Assignment For Chapter 8: Scheduling Assignment 1:: B15 E15 H35 End
Assignment For Chapter 8: Scheduling Assignment 1:: B15 E15 H35 End
ID: BABAIU17021
Class: BABA174WE21 (Tuesday Class)
Subject: Project Management
Assignment 1:
a) Path:
A-D-G: 8 + 7 + 5 = 20
A-C-E-G: 8 + 3 +6 +5 = 22
A-C-F-H: 8 + 3 + 7 + 3 = 21
B-F-H: 10 + 7 + 3 = 20
B-E-G: 10 + 6 + 5 = 21
So, critical path is A-C-E-G.
b) It takes 22 days to complete the project.
c) B is not on critical path, so B can be delayed without delaying completion of the
project. B-E-G path needs 21 days to complete, and it takes 22 days to complete
project. So, B can be delayed 1 day.
Assignment 2:
1. Network diagram:
B15 E15
H35 End
Start A5 C10
G170
F10
D5
2. Paths:
A-B-E-H: 5 + 15 + 15 + 35 = 70
A-B-F-G-H: 5 + 15 + 10 + 170 + 35 = 235
A-C-E-H: 5 + 10 + 15 + 35 = 65
A-C-F-G-H: 5 + 10 + 10 + 170 + 35 = 230
A-D-F-G: 5 + 5 + 10 + 170 + 35 = 225
So, the critical path is A-B-F-G-H.
3. Slack:
Activity LS ES Slack
A 0 0 0
B 5 5 0
C 5 10 5
D 5 15 10
E 20 185 165
F 20 20 0
G 30 30 0
H 200 200 0
Assignment 3:
1. Network diagram
D6 G6
B4
End
E4
Start A3
H8
C6 F4
2. Paths:
A-B-D-G: 3 + 4 + 6 + 6 = 19
A-B-E-H: 3 + 4 + 4 + 8 = 19
A-C-F-H: 3 + 6 + 4 + 8 = 21
So, the critical path is A-C-F-H.
3. Slack:
Activity LS ES Slack
A 0 0 0
B 5 3 2
C 3 3 0
D 9 7 2
E 9 7 2
F 9 9 0
G 15 13 2
H 12 12 0
Assignment 4:
1. Network diagram
C4
A5
D4
Start I4 End
G3
E3
B2
F7 H2
2. Paths:
A-C-I: 5 + 4 + 4 = 13
A-D-G-I: 5 + 4 + 3 + 4 = 16
B-E-G-I: 2 + 3 + 3 + 4 = 12
B-F-H-I: 2 + 7 + 2 + 4 = 15
So, the critical path is A-D-G-I.
3. Slack:
Activity LS ES Slack
A 0 0 0
B 1 0 1
C 8 5 3
D 5 5 0
E 6 2 4
F 3 2 1
G 9 9 0
H 10 9 1
I 12 12 0
Assignment 5:
a) AOA network and critical path:
B BD
D
DF
BE
AB
A F
DE
CB
AC
EF
CD
C CE E
Activity a m b Expected Variance Standard
Time deviation
AB 3 6 9 6 1 1
AC 1 4 7 4 1 1
CB 0 3 6 3 1 1
CD 3 3 3 3 0 0
CE 2 2 8 3 1 1
BD 0 0 6 1 1 1
BE 2 5 8 5 1 1
DF 4 4 10 5 1 1
DE 1 1 1 1 0 0
EF 1 4 7 4 1 1
Paths:
AB-BD-DF: 6 + 1 + 5 = 12
AB-BD-DE-EF: 6 + 1 + 1 + 4 = 12
AB-BE-EF: 6 + 5 + 4 = 15
AC-CB- BD-DF: 4 + 3 + 1 + 5 = 13
AC-CB- BD-DE-EF: 4 + 3 + 1 + 1 + 4 = 13
AC-CB-BE-EF: 4 + 3 + 5 + 4 = 16
AC-CD-DF: 4 + 3 + 5 = 12
AC-CD-DE-EF: 4 + 3 + 1 + 4 = 12
AC-CE-EF: 4 + 3 + 4 = 11
Therefore, critical path is AC-CB-BE-EF.
b) Slack:
Event LS ES Slack
A 0 0 0
B 7 7 0
C 4 4 0
D 11 8 3
E 12 12 0
F 16 16 0
2 d7
5
h5
a3
e5
f10
b6
1 3 7
c8
i6
g4
4 6
b) Paths:
a-d-h: 3 + 7 + 5 = 15
b-e-h: 6 + 5 + 5 = 16
c-f-h: 8 + 10 + 5 = 23
c-g-i: 8 + 4 + 6 = 18
So, critical path is c-f-h.
c) Slack:
Activity LS ES Slack
a 8 0 8
b 7 0 7
c 0 0 0
d 11 3 8
e 13 6 7
f 8 8 0
g 13 8 5
h 18 18 0
i 17 12 5
Assignment 7:
a) AON diagram
5 10
1 13
4 9
15
Start
6 8 12
2 End
14
3 7
11
Activity a m b Expected Variance Standard
Time deviation
1 2 4 6 4 4/9 2/3
2 5 5 5 5 0 0
3 3 5 7 5 4/9 2/3
4 7 10 13 10 1 1
5 11 12 13 12 1/9 1/3
6 5 6 7 6 1/9 1/3
7 9 10 11 10 1/9 1/3
8 5 7 9 7 4/9 2/3
9 7 9 11 9 4/9 2/3
10 3 3 3 3 0 0
11 15 17 19 17 4/9 2/3
12 6 8 10 8 4/9 2/3
13 7 8 15 9 16/9 4/3
14 12 14 16 14 4/9 2/3
15 16 17 18 17 1/9 1/3