c 0 0 0

d 11 3 8

e 13 6 7
f 8 8 0

g 13 8 5

h 18 18 0

i 17 12 5

d) Probability of completion in 25 weeks.


!" $ *+"*,
Z= √&!
= √'../! = 1.87

P (X ≤ 25) = P (Z ≤ 1.87) = 0.9693.


So, the critical path probability of completion in 25 weeks is 0.9693.

Assignment 7:
a) AON diagram

5 10

1 13

4 9
15
Start

6 8 12

2 End
14

3 7
11
Activity a m b Expected Variance Standard
Time deviation

1 2 4 6 4 4/9 2/3

2 5 5 5 5 0 0

3 3 5 7 5 4/9 2/3
4 7 10 13 10 1 1

5 11 12 13 12 1/9 1/3

6 5 6 7 6 1/9 1/3

7 9 10 11 10 1/9 1/3
8 5 7 9 7 4/9 2/3

9 7 9 11 9 4/9 2/3

10 3 3 3 3 0 0
11 15 17 19 17 4/9 2/3

12 6 8 10 8 4/9 2/3
13 7 8 15 9 16/9 4/3

14 12 14 16 14 4/9 2/3

15 16 17 18 17 1/9 1/3

b) Completion time and critical path.


Paths:
1-5-10-13-15: 4 + 12 + 3 +9 + 17 = 45
1-4-9-13-15: 4 + 10 + 9 + 9 + 17 = 49
1-4-6-8-12-15: 4 + 10 + 6 + 7 +8 + 17 = 52
2-6-8-12-15: 5 + 6 + 7 +8 + 17 = 43
2-3-8-12-15: 5 + 5 + 7 +8 + 17 = 42
2-3-7-11: 5 + 5 + 10 + 17 = 37
2-3-7-14: 5 + 5 + 10 + 14 = 34
So, the completion time for the play is 52 days and the critical path is 1-4-6-8-12-15.
c) Find D:
Be 80% confident of achieving: p% = 0.8, then Z = 0.84
√*,
D = 𝜇 + 𝜎.Z = 52 + x 0.84 = 53.34
,

So, we are 80% confident of achieving in 53.34 days.


Be 40% confident of achieving: p% = 0.4, then Z = -0.25
√*,
D = 𝜇 + 𝜎.Z = 52 + ,
x (-0.25) = 51.6

So, we are 40% confident of achieving in 54.6 days.


d) A 1-day delay in this project will be serious since the play is supporting an
Independence Day.